SlideShare a Scribd company logo
Refurbishment of
Heathrow Airport
Terminal 1
Yash Mittal
Yash Mittal © 2
Contents
 Introduction
 Overview
 Project Team
 Challenges
 Solutions
 Conclusion
 References
Yash Mittal © 3
Introduction
 London Heathrow Airport is a major international airport in
West London, England, United Kingdom.
 Heathrow is the busiest airport in the United Kingdom and the busiest airport
in Europe by passenger traffic.
 It is also the third busiest airport in the world by total passenger traffic.
 Heathrow lies 12 nautical miles or 22 kilometers west of Central London, and
has two parallel east–west runways along with five terminals on a site that
covers 12.14 square kilometers.
 The airport is owned and operated by Heathrow Airport Holdings,
formerly BAA, which is the United Kingdom-based operator of London
Heathrow Airport.
 Heathrow is the primary hub for British Airways and the primary operating base
for Virgin Atlantic.
Yash Mittal © 4
Overview
 BAA Airports Ltd. was tasked with the refurbishment of Terminal 1, a 40-year-
old building within Heathrow Airport, whilst constantly keeping the terminal
open to the 20 million annual travelers.
 Terminal 1 had previously been for short-haul European destinations only, but
the introduction of Star Alliance meant that international passengers would
now also be using the terminal.
 The successful completion of this project was the enabler for the complete
transformation of Heathrow Airport that is used by more than 90 airlines,
which fly to more than 180 destinations worldwide.
Yash Mittal © 5
Project Team
 To oversee the whole project Heathrow Holdings Airport Ltd hired David
Buisson, PMP to lead this major project.
 David Buisson is a certified project manager with more than 13 years of
experience of managing different projects.
 Under his direction, a team of professionals, tackled one of the most
important transport projects in the UK, keeping it ahead of its European
competition.
 Time management and communication were big issues that the Buisson
project team had to face because of the scale and size of this project.
• “A strong
project
management
discipline
brings
exceptional
value to the
business,
because when
there is a
demand for a
product, we
are the ones
who deliver
it,”
Yash Mittal © 6
Challenges
 Regular meetings weekly and monthly with all suppliers.
 Project manager dealt with the problems personally and quickly before
moving on to good communication with large number of stakeholders.
 Right balance of day and night work to cut costs and last minute changes had
to be thought of.
 Smart management of storage room.
 An airtight area secured the asbestos roof work so there would be no leak
during the removal work as well as no interruption for terminal operations.
Yash Mittal © 7
Challenges contd..
 Electrical risk of shutting down to limited times at night with less operation
poses a challenge.
 Good risk management according to schedules and constant updates and
reviews was needed.
 IT management must be well organized.
 Problems could therefore be passed on to the project manager very quickly
due to good monitoring.
 Improvements on energy saving and heating.
Yash Mittal © 8
Human Resources Management-The
People
 Management of different people and teams on this project was quite
challenging because of its scale and size.
 There were 11 top-tier suppliers who reported directly to the project
manager, and dozens more who subsequently reported in to them, overall
involving a very large number of workers.
 Communications and time management would prove to be a challenge on a
project involving this many different parties, especially because the project
manager was keen to maintain a collaborative approach to problem solving.
Yash Mittal © 9
Human Resources Management-The
Planning
 The large number of third parties working on this project potentially could
have had severe repercussions on scheduling.
 If one contractor was late in finishing leveling the floor, this could delay the
contractor that was scheduled to install the furniture, causing a larger knock-
on effect throughout the project.
 Clear mandate was issued to third party suppliers and contractors to follow a
very specific framework of the project.
Yash Mittal © 10
Cost and Procurement Management-
Budget changes
 Budgetary reviews on the project meant that some major late changes were
made on the project including some to the original plan with only four weeks
to go.
 The original design for the installation of a “cladding” system above the
ticket desks for BMI Airlines that would improve both the aesthetics and
lighting for the area was deleted from the scope of works just four weeks
before the check-in desks were scheduled to open.
 Upon learning of the decision, the project team was faced with an almost
insurmountable task of finding an alternative solution that was acceptable to
the various stakeholders and could also be procured and installed in less than
four weeks.
Yash Mittal © 11
Scope Management-Structural
Challenges
 A big challenge for the team was repairing damaged floor work in the
terminal that was left when the building was initially constructed 40 years
earlier.
 Repairing the floor potentially added an extra 21 weeks of work to the
project.
 The floor in the East Linear face of the terminal was discovered to have been
constructed from different materials to the rest of the flooring in the
terminal.
 The floor was an uneven concrete surface instead of the regular terrazzo
tiling, which to correct, would have added a significant amount of time to the
refurbishment.
Yash Mittal © 12
Scope Management- Technological
Challenges
 Information Technology (IT) proved another challenge in the delivery of this
project because the team had to replace existing systems within the terminal
building.
 This was a big challenge because it not only included standard office network
systems, but also specialist flight systems such as Flight Information Display
Screens, regulatory systems for passenger processing, and closed-circuit
television.
Yash Mittal © 13
Scope Management- Environmental
Challenges
 Completing this project sustainably and installing sustainable and energy
saving measures were an important component in the refurbishment project.
 Given this was a renovation project and not the construction of a completely
new building, installing truly sustainable features to save water for example,
was very difficult in an old fashioned building.
Yash Mittal © 14
Communications Management
 Communications was also a big challenge for the project because there were
multiple high-level stakeholders involved who had to be consistently updated
each time there was a risk identified or when there was a change to the
schedule or budget.
Yash Mittal © 15
Risk Management- Asbestos risk
 A big concern for the team that could potentially have been very damaging
was discovering asbestos in the ceiling. A number of the ceiling tiles in
Terminal 1 were damaged and needed to be replaced, therefore the asbestos
needed to be removed safely. Bearing in mind that 20 million passengers pass
through Terminal 1 every year, the problem could not simply be solved by
erecting scaffolding in these areas, taking down the damaged tiles and
replacing them, as this would create a health and safety risk to the
passengers and staff of Terminal 1. The agreed plan was to construct an air-
tight floor to ceiling area in the roof void around where the damaged ceiling
tiles were and extract the asbestos accordingly by a suitably qualified
asbestos removal contractor.
Yash Mittal © 16
Risk Management- Electrical risks
 It was discovered that the East Linear check-in facility required the
installation of a new distribution board to meet the greater electricity
demand.
 In installing a new distribution board the power to the entire terminal had to
be temporarily turned off.
 An added dimension to this was that the distribution board in question
provided power to the Central Search Area where passengers were processed
through BAA Security, which is the main route to their departing aircraft.
 It was therefore critical that the project leaders got this process right
otherwise the terminal would not be able to process passengers and may have
to close down until power was restored.
Yash Mittal © 17
Solutions
There were a number of difficulties that arose during
the refurbishment of Terminal 1 and now we will
examine the solutions for these challenges.
Budgetary
Scheduling
Health and Safety
Communications
Yash Mittal © 18
The People
 A very clear mandate was issued to the plethora of third-party suppliers and
contractors involved to ensure that they followed a very specific framework
for the quality and design requirements of the project.
 A competitive tender process was undertaken that ensured the best people
got the job ensuring that maximum value was achieved and maximum
knowledge was extracted from the range of skills and professions contributing
to the project.
 The main contractor was located in the same office as the project team
which helped the to deliver most effectively.
 Weekly and monthly meetings were held with all suppliers to address any
grievances, problems, or issues.
 Good communications and people management ensured that the project
progressed smoothly.
Yash Mittal © 19
The Planning
 The main project was further divided into small sub projects.
 The individual contractors were strictly managed to ensure that each small project was delivered on time.
Yash Mittal © 20
Budget Changes
 The cost estimating and budgeting efforts during the early stages of the
project were very challenging and, in particular, getting the balance right in
terms of work that would be undertaken at night versus those in the daytime
hours.
 Budgetary commitments meant that a number of last-minute changes were
made to the project.
 The project team and main contractor held a brainstorming session where one
of the suggestions.
Yash Mittal © 21
Structural Challenges
 Mending the floor whilst keeping to the project deadline was a challenge,
given that other work was taking place simultaneously in the area.
 To overcome this challenge, the project team met with the main contractor,
terminal maintenance, and other contractors to discuss the issue of re-
flooring this particular area and to develop a joint phasing plan to sequence
the work and what areas would be protected for site storage of materials and
tools.
 Despite the prospect of a 21-week delay, the team still delivered on time.
Yash Mittal © 22
Technological Challenges
 IT was an integral part of the Terminal 1 project because it allowed the
project to be constantly monitored for problems by all parties involved.
 The IT team at BAA developed custom software for the project that
incorporated an “Online Change Control” system that allowed any members
of the team based on- or offsite to capture changes and send them online to
the senior project manager for instant approval or rejection.
 It saved invaluable time on the project and meant that work could continue
with less delay than would have been previously experienced.
Yash Mittal © 23
Environmental Challenges
 BAA has a strong commitment to ethics in their Corporate Sustainability
Programme, which is dedicated to improving design, construction, and
integration and decommissioning.
 Despite the challenges of updating a building from the 60s, the project team
strove to incorporate sustainable changes to the lighting and heating.
 Changes were made where possible including using energy saving bulbs
throughout, and low-energy heating.
Yash Mittal © 24
The Risks-Asbestos Risk
 In response to the asbestos risk,
the project team, including the
Health and Safety officer, main
contractor, and terminal operations
team, reviewed all of the potential
options and risks and agreed that
the solution was to create an
airtight area within the
contaminated roof void that would
not leak into the airport.
 A big part of developing a solution
for the asbestos problem was
assessing and implementing
project risk management.
Risk Management
Schedules
Strategic/Leadership
Level
Day-to-Day Risk
Factors
Yash Mittal © 25
The Risks-Electrical Risk
 Switching off all power to the old terminal building carried the heavy risk of
the power not returning at all.
 The project team therefore convened a high-level meeting with all relevant
stakeholders and the main contractor to discuss the issues and formalize a
plan with subsequent meetings.
 The output and results of the various meetings and discussions were captured
in a formal process guidance document including all relevant technical data
associated with this work.
Yash Mittal © 26
The Risks-Continued
 For every aspect of the project that involved any risk, risk schedules were
reviewed, updated, and published through a formal review meeting held
every month.
 In addition, the main contractor undertook the same process of risk
management for its respective activities along with its key suppliers.
 Through this process, the top three risks identified in the risk schedule were
escalated to the project board every month for elevation within the relevant
business unit.
Yash Mittal © 27
Conclusion
 Heathrow Airport Terminal 1 was completed on time in September 2008. The
project involved more than 500,000 working hours and kept within its £57.6
million budget.
 The project delivered on time and within budget despite the numerous
problems that arose, especially the unexpected extra work that could have
caused major delays to the project delivery.
 The project had a good health and safety record with no reported incidents,
despite dealing with serious hazards like asbestos.
 There was effective team work between the numerous contractors, suppliers,
stakeholders, and various support functions.
 All challenges were successfully met by the project team including £6.3m of
unexpected out-of-scope work that was engineered into the final solution
without an increase to the approved project budget.
Yash Mittal © 28
£6.3million worth of additional work was added without an
increase to the original project budget
Yash Mittal © 29
References
 www.heathrowairport.com
 www.prezi.com/j_ts1rkrrkvs/refurbishment-of-heathrow-airport-terminal-
1/
 www.pmi.org/.../~/.../Heathrow_Airport_Case_Study_New.ashx
 http://www.academia.edu/9699398/HEATHROW_AIRPORT_TERMINAL_1_RISK_
MANAGEMENT_PLAN
 http://www.airport-world.com/item/1536-reinventing-heathrow
Yash Mittal © 30
Yash Mittal © 31
Yash Mittal © 32

More Related Content

What's hot

Airline Budgeting
Airline BudgetingAirline Budgeting
Airline Budgeting
Elizabeth Conley
 
Privatization and Concessions (PPP) In Airports
Privatization and Concessions (PPP) In AirportsPrivatization and Concessions (PPP) In Airports
Privatization and Concessions (PPP) In Airports
Loay Ghazaleh MBA, BSc Civil Eng.
 
Case study presentation on Boeing
Case study presentation on BoeingCase study presentation on Boeing
Case study presentation on Boeing
Manisha Yadav
 
Istanbul New Airport (İstanbul Yeni Havalimanı)
Istanbul New Airport (İstanbul Yeni Havalimanı)Istanbul New Airport (İstanbul Yeni Havalimanı)
Istanbul New Airport (İstanbul Yeni Havalimanı)
BME
 
Construction labor
Construction laborConstruction labor
Construction labor
Arun Kumar
 
LogiQuest Season 2 - Challenges and opportunities in multi modal logistics in...
LogiQuest Season 2 - Challenges and opportunities in multi modal logistics in...LogiQuest Season 2 - Challenges and opportunities in multi modal logistics in...
LogiQuest Season 2 - Challenges and opportunities in multi modal logistics in...
Mahindra Logistics
 
Construction Insurance
Construction InsuranceConstruction Insurance
Consultancy in Airport Sector Scope and Opportunities
Consultancy in  Airport Sector Scope and OpportunitiesConsultancy in  Airport Sector Scope and Opportunities
Consultancy in Airport Sector Scope and Opportunities
Prashanth M R
 
Private conatiner terminal operator
Private conatiner terminal operatorPrivate conatiner terminal operator
Private conatiner terminal operator
AMAN GOYAL
 
Analytical Comparison between BOT,BOOT and PPP Projects
Analytical Comparison between BOT,BOOT and PPP ProjectsAnalytical Comparison between BOT,BOOT and PPP Projects
Analytical Comparison between BOT,BOOT and PPP Projects
Sugiharto TuPiichai
 
Contract Conditions
Contract ConditionsContract Conditions
Contract Conditions
Dr K M SONI
 
Heathrow Strategic Innovation Case Study
Heathrow Strategic Innovation Case StudyHeathrow Strategic Innovation Case Study
Heathrow Strategic Innovation Case Study
Diana Kontsevaia
 
Risk analysis and managements large epc projects
Risk analysis and managements  large epc projectsRisk analysis and managements  large epc projects
Risk analysis and managements large epc projects
PALLA NARASIMHUDU
 
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias TanFIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
Adrias TAN
 
Allcargo Logistic Limited
Allcargo Logistic LimitedAllcargo Logistic Limited
Allcargo Logistic Limited
saurabh kumar
 
E learning initiatives at motorola
E learning initiatives at motorolaE learning initiatives at motorola
E learning initiatives at motorola
Srinibash Dash
 
Project finance delhi international airport
Project finance   delhi international airportProject finance   delhi international airport
Project finance delhi international airport
Maulik Savalia
 
Turnkey projects
Turnkey projectsTurnkey projects
Turnkey projects
Somesh Gurbani
 
Build, operate & transfer
Build, operate & transferBuild, operate & transfer
Build, operate & transfer
Saurav Kumar
 
Build - Operate - Transfer
Build - Operate - TransferBuild - Operate - Transfer
Build - Operate - Transfer
Kshitij Gupta
 

What's hot (20)

Airline Budgeting
Airline BudgetingAirline Budgeting
Airline Budgeting
 
Privatization and Concessions (PPP) In Airports
Privatization and Concessions (PPP) In AirportsPrivatization and Concessions (PPP) In Airports
Privatization and Concessions (PPP) In Airports
 
Case study presentation on Boeing
Case study presentation on BoeingCase study presentation on Boeing
Case study presentation on Boeing
 
Istanbul New Airport (İstanbul Yeni Havalimanı)
Istanbul New Airport (İstanbul Yeni Havalimanı)Istanbul New Airport (İstanbul Yeni Havalimanı)
Istanbul New Airport (İstanbul Yeni Havalimanı)
 
Construction labor
Construction laborConstruction labor
Construction labor
 
LogiQuest Season 2 - Challenges and opportunities in multi modal logistics in...
LogiQuest Season 2 - Challenges and opportunities in multi modal logistics in...LogiQuest Season 2 - Challenges and opportunities in multi modal logistics in...
LogiQuest Season 2 - Challenges and opportunities in multi modal logistics in...
 
Construction Insurance
Construction InsuranceConstruction Insurance
Construction Insurance
 
Consultancy in Airport Sector Scope and Opportunities
Consultancy in  Airport Sector Scope and OpportunitiesConsultancy in  Airport Sector Scope and Opportunities
Consultancy in Airport Sector Scope and Opportunities
 
Private conatiner terminal operator
Private conatiner terminal operatorPrivate conatiner terminal operator
Private conatiner terminal operator
 
Analytical Comparison between BOT,BOOT and PPP Projects
Analytical Comparison between BOT,BOOT and PPP ProjectsAnalytical Comparison between BOT,BOOT and PPP Projects
Analytical Comparison between BOT,BOOT and PPP Projects
 
Contract Conditions
Contract ConditionsContract Conditions
Contract Conditions
 
Heathrow Strategic Innovation Case Study
Heathrow Strategic Innovation Case StudyHeathrow Strategic Innovation Case Study
Heathrow Strategic Innovation Case Study
 
Risk analysis and managements large epc projects
Risk analysis and managements  large epc projectsRisk analysis and managements  large epc projects
Risk analysis and managements large epc projects
 
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias TanFIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
 
Allcargo Logistic Limited
Allcargo Logistic LimitedAllcargo Logistic Limited
Allcargo Logistic Limited
 
E learning initiatives at motorola
E learning initiatives at motorolaE learning initiatives at motorola
E learning initiatives at motorola
 
Project finance delhi international airport
Project finance   delhi international airportProject finance   delhi international airport
Project finance delhi international airport
 
Turnkey projects
Turnkey projectsTurnkey projects
Turnkey projects
 
Build, operate & transfer
Build, operate & transferBuild, operate & transfer
Build, operate & transfer
 
Build - Operate - Transfer
Build - Operate - TransferBuild - Operate - Transfer
Build - Operate - Transfer
 

Viewers also liked

HEATHROW AIRPORT GUIDE
HEATHROW AIRPORT GUIDEHEATHROW AIRPORT GUIDE
HEATHROW AIRPORT GUIDE
frankjohn1988
 
Heathrow Airport in Facts and Figures
Heathrow Airport in Facts and FiguresHeathrow Airport in Facts and Figures
Heathrow Airport in Facts and Figures
Parking 4 Airport
 
Risk management
Risk managementRisk management
Risk management
Iben Engenharia
 
Take a look at some of our recent projects
Take a look at some of our recent projectsTake a look at some of our recent projects
Take a look at some of our recent projects
Katie Hayes
 
NEF – PI – FILE TEST 3 - READING
NEF – PI – FILE TEST 3 - READINGNEF – PI – FILE TEST 3 - READING
NEF – PI – FILE TEST 3 - READING
Alicia Garcia
 
Lecture 7, 8, 9 and 10 Inter Process Communication (IPC) in Operating Systems
Lecture 7, 8, 9 and 10  Inter Process Communication (IPC) in Operating SystemsLecture 7, 8, 9 and 10  Inter Process Communication (IPC) in Operating Systems
Lecture 7, 8, 9 and 10 Inter Process Communication (IPC) in Operating Systems
Rushdi Shams
 
Heathrow Terminal 5 - Success or Failure?
Heathrow Terminal 5 - Success or Failure?Heathrow Terminal 5 - Success or Failure?
Heathrow Terminal 5 - Success or Failure?
Dr David Hancock
 
Producer Consumer Problem
Producer Consumer Problem  Producer Consumer Problem
Producer Consumer Problem
Mohamed Abd-elmotty
 
Dining Philosopher's Problem
Dining Philosopher's ProblemDining Philosopher's Problem
Dining Philosopher's Problem
Yash Mittal
 
Construction Risk Summit "benefit and pits of Construction Risk Management"
Construction Risk Summit   "benefit and pits of Construction Risk Management"Construction Risk Summit   "benefit and pits of Construction Risk Management"
Construction Risk Summit "benefit and pits of Construction Risk Management"
bfriday
 
Heathrow airport Presentation by Ayisha Irshad
Heathrow airport Presentation by Ayisha IrshadHeathrow airport Presentation by Ayisha Irshad
Heathrow airport Presentation by Ayisha Irshad
ayishairshad
 
Project Management Theory and Practice
Project Management Theory and Practice Project Management Theory and Practice
Project Management Theory and Practice
Rick Holman
 
Pmbok 4th edition chapter 11 - Project Risk Management
Pmbok 4th edition   chapter 11 - Project Risk ManagementPmbok 4th edition   chapter 11 - Project Risk Management
Pmbok 4th edition chapter 11 - Project Risk Management
Ahmad Maharma, PMP,RMP
 
Ch7 OS
Ch7 OSCh7 OS
Ch7 OS
C.U
 
Airport terminal design (lecture note)
Airport terminal design (lecture note)Airport terminal design (lecture note)
Airport terminal design (lecture note)
Sarah Shuchi
 
Terminal Design
Terminal DesignTerminal Design
Terminal Design
Mal Mai
 
Airport planning and Design
Airport planning and DesignAirport planning and Design
Airport planning and Design
srinivas2036
 
Risk Management Framework
Risk Management FrameworkRisk Management Framework
Risk Management Framework
Anand Subramaniam
 

Viewers also liked (18)

HEATHROW AIRPORT GUIDE
HEATHROW AIRPORT GUIDEHEATHROW AIRPORT GUIDE
HEATHROW AIRPORT GUIDE
 
Heathrow Airport in Facts and Figures
Heathrow Airport in Facts and FiguresHeathrow Airport in Facts and Figures
Heathrow Airport in Facts and Figures
 
Risk management
Risk managementRisk management
Risk management
 
Take a look at some of our recent projects
Take a look at some of our recent projectsTake a look at some of our recent projects
Take a look at some of our recent projects
 
NEF – PI – FILE TEST 3 - READING
NEF – PI – FILE TEST 3 - READINGNEF – PI – FILE TEST 3 - READING
NEF – PI – FILE TEST 3 - READING
 
Lecture 7, 8, 9 and 10 Inter Process Communication (IPC) in Operating Systems
Lecture 7, 8, 9 and 10  Inter Process Communication (IPC) in Operating SystemsLecture 7, 8, 9 and 10  Inter Process Communication (IPC) in Operating Systems
Lecture 7, 8, 9 and 10 Inter Process Communication (IPC) in Operating Systems
 
Heathrow Terminal 5 - Success or Failure?
Heathrow Terminal 5 - Success or Failure?Heathrow Terminal 5 - Success or Failure?
Heathrow Terminal 5 - Success or Failure?
 
Producer Consumer Problem
Producer Consumer Problem  Producer Consumer Problem
Producer Consumer Problem
 
Dining Philosopher's Problem
Dining Philosopher's ProblemDining Philosopher's Problem
Dining Philosopher's Problem
 
Construction Risk Summit "benefit and pits of Construction Risk Management"
Construction Risk Summit   "benefit and pits of Construction Risk Management"Construction Risk Summit   "benefit and pits of Construction Risk Management"
Construction Risk Summit "benefit and pits of Construction Risk Management"
 
Heathrow airport Presentation by Ayisha Irshad
Heathrow airport Presentation by Ayisha IrshadHeathrow airport Presentation by Ayisha Irshad
Heathrow airport Presentation by Ayisha Irshad
 
Project Management Theory and Practice
Project Management Theory and Practice Project Management Theory and Practice
Project Management Theory and Practice
 
Pmbok 4th edition chapter 11 - Project Risk Management
Pmbok 4th edition   chapter 11 - Project Risk ManagementPmbok 4th edition   chapter 11 - Project Risk Management
Pmbok 4th edition chapter 11 - Project Risk Management
 
Ch7 OS
Ch7 OSCh7 OS
Ch7 OS
 
Airport terminal design (lecture note)
Airport terminal design (lecture note)Airport terminal design (lecture note)
Airport terminal design (lecture note)
 
Terminal Design
Terminal DesignTerminal Design
Terminal Design
 
Airport planning and Design
Airport planning and DesignAirport planning and Design
Airport planning and Design
 
Risk Management Framework
Risk Management FrameworkRisk Management Framework
Risk Management Framework
 

Similar to Heathrow Airport - Refurbishment of Terminal 1

Changing the Face at the Busiest Airport in the World th.docx
Changing the Face  at the Busiest Airport  in the World th.docxChanging the Face  at the Busiest Airport  in the World th.docx
Changing the Face at the Busiest Airport in the World th.docx
cravennichole326
 
Changing the Face at the Busiest Airport in the World thro.docx
Changing the Face at the Busiest Airport in the World thro.docxChanging the Face at the Busiest Airport in the World thro.docx
Changing the Face at the Busiest Airport in the World thro.docx
cravennichole326
 
Project management 250613
Project management 250613Project management 250613
Project management 250613
NMIMS ASSIGNMENTS HELP
 
Project management 250613
Project management 250613Project management 250613
Project management 250613
NMIMS ASSIGNMENTS HELP
 
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Controls Expo
 
Project management 250613
Project management 250613Project management 250613
Project management 250613
Pankaj Roy
 
Project management 250613
Project management 250613Project management 250613
Project management 250613
Pankaj Roy
 
M25 Media Pack
M25 Media PackM25 Media Pack
M25 Media Pack
Anthony Jones
 
road_map (1)
road_map (1)road_map (1)
road_map (1)
Stavros Thomas
 
Capital Programs - O'Hare 21
Capital Programs - O'Hare 21 Capital Programs - O'Hare 21
Capital Programs - O'Hare 21
Ausrine Rakauskaite
 
CV- Project Control Manager PMP
CV- Project Control Manager PMPCV- Project Control Manager PMP
CV- Project Control Manager PMP
Faheem Ijaz Janjua, PMP
 
PPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudevaPPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudeva
Narendra Vasudeva
 
CV-MEP-Ahmad Majdalawi
CV-MEP-Ahmad MajdalawiCV-MEP-Ahmad Majdalawi
CV-MEP-Ahmad Majdalawi
Ahmad Majdalawi
 
CV-MEP-Ahmad Majdalawi
CV-MEP-Ahmad MajdalawiCV-MEP-Ahmad Majdalawi
CV-MEP-Ahmad Majdalawi
Ahmad Majdalawi
 
Cv jason dixon dated 20160124
Cv jason dixon dated 20160124Cv jason dixon dated 20160124
Cv jason dixon dated 20160124
Jason Dixon
 
CHAPTER-1 INTRODUCTION.pdf
CHAPTER-1 INTRODUCTION.pdfCHAPTER-1 INTRODUCTION.pdf
CHAPTER-1 INTRODUCTION.pdf
Bereketgebreselassie3
 
The Construction Manager-General Contractor method for consctruction of trans...
The Construction Manager-General Contractor method for consctruction of trans...The Construction Manager-General Contractor method for consctruction of trans...
The Construction Manager-General Contractor method for consctruction of trans...
Angel Damian Rivera-Saez
 
Kcn 2016 March Resume
Kcn 2016 March ResumeKcn 2016 March Resume
Kcn 2016 March Resume
Kurt Nicholas
 
EMPLOYMENT HISTORY April 2015
EMPLOYMENT HISTORY April 2015EMPLOYMENT HISTORY April 2015
EMPLOYMENT HISTORY April 2015
Danny Buxton
 
1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx
1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx
1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx
MargaritoWhitt221
 

Similar to Heathrow Airport - Refurbishment of Terminal 1 (20)

Changing the Face at the Busiest Airport in the World th.docx
Changing the Face  at the Busiest Airport  in the World th.docxChanging the Face  at the Busiest Airport  in the World th.docx
Changing the Face at the Busiest Airport in the World th.docx
 
Changing the Face at the Busiest Airport in the World thro.docx
Changing the Face at the Busiest Airport in the World thro.docxChanging the Face at the Busiest Airport in the World thro.docx
Changing the Face at the Busiest Airport in the World thro.docx
 
Project management 250613
Project management 250613Project management 250613
Project management 250613
 
Project management 250613
Project management 250613Project management 250613
Project management 250613
 
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
 
Project management 250613
Project management 250613Project management 250613
Project management 250613
 
Project management 250613
Project management 250613Project management 250613
Project management 250613
 
M25 Media Pack
M25 Media PackM25 Media Pack
M25 Media Pack
 
road_map (1)
road_map (1)road_map (1)
road_map (1)
 
Capital Programs - O'Hare 21
Capital Programs - O'Hare 21 Capital Programs - O'Hare 21
Capital Programs - O'Hare 21
 
CV- Project Control Manager PMP
CV- Project Control Manager PMPCV- Project Control Manager PMP
CV- Project Control Manager PMP
 
PPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudevaPPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudeva
 
CV-MEP-Ahmad Majdalawi
CV-MEP-Ahmad MajdalawiCV-MEP-Ahmad Majdalawi
CV-MEP-Ahmad Majdalawi
 
CV-MEP-Ahmad Majdalawi
CV-MEP-Ahmad MajdalawiCV-MEP-Ahmad Majdalawi
CV-MEP-Ahmad Majdalawi
 
Cv jason dixon dated 20160124
Cv jason dixon dated 20160124Cv jason dixon dated 20160124
Cv jason dixon dated 20160124
 
CHAPTER-1 INTRODUCTION.pdf
CHAPTER-1 INTRODUCTION.pdfCHAPTER-1 INTRODUCTION.pdf
CHAPTER-1 INTRODUCTION.pdf
 
The Construction Manager-General Contractor method for consctruction of trans...
The Construction Manager-General Contractor method for consctruction of trans...The Construction Manager-General Contractor method for consctruction of trans...
The Construction Manager-General Contractor method for consctruction of trans...
 
Kcn 2016 March Resume
Kcn 2016 March ResumeKcn 2016 March Resume
Kcn 2016 March Resume
 
EMPLOYMENT HISTORY April 2015
EMPLOYMENT HISTORY April 2015EMPLOYMENT HISTORY April 2015
EMPLOYMENT HISTORY April 2015
 
1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx
1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx
1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx
 

Recently uploaded

Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
dsnow9802
 
Designing and Sustaining Large-Scale Value-Centered Agile Ecosystems (powered...
Designing and Sustaining Large-Scale Value-Centered Agile Ecosystems (powered...Designing and Sustaining Large-Scale Value-Centered Agile Ecosystems (powered...
Designing and Sustaining Large-Scale Value-Centered Agile Ecosystems (powered...
Alexey Krivitsky
 
Addiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdfAddiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdf
Bill641377
 
Chart--Time Management.pdf How to time is spent
Chart--Time Management.pdf How to time is spentChart--Time Management.pdf How to time is spent
Chart--Time Management.pdf How to time is spent
spandane
 
Team Building and TUCKMANS MODEL Explained
Team Building and TUCKMANS MODEL ExplainedTeam Building and TUCKMANS MODEL Explained
Team Building and TUCKMANS MODEL Explained
iampriyanshujaiswal
 
12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve
Pierre E. NEIS
 
Impact of Effective Performance Appraisal Systems on Employee Motivation and ...
Impact of Effective Performance Appraisal Systems on Employee Motivation and ...Impact of Effective Performance Appraisal Systems on Employee Motivation and ...
Impact of Effective Performance Appraisal Systems on Employee Motivation and ...
Dr. Nazrul Islam
 
innovation in nursing practice, education and management.pptx
innovation in nursing practice, education and management.pptxinnovation in nursing practice, education and management.pptx
innovation in nursing practice, education and management.pptx
TulsiDhidhi1
 
The Management Guide: From Projects to Portfolio
The Management Guide: From Projects to PortfolioThe Management Guide: From Projects to Portfolio
The Management Guide: From Projects to Portfolio
Ahmed AbdelMoneim
 
一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理
8p28uk6g
 
Stuart Wilson the teams I have led - 2024
Stuart Wilson the teams I have led - 2024Stuart Wilson the teams I have led - 2024
Stuart Wilson the teams I have led - 2024
stuwilson.co.uk
 
Conflict resololution,role of hr in resolution
Conflict resololution,role of hr in resolutionConflict resololution,role of hr in resolution
Conflict resololution,role of hr in resolution
Dr. Christine Ngari ,Ph.D (HRM)
 
All the Small Things - XP2024 Bolzano/Bozen
All the Small Things - XP2024 Bolzano/BozenAll the Small Things - XP2024 Bolzano/Bozen
All the Small Things - XP2024 Bolzano/Bozen
Alberto Brandolini
 
Ganpati Kumar Choudhary Indian Ethos PPT.pptx
Ganpati Kumar Choudhary Indian Ethos PPT.pptxGanpati Kumar Choudhary Indian Ethos PPT.pptx
Ganpati Kumar Choudhary Indian Ethos PPT.pptx
GanpatiKumarChoudhar
 

Recently uploaded (14)

Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
 
Designing and Sustaining Large-Scale Value-Centered Agile Ecosystems (powered...
Designing and Sustaining Large-Scale Value-Centered Agile Ecosystems (powered...Designing and Sustaining Large-Scale Value-Centered Agile Ecosystems (powered...
Designing and Sustaining Large-Scale Value-Centered Agile Ecosystems (powered...
 
Addiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdfAddiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdf
 
Chart--Time Management.pdf How to time is spent
Chart--Time Management.pdf How to time is spentChart--Time Management.pdf How to time is spent
Chart--Time Management.pdf How to time is spent
 
Team Building and TUCKMANS MODEL Explained
Team Building and TUCKMANS MODEL ExplainedTeam Building and TUCKMANS MODEL Explained
Team Building and TUCKMANS MODEL Explained
 
12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve
 
Impact of Effective Performance Appraisal Systems on Employee Motivation and ...
Impact of Effective Performance Appraisal Systems on Employee Motivation and ...Impact of Effective Performance Appraisal Systems on Employee Motivation and ...
Impact of Effective Performance Appraisal Systems on Employee Motivation and ...
 
innovation in nursing practice, education and management.pptx
innovation in nursing practice, education and management.pptxinnovation in nursing practice, education and management.pptx
innovation in nursing practice, education and management.pptx
 
The Management Guide: From Projects to Portfolio
The Management Guide: From Projects to PortfolioThe Management Guide: From Projects to Portfolio
The Management Guide: From Projects to Portfolio
 
一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理
 
Stuart Wilson the teams I have led - 2024
Stuart Wilson the teams I have led - 2024Stuart Wilson the teams I have led - 2024
Stuart Wilson the teams I have led - 2024
 
Conflict resololution,role of hr in resolution
Conflict resololution,role of hr in resolutionConflict resololution,role of hr in resolution
Conflict resololution,role of hr in resolution
 
All the Small Things - XP2024 Bolzano/Bozen
All the Small Things - XP2024 Bolzano/BozenAll the Small Things - XP2024 Bolzano/Bozen
All the Small Things - XP2024 Bolzano/Bozen
 
Ganpati Kumar Choudhary Indian Ethos PPT.pptx
Ganpati Kumar Choudhary Indian Ethos PPT.pptxGanpati Kumar Choudhary Indian Ethos PPT.pptx
Ganpati Kumar Choudhary Indian Ethos PPT.pptx
 

Heathrow Airport - Refurbishment of Terminal 1

  • 3. Contents  Introduction  Overview  Project Team  Challenges  Solutions  Conclusion  References Yash Mittal © 3
  • 4. Introduction  London Heathrow Airport is a major international airport in West London, England, United Kingdom.  Heathrow is the busiest airport in the United Kingdom and the busiest airport in Europe by passenger traffic.  It is also the third busiest airport in the world by total passenger traffic.  Heathrow lies 12 nautical miles or 22 kilometers west of Central London, and has two parallel east–west runways along with five terminals on a site that covers 12.14 square kilometers.  The airport is owned and operated by Heathrow Airport Holdings, formerly BAA, which is the United Kingdom-based operator of London Heathrow Airport.  Heathrow is the primary hub for British Airways and the primary operating base for Virgin Atlantic. Yash Mittal © 4
  • 5. Overview  BAA Airports Ltd. was tasked with the refurbishment of Terminal 1, a 40-year- old building within Heathrow Airport, whilst constantly keeping the terminal open to the 20 million annual travelers.  Terminal 1 had previously been for short-haul European destinations only, but the introduction of Star Alliance meant that international passengers would now also be using the terminal.  The successful completion of this project was the enabler for the complete transformation of Heathrow Airport that is used by more than 90 airlines, which fly to more than 180 destinations worldwide. Yash Mittal © 5
  • 6. Project Team  To oversee the whole project Heathrow Holdings Airport Ltd hired David Buisson, PMP to lead this major project.  David Buisson is a certified project manager with more than 13 years of experience of managing different projects.  Under his direction, a team of professionals, tackled one of the most important transport projects in the UK, keeping it ahead of its European competition.  Time management and communication were big issues that the Buisson project team had to face because of the scale and size of this project. • “A strong project management discipline brings exceptional value to the business, because when there is a demand for a product, we are the ones who deliver it,” Yash Mittal © 6
  • 7. Challenges  Regular meetings weekly and monthly with all suppliers.  Project manager dealt with the problems personally and quickly before moving on to good communication with large number of stakeholders.  Right balance of day and night work to cut costs and last minute changes had to be thought of.  Smart management of storage room.  An airtight area secured the asbestos roof work so there would be no leak during the removal work as well as no interruption for terminal operations. Yash Mittal © 7
  • 8. Challenges contd..  Electrical risk of shutting down to limited times at night with less operation poses a challenge.  Good risk management according to schedules and constant updates and reviews was needed.  IT management must be well organized.  Problems could therefore be passed on to the project manager very quickly due to good monitoring.  Improvements on energy saving and heating. Yash Mittal © 8
  • 9. Human Resources Management-The People  Management of different people and teams on this project was quite challenging because of its scale and size.  There were 11 top-tier suppliers who reported directly to the project manager, and dozens more who subsequently reported in to them, overall involving a very large number of workers.  Communications and time management would prove to be a challenge on a project involving this many different parties, especially because the project manager was keen to maintain a collaborative approach to problem solving. Yash Mittal © 9
  • 10. Human Resources Management-The Planning  The large number of third parties working on this project potentially could have had severe repercussions on scheduling.  If one contractor was late in finishing leveling the floor, this could delay the contractor that was scheduled to install the furniture, causing a larger knock- on effect throughout the project.  Clear mandate was issued to third party suppliers and contractors to follow a very specific framework of the project. Yash Mittal © 10
  • 11. Cost and Procurement Management- Budget changes  Budgetary reviews on the project meant that some major late changes were made on the project including some to the original plan with only four weeks to go.  The original design for the installation of a “cladding” system above the ticket desks for BMI Airlines that would improve both the aesthetics and lighting for the area was deleted from the scope of works just four weeks before the check-in desks were scheduled to open.  Upon learning of the decision, the project team was faced with an almost insurmountable task of finding an alternative solution that was acceptable to the various stakeholders and could also be procured and installed in less than four weeks. Yash Mittal © 11
  • 12. Scope Management-Structural Challenges  A big challenge for the team was repairing damaged floor work in the terminal that was left when the building was initially constructed 40 years earlier.  Repairing the floor potentially added an extra 21 weeks of work to the project.  The floor in the East Linear face of the terminal was discovered to have been constructed from different materials to the rest of the flooring in the terminal.  The floor was an uneven concrete surface instead of the regular terrazzo tiling, which to correct, would have added a significant amount of time to the refurbishment. Yash Mittal © 12
  • 13. Scope Management- Technological Challenges  Information Technology (IT) proved another challenge in the delivery of this project because the team had to replace existing systems within the terminal building.  This was a big challenge because it not only included standard office network systems, but also specialist flight systems such as Flight Information Display Screens, regulatory systems for passenger processing, and closed-circuit television. Yash Mittal © 13
  • 14. Scope Management- Environmental Challenges  Completing this project sustainably and installing sustainable and energy saving measures were an important component in the refurbishment project.  Given this was a renovation project and not the construction of a completely new building, installing truly sustainable features to save water for example, was very difficult in an old fashioned building. Yash Mittal © 14
  • 15. Communications Management  Communications was also a big challenge for the project because there were multiple high-level stakeholders involved who had to be consistently updated each time there was a risk identified or when there was a change to the schedule or budget. Yash Mittal © 15
  • 16. Risk Management- Asbestos risk  A big concern for the team that could potentially have been very damaging was discovering asbestos in the ceiling. A number of the ceiling tiles in Terminal 1 were damaged and needed to be replaced, therefore the asbestos needed to be removed safely. Bearing in mind that 20 million passengers pass through Terminal 1 every year, the problem could not simply be solved by erecting scaffolding in these areas, taking down the damaged tiles and replacing them, as this would create a health and safety risk to the passengers and staff of Terminal 1. The agreed plan was to construct an air- tight floor to ceiling area in the roof void around where the damaged ceiling tiles were and extract the asbestos accordingly by a suitably qualified asbestos removal contractor. Yash Mittal © 16
  • 17. Risk Management- Electrical risks  It was discovered that the East Linear check-in facility required the installation of a new distribution board to meet the greater electricity demand.  In installing a new distribution board the power to the entire terminal had to be temporarily turned off.  An added dimension to this was that the distribution board in question provided power to the Central Search Area where passengers were processed through BAA Security, which is the main route to their departing aircraft.  It was therefore critical that the project leaders got this process right otherwise the terminal would not be able to process passengers and may have to close down until power was restored. Yash Mittal © 17
  • 18. Solutions There were a number of difficulties that arose during the refurbishment of Terminal 1 and now we will examine the solutions for these challenges. Budgetary Scheduling Health and Safety Communications Yash Mittal © 18
  • 19. The People  A very clear mandate was issued to the plethora of third-party suppliers and contractors involved to ensure that they followed a very specific framework for the quality and design requirements of the project.  A competitive tender process was undertaken that ensured the best people got the job ensuring that maximum value was achieved and maximum knowledge was extracted from the range of skills and professions contributing to the project.  The main contractor was located in the same office as the project team which helped the to deliver most effectively.  Weekly and monthly meetings were held with all suppliers to address any grievances, problems, or issues.  Good communications and people management ensured that the project progressed smoothly. Yash Mittal © 19
  • 20. The Planning  The main project was further divided into small sub projects.  The individual contractors were strictly managed to ensure that each small project was delivered on time. Yash Mittal © 20
  • 21. Budget Changes  The cost estimating and budgeting efforts during the early stages of the project were very challenging and, in particular, getting the balance right in terms of work that would be undertaken at night versus those in the daytime hours.  Budgetary commitments meant that a number of last-minute changes were made to the project.  The project team and main contractor held a brainstorming session where one of the suggestions. Yash Mittal © 21
  • 22. Structural Challenges  Mending the floor whilst keeping to the project deadline was a challenge, given that other work was taking place simultaneously in the area.  To overcome this challenge, the project team met with the main contractor, terminal maintenance, and other contractors to discuss the issue of re- flooring this particular area and to develop a joint phasing plan to sequence the work and what areas would be protected for site storage of materials and tools.  Despite the prospect of a 21-week delay, the team still delivered on time. Yash Mittal © 22
  • 23. Technological Challenges  IT was an integral part of the Terminal 1 project because it allowed the project to be constantly monitored for problems by all parties involved.  The IT team at BAA developed custom software for the project that incorporated an “Online Change Control” system that allowed any members of the team based on- or offsite to capture changes and send them online to the senior project manager for instant approval or rejection.  It saved invaluable time on the project and meant that work could continue with less delay than would have been previously experienced. Yash Mittal © 23
  • 24. Environmental Challenges  BAA has a strong commitment to ethics in their Corporate Sustainability Programme, which is dedicated to improving design, construction, and integration and decommissioning.  Despite the challenges of updating a building from the 60s, the project team strove to incorporate sustainable changes to the lighting and heating.  Changes were made where possible including using energy saving bulbs throughout, and low-energy heating. Yash Mittal © 24
  • 25. The Risks-Asbestos Risk  In response to the asbestos risk, the project team, including the Health and Safety officer, main contractor, and terminal operations team, reviewed all of the potential options and risks and agreed that the solution was to create an airtight area within the contaminated roof void that would not leak into the airport.  A big part of developing a solution for the asbestos problem was assessing and implementing project risk management. Risk Management Schedules Strategic/Leadership Level Day-to-Day Risk Factors Yash Mittal © 25
  • 26. The Risks-Electrical Risk  Switching off all power to the old terminal building carried the heavy risk of the power not returning at all.  The project team therefore convened a high-level meeting with all relevant stakeholders and the main contractor to discuss the issues and formalize a plan with subsequent meetings.  The output and results of the various meetings and discussions were captured in a formal process guidance document including all relevant technical data associated with this work. Yash Mittal © 26
  • 27. The Risks-Continued  For every aspect of the project that involved any risk, risk schedules were reviewed, updated, and published through a formal review meeting held every month.  In addition, the main contractor undertook the same process of risk management for its respective activities along with its key suppliers.  Through this process, the top three risks identified in the risk schedule were escalated to the project board every month for elevation within the relevant business unit. Yash Mittal © 27
  • 28. Conclusion  Heathrow Airport Terminal 1 was completed on time in September 2008. The project involved more than 500,000 working hours and kept within its £57.6 million budget.  The project delivered on time and within budget despite the numerous problems that arose, especially the unexpected extra work that could have caused major delays to the project delivery.  The project had a good health and safety record with no reported incidents, despite dealing with serious hazards like asbestos.  There was effective team work between the numerous contractors, suppliers, stakeholders, and various support functions.  All challenges were successfully met by the project team including £6.3m of unexpected out-of-scope work that was engineered into the final solution without an increase to the approved project budget. Yash Mittal © 28
  • 29. £6.3million worth of additional work was added without an increase to the original project budget Yash Mittal © 29
  • 30. References  www.heathrowairport.com  www.prezi.com/j_ts1rkrrkvs/refurbishment-of-heathrow-airport-terminal- 1/  www.pmi.org/.../~/.../Heathrow_Airport_Case_Study_New.ashx  http://www.academia.edu/9699398/HEATHROW_AIRPORT_TERMINAL_1_RISK_ MANAGEMENT_PLAN  http://www.airport-world.com/item/1536-reinventing-heathrow Yash Mittal © 30