SlideShare a Scribd company logo
1 of 6
Download to read offline
Debniloy De et al Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 4, Issue 4( Version 2), April 2014, pp.39-44
www.ijera.com 39 | P a g e
Optimum Overcurrent Relay Coordination of a Power Grid
Sheila Mahapatra*, Debniloy De**, Shivanjali A. Mishra***,Aditya Kar****
*(Department of Electrical, Electronics and Communication Engineering, ITM University, Haryana-122017)
** (Department of Electrical, Electronics and Communication Engineering, ITM University, Haryana-122017)
*** (Department of Electrical, Electronics and Communication Engineering, ITM University, Haryana-122017)
**** (Department of Electrical, Electronics and Communication Engineering, ITM University, Haryana-
122017)
ABSTRACT
Protective system plays a pivotal role in any power system operation. In a typical power system there are large
numbers of circuit breakers and relays installed which constitute an integral part of the protective scheme. Relay
is a device that senses and locates the fault and sends a command to the circuit breaker to disconnect the faulty
element. Relay coordination is done to provide primary as well as back up protection from any fault that is
likely to occur in the system. In this paper, overcurrent relay coordination is implemented on a 72 bus 220 KV
substation. Load flow studies and the short circuit analysis on the test system is initially done followed by relay
coordination. Fault current data obtained from short circuit studies enables us to obtain operating time of the
relays used in the test system. The simulated value of operating time provides the coordinated operation of all
the relays connected from 220kV to 33kV line thereby protecting the equipment of the test system.
Keywords-PSM (Plug Setting Multiplier), Relay coordination, Three phase to ground fault, TMS (Time
Multiplier Settings)
I. INTRODUCTION
Protection system does the function of
detecting the faults and clearing the fault as quickly
as possible. Protection system includes circuit
breakers, relays, current transformer, potential
transformers and transducers. A protective relay is
one of the most important part of a power system
network and it is necessary to coordinate them
properly so that the customers can get undisturbed
supply. Over current relay coordination can be done
with utmost accuracy and tolerance using the
MiPower software. MiPower software is very
interactive and has user friendly windows based
power system analysis package. Load flow studies
and short circuit analysis is done using the same
software and the results of these analysis are used to
have an optimal coordination of the relays. The
protective devices are installed to protect the system
from any fault that is likely to occur. The quantities
that may change due to occurrence of fault are
current, voltage, phase angle and frequency. A power
system is mainly divided into a number of protective
zones so that no part of the system is left unprotected.
The protective devices in each zone isolate the faulty
part from the healthy part as soon as possible to avoid
further damage to equipment .If the fault is not
cleared, then the system voltage will reduce and the
generators will lose synchronism. Several methods
are there to provide relay coordination. One such
method is linear programming which is used to
optimize the time multiplier setting of the relays [1].
Another method is to apply linear programming
technique to minimize the operating time [2].
Therefore relay coordination is the most important
part of a protective system design.
II. Case study: 220 kv Masudpur
substation
Relay coordination is done on 220 KV
Masudpur Substation. This substation is located in
Hisar, Haryana. It is a 72 bus system receiving an
incoming of 220 KV double circuit line and delivers
two 220 KV double circuit line to 400 KV Kirori
Substation and Samain Substation respectively. It has
two step down transformers of 220/132 KV and
220/33KV which steps down the 220KV to 132KV
and 33KV respectively. In total there are 23 breakers
and 66 isolators. There are 4 loads in the system
which sums up to 12.41 MW.132KV subsystem and
capacitor banks are currently not in use in the
existing substation operation.Fig.1 shows the
pictorial view of the 220Kv Masudpur substation.
From the Fig.1 we can see that there are three
different voltage levels i.e. 220Kv, 132Kv, 33Kv in
this substation. For 220 Kv and 33 Kv voltages level,
main bus-1 is working. All the outgoing feeders are
connected are 33Kv voltage level.
RESEARCH ARTICLE OPEN ACCESS
Debniloy De et al Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 4, Issue 4( Version 2), April 2014, pp.39-44
www.ijera.com 40 | P a g e
Fig.1:220 kv Masudpur Substation, Hisar, Haryana
III. System Data
1.Bus Data
Table 1: Bus voltages
Bus Number Bus(KV)
1,2,3,4,5,6,7,8,9,10,11,12,13,14,15,1
6,17,18,19,20,21,22,23,24,27,38
220
25, 26, 28, 29, 30, 31, 32, 33, 34, 35,
36, 37
132
39, 40, 41, 42, 43, 44, 45, 46, 47, 48,
49, 50, 51, 52, 53, 53, 54, 55, 56, 57,
58, 59, 60, 61, 62, 63, 64, 65, 66, 67,
68, 69, 74
33
72,73 0.4
2.Transformer Data
Table 2: Transformer Ratings
Fro
m
To POSITIVE ZERO
Bus
Na
me
Bus
Name
R(P.U)
TAP
X(P.U)
PHASE
R(P.U)
FB-
MVA
X(P.U)
TB-
MVA
27 28 0.00501
1.00000
0.10027
0.000
0.00501
10000
0.10027
5000
38 39 0.00501
1.00000
0.10027
0.000
0.00501
10000
0.10027
1500
53 72 0.00294
1.05000
0.05883
0.000
0.00294
1500
0.05883
0
52 73 0.00294
1.05000
0.05883
0.000
0.00294
1500
0.05883
0
3.Load Data
Table 3: Loads connected to 33Kv Bays
Bus
Number
Real Power
(MW)
Reactive Power
(MVAR)
55 1.61 1.04
65 4.59 0
66 1.81 1.22
67 4.4 3.07
IV. Implementation: Simulation And
Results
1.Load Flow Studies
Load flow studies forms the basis for any
further analysis done in power system. This gives an
idea to power engineers about the actual power flows
both real and reactive power taking place in the
system. Load flow analysis is important for planning
future expansions of the power system networks and
determining the best operation of the existing
equipment. Load flow study gives the optimal value
of the voltage and the real and reactive power
flowing in the line. The load flow study helps to
minimize the transmission line losses and also
reduces the cost of generation. Fig 2 shows load flow
simulation circuit of 220 KV Masudpur substation. It
can be seen from the Fig.2 that system is under
loaded as the real and reactive power flows are
indicated in green. The software indicates the power
flows in blue under normal loading condition and in
red for overloaded condition. The simulation is
carried on the test system to give the load flow data
as follows:
Table 4: Load Flow Results
Table 4 shows the real power (MW) generation, MW
loss and MW load. It also shows the reactive power
(MVAR) generation, MVAR loss and MVAR load.
Fig.2: load flow simulation circuit of 220 kv
Masudpur substation
2.Short Circuit Analysis
Prior to relay coordination, we consider
short circuit studies which help us to know fault
current, fault MVA and suitable develops a
protection scheme for the grid. Devices like
Generators, Transformers and Motors which are
integral part of the power system should have their
rating which exceeds the maximum fault current level
and fault MVA value. So short circuit studies helps
MW generation 12.4312
MVAR generation 5.525
MW load 12.41
MVAR load 5.3725
MW loss 0.212
MVAR loss 0.1975
Debniloy De et al Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 4, Issue 4( Version 2), April 2014, pp.39-44
www.ijera.com 41 | P a g e
us to get values of fault current, fault MVA which
helps us in designing proper protection scheme. The
huge fault current causes an extreme damage to the
equipment if suitable protective scheme is not
incorporated in the power system. Short circuits are
generally caused by insulation failures or conducting
path failures. Short circuits on the transmission and
the distribution lines are caused by over voltages due
to lightning or switching surges. Faults can be
classified as series and shunt faults. Series faults are
also known as symmetrical faults. Three phase to
ground fault comes under symmetrical faults and they
are the most severe fault. They occur rarely in the
power system. Shunt faults are also known as
unsymmetrical faults and they are very common in
the power system. There are three types of
unsymmetrical faults. They are single line to ground
(SLG), line to line fault (LL), double line to ground
fault (LLG). In this paper, three phase to ground fault
has been performed as it forms a basis for the
selection of the circuit breakers, relays and also of
instrument transformers. Three phase to ground fault
analysis is done on bus 65 and the following fault
current, fault MVA and the post fault voltages are
obtained.
Table 5: Fault Current (Amp/deg) at Bus 65
Sequence(1,2,0) Phase (A,B,C)
Mag Ang Mag Ang
14310 -82.47 14310 -82.47
0 -90.00 14310 157.53
0 -90.00 14310 37.53
R/X Ratio of the short circuit path =0.1321
Peak Asymmetrical short circuit current* = 34694
Amps
*pascc = k X sqrt(2) X If , k=1.7144
Table 6: Fault contribution from shunt connection
BUS
NAME
CURRENT (AMPS/DEFREE) MVA
SEQUENCE
(1,2,0)
PHASE
(A,B,C)
PHASE
(A,B,C)
Mag Ang Mag Ang MAG
19 2146 97.53 2146 97.53 818
0 -90.00 2146 -22.47 818
0 -90.00 2146 -
142.47
818
55,65,
66,67
0 -90.00 0 -90.00 0
0 -90.00 0 -90.00 0
0 -90.00 0 -90.00 0
Table 7: Three phase fault level
BUS NAME BUS kV
NOMIN
AL
3PH-
fMVA
FAULT I
kA
1,3,6,7,8,9,10,
11,12,13,14,16
,17,18,19,21,2
2,23,24,27,38
220.000 0.3 0.001
2,4,14,20 220.000 0.4 0.001
25,26,30,31,32
,33,34,35,36,3
7
132.000 0.2 0.001
39,40,41,42,43
,44,45,46,47,4
8,49,50,51,52,
53,54,55,56,57
,58,59,60,61,6
2,63,64,66,67,
68,69,74
33.000 0.0 0.000
65 33.000 817.9 14.310
72,73 0.400 0.0 0.000
Table 8: Fault MVA at bus 65
FAULT MVA
SEQUENCE (1,2,0) PHASE (A,B,C)
MAGNITUDE MAGNITUDE
818 818
0 818
0 818
Table 9(a): Post fault voltages after creating fault at
bus 65
Post Fault Voltages
Bus
Name
Sequence
Current
(1,2,0)
Phase (A,B,C)
Line-
Line
Mag
V Ang V Ang
Pu on
L-L
base
1,3,5,7,8,
9,10,11,1
5,16,17,1
8,21,22,2
3,24,27,2
8,29
0.88 1.14 0.88 1.14 0.88
0 -90 0.88 -118.86 0.88
0 -90 0.88 121.14 0.88
Debniloy De et al Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 4, Issue 4( Version 2), April 2014, pp.39-44
www.ijera.com 42 | P a g e
Table 9(b): Post fault voltages after creating fault at
bus 65
Bus Name Sequence
Current
(1,2,0)
Phase (A,B,C)
Line-
Line
Mag
V Ang V Ang
Pu on
L-L
base
2,4,14,20,
25,26,30,3
1,32,33,34
,35,36,37
1 0 1 0 1
0 -90 1 -120 1
0 -90 1 120 1
Table 9(c): Post fault voltages after creating fault at
bus 65
Bus Name Sequence
Current
(1,2,0)
Phase (A,B,C) Line-
Line
Mag
V Ang V Angle
Pu on
L-L
base
Bus 65 0 -90 0 -90 0
0 -90 0 150 0
0 -90 0 30 0
Fig.3: Three phase fault created at bus 65
Fig.4: Waveform of Three phase symmetrical fault at
bus 65
Fig.4 shows the phase A fault current at bus
65 when a three phase to ground fault is applied at
bus 65.This graph shows the superimposition of dc
offset current with the ac current to give the total
asymmetrical (ac+dc) current.
3. Relay Coordination
When a fault occurs it may cause heavy
damage to the power system and the equipment.
Therefore, a suitable protective device is needed to
protect the system from any damage. The protective
device should be selective enough to distinguish
between normal condition and faulty condition. One
such protective device is the relay. A relay senses the
fault and sends a signal to the circuit breaker to trip.
There is a primary relay installed in every zone of the
system to protect the system. After the occurrence of
fault, the primary relay senses the fault and locates
the fault. The primary relay sends the alarm to the
circuit breaker and the circuit breaker trips. If the
primary relay fails to operate then there is a backup
relay to clear the fault. Relay coordination is done to
check if the relay is fast enough or reliable enough to
detect the fault at the proper time and send the signal
to the auxiliary devices. Relays can be classified into
different types. One such type is the over current
relay. For over current protection different types of
relays are used like electromagnet relay, induction
disc type relay and static relay. The over current relay
shows the relation between relay operating time in
terms of TMS (Time Multiplier Setting) and
actuating current in terms of PMS(Plug
SettingMultiplier). The core of the relay is made to
saturate for a given actuating current. The minimum
time for relay to operate is the current setting or
settling time. Relay shall not operate at a time less
than the settling time. The settling time depends on
X/R ratio between fault location and source and the
ratio of the impedance between fault and source and
the impedance of zone. The relay co-ordination study
of an electric power system consists of an organized
Debniloy De et al Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 4, Issue 4( Version 2), April 2014, pp.39-44
www.ijera.com 43 | P a g e
time-current study of all devices in series from
utilization device to source. It is a study of organized
time – current of all the equipment connected from
the load to source. The main motive of this study is to
determine the ratings of the over current protective
devices which will see that the minimum portion of
the system is effected when the protective devices
removes a fault in the system. On other hand, it must
provide protection to the equipment and remove short
circuit conditions as quickly as possible.
Coordination ensures that protective relays work
properly to provide safe and reliable protection.In
220KV Masudpur substation, ABB manufactured
REF 615 relay is used.REF615 relays are generally
used for feeder protection. IECN curve type is used
for all relay calculation. Operating time of any relay
depends on three factors i.e. TMS, Fault current and
plug setting. Different relays used and their
respective TMS and plug settings are as follows:
Table 10: Relay Settings
Sn
no.
CT
ratio
Overcurrent setting Earth fault setting
Pl
ug
Se
t
in
%
Ip
>
TMS
(Tp>
sec)
Ins Set
( Ip >>
in %
&Tp>>
in sec)
Pl
ug
Se
t
in
%
Ie
>
TMS
(Te>
Sec)
Ins
Set
( Ie>>
in %
&Te>
> in
sec)
R1
-
R4
300
/ 5
10
0
0.15
Ip >>
500
&Tp>>
0
20 0.15
Ie>>
200&
Te>>
0
R5
-
R6
400
/ 5
10
0
0.05
Ip >>
500
&Tp>>
0
20 0.05
Ie>>
200
&Te>
>0
R7
200
0 / 5
10
0
0.2 Dis 20 0.2 Dis
R8
200
0 / 5
10
0
0.2 Dis 20 0.2 Dis
R9
300
/ 1
10
0
0.25
Ip >>
850
&Tp>>
0
Di
s
0 Dis
R1
0-
R1
6
120
0 / 1
10
0
0.3 Dis 20 0.3 Dis
R1
7
500
/ 1
10
0
0.25 Dis 20 0.25 Dis
R1
-
R2
0
600/
1
10
0
0.2 Dis 20 0.2 Dis
Overcurrent relay coordination studies done at bus 65
gives the following results:
Table 11: 3 Phase to ground fault is created at bus
Bus65
Table 11 shows the operating time of the
relays when a three phase to ground fault occurs at
bus 65. Relay R2 acts instantaneously after the
occurrence of fault. This can also be seen from Fig.5
which shows the overcurrent graphs of relays used in
the test system. The relay R2 is provided with
instantaneous settings as it is present closest to the
feeder bus 65. It acts as a primary defense to any
fault occurring at bus 65. If this relay fails to operate
then the remaining relays R8, R9 and R15 will act
according to their respective operating time.
Fig.5: Relay coordination graph at bus 65
V. Conclusions
This paper presents the load flow studies,
short circuit analysis and relay coordination of a 220
Kv Masudpur substation. Load flow studies show the
proper power flow in the power system. It also shows
that system is under loaded with 132 KV subsystem
being non-operative. Short circuit studies is done on
bus 65 which gives fault current of 14310 Amperes
and fault MVA of 818. Fault current obtained is
thereby utilized to determine the operating time for
all the four relays connected between 220kV and 33
kV line such that their operation is properly
coordinated. This ensures system protection scheme
is adequate under existing working condition.
Relay name Phase a fault current Operating
time
R2 14309 Inst(0.00)
R8 14309 0.7021
R9 2146 0.8776
R15 2146 3.5638
Debniloy De et al Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 4, Issue 4( Version 2), April 2014, pp.39-44
www.ijera.com 44 | P a g e
References
[1] N.A. Laway, H.O. Gupta, "A Method for
Coordination of Overcurrent Relays in
Interconnected Power System", IEJ, vol.
74(1993), pp. 59-65
[2] B.Chattopadhyay, et al "An on-line Relay
Coordination Algorithm for Adaptive
Protection Using Linear Programming
Technique", IEEE Trans. on Power
Delivery, vol. 11 (1996), no. 1, pp. 165-173
[3] ShimpyRalhan, ShashwatiRay,”Optimal
Coordination of Directional Overcurrent
Relays using Interval Two Phase Simplex
Linear Programming”,International Journal
of Advanced Computer Research, Volume-3
Number-3 Issue-11 September-2013
[4] D.Vijayakumar and R. K. Nema,”
Simplified Velocity MPSO for Directional
Over Current Relay Coordination”,
International Journal of Recent Trends in
Engineering, Vol 1, No. 3, May 2009
[5] Dharmendra Kumar Singh, Dr. S.
Gupta,”Protection Of Power System By
Optimal Co-ordination of Directional
Overcurrent Relays Using Genetic
Algorithm”,International Journal of Modern
Engineering Research, Vol.2, Issue.1, Jan-
Feb 2012
[6] Dinesh Birla, RudraPrakashMaheshwari,
and H. O. Gupta, “A New Nonlinear
Directional Overcurrent Relay Coordination
Technique, and Banes and Boons of Near-
End Faults Based Approach “, IEEE
TRANSACTIONS ON POWER DELIVERY,
VOL. 21, NO. 3, JULY 2006
[7] Vipul N Rajput, Rashesh P. Mehta,
Bhuvanesh A. Oza,” Coordination of
Overcurrent Relays for Industrial Radial
System”, National Conference on Recent
Trends in Engineering & Technology
[8] JavedSadeh, “Optimal Coordination of
Overcurrent Relays in an interconnected
power system”, 15th
PSCC Liege, section
19(2005).

More Related Content

What's hot

Three zone detection and distance relay co-ordination of power system protect...
Three zone detection and distance relay co-ordination of power system protect...Three zone detection and distance relay co-ordination of power system protect...
Three zone detection and distance relay co-ordination of power system protect...IJECEIAES
 
distribution system fault mangement
distribution system fault mangementdistribution system fault mangement
distribution system fault mangementManjunath Ds
 
Open switch fault diagnosis in three phase inverter using diagnostic variable...
Open switch fault diagnosis in three phase inverter using diagnostic variable...Open switch fault diagnosis in three phase inverter using diagnostic variable...
Open switch fault diagnosis in three phase inverter using diagnostic variable...eSAT Journals
 
DC_RING-BUS_MICROGRID_FAULT_PROTECTION
DC_RING-BUS_MICROGRID_FAULT_PROTECTIONDC_RING-BUS_MICROGRID_FAULT_PROTECTION
DC_RING-BUS_MICROGRID_FAULT_PROTECTIONVignesh M
 
Fault protection of a loop type low voltage dc bus based microgrids
Fault protection of a loop type low voltage dc bus based microgridsFault protection of a loop type low voltage dc bus based microgrids
Fault protection of a loop type low voltage dc bus based microgridsIAEME Publication
 
Detection of Power Grid Synchronization Failure on Sensing Frequency and Volt...
Detection of Power Grid Synchronization Failure on Sensing Frequency and Volt...Detection of Power Grid Synchronization Failure on Sensing Frequency and Volt...
Detection of Power Grid Synchronization Failure on Sensing Frequency and Volt...IRJET Journal
 
EEE 321( Power System Analysis and Principle of Power System and Power syste...
EEE 321( Power System Analysis and Principle of Power System and  Power syste...EEE 321( Power System Analysis and Principle of Power System and  Power syste...
EEE 321( Power System Analysis and Principle of Power System and Power syste...UthsoNandy
 
wireless fault protection and detection for dc microgrid
wireless fault protection and detection for dc microgrid wireless fault protection and detection for dc microgrid
wireless fault protection and detection for dc microgrid MAHESH M
 
Impact of LCC–HVDC multiterminal on generator rotor angle stability
Impact of LCC–HVDC multiterminal on generator rotor  angle stability  Impact of LCC–HVDC multiterminal on generator rotor  angle stability
Impact of LCC–HVDC multiterminal on generator rotor angle stability IJECEIAES
 
Detection and analysis of power quality disturbances under faulty conditions ...
Detection and analysis of power quality disturbances under faulty conditions ...Detection and analysis of power quality disturbances under faulty conditions ...
Detection and analysis of power quality disturbances under faulty conditions ...IAEME Publication
 
EHVAC transmission line maintenance techniques
EHVAC transmission line maintenance techniquesEHVAC transmission line maintenance techniques
EHVAC transmission line maintenance techniquesYashwant Chaudhari
 
MRA Analysis for Faults Indentification in Multilevel Inverter
MRA Analysis for Faults Indentification in Multilevel InverterMRA Analysis for Faults Indentification in Multilevel Inverter
MRA Analysis for Faults Indentification in Multilevel InverterIRJET Journal
 

What's hot (20)

Three zone detection and distance relay co-ordination of power system protect...
Three zone detection and distance relay co-ordination of power system protect...Three zone detection and distance relay co-ordination of power system protect...
Three zone detection and distance relay co-ordination of power system protect...
 
distribution system fault mangement
distribution system fault mangementdistribution system fault mangement
distribution system fault mangement
 
ISLANDING DETECTION TECHNIQUE FOR DISTRIBUTED GENERATION SYSTEM
ISLANDING DETECTION TECHNIQUE FOR DISTRIBUTED GENERATION SYSTEMISLANDING DETECTION TECHNIQUE FOR DISTRIBUTED GENERATION SYSTEM
ISLANDING DETECTION TECHNIQUE FOR DISTRIBUTED GENERATION SYSTEM
 
Open switch fault diagnosis in three phase inverter using diagnostic variable...
Open switch fault diagnosis in three phase inverter using diagnostic variable...Open switch fault diagnosis in three phase inverter using diagnostic variable...
Open switch fault diagnosis in three phase inverter using diagnostic variable...
 
DC_RING-BUS_MICROGRID_FAULT_PROTECTION
DC_RING-BUS_MICROGRID_FAULT_PROTECTIONDC_RING-BUS_MICROGRID_FAULT_PROTECTION
DC_RING-BUS_MICROGRID_FAULT_PROTECTION
 
Microgrid Protection
Microgrid ProtectionMicrogrid Protection
Microgrid Protection
 
Fault protection of a loop type low voltage dc bus based microgrids
Fault protection of a loop type low voltage dc bus based microgridsFault protection of a loop type low voltage dc bus based microgrids
Fault protection of a loop type low voltage dc bus based microgrids
 
Detection of Power Grid Synchronization Failure on Sensing Frequency and Volt...
Detection of Power Grid Synchronization Failure on Sensing Frequency and Volt...Detection of Power Grid Synchronization Failure on Sensing Frequency and Volt...
Detection of Power Grid Synchronization Failure on Sensing Frequency and Volt...
 
EEE 321( Power System Analysis and Principle of Power System and Power syste...
EEE 321( Power System Analysis and Principle of Power System and  Power syste...EEE 321( Power System Analysis and Principle of Power System and  Power syste...
EEE 321( Power System Analysis and Principle of Power System and Power syste...
 
fault
faultfault
fault
 
Fault location techniques in smart distribution system
Fault location techniques in smart distribution systemFault location techniques in smart distribution system
Fault location techniques in smart distribution system
 
wireless fault protection and detection for dc microgrid
wireless fault protection and detection for dc microgrid wireless fault protection and detection for dc microgrid
wireless fault protection and detection for dc microgrid
 
Impact of LCC–HVDC multiterminal on generator rotor angle stability
Impact of LCC–HVDC multiterminal on generator rotor  angle stability  Impact of LCC–HVDC multiterminal on generator rotor  angle stability
Impact of LCC–HVDC multiterminal on generator rotor angle stability
 
Droop control approach for power sharing in AC microgrid
Droop control approach for power sharing in AC microgrid Droop control approach for power sharing in AC microgrid
Droop control approach for power sharing in AC microgrid
 
Ppt iitr
Ppt iitrPpt iitr
Ppt iitr
 
Detection and analysis of power quality disturbances under faulty conditions ...
Detection and analysis of power quality disturbances under faulty conditions ...Detection and analysis of power quality disturbances under faulty conditions ...
Detection and analysis of power quality disturbances under faulty conditions ...
 
Modeling and design of an adaptive control for VSC-HVDC system under paramete...
Modeling and design of an adaptive control for VSC-HVDC system under paramete...Modeling and design of an adaptive control for VSC-HVDC system under paramete...
Modeling and design of an adaptive control for VSC-HVDC system under paramete...
 
Wide area monitoring, protection and control in future smart grid
Wide area monitoring, protection and control in future smart gridWide area monitoring, protection and control in future smart grid
Wide area monitoring, protection and control in future smart grid
 
EHVAC transmission line maintenance techniques
EHVAC transmission line maintenance techniquesEHVAC transmission line maintenance techniques
EHVAC transmission line maintenance techniques
 
MRA Analysis for Faults Indentification in Multilevel Inverter
MRA Analysis for Faults Indentification in Multilevel InverterMRA Analysis for Faults Indentification in Multilevel Inverter
MRA Analysis for Faults Indentification in Multilevel Inverter
 

Viewers also liked

Early Detection of Lung Cancer Using Neural Network Techniques
Early Detection of Lung Cancer Using Neural Network TechniquesEarly Detection of Lung Cancer Using Neural Network Techniques
Early Detection of Lung Cancer Using Neural Network TechniquesIJERA Editor
 
The Development of Financial Information System and Business Intelligence Usi...
The Development of Financial Information System and Business Intelligence Usi...The Development of Financial Information System and Business Intelligence Usi...
The Development of Financial Information System and Business Intelligence Usi...IJERA Editor
 
An Overview on Authentication Approaches and Their Usability in Conjunction w...
An Overview on Authentication Approaches and Their Usability in Conjunction w...An Overview on Authentication Approaches and Their Usability in Conjunction w...
An Overview on Authentication Approaches and Their Usability in Conjunction w...IJERA Editor
 
Size and Time Estimation in Goal Graph Using Use Case Points (UCP): A Survey
Size and Time Estimation in Goal Graph Using Use Case Points (UCP): A SurveySize and Time Estimation in Goal Graph Using Use Case Points (UCP): A Survey
Size and Time Estimation in Goal Graph Using Use Case Points (UCP): A SurveyIJERA Editor
 
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow Management
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow ManagementA Multi-Objective Fuzzy Linear Programming Model for Cash Flow Management
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow ManagementIJERA Editor
 
Advanced Design of Composite Steel-Concrete Structural element
Advanced Design of Composite Steel-Concrete Structural elementAdvanced Design of Composite Steel-Concrete Structural element
Advanced Design of Composite Steel-Concrete Structural elementIJERA Editor
 

Viewers also liked (20)

G044023238
G044023238G044023238
G044023238
 
K44085861
K44085861K44085861
K44085861
 
E44082429
E44082429E44082429
E44082429
 
I0444751
I0444751I0444751
I0444751
 
F044043741
F044043741F044043741
F044043741
 
O0447796
O0447796O0447796
O0447796
 
G044063437
G044063437G044063437
G044063437
 
J44094650
J44094650J44094650
J44094650
 
H044045054
H044045054H044045054
H044045054
 
F44092630
F44092630F44092630
F44092630
 
L044026068
L044026068L044026068
L044026068
 
L044047379
L044047379L044047379
L044047379
 
Early Detection of Lung Cancer Using Neural Network Techniques
Early Detection of Lung Cancer Using Neural Network TechniquesEarly Detection of Lung Cancer Using Neural Network Techniques
Early Detection of Lung Cancer Using Neural Network Techniques
 
The Development of Financial Information System and Business Intelligence Usi...
The Development of Financial Information System and Business Intelligence Usi...The Development of Financial Information System and Business Intelligence Usi...
The Development of Financial Information System and Business Intelligence Usi...
 
J0460455055
J0460455055J0460455055
J0460455055
 
An Overview on Authentication Approaches and Their Usability in Conjunction w...
An Overview on Authentication Approaches and Their Usability in Conjunction w...An Overview on Authentication Approaches and Their Usability in Conjunction w...
An Overview on Authentication Approaches and Their Usability in Conjunction w...
 
Size and Time Estimation in Goal Graph Using Use Case Points (UCP): A Survey
Size and Time Estimation in Goal Graph Using Use Case Points (UCP): A SurveySize and Time Estimation in Goal Graph Using Use Case Points (UCP): A Survey
Size and Time Estimation in Goal Graph Using Use Case Points (UCP): A Survey
 
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow Management
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow ManagementA Multi-Objective Fuzzy Linear Programming Model for Cash Flow Management
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow Management
 
Advanced Design of Composite Steel-Concrete Structural element
Advanced Design of Composite Steel-Concrete Structural elementAdvanced Design of Composite Steel-Concrete Structural element
Advanced Design of Composite Steel-Concrete Structural element
 
UC AMA preso, 5 11
UC AMA preso, 5 11UC AMA preso, 5 11
UC AMA preso, 5 11
 

Similar to H044023944

Synchrophasor Based Ocillation Detection: A Case Study for Indian Power Grid
Synchrophasor Based Ocillation Detection: A Case Study for Indian Power GridSynchrophasor Based Ocillation Detection: A Case Study for Indian Power Grid
Synchrophasor Based Ocillation Detection: A Case Study for Indian Power GridPower System Operation
 
Distribution Network Power Quality Improvement by D-STATCOM & DVR Under Vario...
Distribution Network Power Quality Improvement by D-STATCOM & DVR Under Vario...Distribution Network Power Quality Improvement by D-STATCOM & DVR Under Vario...
Distribution Network Power Quality Improvement by D-STATCOM & DVR Under Vario...IRJET Journal
 
SRF CONTROLLED DVR FOR COMPENSATION OF BALANCED AND UNBALANCED VOLTAGE DISTUR...
SRF CONTROLLED DVR FOR COMPENSATION OF BALANCED AND UNBALANCED VOLTAGE DISTUR...SRF CONTROLLED DVR FOR COMPENSATION OF BALANCED AND UNBALANCED VOLTAGE DISTUR...
SRF CONTROLLED DVR FOR COMPENSATION OF BALANCED AND UNBALANCED VOLTAGE DISTUR...IAEME Publication
 
DESIGN AND DEVELOPMENT OF SMES BASED DVR MODEL IN SIMULINK
DESIGN AND DEVELOPMENT OF SMES BASED DVR MODEL IN SIMULINKDESIGN AND DEVELOPMENT OF SMES BASED DVR MODEL IN SIMULINK
DESIGN AND DEVELOPMENT OF SMES BASED DVR MODEL IN SIMULINKpaperpublications3
 
Compensation of Balanced and Unbalanced Voltage Disturbance using SRF Control...
Compensation of Balanced and Unbalanced Voltage Disturbance using SRF Control...Compensation of Balanced and Unbalanced Voltage Disturbance using SRF Control...
Compensation of Balanced and Unbalanced Voltage Disturbance using SRF Control...IRJET Journal
 
Fuzzy-Logic-Controller-Based Fault Isolation in PWM VSI for Vector Controlled...
Fuzzy-Logic-Controller-Based Fault Isolation in PWM VSI for Vector Controlled...Fuzzy-Logic-Controller-Based Fault Isolation in PWM VSI for Vector Controlled...
Fuzzy-Logic-Controller-Based Fault Isolation in PWM VSI for Vector Controlled...iosrjce
 
Analysis of Total Harmonic Distortion (THD) Level of Distribution Network Usi...
Analysis of Total Harmonic Distortion (THD) Level of Distribution Network Usi...Analysis of Total Harmonic Distortion (THD) Level of Distribution Network Usi...
Analysis of Total Harmonic Distortion (THD) Level of Distribution Network Usi...IJERA Editor
 
IRJET- Overhead Line Protection with Automatic Switch by using PLC Automation
IRJET- Overhead Line Protection with Automatic Switch by using PLC AutomationIRJET- Overhead Line Protection with Automatic Switch by using PLC Automation
IRJET- Overhead Line Protection with Automatic Switch by using PLC AutomationIRJET Journal
 
Voltage Sag and Swell Identification Using FFT Analysis and Mitigation with DVR
Voltage Sag and Swell Identification Using FFT Analysis and Mitigation with DVRVoltage Sag and Swell Identification Using FFT Analysis and Mitigation with DVR
Voltage Sag and Swell Identification Using FFT Analysis and Mitigation with DVRIOSRJEEE
 
SHORT CIRCUIT ANALYSIS OF ELECTRICAL DISTRIBUTION SYSTEM FOR INDUSTRY APPLICA...
SHORT CIRCUIT ANALYSIS OF ELECTRICAL DISTRIBUTION SYSTEM FOR INDUSTRY APPLICA...SHORT CIRCUIT ANALYSIS OF ELECTRICAL DISTRIBUTION SYSTEM FOR INDUSTRY APPLICA...
SHORT CIRCUIT ANALYSIS OF ELECTRICAL DISTRIBUTION SYSTEM FOR INDUSTRY APPLICA...IRJET Journal
 
Dynamic Performance of Distance Relayson Series Compensated Transmission Line...
Dynamic Performance of Distance Relayson Series Compensated Transmission Line...Dynamic Performance of Distance Relayson Series Compensated Transmission Line...
Dynamic Performance of Distance Relayson Series Compensated Transmission Line...Premier Publishers
 
IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...
IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...
IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...IRJET Journal
 
A Novel Study on Bipolar High Voltage Direct Current Transmission Lines Prote...
A Novel Study on Bipolar High Voltage Direct Current Transmission Lines Prote...A Novel Study on Bipolar High Voltage Direct Current Transmission Lines Prote...
A Novel Study on Bipolar High Voltage Direct Current Transmission Lines Prote...IJECEIAES
 
IRJET - Transmission Line Fault Classification using DWT
IRJET -  	  Transmission Line Fault Classification using DWTIRJET -  	  Transmission Line Fault Classification using DWT
IRJET - Transmission Line Fault Classification using DWTIRJET Journal
 
IRJET- SVPWM Technique based D-STATCOM to Improve Power Quality in Distributi...
IRJET- SVPWM Technique based D-STATCOM to Improve Power Quality in Distributi...IRJET- SVPWM Technique based D-STATCOM to Improve Power Quality in Distributi...
IRJET- SVPWM Technique based D-STATCOM to Improve Power Quality in Distributi...IRJET Journal
 
IRJET - Overview of Smart Tower Technology for Transmission Lines
IRJET - 	  Overview of Smart Tower Technology for Transmission LinesIRJET - 	  Overview of Smart Tower Technology for Transmission Lines
IRJET - Overview of Smart Tower Technology for Transmission LinesIRJET Journal
 
A Fault Detection and Classification Method for SC Transmission Line Using Ph...
A Fault Detection and Classification Method for SC Transmission Line Using Ph...A Fault Detection and Classification Method for SC Transmission Line Using Ph...
A Fault Detection and Classification Method for SC Transmission Line Using Ph...paperpublications3
 

Similar to H044023944 (20)

Synchrophasor Based Ocillation Detection: A Case Study for Indian Power Grid
Synchrophasor Based Ocillation Detection: A Case Study for Indian Power GridSynchrophasor Based Ocillation Detection: A Case Study for Indian Power Grid
Synchrophasor Based Ocillation Detection: A Case Study for Indian Power Grid
 
Distribution Network Power Quality Improvement by D-STATCOM & DVR Under Vario...
Distribution Network Power Quality Improvement by D-STATCOM & DVR Under Vario...Distribution Network Power Quality Improvement by D-STATCOM & DVR Under Vario...
Distribution Network Power Quality Improvement by D-STATCOM & DVR Under Vario...
 
SRF CONTROLLED DVR FOR COMPENSATION OF BALANCED AND UNBALANCED VOLTAGE DISTUR...
SRF CONTROLLED DVR FOR COMPENSATION OF BALANCED AND UNBALANCED VOLTAGE DISTUR...SRF CONTROLLED DVR FOR COMPENSATION OF BALANCED AND UNBALANCED VOLTAGE DISTUR...
SRF CONTROLLED DVR FOR COMPENSATION OF BALANCED AND UNBALANCED VOLTAGE DISTUR...
 
DESIGN AND DEVELOPMENT OF SMES BASED DVR MODEL IN SIMULINK
DESIGN AND DEVELOPMENT OF SMES BASED DVR MODEL IN SIMULINKDESIGN AND DEVELOPMENT OF SMES BASED DVR MODEL IN SIMULINK
DESIGN AND DEVELOPMENT OF SMES BASED DVR MODEL IN SIMULINK
 
Compensation of Balanced and Unbalanced Voltage Disturbance using SRF Control...
Compensation of Balanced and Unbalanced Voltage Disturbance using SRF Control...Compensation of Balanced and Unbalanced Voltage Disturbance using SRF Control...
Compensation of Balanced and Unbalanced Voltage Disturbance using SRF Control...
 
Fuzzy-Logic-Controller-Based Fault Isolation in PWM VSI for Vector Controlled...
Fuzzy-Logic-Controller-Based Fault Isolation in PWM VSI for Vector Controlled...Fuzzy-Logic-Controller-Based Fault Isolation in PWM VSI for Vector Controlled...
Fuzzy-Logic-Controller-Based Fault Isolation in PWM VSI for Vector Controlled...
 
Analysis of Total Harmonic Distortion (THD) Level of Distribution Network Usi...
Analysis of Total Harmonic Distortion (THD) Level of Distribution Network Usi...Analysis of Total Harmonic Distortion (THD) Level of Distribution Network Usi...
Analysis of Total Harmonic Distortion (THD) Level of Distribution Network Usi...
 
IRJET- Overhead Line Protection with Automatic Switch by using PLC Automation
IRJET- Overhead Line Protection with Automatic Switch by using PLC AutomationIRJET- Overhead Line Protection with Automatic Switch by using PLC Automation
IRJET- Overhead Line Protection with Automatic Switch by using PLC Automation
 
Voltage Sag and Swell Identification Using FFT Analysis and Mitigation with DVR
Voltage Sag and Swell Identification Using FFT Analysis and Mitigation with DVRVoltage Sag and Swell Identification Using FFT Analysis and Mitigation with DVR
Voltage Sag and Swell Identification Using FFT Analysis and Mitigation with DVR
 
SHORT CIRCUIT ANALYSIS OF ELECTRICAL DISTRIBUTION SYSTEM FOR INDUSTRY APPLICA...
SHORT CIRCUIT ANALYSIS OF ELECTRICAL DISTRIBUTION SYSTEM FOR INDUSTRY APPLICA...SHORT CIRCUIT ANALYSIS OF ELECTRICAL DISTRIBUTION SYSTEM FOR INDUSTRY APPLICA...
SHORT CIRCUIT ANALYSIS OF ELECTRICAL DISTRIBUTION SYSTEM FOR INDUSTRY APPLICA...
 
Dynamic Performance of Distance Relayson Series Compensated Transmission Line...
Dynamic Performance of Distance Relayson Series Compensated Transmission Line...Dynamic Performance of Distance Relayson Series Compensated Transmission Line...
Dynamic Performance of Distance Relayson Series Compensated Transmission Line...
 
IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...
IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...
IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...
 
A Novel Study on Bipolar High Voltage Direct Current Transmission Lines Prote...
A Novel Study on Bipolar High Voltage Direct Current Transmission Lines Prote...A Novel Study on Bipolar High Voltage Direct Current Transmission Lines Prote...
A Novel Study on Bipolar High Voltage Direct Current Transmission Lines Prote...
 
IRJET - Transmission Line Fault Classification using DWT
IRJET -  	  Transmission Line Fault Classification using DWTIRJET -  	  Transmission Line Fault Classification using DWT
IRJET - Transmission Line Fault Classification using DWT
 
B010620715
B010620715B010620715
B010620715
 
Bb4103331337
Bb4103331337Bb4103331337
Bb4103331337
 
IRJET- SVPWM Technique based D-STATCOM to Improve Power Quality in Distributi...
IRJET- SVPWM Technique based D-STATCOM to Improve Power Quality in Distributi...IRJET- SVPWM Technique based D-STATCOM to Improve Power Quality in Distributi...
IRJET- SVPWM Technique based D-STATCOM to Improve Power Quality in Distributi...
 
Lp3619931999
Lp3619931999Lp3619931999
Lp3619931999
 
IRJET - Overview of Smart Tower Technology for Transmission Lines
IRJET - 	  Overview of Smart Tower Technology for Transmission LinesIRJET - 	  Overview of Smart Tower Technology for Transmission Lines
IRJET - Overview of Smart Tower Technology for Transmission Lines
 
A Fault Detection and Classification Method for SC Transmission Line Using Ph...
A Fault Detection and Classification Method for SC Transmission Line Using Ph...A Fault Detection and Classification Method for SC Transmission Line Using Ph...
A Fault Detection and Classification Method for SC Transmission Line Using Ph...
 

Recently uploaded

Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesSinan KOZAK
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphNeo4j
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Paola De la Torre
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...shyamraj55
 
How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?XfilesPro
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...HostedbyConfluent
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
Pigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping ElbowsPigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping ElbowsPigging Solutions
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxOnBoard
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 

Recently uploaded (20)

Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen Frames
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
 
How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Pigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping ElbowsPigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping Elbows
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptx
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 

H044023944

  • 1. Debniloy De et al Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 4, Issue 4( Version 2), April 2014, pp.39-44 www.ijera.com 39 | P a g e Optimum Overcurrent Relay Coordination of a Power Grid Sheila Mahapatra*, Debniloy De**, Shivanjali A. Mishra***,Aditya Kar**** *(Department of Electrical, Electronics and Communication Engineering, ITM University, Haryana-122017) ** (Department of Electrical, Electronics and Communication Engineering, ITM University, Haryana-122017) *** (Department of Electrical, Electronics and Communication Engineering, ITM University, Haryana-122017) **** (Department of Electrical, Electronics and Communication Engineering, ITM University, Haryana- 122017) ABSTRACT Protective system plays a pivotal role in any power system operation. In a typical power system there are large numbers of circuit breakers and relays installed which constitute an integral part of the protective scheme. Relay is a device that senses and locates the fault and sends a command to the circuit breaker to disconnect the faulty element. Relay coordination is done to provide primary as well as back up protection from any fault that is likely to occur in the system. In this paper, overcurrent relay coordination is implemented on a 72 bus 220 KV substation. Load flow studies and the short circuit analysis on the test system is initially done followed by relay coordination. Fault current data obtained from short circuit studies enables us to obtain operating time of the relays used in the test system. The simulated value of operating time provides the coordinated operation of all the relays connected from 220kV to 33kV line thereby protecting the equipment of the test system. Keywords-PSM (Plug Setting Multiplier), Relay coordination, Three phase to ground fault, TMS (Time Multiplier Settings) I. INTRODUCTION Protection system does the function of detecting the faults and clearing the fault as quickly as possible. Protection system includes circuit breakers, relays, current transformer, potential transformers and transducers. A protective relay is one of the most important part of a power system network and it is necessary to coordinate them properly so that the customers can get undisturbed supply. Over current relay coordination can be done with utmost accuracy and tolerance using the MiPower software. MiPower software is very interactive and has user friendly windows based power system analysis package. Load flow studies and short circuit analysis is done using the same software and the results of these analysis are used to have an optimal coordination of the relays. The protective devices are installed to protect the system from any fault that is likely to occur. The quantities that may change due to occurrence of fault are current, voltage, phase angle and frequency. A power system is mainly divided into a number of protective zones so that no part of the system is left unprotected. The protective devices in each zone isolate the faulty part from the healthy part as soon as possible to avoid further damage to equipment .If the fault is not cleared, then the system voltage will reduce and the generators will lose synchronism. Several methods are there to provide relay coordination. One such method is linear programming which is used to optimize the time multiplier setting of the relays [1]. Another method is to apply linear programming technique to minimize the operating time [2]. Therefore relay coordination is the most important part of a protective system design. II. Case study: 220 kv Masudpur substation Relay coordination is done on 220 KV Masudpur Substation. This substation is located in Hisar, Haryana. It is a 72 bus system receiving an incoming of 220 KV double circuit line and delivers two 220 KV double circuit line to 400 KV Kirori Substation and Samain Substation respectively. It has two step down transformers of 220/132 KV and 220/33KV which steps down the 220KV to 132KV and 33KV respectively. In total there are 23 breakers and 66 isolators. There are 4 loads in the system which sums up to 12.41 MW.132KV subsystem and capacitor banks are currently not in use in the existing substation operation.Fig.1 shows the pictorial view of the 220Kv Masudpur substation. From the Fig.1 we can see that there are three different voltage levels i.e. 220Kv, 132Kv, 33Kv in this substation. For 220 Kv and 33 Kv voltages level, main bus-1 is working. All the outgoing feeders are connected are 33Kv voltage level. RESEARCH ARTICLE OPEN ACCESS
  • 2. Debniloy De et al Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 4, Issue 4( Version 2), April 2014, pp.39-44 www.ijera.com 40 | P a g e Fig.1:220 kv Masudpur Substation, Hisar, Haryana III. System Data 1.Bus Data Table 1: Bus voltages Bus Number Bus(KV) 1,2,3,4,5,6,7,8,9,10,11,12,13,14,15,1 6,17,18,19,20,21,22,23,24,27,38 220 25, 26, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37 132 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 53, 54, 55, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 74 33 72,73 0.4 2.Transformer Data Table 2: Transformer Ratings Fro m To POSITIVE ZERO Bus Na me Bus Name R(P.U) TAP X(P.U) PHASE R(P.U) FB- MVA X(P.U) TB- MVA 27 28 0.00501 1.00000 0.10027 0.000 0.00501 10000 0.10027 5000 38 39 0.00501 1.00000 0.10027 0.000 0.00501 10000 0.10027 1500 53 72 0.00294 1.05000 0.05883 0.000 0.00294 1500 0.05883 0 52 73 0.00294 1.05000 0.05883 0.000 0.00294 1500 0.05883 0 3.Load Data Table 3: Loads connected to 33Kv Bays Bus Number Real Power (MW) Reactive Power (MVAR) 55 1.61 1.04 65 4.59 0 66 1.81 1.22 67 4.4 3.07 IV. Implementation: Simulation And Results 1.Load Flow Studies Load flow studies forms the basis for any further analysis done in power system. This gives an idea to power engineers about the actual power flows both real and reactive power taking place in the system. Load flow analysis is important for planning future expansions of the power system networks and determining the best operation of the existing equipment. Load flow study gives the optimal value of the voltage and the real and reactive power flowing in the line. The load flow study helps to minimize the transmission line losses and also reduces the cost of generation. Fig 2 shows load flow simulation circuit of 220 KV Masudpur substation. It can be seen from the Fig.2 that system is under loaded as the real and reactive power flows are indicated in green. The software indicates the power flows in blue under normal loading condition and in red for overloaded condition. The simulation is carried on the test system to give the load flow data as follows: Table 4: Load Flow Results Table 4 shows the real power (MW) generation, MW loss and MW load. It also shows the reactive power (MVAR) generation, MVAR loss and MVAR load. Fig.2: load flow simulation circuit of 220 kv Masudpur substation 2.Short Circuit Analysis Prior to relay coordination, we consider short circuit studies which help us to know fault current, fault MVA and suitable develops a protection scheme for the grid. Devices like Generators, Transformers and Motors which are integral part of the power system should have their rating which exceeds the maximum fault current level and fault MVA value. So short circuit studies helps MW generation 12.4312 MVAR generation 5.525 MW load 12.41 MVAR load 5.3725 MW loss 0.212 MVAR loss 0.1975
  • 3. Debniloy De et al Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 4, Issue 4( Version 2), April 2014, pp.39-44 www.ijera.com 41 | P a g e us to get values of fault current, fault MVA which helps us in designing proper protection scheme. The huge fault current causes an extreme damage to the equipment if suitable protective scheme is not incorporated in the power system. Short circuits are generally caused by insulation failures or conducting path failures. Short circuits on the transmission and the distribution lines are caused by over voltages due to lightning or switching surges. Faults can be classified as series and shunt faults. Series faults are also known as symmetrical faults. Three phase to ground fault comes under symmetrical faults and they are the most severe fault. They occur rarely in the power system. Shunt faults are also known as unsymmetrical faults and they are very common in the power system. There are three types of unsymmetrical faults. They are single line to ground (SLG), line to line fault (LL), double line to ground fault (LLG). In this paper, three phase to ground fault has been performed as it forms a basis for the selection of the circuit breakers, relays and also of instrument transformers. Three phase to ground fault analysis is done on bus 65 and the following fault current, fault MVA and the post fault voltages are obtained. Table 5: Fault Current (Amp/deg) at Bus 65 Sequence(1,2,0) Phase (A,B,C) Mag Ang Mag Ang 14310 -82.47 14310 -82.47 0 -90.00 14310 157.53 0 -90.00 14310 37.53 R/X Ratio of the short circuit path =0.1321 Peak Asymmetrical short circuit current* = 34694 Amps *pascc = k X sqrt(2) X If , k=1.7144 Table 6: Fault contribution from shunt connection BUS NAME CURRENT (AMPS/DEFREE) MVA SEQUENCE (1,2,0) PHASE (A,B,C) PHASE (A,B,C) Mag Ang Mag Ang MAG 19 2146 97.53 2146 97.53 818 0 -90.00 2146 -22.47 818 0 -90.00 2146 - 142.47 818 55,65, 66,67 0 -90.00 0 -90.00 0 0 -90.00 0 -90.00 0 0 -90.00 0 -90.00 0 Table 7: Three phase fault level BUS NAME BUS kV NOMIN AL 3PH- fMVA FAULT I kA 1,3,6,7,8,9,10, 11,12,13,14,16 ,17,18,19,21,2 2,23,24,27,38 220.000 0.3 0.001 2,4,14,20 220.000 0.4 0.001 25,26,30,31,32 ,33,34,35,36,3 7 132.000 0.2 0.001 39,40,41,42,43 ,44,45,46,47,4 8,49,50,51,52, 53,54,55,56,57 ,58,59,60,61,6 2,63,64,66,67, 68,69,74 33.000 0.0 0.000 65 33.000 817.9 14.310 72,73 0.400 0.0 0.000 Table 8: Fault MVA at bus 65 FAULT MVA SEQUENCE (1,2,0) PHASE (A,B,C) MAGNITUDE MAGNITUDE 818 818 0 818 0 818 Table 9(a): Post fault voltages after creating fault at bus 65 Post Fault Voltages Bus Name Sequence Current (1,2,0) Phase (A,B,C) Line- Line Mag V Ang V Ang Pu on L-L base 1,3,5,7,8, 9,10,11,1 5,16,17,1 8,21,22,2 3,24,27,2 8,29 0.88 1.14 0.88 1.14 0.88 0 -90 0.88 -118.86 0.88 0 -90 0.88 121.14 0.88
  • 4. Debniloy De et al Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 4, Issue 4( Version 2), April 2014, pp.39-44 www.ijera.com 42 | P a g e Table 9(b): Post fault voltages after creating fault at bus 65 Bus Name Sequence Current (1,2,0) Phase (A,B,C) Line- Line Mag V Ang V Ang Pu on L-L base 2,4,14,20, 25,26,30,3 1,32,33,34 ,35,36,37 1 0 1 0 1 0 -90 1 -120 1 0 -90 1 120 1 Table 9(c): Post fault voltages after creating fault at bus 65 Bus Name Sequence Current (1,2,0) Phase (A,B,C) Line- Line Mag V Ang V Angle Pu on L-L base Bus 65 0 -90 0 -90 0 0 -90 0 150 0 0 -90 0 30 0 Fig.3: Three phase fault created at bus 65 Fig.4: Waveform of Three phase symmetrical fault at bus 65 Fig.4 shows the phase A fault current at bus 65 when a three phase to ground fault is applied at bus 65.This graph shows the superimposition of dc offset current with the ac current to give the total asymmetrical (ac+dc) current. 3. Relay Coordination When a fault occurs it may cause heavy damage to the power system and the equipment. Therefore, a suitable protective device is needed to protect the system from any damage. The protective device should be selective enough to distinguish between normal condition and faulty condition. One such protective device is the relay. A relay senses the fault and sends a signal to the circuit breaker to trip. There is a primary relay installed in every zone of the system to protect the system. After the occurrence of fault, the primary relay senses the fault and locates the fault. The primary relay sends the alarm to the circuit breaker and the circuit breaker trips. If the primary relay fails to operate then there is a backup relay to clear the fault. Relay coordination is done to check if the relay is fast enough or reliable enough to detect the fault at the proper time and send the signal to the auxiliary devices. Relays can be classified into different types. One such type is the over current relay. For over current protection different types of relays are used like electromagnet relay, induction disc type relay and static relay. The over current relay shows the relation between relay operating time in terms of TMS (Time Multiplier Setting) and actuating current in terms of PMS(Plug SettingMultiplier). The core of the relay is made to saturate for a given actuating current. The minimum time for relay to operate is the current setting or settling time. Relay shall not operate at a time less than the settling time. The settling time depends on X/R ratio between fault location and source and the ratio of the impedance between fault and source and the impedance of zone. The relay co-ordination study of an electric power system consists of an organized
  • 5. Debniloy De et al Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 4, Issue 4( Version 2), April 2014, pp.39-44 www.ijera.com 43 | P a g e time-current study of all devices in series from utilization device to source. It is a study of organized time – current of all the equipment connected from the load to source. The main motive of this study is to determine the ratings of the over current protective devices which will see that the minimum portion of the system is effected when the protective devices removes a fault in the system. On other hand, it must provide protection to the equipment and remove short circuit conditions as quickly as possible. Coordination ensures that protective relays work properly to provide safe and reliable protection.In 220KV Masudpur substation, ABB manufactured REF 615 relay is used.REF615 relays are generally used for feeder protection. IECN curve type is used for all relay calculation. Operating time of any relay depends on three factors i.e. TMS, Fault current and plug setting. Different relays used and their respective TMS and plug settings are as follows: Table 10: Relay Settings Sn no. CT ratio Overcurrent setting Earth fault setting Pl ug Se t in % Ip > TMS (Tp> sec) Ins Set ( Ip >> in % &Tp>> in sec) Pl ug Se t in % Ie > TMS (Te> Sec) Ins Set ( Ie>> in % &Te> > in sec) R1 - R4 300 / 5 10 0 0.15 Ip >> 500 &Tp>> 0 20 0.15 Ie>> 200& Te>> 0 R5 - R6 400 / 5 10 0 0.05 Ip >> 500 &Tp>> 0 20 0.05 Ie>> 200 &Te> >0 R7 200 0 / 5 10 0 0.2 Dis 20 0.2 Dis R8 200 0 / 5 10 0 0.2 Dis 20 0.2 Dis R9 300 / 1 10 0 0.25 Ip >> 850 &Tp>> 0 Di s 0 Dis R1 0- R1 6 120 0 / 1 10 0 0.3 Dis 20 0.3 Dis R1 7 500 / 1 10 0 0.25 Dis 20 0.25 Dis R1 - R2 0 600/ 1 10 0 0.2 Dis 20 0.2 Dis Overcurrent relay coordination studies done at bus 65 gives the following results: Table 11: 3 Phase to ground fault is created at bus Bus65 Table 11 shows the operating time of the relays when a three phase to ground fault occurs at bus 65. Relay R2 acts instantaneously after the occurrence of fault. This can also be seen from Fig.5 which shows the overcurrent graphs of relays used in the test system. The relay R2 is provided with instantaneous settings as it is present closest to the feeder bus 65. It acts as a primary defense to any fault occurring at bus 65. If this relay fails to operate then the remaining relays R8, R9 and R15 will act according to their respective operating time. Fig.5: Relay coordination graph at bus 65 V. Conclusions This paper presents the load flow studies, short circuit analysis and relay coordination of a 220 Kv Masudpur substation. Load flow studies show the proper power flow in the power system. It also shows that system is under loaded with 132 KV subsystem being non-operative. Short circuit studies is done on bus 65 which gives fault current of 14310 Amperes and fault MVA of 818. Fault current obtained is thereby utilized to determine the operating time for all the four relays connected between 220kV and 33 kV line such that their operation is properly coordinated. This ensures system protection scheme is adequate under existing working condition. Relay name Phase a fault current Operating time R2 14309 Inst(0.00) R8 14309 0.7021 R9 2146 0.8776 R15 2146 3.5638
  • 6. Debniloy De et al Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 4, Issue 4( Version 2), April 2014, pp.39-44 www.ijera.com 44 | P a g e References [1] N.A. Laway, H.O. Gupta, "A Method for Coordination of Overcurrent Relays in Interconnected Power System", IEJ, vol. 74(1993), pp. 59-65 [2] B.Chattopadhyay, et al "An on-line Relay Coordination Algorithm for Adaptive Protection Using Linear Programming Technique", IEEE Trans. on Power Delivery, vol. 11 (1996), no. 1, pp. 165-173 [3] ShimpyRalhan, ShashwatiRay,”Optimal Coordination of Directional Overcurrent Relays using Interval Two Phase Simplex Linear Programming”,International Journal of Advanced Computer Research, Volume-3 Number-3 Issue-11 September-2013 [4] D.Vijayakumar and R. K. Nema,” Simplified Velocity MPSO for Directional Over Current Relay Coordination”, International Journal of Recent Trends in Engineering, Vol 1, No. 3, May 2009 [5] Dharmendra Kumar Singh, Dr. S. Gupta,”Protection Of Power System By Optimal Co-ordination of Directional Overcurrent Relays Using Genetic Algorithm”,International Journal of Modern Engineering Research, Vol.2, Issue.1, Jan- Feb 2012 [6] Dinesh Birla, RudraPrakashMaheshwari, and H. O. Gupta, “A New Nonlinear Directional Overcurrent Relay Coordination Technique, and Banes and Boons of Near- End Faults Based Approach “, IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 21, NO. 3, JULY 2006 [7] Vipul N Rajput, Rashesh P. Mehta, Bhuvanesh A. Oza,” Coordination of Overcurrent Relays for Industrial Radial System”, National Conference on Recent Trends in Engineering & Technology [8] JavedSadeh, “Optimal Coordination of Overcurrent Relays in an interconnected power system”, 15th PSCC Liege, section 19(2005).