SlideShare a Scribd company logo
1 of 36
DISTRBUTION
SYSTEM FAULT
MANAGEMENT.
VISHVESHWARAYA TECHNOLOGICAL
UNIVERSITY,
BELGAUM.
DEPT OF ELECTRICAL AND
ELCTRONICS
BMS COLLAGE OF ENGINEERING
(EVENINIG)
BENGALURU .
TEAM
MEMBERS
 D.S.MANJUNATH
 VINAY KUMAR.M
 VISHNUVARDHANA .H.V.
 KIRAN KUMAR.G.
GUIDED BY:
ASSOCIATE PROF, SRI S. PRAKASH.
ELECTRICAL AND E,ECTRONICS DPT.
BMSCOLLAG OF ENGINEERING (EVEN).
AGENDA
 INTRODUCTION.
 CURRENTLY EXISTING SYSTEM.
 NEW FAULT MANAGEMENT
SYSTEM.
 ADVANTAGES, APPLICATIONS, IMP
ROVEMENTS.
DISTRIBUTION SYSTEM.
Distribution system is that part of the
power system which distributes power
from distribution substation to local
use .
Generally the higher voltage
for distribution is 11000v and the
lower voltages are 400 v and 220v.
General
layout of
distribution
system
7
33KV
Sub station
11KV
Distribution
Transformer
11KV
Distribution
Substation
0.4KV
TRANSFORMERSwitch(OPEN)
SUBSTATION BUS
SWITCH
(CLOSED)
STATION CIRCUIT
BREAKER
OPEN LOOP SYSTEM
HRC FUSE
Load
TYPICAL DISTRIBUTION SYSTEM
8
TYPES OF FAULTS IN DISTRIBUTION
SYSTEM.
 LINE TO LINE FAULT .
 LINE TO GROUND FAULT .
 3 PHASE FAULTS.
 OVER CURRENT FAULTS .
LINE TO LINE FAULT.
 IT’S THE FAULT WHICH OCCURS
BETWEEN ANY OF THE 2 LINES .
 AT THIS FAULT THE VOLTAGE
ACROSS TWO LINES WILL BE
ZERO, AND CURRENT IS
MAXIMUM.
 V=0,I=∞
LINE TO GROUND FAULT
 IT IS THE FAULT OCCURS
BETWEEN ANY LINE TO GROUND.
 AT THIS FAULT THE VOLTAGE
ACROSS LINE TO GROUND IS
ZERO, AND CURRENT IS
MAXIMUM.
 V=0,I=∞
THREE PHASE FAULTS
 OVER CURRENT FAULTS
 IN OVERCURRENT FAULTS THE
CURRENT IS MAXIMUM ,THAT IS
MORE THAN RATED VALUE.
EFFECT OF FAULTS.
Over view of currently existing
system.
Service station
Service vehicle
Consumer under dark
fault clearing system of current
existing system.
Sub A
Feeder B010
from Sub BFeeder A007
from Sub A
Open
Tie-Switch
Closed
Switches
Distribution
Transformers
Inferred Fault
Location
Customer
trouble calls
Sub A
Feeder B010
from Sub BFeeder A007
from Sub A
Open
Tie-Switch
Closed
Switches
Distribution
Transformers
fault clearing system of current
existing system.
Inferred Fault
Location
Customer
trouble calls
Customer
trouble calls
Difficulties in currently existing
system.
 Fault Identification takes too much time.
 At the time of raining it is too difficult find
and correct faults.
 With the human error fatal accidents are
common .
 L.V. distribution faults(after the
secondary of distribution transformer)
are cannot be identified from existing
relays, faults like conductor
down, overloading, short circuiting of
conductors etc. which unexpected and
very difficult identify.
Objective of fault management
system.
 To improve reliability and quality of
service of distribution system by
 Reducing frequency and duration of power
interruptions to targets consistent with best
international practice
 To operate efficiently and safely by
 Minimizing power losses
 Applying manpower resources effectively
Method involved
 It will be consisting of control room with a
signal indicating system it may be a
computer monitor or big screen
 Which will be indicating the status of all
section voltage and current with alarm
for any abnormal conditions .
 After I identifying the fault feeder all
loads are removed from the network and
network will be charged idly with full
voltage and limiting current through a
current limiter which may be a saturable
reactor so it limits the fault currents.
Continued…….
 After charging the line idly , all sections
current and voltage status will be
absorbed and faulty section is identified.
 after identifying faulty section, it will be
isolated from the healthy one from
remotely .
 After clearing the fault the section will be
closed.
 Fault cleared successfully.
on on
TRANSFORMERSwitch(OPEN)
SUBSTATION BUS
SWITCH
(CLOSED)
STATION CIRCUIT
BREAKER
OPEN LOOP SYSTEM
HRC FUSE
Load
TYPICAL DISTRIBUTION SYSTEM WITH FAULT MANGEMENT SYSTEM
24
on off
TRANSFORMERSwitch(OPEN)
SUBSTATION BUS
SWITCH
(CLOSED)
STATION CIRCUIT
BREAKER
OPEN LOOP SYSTEM
HRC FUSE
Load
TYPICAL DISTRIBUTION SYSTEM WITH FAULT MANGEMENT SYSTEM
25
Saturable reactor
on on
TRANSFORMERSwitch(OPEN)
SUBSTATION BUS
SWITCH
(CLOSED)
STATION CIRCUIT
BREAKER
OPEN LOOP SYSTEM
HRC FUSE
Load
TYPICAL DISTRIBUTION SYSTEM WITH FAULT MANGEMENT SYSTEM
26
Saturable reactor
lV. Remote-
controlled switch
network
Normally-open point
Telecontrolled Switches
Substation CBs
33/11kV Substation
10km
10km
12.5km
10km
10km
10km
10km
10km
10km
10km
10km
10km
10km
10km
17.5km
10km 10km
20km
Feeder 1
Feeder 2
Optical Fiber
Fault
Control
room
Communications
Advantages
 The new fault management system has a
wide and verity range of applications and
advantages .
 The down time is got reduced.
 Less interruption system can be ensured to
the customer.
 Revenue loss is got reduced.
 With moves toward deregulation and open
competition, access to accurate and timely
outage information is critical in order to
maximize operational efficiency, minimize
customer complaints, and maintain electric
system reliability
Continued…..
 Implementing same system to the L.V.
distribution the transformer secondary
side faults can be identified and
cleared immediately which ensures
the safety for men and machines.
Present Operations ( Average time to restore Power Supply 40 Minutes )
Circuit
Breaker
R/S feederR/S feeder
Normally open
point
RMU / DT
R/S feeder
Circuit
Breaker
R/S feeder
Normally open
point
Supply restored
manually for part
network typical
time 15 – 20 mins
Circuit
Breaker
R/S feederR/S feeder
Normally
open point
RMU / DT
CB Trips on fault
Circuit
Breaker
R/S feederR/S feeder
Normally open point
now closed manually
Additional
network
restored
manually, total
time 40 mins
Faulty
Section
Circuit
Breaker
R/S feederR/S feeder
Remote operation to
close switch
Additional
network
restored, total
time 11-18 mins
Circuit
Breaker
R/S feederR/S feeder
Normally open
point
Automated RMU
/ DT with FPI
Circuit
Breaker
R/S feederR/S feeder
Normally open
point
FPI indicates
passage of
fault current
CB Trips
Circuit
Breaker
R/S feederR/S feeder
Normally open
point
Remote Operation
of RMU Switch &
Partial Restoration
of supply –
typically 1-2 mins
After Automation ( Average time to restore Power Supply to healthy section 1-2 Minutes)
Impact of new fault management System.
Power Restored
to Customers on
Healthy Sections
of Feeder
Fault
Occurs
Customer
Reports
Outage
Travel Time
Fault
Located
Investigation
& Patrol Time
Time to Perform
Manual Switching Repair Time
Feeder
Back to
Normal
5– 10
minutes
15– 20
minutes
10- 15
minutes
45– 75
minutes
15– 30
minutes
1- 4
Hours
Power Restored
to Customers on
Healthy Sections
of Feeder
Fault
Occurs
Customer
Reports
Outage
Travel Time
Fault
Located
Investigation
& Patrol Time
Time to Perform
Manual Switching Repair Time
Feeder
Back to
Normal
5– 10
minutes
15– 20
minutes
10- 15
minutes
45– 75
minutes
15– 30
minutes
1- 4
Hours
Fault
Occurs
Customer
Reports
Outage
Travel Time
Fault
Located
Investigation
& Patrol Time
Time to Perform
Manual Switching Repair Time
Feeder
Back to
Normal
5– 10
minutes
15– 20
minutes
10- 15
minutes
45– 75
minutes
15– 30
minutes
1- 4
Hours
Without Automation
With Automation
minutes Hoursminutesminutes Hoursminutesminutes Hoursminutes
1– 2
minutes
1– 2
minutes
1– 2
minutes
Field
Crews
On- Scene
15– 30
Feeder
Back to
Normal
Power Restored
to Customers on
Healthy Sections
of Feeder
Travel Time Repair Time
1- 45- 10
Patrol
Time
Customer
Reports
Outage
Fault
Occurs
Field
Crews
On- Scene
15– 30
Feeder
Back to
Normal
Power Restored
to Customers on
Healthy Sections
of Feeder
Travel Time Repair Time
1- 45- 10
Patrol
Time
Customer
Reports
Outage
Fault
Occurs
Field
Crews
On- Scene
15– 30
Feeder
Back to
Normal
Power Restored
to Customers on
Healthy Sections
of Feeder
Travel Time Repair Time
1- 45- 10
Patrol
Time
Customer
Reports
Outage
Fault
Occurs
Applications.
 Fault Location, Isolation, and Service
Restoration
◦ Can detect and locate fault, isolate the faulty
section, restore power to “healthy” feeder
segments
 Load Shedding
◦ Can shed one feeder section if necessary
 Cold Load Pickup
◦ Can pick up feeder load one section at a time
 Feeder Reconfiguration
◦ Can balance load between feeders and reduce
losses
 “Intelligent” Substation Bus Transfer
◦ Can transfer load to another substation following
transformer failure
R
T
U
R
T
U
Primary Plant
Interface
KEY ELEMENTS of DAS
Data & Control
Pathway
Communications
Master
Station
Substation
1
2
3
4
Optical
Fibre, Cable
Radio
Microwave
R
T
U
1
2 RTU
3
4
Communications
Master Station
Line
Reporting
Analysis
5
5
Control
Room, Corporate
Control Room
Operators
Outage Analysis
Operational
analysis, decisions, issue
controls
5
distribution system fault mangement

More Related Content

What's hot

POWER QUALITY AND MANAGEMENT. EARTH GROUND GRID SYSTEM AND POWER GROUND SYSTE...
POWER QUALITY AND MANAGEMENT. EARTH GROUND GRID SYSTEM AND POWER GROUND SYSTE...POWER QUALITY AND MANAGEMENT. EARTH GROUND GRID SYSTEM AND POWER GROUND SYSTE...
POWER QUALITY AND MANAGEMENT. EARTH GROUND GRID SYSTEM AND POWER GROUND SYSTE...Jobin Abraham
 
Power quality disturbances
Power quality disturbancesPower quality disturbances
Power quality disturbancesManasKumarPatro
 
Unit 1 Power System Stability
Unit 1 Power System Stability Unit 1 Power System Stability
Unit 1 Power System Stability SANTOSH GADEKAR
 
substation internship report
substation internship report substation internship report
substation internship report Arun Thapa
 
Synchronous machines
Synchronous machinesSynchronous machines
Synchronous machinesAnu71
 
Design of substation (with Transformer Design)
Design of substation (with Transformer Design) Design of substation (with Transformer Design)
Design of substation (with Transformer Design) SayanSarkar55
 
DISTANCE PROTECTION RELAY
DISTANCE PROTECTION RELAYDISTANCE PROTECTION RELAY
DISTANCE PROTECTION RELAYRaviraj solanki
 
speed control of three phase induction motor
speed control of three phase induction motorspeed control of three phase induction motor
speed control of three phase induction motorAshvani Shukla
 
Excitation system for alternator
Excitation system for alternatorExcitation system for alternator
Excitation system for alternatorsantu sutradhar
 
Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV Girish Gupta
 
24620708 feeder-protection (1)
24620708 feeder-protection (1)24620708 feeder-protection (1)
24620708 feeder-protection (1)Adarsh Verma
 
Ppt of ehv ac transmission
Ppt of ehv ac transmissionPpt of ehv ac transmission
Ppt of ehv ac transmissionSumit Kumar
 
Major electrical equipment in power plants
Major electrical equipment in power plantsMajor electrical equipment in power plants
Major electrical equipment in power plantsFateh Singh
 
Generator Protection
Generator ProtectionGenerator Protection
Generator ProtectionPriten Vasa
 

What's hot (20)

POWER QUALITY AND MANAGEMENT. EARTH GROUND GRID SYSTEM AND POWER GROUND SYSTE...
POWER QUALITY AND MANAGEMENT. EARTH GROUND GRID SYSTEM AND POWER GROUND SYSTE...POWER QUALITY AND MANAGEMENT. EARTH GROUND GRID SYSTEM AND POWER GROUND SYSTE...
POWER QUALITY AND MANAGEMENT. EARTH GROUND GRID SYSTEM AND POWER GROUND SYSTE...
 
BUSBAR PROTECTION
BUSBAR PROTECTIONBUSBAR PROTECTION
BUSBAR PROTECTION
 
Hvdc notes
Hvdc notesHvdc notes
Hvdc notes
 
Power quality disturbances
Power quality disturbancesPower quality disturbances
Power quality disturbances
 
Unit 1 Power System Stability
Unit 1 Power System Stability Unit 1 Power System Stability
Unit 1 Power System Stability
 
substation internship report
substation internship report substation internship report
substation internship report
 
Fault analysis
Fault analysisFault analysis
Fault analysis
 
Synchronous machines
Synchronous machinesSynchronous machines
Synchronous machines
 
Design of substation (with Transformer Design)
Design of substation (with Transformer Design) Design of substation (with Transformer Design)
Design of substation (with Transformer Design)
 
Chapter 01- High Voltage Engineering Introduction
Chapter 01- High Voltage Engineering IntroductionChapter 01- High Voltage Engineering Introduction
Chapter 01- High Voltage Engineering Introduction
 
DISTANCE PROTECTION RELAY
DISTANCE PROTECTION RELAYDISTANCE PROTECTION RELAY
DISTANCE PROTECTION RELAY
 
speed control of three phase induction motor
speed control of three phase induction motorspeed control of three phase induction motor
speed control of three phase induction motor
 
Excitation system for alternator
Excitation system for alternatorExcitation system for alternator
Excitation system for alternator
 
IEEE substation design
IEEE substation designIEEE substation design
IEEE substation design
 
Neutral grounding
Neutral groundingNeutral grounding
Neutral grounding
 
Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV
 
24620708 feeder-protection (1)
24620708 feeder-protection (1)24620708 feeder-protection (1)
24620708 feeder-protection (1)
 
Ppt of ehv ac transmission
Ppt of ehv ac transmissionPpt of ehv ac transmission
Ppt of ehv ac transmission
 
Major electrical equipment in power plants
Major electrical equipment in power plantsMajor electrical equipment in power plants
Major electrical equipment in power plants
 
Generator Protection
Generator ProtectionGenerator Protection
Generator Protection
 

Viewers also liked

400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohitMohit Awasthi
 
Practical HV and LV Switching Operations and Safety Rules
Practical HV and LV Switching Operations and Safety RulesPractical HV and LV Switching Operations and Safety Rules
Practical HV and LV Switching Operations and Safety RulesLiving Online
 
File 1 power system fault analysis
File 1 power system fault analysisFile 1 power system fault analysis
File 1 power system fault analysiskirkusawi
 
Power system fault analysis ppt
Power system fault analysis pptPower system fault analysis ppt
Power system fault analysis pptkarikalan123
 
Y R ENGG Company Profile 2
Y R ENGG Company Profile 2Y R ENGG Company Profile 2
Y R ENGG Company Profile 2R.K. Mathuria
 
Practical Electrical Wiring Standards - National Rules for Electrical Install...
Practical Electrical Wiring Standards - National Rules for Electrical Install...Practical Electrical Wiring Standards - National Rules for Electrical Install...
Practical Electrical Wiring Standards - National Rules for Electrical Install...Living Online
 
ppt of Three phase fault analysis with auto reset for temporary fault and tri...
ppt of Three phase fault analysis with auto reset for temporary fault and tri...ppt of Three phase fault analysis with auto reset for temporary fault and tri...
ppt of Three phase fault analysis with auto reset for temporary fault and tri...Vikram Rawani
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSPartha Parida
 
Electrical grounding and earthing
Electrical grounding and earthingElectrical grounding and earthing
Electrical grounding and earthingNitesh Dash
 
Earthing Concepts
Earthing ConceptsEarthing Concepts
Earthing Conceptsmvrkprasad
 
Electrical grounding and earthing systems
Electrical grounding and earthing systemsElectrical grounding and earthing systems
Electrical grounding and earthing systemsBiswajit Pratihari
 
Electrical earthing
Electrical earthingElectrical earthing
Electrical earthingDenuka
 
POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION moiz89
 
Electrical Safety
Electrical  Safety Electrical  Safety
Electrical Safety Reliance
 
Top 10 rules for electric safety
Top 10 rules for electric safetyTop 10 rules for electric safety
Top 10 rules for electric safetyRock Wood
 

Viewers also liked (20)

400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit
 
Practical HV and LV Switching Operations and Safety Rules
Practical HV and LV Switching Operations and Safety RulesPractical HV and LV Switching Operations and Safety Rules
Practical HV and LV Switching Operations and Safety Rules
 
File 1 power system fault analysis
File 1 power system fault analysisFile 1 power system fault analysis
File 1 power system fault analysis
 
Power system fault analysis ppt
Power system fault analysis pptPower system fault analysis ppt
Power system fault analysis ppt
 
Y R ENGG Company Profile 2
Y R ENGG Company Profile 2Y R ENGG Company Profile 2
Y R ENGG Company Profile 2
 
Practical Electrical Wiring Standards - National Rules for Electrical Install...
Practical Electrical Wiring Standards - National Rules for Electrical Install...Practical Electrical Wiring Standards - National Rules for Electrical Install...
Practical Electrical Wiring Standards - National Rules for Electrical Install...
 
ppt of Three phase fault analysis with auto reset for temporary fault and tri...
ppt of Three phase fault analysis with auto reset for temporary fault and tri...ppt of Three phase fault analysis with auto reset for temporary fault and tri...
ppt of Three phase fault analysis with auto reset for temporary fault and tri...
 
Earthing system
Earthing systemEarthing system
Earthing system
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
 
Electrical grounding and earthing
Electrical grounding and earthingElectrical grounding and earthing
Electrical grounding and earthing
 
Earthing Concepts
Earthing ConceptsEarthing Concepts
Earthing Concepts
 
Electrical grounding and earthing systems
Electrical grounding and earthing systemsElectrical grounding and earthing systems
Electrical grounding and earthing systems
 
Electrical earthing
Electrical earthingElectrical earthing
Electrical earthing
 
POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION
 
Importance of industrial safety
Importance of industrial safetyImportance of industrial safety
Importance of industrial safety
 
Electrical Safety
Electrical  Safety Electrical  Safety
Electrical Safety
 
Top 10 rules for electric safety
Top 10 rules for electric safetyTop 10 rules for electric safety
Top 10 rules for electric safety
 
Electrical safety new
Electrical safety newElectrical safety new
Electrical safety new
 
Industrial safety
Industrial safetyIndustrial safety
Industrial safety
 
Substation overview
Substation overviewSubstation overview
Substation overview
 

Similar to distribution system fault mangement

1660034363151685.pptx
1660034363151685.pptx1660034363151685.pptx
1660034363151685.pptxPradip khatri
 
Power quality of PV Inverters,Related To Topology & Control
Power quality of PV Inverters,Related To Topology & ControlPower quality of PV Inverters,Related To Topology & Control
Power quality of PV Inverters,Related To Topology & Controlseema appa
 
Equipments in distribution system
Equipments in distribution systemEquipments in distribution system
Equipments in distribution systemEranga Pathiranage
 
DISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROLDISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROLyohannes feleke
 
Power quality-disturbances and monitoring Seminar
Power quality-disturbances and monitoring  SeminarPower quality-disturbances and monitoring  Seminar
Power quality-disturbances and monitoring SeminarSurabhi Vasudev
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at JassureShuvam Pathania
 
PLC based Multichannel Automatic Liquid Level Controller
PLC based Multichannel Automatic Liquid Level ControllerPLC based Multichannel Automatic Liquid Level Controller
PLC based Multichannel Automatic Liquid Level ControllerVijay Badgujar
 
Iaetsd minimization of voltage sags and swells using dvr
Iaetsd minimization of voltage sags and swells using dvrIaetsd minimization of voltage sags and swells using dvr
Iaetsd minimization of voltage sags and swells using dvrIaetsd Iaetsd
 
Force Sensor Data Acquisition
Force Sensor Data AcquisitionForce Sensor Data Acquisition
Force Sensor Data AcquisitionTacuna Systems
 
Transformer failure prevent
Transformer failure preventTransformer failure prevent
Transformer failure preventVitthal Adhav
 
Flexible AC Transmission (FACTS)
Flexible AC Transmission (FACTS)Flexible AC Transmission (FACTS)
Flexible AC Transmission (FACTS)SHIMI S L
 
Monitoring of Distribution Transformer Parameters Using Plc
Monitoring of Distribution Transformer Parameters Using PlcMonitoring of Distribution Transformer Parameters Using Plc
Monitoring of Distribution Transformer Parameters Using PlcIRJET Journal
 
Health monitoring of transformer using plc
Health monitoring of transformer using plcHealth monitoring of transformer using plc
Health monitoring of transformer using plcRohith sai
 
Research Inventy : International Journal of Engineering and Science
Research Inventy : International Journal of Engineering and ScienceResearch Inventy : International Journal of Engineering and Science
Research Inventy : International Journal of Engineering and Scienceinventy
 
POWER QUALITY ENHANCEMENT USING UPQC
POWER QUALITY ENHANCEMENT USING UPQCPOWER QUALITY ENHANCEMENT USING UPQC
POWER QUALITY ENHANCEMENT USING UPQCIRJET Journal
 
Power quality & demand side management
Power quality & demand side managementPower quality & demand side management
Power quality & demand side managementMark Anthony Enoy
 
IRJET- Wireless Power Theft Monitoring System using Zigbee
IRJET- Wireless Power Theft Monitoring System using ZigbeeIRJET- Wireless Power Theft Monitoring System using Zigbee
IRJET- Wireless Power Theft Monitoring System using ZigbeeIRJET Journal
 

Similar to distribution system fault mangement (20)

1660034363151685.pptx
1660034363151685.pptx1660034363151685.pptx
1660034363151685.pptx
 
Power quality of PV Inverters,Related To Topology & Control
Power quality of PV Inverters,Related To Topology & ControlPower quality of PV Inverters,Related To Topology & Control
Power quality of PV Inverters,Related To Topology & Control
 
Equipments in distribution system
Equipments in distribution systemEquipments in distribution system
Equipments in distribution system
 
Power quality 5
Power quality 5Power quality 5
Power quality 5
 
DISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROLDISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROL
 
Power quality-disturbances and monitoring Seminar
Power quality-disturbances and monitoring  SeminarPower quality-disturbances and monitoring  Seminar
Power quality-disturbances and monitoring Seminar
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at Jassure
 
PLC based Multichannel Automatic Liquid Level Controller
PLC based Multichannel Automatic Liquid Level ControllerPLC based Multichannel Automatic Liquid Level Controller
PLC based Multichannel Automatic Liquid Level Controller
 
Iaetsd minimization of voltage sags and swells using dvr
Iaetsd minimization of voltage sags and swells using dvrIaetsd minimization of voltage sags and swells using dvr
Iaetsd minimization of voltage sags and swells using dvr
 
Force Sensor Data Acquisition
Force Sensor Data AcquisitionForce Sensor Data Acquisition
Force Sensor Data Acquisition
 
Power quality
Power qualityPower quality
Power quality
 
RPPT.pptx
RPPT.pptxRPPT.pptx
RPPT.pptx
 
Transformer failure prevent
Transformer failure preventTransformer failure prevent
Transformer failure prevent
 
Flexible AC Transmission (FACTS)
Flexible AC Transmission (FACTS)Flexible AC Transmission (FACTS)
Flexible AC Transmission (FACTS)
 
Monitoring of Distribution Transformer Parameters Using Plc
Monitoring of Distribution Transformer Parameters Using PlcMonitoring of Distribution Transformer Parameters Using Plc
Monitoring of Distribution Transformer Parameters Using Plc
 
Health monitoring of transformer using plc
Health monitoring of transformer using plcHealth monitoring of transformer using plc
Health monitoring of transformer using plc
 
Research Inventy : International Journal of Engineering and Science
Research Inventy : International Journal of Engineering and ScienceResearch Inventy : International Journal of Engineering and Science
Research Inventy : International Journal of Engineering and Science
 
POWER QUALITY ENHANCEMENT USING UPQC
POWER QUALITY ENHANCEMENT USING UPQCPOWER QUALITY ENHANCEMENT USING UPQC
POWER QUALITY ENHANCEMENT USING UPQC
 
Power quality & demand side management
Power quality & demand side managementPower quality & demand side management
Power quality & demand side management
 
IRJET- Wireless Power Theft Monitoring System using Zigbee
IRJET- Wireless Power Theft Monitoring System using ZigbeeIRJET- Wireless Power Theft Monitoring System using Zigbee
IRJET- Wireless Power Theft Monitoring System using Zigbee
 

distribution system fault mangement

  • 2. VISHVESHWARAYA TECHNOLOGICAL UNIVERSITY, BELGAUM. DEPT OF ELECTRICAL AND ELCTRONICS BMS COLLAGE OF ENGINEERING (EVENINIG) BENGALURU .
  • 3. TEAM MEMBERS  D.S.MANJUNATH  VINAY KUMAR.M  VISHNUVARDHANA .H.V.  KIRAN KUMAR.G. GUIDED BY: ASSOCIATE PROF, SRI S. PRAKASH. ELECTRICAL AND E,ECTRONICS DPT. BMSCOLLAG OF ENGINEERING (EVEN).
  • 4. AGENDA  INTRODUCTION.  CURRENTLY EXISTING SYSTEM.  NEW FAULT MANAGEMENT SYSTEM.  ADVANTAGES, APPLICATIONS, IMP ROVEMENTS.
  • 5.
  • 6. DISTRIBUTION SYSTEM. Distribution system is that part of the power system which distributes power from distribution substation to local use . Generally the higher voltage for distribution is 11000v and the lower voltages are 400 v and 220v.
  • 8. TRANSFORMERSwitch(OPEN) SUBSTATION BUS SWITCH (CLOSED) STATION CIRCUIT BREAKER OPEN LOOP SYSTEM HRC FUSE Load TYPICAL DISTRIBUTION SYSTEM 8
  • 9. TYPES OF FAULTS IN DISTRIBUTION SYSTEM.  LINE TO LINE FAULT .  LINE TO GROUND FAULT .  3 PHASE FAULTS.  OVER CURRENT FAULTS .
  • 10. LINE TO LINE FAULT.  IT’S THE FAULT WHICH OCCURS BETWEEN ANY OF THE 2 LINES .  AT THIS FAULT THE VOLTAGE ACROSS TWO LINES WILL BE ZERO, AND CURRENT IS MAXIMUM.  V=0,I=∞
  • 11. LINE TO GROUND FAULT  IT IS THE FAULT OCCURS BETWEEN ANY LINE TO GROUND.  AT THIS FAULT THE VOLTAGE ACROSS LINE TO GROUND IS ZERO, AND CURRENT IS MAXIMUM.  V=0,I=∞
  • 12. THREE PHASE FAULTS  OVER CURRENT FAULTS  IN OVERCURRENT FAULTS THE CURRENT IS MAXIMUM ,THAT IS MORE THAN RATED VALUE.
  • 14.
  • 15.
  • 16. Over view of currently existing system. Service station Service vehicle Consumer under dark
  • 17. fault clearing system of current existing system. Sub A Feeder B010 from Sub BFeeder A007 from Sub A Open Tie-Switch Closed Switches Distribution Transformers Inferred Fault Location Customer trouble calls
  • 18. Sub A Feeder B010 from Sub BFeeder A007 from Sub A Open Tie-Switch Closed Switches Distribution Transformers fault clearing system of current existing system. Inferred Fault Location Customer trouble calls Customer trouble calls
  • 19. Difficulties in currently existing system.  Fault Identification takes too much time.  At the time of raining it is too difficult find and correct faults.  With the human error fatal accidents are common .  L.V. distribution faults(after the secondary of distribution transformer) are cannot be identified from existing relays, faults like conductor down, overloading, short circuiting of conductors etc. which unexpected and very difficult identify.
  • 20.
  • 21. Objective of fault management system.  To improve reliability and quality of service of distribution system by  Reducing frequency and duration of power interruptions to targets consistent with best international practice  To operate efficiently and safely by  Minimizing power losses  Applying manpower resources effectively
  • 22. Method involved  It will be consisting of control room with a signal indicating system it may be a computer monitor or big screen  Which will be indicating the status of all section voltage and current with alarm for any abnormal conditions .  After I identifying the fault feeder all loads are removed from the network and network will be charged idly with full voltage and limiting current through a current limiter which may be a saturable reactor so it limits the fault currents.
  • 23. Continued…….  After charging the line idly , all sections current and voltage status will be absorbed and faulty section is identified.  after identifying faulty section, it will be isolated from the healthy one from remotely .  After clearing the fault the section will be closed.  Fault cleared successfully.
  • 24. on on TRANSFORMERSwitch(OPEN) SUBSTATION BUS SWITCH (CLOSED) STATION CIRCUIT BREAKER OPEN LOOP SYSTEM HRC FUSE Load TYPICAL DISTRIBUTION SYSTEM WITH FAULT MANGEMENT SYSTEM 24
  • 25. on off TRANSFORMERSwitch(OPEN) SUBSTATION BUS SWITCH (CLOSED) STATION CIRCUIT BREAKER OPEN LOOP SYSTEM HRC FUSE Load TYPICAL DISTRIBUTION SYSTEM WITH FAULT MANGEMENT SYSTEM 25 Saturable reactor
  • 26. on on TRANSFORMERSwitch(OPEN) SUBSTATION BUS SWITCH (CLOSED) STATION CIRCUIT BREAKER OPEN LOOP SYSTEM HRC FUSE Load TYPICAL DISTRIBUTION SYSTEM WITH FAULT MANGEMENT SYSTEM 26 Saturable reactor
  • 27. lV. Remote- controlled switch network Normally-open point Telecontrolled Switches Substation CBs 33/11kV Substation 10km 10km 12.5km 10km 10km 10km 10km 10km 10km 10km 10km 10km 10km 10km 17.5km 10km 10km 20km Feeder 1 Feeder 2 Optical Fiber Fault Control room Communications
  • 28.
  • 29. Advantages  The new fault management system has a wide and verity range of applications and advantages .  The down time is got reduced.  Less interruption system can be ensured to the customer.  Revenue loss is got reduced.  With moves toward deregulation and open competition, access to accurate and timely outage information is critical in order to maximize operational efficiency, minimize customer complaints, and maintain electric system reliability
  • 30. Continued…..  Implementing same system to the L.V. distribution the transformer secondary side faults can be identified and cleared immediately which ensures the safety for men and machines.
  • 31. Present Operations ( Average time to restore Power Supply 40 Minutes ) Circuit Breaker R/S feederR/S feeder Normally open point RMU / DT R/S feeder Circuit Breaker R/S feeder Normally open point Supply restored manually for part network typical time 15 – 20 mins Circuit Breaker R/S feederR/S feeder Normally open point RMU / DT CB Trips on fault Circuit Breaker R/S feederR/S feeder Normally open point now closed manually Additional network restored manually, total time 40 mins Faulty Section
  • 32. Circuit Breaker R/S feederR/S feeder Remote operation to close switch Additional network restored, total time 11-18 mins Circuit Breaker R/S feederR/S feeder Normally open point Automated RMU / DT with FPI Circuit Breaker R/S feederR/S feeder Normally open point FPI indicates passage of fault current CB Trips Circuit Breaker R/S feederR/S feeder Normally open point Remote Operation of RMU Switch & Partial Restoration of supply – typically 1-2 mins After Automation ( Average time to restore Power Supply to healthy section 1-2 Minutes)
  • 33. Impact of new fault management System. Power Restored to Customers on Healthy Sections of Feeder Fault Occurs Customer Reports Outage Travel Time Fault Located Investigation & Patrol Time Time to Perform Manual Switching Repair Time Feeder Back to Normal 5– 10 minutes 15– 20 minutes 10- 15 minutes 45– 75 minutes 15– 30 minutes 1- 4 Hours Power Restored to Customers on Healthy Sections of Feeder Fault Occurs Customer Reports Outage Travel Time Fault Located Investigation & Patrol Time Time to Perform Manual Switching Repair Time Feeder Back to Normal 5– 10 minutes 15– 20 minutes 10- 15 minutes 45– 75 minutes 15– 30 minutes 1- 4 Hours Fault Occurs Customer Reports Outage Travel Time Fault Located Investigation & Patrol Time Time to Perform Manual Switching Repair Time Feeder Back to Normal 5– 10 minutes 15– 20 minutes 10- 15 minutes 45– 75 minutes 15– 30 minutes 1- 4 Hours Without Automation With Automation minutes Hoursminutesminutes Hoursminutesminutes Hoursminutes 1– 2 minutes 1– 2 minutes 1– 2 minutes Field Crews On- Scene 15– 30 Feeder Back to Normal Power Restored to Customers on Healthy Sections of Feeder Travel Time Repair Time 1- 45- 10 Patrol Time Customer Reports Outage Fault Occurs Field Crews On- Scene 15– 30 Feeder Back to Normal Power Restored to Customers on Healthy Sections of Feeder Travel Time Repair Time 1- 45- 10 Patrol Time Customer Reports Outage Fault Occurs Field Crews On- Scene 15– 30 Feeder Back to Normal Power Restored to Customers on Healthy Sections of Feeder Travel Time Repair Time 1- 45- 10 Patrol Time Customer Reports Outage Fault Occurs
  • 34. Applications.  Fault Location, Isolation, and Service Restoration ◦ Can detect and locate fault, isolate the faulty section, restore power to “healthy” feeder segments  Load Shedding ◦ Can shed one feeder section if necessary  Cold Load Pickup ◦ Can pick up feeder load one section at a time  Feeder Reconfiguration ◦ Can balance load between feeders and reduce losses  “Intelligent” Substation Bus Transfer ◦ Can transfer load to another substation following transformer failure
  • 35. R T U R T U Primary Plant Interface KEY ELEMENTS of DAS Data & Control Pathway Communications Master Station Substation 1 2 3 4 Optical Fibre, Cable Radio Microwave R T U 1 2 RTU 3 4 Communications Master Station Line Reporting Analysis 5 5 Control Room, Corporate Control Room Operators Outage Analysis Operational analysis, decisions, issue controls 5