SlideShare a Scribd company logo
GEF-6 Policies 
IFAD and FAO Learning Event 
on GEF 
Rome, Italy 
December 10-12, 2014
2 
Overview 
Background: GEF Policies are usually submitted to Council for approval via Council 
papers but do not capture discussions/views of Council during the meeting. 
GEF Policy Framework: 
In GEF-6: Types and Hierarchy of Policy and Procedure Framework was established 
Policy: A statement of principles or values approved by the GEF Council that mandates or 
constrains activities undertaken to achieve the institutional goals of the GEF Secretariat. A 
Policy’s legal power is higher than that of procedures and guidelines. 
Procedures: A set of instructions or process that must be followed to adhere to a particular 
Policy or to accomplish an operational function or a specific task. Procedures are approved by 
the GEF CEO with the responsibility for the relevant Policy or relevant operational area or 
subject matter. 
Guideline: Additional information to help explain or implement a particular policy. Guidelines 
are approved by the CEO or by Team Leaders with responsibility of the relevant Policy or 
relevant operational area or subject matter. Guidelines have the lowest power in the strata of 
Policies, Procedures and Guidelines.
3 
Overview…………(2) 
1. GEF Programmatic Approach, 47th Council Meeting 
2. Update on Project Cancellation Policy, 
47th Council Meeting 
3. Co-financing Policy, 46th Council Meeting 
4. Non-Grant Instrument, 47th Council Meeting 
5. Policy on Gender Mainstreaming, 47th Council 
Meeting 
6. Public Involvement Policy, 7th Council Meeting
4 
Programmatic Approach 
 Key document = a Program Framework Document (PFD) submitted in a 
work program for Council approval; 
 Program can be single-Agency or multi-Agency; single focal area or 
mutli-focal area, single trust fund or multi-trust fund; 
 For multi-Agency program, a Lead Agency will be identified to manage 
the program in all related administrative matters; 
 Extensive upstream consultation among relevant stakeholders; 
 Key Features in a PFD: 
• Discuss program objectives; 
• Describe all child project contributions to the program objective; 
• Establish a program commitment deadline.
5 
Project Cancellation Policy 
Objectives: 
 to improve the GEF’s operational efficiency, particularly in the amount of 
time it takes to prepare and deliver projects; 
 to ensure that GEF-financed projects remain relevant to the objectives and 
priorities of the GEF and recipient countries. 
Using Phased approach to implement the policy: 
• After 12 months of Council approval of PIF, a notification will be sent to the 
Agency and OFP of the recipient country to alert them of the remaining 6 months 
for submission of project for CEO endorsement; 
• After 18 months, the Secretariat informs all relevant stakeholders on the 
cancellation of the project. 
• The Secretariat will consider exception to the above cancellation only on 
extraordinary events, and if agreed, will notify Council. 
• Cancelled projects maybe resubmitted within a year for consideration of CEO 
endorsement if resources are available.
6 
Project Cancellation Policy……..(2) 
Cancellation of child projects under a program and unused program 
amount: 
• All child projects should be submitted for CEO endorsement by 
the program commitment deadline. 
• Six months before the program commitment deadline, if there 
are still program funds of child projects not yet CEO endorsed, 
the Secretariat sends a notification to the Lead Agency notifying 
it of the upcoming cancellation of such program funds. 
• After the passing of the program commitment deadline, the CEO 
notifies the relevant Lead Agency and the Trustee of the 
cancellation for the remaining program funds.
7 
GEF Co-financing Policy 
• Approved by Council in May 2014, which has been posted as Policy FI/PL/01. 
This Policy: 
 establishes the objectives for co-financing in GEF-financed projects; 
 Defines co-financing for GEF-financed projects and programs; and 
 Provides rules/requirements on co-financing for GEF-financed projects and 
programs. 
• Applies to GEF Trust Fund and the Nagoya Protocol Implementation Fund 
(GEF-financed projects) financed projects and programs but not to LDCF or 
SCCF financed projects. 
• Council Document that proposed the Policy to the Council (Document 
GEF/C.20/6/Rev.1, Co-financing) contains helpful background and guidance 
on how it will be implemented.
8 
GEF Co-financing Policy……..(2) 
• Objective: “to attain adequate levels of co-financing as a means to: 
 enhance the effectiveness and sustainability of the GEF in 
achieving global environmental benefits; 
 strengthen partnerships with recipient country governments, 
multilateral and bilateral financing entities, the private sector, and 
civil society.” 
• Includes “an ambition for the overall GEF portfolio to reach a co-financing 
ratio of at least 6:1, with expectations for greater co-financing 
in upper-middle income countries that are not SIDs.” 
 This is a portfolio ambition, not project-by-project. 
 GEF Secretariat “will not impose minimum thresholds and/or 
specific co-financing sources in the review of individual projects or 
work programs.”
9 
GEF Co-financing Policy……..(3) 
• Definition: “resources that are additional to the GEF grant1 and that are 
provided by the GEF Partner Agency itself and/or by other non-GEF sources 
that support the implementation of the GEF-financed project and the 
achievement of its objectives.” 
• Co-financing is required for all GEF full-sized and medium-sized projects 
and programmatic approaches (PAs). Optional for enabling activities. 
 PIFs & PAs must list indicative co-financing for work program 
inclusion. 
 For CEO endorsement, Agencies must confirm co-financing and 
provide evidence. 
 Agencies must list co-financing by source and type. 
 Secretariat reviews proposals for consistency with Policy. 
____________ 
1 GEF financing (e.g. the GEF grants) is determined on the basis of the agreed incremental cost 
principle.
10 
GEF Co-financing Policy……..(4) 
Council Document GEF/C.20/6/Rev.1 also notes that the Secretariat 
will “continue to review project co-financing as part of its assessment 
of whether the project is supported by an adequate financing package 
in light of the needs of the project.” (Paragraph 16) 
• GEF Secretariat will also monitor portfolio co-financing and report 
to Council through Annual Monitoring Review (AMR). 
• Agencies to report on materialized co-financing during 
implementation and project closure (per GEF PIR and TER-Terminal 
Evaluation Report) 
• Evaluation Office may evaluate co-financing through Overall 
Performance Studies. 
Link to the paper: http://www.thegef.org/gef/policy/co-financing
11 
Non-Grant Instrument 
GEF’s experience to date suggests that non-grant instruments 
can make an important contribution to the achievement of the 
GEF’s objectives. They have helped deliver innovative projects 
and catalytic partnerships. 
GEF-6 Policy Recommendations: expand the use of non-grant 
instruments, in view of the contributions these can make to 
leverage capital from private sector, to long-term financial 
sustainability through their potential for generating reflows, as 
well as the usefulness of assessing the demand for non-grant 
instruments for the public sector in GEF recipient countries.
12 
Non-Grant Instrument…………(2) 
• Since the GEF’s inception, a total of 86 projects have been recorded 
as having utilized a “non-grant” instrument, totaling $715 million of 
GEF financing (about 6% of the GEF’s total programmed amount); 
• Co-financing ratio of these projects has trended high over time, 
and is well above co-financing levels of GEF grant programming; 
• The largest share of projects has been in the CCM focal area (80% 
of the funds). 7 projects have been in the BD; 
• Debt instruments and risk mitigation products are the most 
frequently used non-grant instruments (71 % of the funds)
13 
GEF-6 Non-Grant Pilot 
• will play a key role in supporting the GEF’s efforts to leverage significant 
capital from the private sector through the use of innovative and flexible 
financial instruments. 
• will expand the range of tools available to the GEF and allow the GEF to 
assess the demand and applicability of GEF non-grant instruments for 
public sector recipients. 
• By demonstrating and validating successful models for the use of non-grant 
instruments, the GEF can help catalyze large-scale changes through 
broader adoption and generate experiences which may also be useful for 
other international environmental funding mechanisms such as the Green 
Climate Fund. 
• by focusing the Pilot on non-grant instruments that have the potential to 
generate reflows, the Pilot can make a contribution to the GEF Trust 
Fund’s financial sustainability.
14 
NGI Pilot: Implementation 
• A set-aside of $110 million for the Non-Grant Pilot. 
• The maximum amount of funding for each project is approximately $15 
million. 
• Proposals must be submitted by one of the GEF Partner Agencies on 
behalf of the potential project proponent. Interested parties are 
encouraged to contact the relevant GEF Partner Agency focal point. 
• Only proposals using non-grant instruments with a potential for 
reflows to the GEF Trust Fund will be funded under the Pilot. 
• Consistent with the Policy on Non-Grant Instruments, a broad and 
flexible range of debt, equity and guarantee instruments will be 
supported under the Pilot. For projects/programs with public sector 
recipients, instruments include concessional loans and guarantee 
instruments; an emphasis on concessional loans is expected.
15 
NGI Pilot Implementation – Selection Criteria 
• Project proposals are eligible as long as they contribute GEBs as per 
GEF’s strategic programming under GEF-6. 
• The Pilot will seek to fund a diversity of recipient countries, 
regions, and Focal Areas. Proposals for both full-sized projects and 
medium-sized projects will be considered. 
• The Pilot will support capacity building, technical assistance, and 
advisory services only if they are included as part of the overall 
investment using the non-grant instrument and if the overall 
investment has potential for reflow to the GEF Trust Fund.
16 
Implementation – Selection Criteria 
Following elements are especially encouraged: 
• demonstrate innovative application of financial 
mechanisms and partnerships that may be broadly adopted 
and can be scaled-up; 
• demonstrate use of non-grant instruments in areas other 
than CC; 
• deliver innovative engagement with the private sector and 
innovative business models; 
• deliver high levels of co-financing.
17 
Implementation – Financing Terms……(1) 
• For projects with private sector, the GEF Partner Agency 
will negotiate an appropriate lending rate or return on 
investment that is consistent with the Agency’s standard 
practices; 
• Ensures a minimum level of concessionality; 
• Avoids displacing other finance; 
• Catalyzes other investments; 
• The maximum maturity for private sector loans is twenty 
years; the exit date for equity investments will be negotiated 
case by case.
18 
Implementation – Financing Terms……(2) 
For projects/programs with loans to public sector recipients, the Pilot will 
use differentiated terms: softer concessional terms will be offered to LDCs 
and SIDS, while harder concessional terms will be offered to other countries 
as follows: 
GEF 
concessional 
loans under 
the Pilot 
Maturity 
(Years) 
Grace 
Period 
(Years) 
Annual Principal 
Repayment Years 
11-20 
(% of initial 
principal) 
Annual 
Principal 
Repayment 
Years 21-40 
(% of initial 
principal) 
Interest 
To LDCs 
and SIDS 
40 10 2% 4% 0.25% 
To Other 
Recipient 
Countries 
20 10 10% NA 0.75%
19 
Implementation – Financing Terms ………..(3) 
• Consistent with MDB standard lending practice, the GEF Agencies 
will not seek any guarantee or security for lending to sovereign 
governments under the Pilot. If a GEF loan under the Pilot is made 
to a sub-national entity, the beneficiary country will be required to 
guarantee the loan if the GEF Partner Agency requires such 
guarantees for sub-sovereign lending. 
• In case of the use of guarantee instruments for public sector entities, 
the reflow schedule and fees will be negotiated on a case-by-case 
basis by the GEF Partner Agency. There will be no requirement for 
sovereign government indemnity for any guarantee product
20 
Implementation - Application 
Schedule: 
• It is anticipated that funds under the Pilot could be allocated rapidly -- 
the Pilot aspires to be fully programed by the end of the calendar year 
2015. This will facilitate early compilation of lessons learned that 
might be useful for GEF-7 and for other interested parties. 
• The first opportunity for FSPs will open in Nov 2014 . Agencies are 
encouraged to submit projects/programs in time for consideration by 
Council in the June 2015 WP. The second opportunity for FSPs will 
open in July 2015. 
• Medium-sized projects can be submitted for CEO consideration under 
the Pilot on a rolling basis, consistent with regular processing of 
medium-sized projects.
21 
Gender Mainstreaming 
Policy on Gender Mainstreaming (PL/SD/02) was adopted in 2011 
• GEF’s commitment to enhancing gender equality through GEF operations. 
• The Policy calls on the GEF Agencies to have policies, strategies, or action 
plans that meet the seven minimum standards: 
1) Institutional capacity for gender mainstreaming 
2) Consideration of gender elements in project design, 
implementation and review 
3) Undertake project gender analysis 
4) Measures to minimize/mitigate adverse gender impacts 
5) Integration of gender sensitive activities 
6) Monitoring and evaluation of gender mainstreaming progress 
7) Inclusion of gender experts in projects
22 
Gender Equality Action Plan 
To operationalize the Policy on Gender Mainstreaming, a Gender 
Equality Action Plan was approved by Council in the October 2014 
meeting where the following was established: 
• Concrete road map to implement the GEF Policy on Gender 
Mainstreaming that builds on the existing and planned gender 
strategies and plans of the GEF Agencies 
• Goal: to operationalize the mainstreaming of gender in GEF policy 
and programming to advance both the GEF’s goals for attaining 
GEBs and the goal of gender equality and women’s empowerment. 
• Initially serves during the GEF-6 period (FY15-18).
23 
Key Elements 
1. Project Cycle 
• Develop a Guideline on Mainstreaming Gender in GEF Project Cycle 
• Incorporate in Project Templates and Guidelines 
2. Programming and Policies 
• Support gender responsive projects, based on country demand and GEF-6 
Strategy 
• Mainstream gender in key GEF Strategy and Policy documents. 
3. Knowledge Management 
• Enhance KM on gender equality, in line with new KM strategy (Knowledge 
products, webpage, etc) 
4. Results Based Management 
• Strengthen GEF-wide accountability for gender mainstreaming by having 
Corporate and Focal Area level indicators and targets. 
5. Capacity Development 
• Strengthen capacity at GEFSEC institution and staff levels, OFPs and partners 
at the country level
24 
GEF-6 Core Gender Indicators 
1. Percentage of projects that have conducted gender analysis during 
project preparation. 
2. Percentage of projects that have incorporated gender responsive 
project results framework (e.g. gender responsive output, outcome, 
indicator, budget, etc). 
3. Share of women and men as direct beneficiaries of project. 
4. Share of convention related national reports incorporated gender 
dimensions (e.g. NBSAP, NAPA, TDA/SAP, etc.). 
5. Percentage of monitoring and evaluation reports that incorporates 
gender equality/women’s empowerment issues and assess 
results/progress.
25 
Public Involvement Policy 
Policy: Public Involvement in GEF Projects, GEF/PL/SD/01 
http://www.thegef.org/gef/content/public-involvement-policy 
• Approved by GEF Council in April 1996, based on paragraph 5 of the 
GEF Instrument. 
• Effective public involvement is critical to the success of GEF-financed 
projects, with emphasis on local participation. 
• Includes five principles and related requirements that all GEF Partner 
Agencies are required to follow to ensure public involvement in the 
design, implementation, and evaluation of GEF-financed projects. 
• GEF Partner Agencies must describe (in PIF and CEO endorsement) how 
they have ensured public involvement in project design and will continue 
during implementation.
26 
The Rationale for Public Involvement in 
GEF-financed Projects 
Public involvement improves the performance and impact of projects by: 
• Enhancing recipient country ownership of, and accountability for, 
project outcomes 
• Addressing the social and economic needs of affected people 
• Building partnerships among project executing agencies and 
stakeholders 
• Making use of skills, experiences, and knowledge, specifically of 
non-governmental organizations (NGOs), community and local 
groups, and the private sector in the design, implementation and 
evaluation of project activities.
27 
Public Involvement Guidelines: Overview 
 Information Dissemination 
 Consultation for Setting Priorities 
 Consultation for Project/Program Design and 
Implementation 
 Reporting, Monitoring and Evaluation
28 
Action Plan for Implementing Public Involvement 
Policy and Guidelines 
 Information Dissemination 
 Design of programs and projects 
 Knowledge Management 
 Monitoring 
 Capacity Development 
 Policy and Guidelines 
 Conflict Resolution
29 
Related Council Paper Links 
GEF website: www.thegef.org for all relevant project cycle papers 
for more detailed policies and procedures. 
GEF/C.38/05/Rev.1 
Streamlining the Project Cycle and Refining the Programmatic Approach 
GEF/C.39/Inf.03 GEF Project and Programmatic Approach Cycles 
GEF/C.43/06 Streamlining of Project Cycle 
GEF/C.47/07 Improving the GEF Project Cycle 
GEF/C.46/09 Co-financing Policy, http://www.thegef.org/gef/policy/co-financing 
For GEF Policies and Strategies, http://www.thegef.org/gef/policies 
For key GEF Policy and Procedure Documents: 
http://www.thegef.org/gef/policies_procedures
30 
. 
Thank you for your attention! 
Questions? 
Lily Uy Hale (Lhale@thegef.org) 
Sr. Operations Officer 
Operations and Business Strategy, GEF 
17

More Related Content

What's hot

From the medium term fiscal frameworkto ministries' ceilings
From the medium term fiscal frameworkto ministries' ceilingsFrom the medium term fiscal frameworkto ministries' ceilings
From the medium term fiscal frameworkto ministries' ceilings
Jean-Marc Lepain
 
Cambodia: Education Sector; A Short Fiscal Assessment
Cambodia: Education Sector; A Short Fiscal AssessmentCambodia: Education Sector; A Short Fiscal Assessment
Cambodia: Education Sector; A Short Fiscal Assessment
Jean-Marc Lepain
 
Facts on Public Finance Management
Facts on Public Finance ManagementFacts on Public Finance Management
Facts on Public Finance Management
Governance & Public Sector Management - The World Bank
 
Fiscal decentralisation and health sector financing formulae (lao pdr)
Fiscal decentralisation and health sector financing formulae (lao pdr)Fiscal decentralisation and health sector financing formulae (lao pdr)
Fiscal decentralisation and health sector financing formulae (lao pdr)
Jean-Marc Lepain
 
Pefa presentation by dr malik khalid mehmood ph_d
Pefa presentation   by dr malik khalid mehmood ph_dPefa presentation   by dr malik khalid mehmood ph_d
Pefa presentation by dr malik khalid mehmood ph_d
Malik Khalid Mehmood
 
Country dialogue training external
Country dialogue training externalCountry dialogue training external
Country dialogue training external
clac.cab
 
Country dialog training external
Country dialog training externalCountry dialog training external
Country dialog training external
clac.cab
 
Decc discussion slides investor simulation workshop breakout_onshore large-sc...
Decc discussion slides investor simulation workshop breakout_onshore large-sc...Decc discussion slides investor simulation workshop breakout_onshore large-sc...
Decc discussion slides investor simulation workshop breakout_onshore large-sc...
Department of Energy and Climate Change
 
Global Financing Facility (GFF) in Support of Every Woman Every Child Worksho...
Global Financing Facility (GFF) in Support of Every Woman Every Child Worksho...Global Financing Facility (GFF) in Support of Every Woman Every Child Worksho...
Global Financing Facility (GFF) in Support of Every Woman Every Child Worksho...
Global Financing Facility in support of Every Woman Every Child
 
Framework for Analyzing Public Investment Management
Framework for Analyzing Public Investment ManagementFramework for Analyzing Public Investment Management
Framework for Analyzing Public Investment Management
icgfmconference
 
Ihp Review 2008 Final Presentation
Ihp Review 2008 Final PresentationIhp Review 2008 Final Presentation
Ihp Review 2008 Final Presentation
ihp
 
Decc discussion slides investor simulation workshop breakout_biomass conversi...
Decc discussion slides investor simulation workshop breakout_biomass conversi...Decc discussion slides investor simulation workshop breakout_biomass conversi...
Decc discussion slides investor simulation workshop breakout_biomass conversi...
Department of Energy and Climate Change
 
NFM_master deck
NFM_master deckNFM_master deck
NFM_master deck
clac.cab
 
Decc discussion slides investor simulation workshop breakout_offshore_v 1 0
Decc discussion slides investor simulation workshop breakout_offshore_v 1 0Decc discussion slides investor simulation workshop breakout_offshore_v 1 0
Decc discussion slides investor simulation workshop breakout_offshore_v 1 0
Department of Energy and Climate Change
 
Blended Finance - Session 11 Managing Project Preparation for Climate Change ...
Blended Finance - Session 11 Managing Project Preparation for Climate Change ...Blended Finance - Session 11 Managing Project Preparation for Climate Change ...
Blended Finance - Session 11 Managing Project Preparation for Climate Change ...
UNDP Climate
 
Principles of budgetary governance - Ronnie Downes, OECD
Principles of budgetary governance - Ronnie Downes, OECDPrinciples of budgetary governance - Ronnie Downes, OECD
Principles of budgetary governance - Ronnie Downes, OECD
OECD Governance
 
Risk Management
Risk ManagementRisk Management
Risk Management
Fernando Penarroyo
 
#Managing Project Financial Auditing# By SN Panigrahi
#Managing Project Financial Auditing# By SN Panigrahi#Managing Project Financial Auditing# By SN Panigrahi
#Managing Project Financial Auditing# By SN Panigrahi
SN Panigrahi, PMP
 
From Strategy to Practice: The Tonle Sap Initiative
From Strategy to Practice: The Tonle Sap InitiativeFrom Strategy to Practice: The Tonle Sap Initiative
From Strategy to Practice: The Tonle Sap Initiative
Olivier Serrat
 
Dhaka revpres160814
Dhaka revpres160814Dhaka revpres160814
Dhaka revpres160814
Nizam Al-Hussainy
 

What's hot (20)

From the medium term fiscal frameworkto ministries' ceilings
From the medium term fiscal frameworkto ministries' ceilingsFrom the medium term fiscal frameworkto ministries' ceilings
From the medium term fiscal frameworkto ministries' ceilings
 
Cambodia: Education Sector; A Short Fiscal Assessment
Cambodia: Education Sector; A Short Fiscal AssessmentCambodia: Education Sector; A Short Fiscal Assessment
Cambodia: Education Sector; A Short Fiscal Assessment
 
Facts on Public Finance Management
Facts on Public Finance ManagementFacts on Public Finance Management
Facts on Public Finance Management
 
Fiscal decentralisation and health sector financing formulae (lao pdr)
Fiscal decentralisation and health sector financing formulae (lao pdr)Fiscal decentralisation and health sector financing formulae (lao pdr)
Fiscal decentralisation and health sector financing formulae (lao pdr)
 
Pefa presentation by dr malik khalid mehmood ph_d
Pefa presentation   by dr malik khalid mehmood ph_dPefa presentation   by dr malik khalid mehmood ph_d
Pefa presentation by dr malik khalid mehmood ph_d
 
Country dialogue training external
Country dialogue training externalCountry dialogue training external
Country dialogue training external
 
Country dialog training external
Country dialog training externalCountry dialog training external
Country dialog training external
 
Decc discussion slides investor simulation workshop breakout_onshore large-sc...
Decc discussion slides investor simulation workshop breakout_onshore large-sc...Decc discussion slides investor simulation workshop breakout_onshore large-sc...
Decc discussion slides investor simulation workshop breakout_onshore large-sc...
 
Global Financing Facility (GFF) in Support of Every Woman Every Child Worksho...
Global Financing Facility (GFF) in Support of Every Woman Every Child Worksho...Global Financing Facility (GFF) in Support of Every Woman Every Child Worksho...
Global Financing Facility (GFF) in Support of Every Woman Every Child Worksho...
 
Framework for Analyzing Public Investment Management
Framework for Analyzing Public Investment ManagementFramework for Analyzing Public Investment Management
Framework for Analyzing Public Investment Management
 
Ihp Review 2008 Final Presentation
Ihp Review 2008 Final PresentationIhp Review 2008 Final Presentation
Ihp Review 2008 Final Presentation
 
Decc discussion slides investor simulation workshop breakout_biomass conversi...
Decc discussion slides investor simulation workshop breakout_biomass conversi...Decc discussion slides investor simulation workshop breakout_biomass conversi...
Decc discussion slides investor simulation workshop breakout_biomass conversi...
 
NFM_master deck
NFM_master deckNFM_master deck
NFM_master deck
 
Decc discussion slides investor simulation workshop breakout_offshore_v 1 0
Decc discussion slides investor simulation workshop breakout_offshore_v 1 0Decc discussion slides investor simulation workshop breakout_offshore_v 1 0
Decc discussion slides investor simulation workshop breakout_offshore_v 1 0
 
Blended Finance - Session 11 Managing Project Preparation for Climate Change ...
Blended Finance - Session 11 Managing Project Preparation for Climate Change ...Blended Finance - Session 11 Managing Project Preparation for Climate Change ...
Blended Finance - Session 11 Managing Project Preparation for Climate Change ...
 
Principles of budgetary governance - Ronnie Downes, OECD
Principles of budgetary governance - Ronnie Downes, OECDPrinciples of budgetary governance - Ronnie Downes, OECD
Principles of budgetary governance - Ronnie Downes, OECD
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
#Managing Project Financial Auditing# By SN Panigrahi
#Managing Project Financial Auditing# By SN Panigrahi#Managing Project Financial Auditing# By SN Panigrahi
#Managing Project Financial Auditing# By SN Panigrahi
 
From Strategy to Practice: The Tonle Sap Initiative
From Strategy to Practice: The Tonle Sap InitiativeFrom Strategy to Practice: The Tonle Sap Initiative
From Strategy to Practice: The Tonle Sap Initiative
 
Dhaka revpres160814
Dhaka revpres160814Dhaka revpres160814
Dhaka revpres160814
 

Viewers also liked

Art4c
Art4cArt4c
Tu empresa en internet (1)
Tu empresa en internet (1)Tu empresa en internet (1)
Tu empresa en internet (1)
Digital Pymes
 
2012trendraporufanzineri
2012trendraporufanzineri2012trendraporufanzineri
2012trendraporufanzineriFanzineri
 
App economics: emprender en el móvil
App economics: emprender en el móvilApp economics: emprender en el móvil
App economics: emprender en el móvil
Enrique Farez
 
Accelerating Media Business Developments
Accelerating Media Business DevelopmentsAccelerating Media Business Developments
Accelerating Media Business Developments
Alpen-Adria-Universität
 
the screener
the screenerthe screener
Clases para matrimonio 5
Clases para matrimonio 5Clases para matrimonio 5
Clases para matrimonio 5
Iglesia Lirio del valle
 
Tolerancia a fallos y la TVDI - Josemar Rodrigues de Souza
Tolerancia a fallos y la TVDI - Josemar Rodrigues de SouzaTolerancia a fallos y la TVDI - Josemar Rodrigues de Souza
Tolerancia a fallos y la TVDI - Josemar Rodrigues de Souza
Red Auti
 
Curso Experto Auditoria 11 / 12
Curso Experto Auditoria 11 / 12Curso Experto Auditoria 11 / 12
Curso Experto Auditoria 11 / 12
Centro Desarrollo Directivo
 
Paper & More Express
Paper & More ExpressPaper & More Express
Paper & More Express
Jose_Segundo
 
Gia cong balo
Gia cong baloGia cong balo
Gia cong balo
Bin Nguyễn
 
Brief Introduction Of Products
Brief Introduction Of ProductsBrief Introduction Of Products
Brief Introduction Of Products
Catherine Liu
 
Buz dg credentials
Buz dg credentialsBuz dg credentials
Using Email To Engage Users & Drive Product Innovation - A Ziff Davis Enterpr...
Using Email To Engage Users & Drive Product Innovation - A Ziff Davis Enterpr...Using Email To Engage Users & Drive Product Innovation - A Ziff Davis Enterpr...
Using Email To Engage Users & Drive Product Innovation - A Ziff Davis Enterpr...
WhatCounts, Inc.
 
707 zile subt cultura pumnului german virgiliu n. drăghiceanu
707 zile subt cultura pumnului german   virgiliu n. drăghiceanu707 zile subt cultura pumnului german   virgiliu n. drăghiceanu
707 zile subt cultura pumnului german virgiliu n. drăghiceanu
salaru
 
Strategy for digital welfare 2013-2020 - Suzanne Duus, Denmark
Strategy for digital welfare 2013-2020 - Suzanne Duus, DenmarkStrategy for digital welfare 2013-2020 - Suzanne Duus, Denmark
Strategy for digital welfare 2013-2020 - Suzanne Duus, Denmark
OECD Governance
 
Tdh - Ayuda a la infancia. Presentación a empresas 2013
Tdh - Ayuda a la infancia. Presentación a empresas 2013Tdh - Ayuda a la infancia. Presentación a empresas 2013
Tdh - Ayuda a la infancia. Presentación a empresas 2013
Tierra de hombres - Ayuda a la infancia
 
IT-Sicherheit - Themenfokus Website - Netzwerk Elektronischer Geschäftsverkehr
IT-Sicherheit - Themenfokus Website - Netzwerk Elektronischer GeschäftsverkehrIT-Sicherheit - Themenfokus Website - Netzwerk Elektronischer Geschäftsverkehr
IT-Sicherheit - Themenfokus Website - Netzwerk Elektronischer GeschäftsverkehreBusinessLotse-Suedwestfalen-Hagen
 
The Weichert Princeton Office September Training Calendar
The Weichert Princeton Office September Training CalendarThe Weichert Princeton Office September Training Calendar
The Weichert Princeton Office September Training Calendar
Weichert Realtors
 
Dynamic Resource Allocation Strategy CL 12-16-2014
Dynamic Resource Allocation Strategy CL 12-16-2014Dynamic Resource Allocation Strategy CL 12-16-2014
Dynamic Resource Allocation Strategy CL 12-16-2014
Christopher Lietz
 

Viewers also liked (20)

Art4c
Art4cArt4c
Art4c
 
Tu empresa en internet (1)
Tu empresa en internet (1)Tu empresa en internet (1)
Tu empresa en internet (1)
 
2012trendraporufanzineri
2012trendraporufanzineri2012trendraporufanzineri
2012trendraporufanzineri
 
App economics: emprender en el móvil
App economics: emprender en el móvilApp economics: emprender en el móvil
App economics: emprender en el móvil
 
Accelerating Media Business Developments
Accelerating Media Business DevelopmentsAccelerating Media Business Developments
Accelerating Media Business Developments
 
the screener
the screenerthe screener
the screener
 
Clases para matrimonio 5
Clases para matrimonio 5Clases para matrimonio 5
Clases para matrimonio 5
 
Tolerancia a fallos y la TVDI - Josemar Rodrigues de Souza
Tolerancia a fallos y la TVDI - Josemar Rodrigues de SouzaTolerancia a fallos y la TVDI - Josemar Rodrigues de Souza
Tolerancia a fallos y la TVDI - Josemar Rodrigues de Souza
 
Curso Experto Auditoria 11 / 12
Curso Experto Auditoria 11 / 12Curso Experto Auditoria 11 / 12
Curso Experto Auditoria 11 / 12
 
Paper & More Express
Paper & More ExpressPaper & More Express
Paper & More Express
 
Gia cong balo
Gia cong baloGia cong balo
Gia cong balo
 
Brief Introduction Of Products
Brief Introduction Of ProductsBrief Introduction Of Products
Brief Introduction Of Products
 
Buz dg credentials
Buz dg credentialsBuz dg credentials
Buz dg credentials
 
Using Email To Engage Users & Drive Product Innovation - A Ziff Davis Enterpr...
Using Email To Engage Users & Drive Product Innovation - A Ziff Davis Enterpr...Using Email To Engage Users & Drive Product Innovation - A Ziff Davis Enterpr...
Using Email To Engage Users & Drive Product Innovation - A Ziff Davis Enterpr...
 
707 zile subt cultura pumnului german virgiliu n. drăghiceanu
707 zile subt cultura pumnului german   virgiliu n. drăghiceanu707 zile subt cultura pumnului german   virgiliu n. drăghiceanu
707 zile subt cultura pumnului german virgiliu n. drăghiceanu
 
Strategy for digital welfare 2013-2020 - Suzanne Duus, Denmark
Strategy for digital welfare 2013-2020 - Suzanne Duus, DenmarkStrategy for digital welfare 2013-2020 - Suzanne Duus, Denmark
Strategy for digital welfare 2013-2020 - Suzanne Duus, Denmark
 
Tdh - Ayuda a la infancia. Presentación a empresas 2013
Tdh - Ayuda a la infancia. Presentación a empresas 2013Tdh - Ayuda a la infancia. Presentación a empresas 2013
Tdh - Ayuda a la infancia. Presentación a empresas 2013
 
IT-Sicherheit - Themenfokus Website - Netzwerk Elektronischer Geschäftsverkehr
IT-Sicherheit - Themenfokus Website - Netzwerk Elektronischer GeschäftsverkehrIT-Sicherheit - Themenfokus Website - Netzwerk Elektronischer Geschäftsverkehr
IT-Sicherheit - Themenfokus Website - Netzwerk Elektronischer Geschäftsverkehr
 
The Weichert Princeton Office September Training Calendar
The Weichert Princeton Office September Training CalendarThe Weichert Princeton Office September Training Calendar
The Weichert Princeton Office September Training Calendar
 
Dynamic Resource Allocation Strategy CL 12-16-2014
Dynamic Resource Allocation Strategy CL 12-16-2014Dynamic Resource Allocation Strategy CL 12-16-2014
Dynamic Resource Allocation Strategy CL 12-16-2014
 

Similar to GEF policies

Programmatic approach
Programmatic approach Programmatic approach
Programmatic approach
Programmatic approach Programmatic approach
Gfatm 081208 partnership forum arnsa pres v9
Gfatm 081208 partnership forum arnsa pres v9Gfatm 081208 partnership forum arnsa pres v9
Gfatm 081208 partnership forum arnsa pres v9
Mohamed Rafique
 
FPS FUNDING REPORT nov 2015
FPS FUNDING REPORT nov 2015 FPS FUNDING REPORT nov 2015
FPS FUNDING REPORT nov 2015
dadco
 
Progress towards Results: Overall Performance Study of the GEF (IWC5 Presenta...
Progress towards Results: Overall Performance Study of the GEF (IWC5 Presenta...Progress towards Results: Overall Performance Study of the GEF (IWC5 Presenta...
Progress towards Results: Overall Performance Study of the GEF (IWC5 Presenta...
Iwl Pcu
 
A Public Private Partnership Approch to Climate Finance
A Public Private Partnership Approch to Climate FinanceA Public Private Partnership Approch to Climate Finance
A Public Private Partnership Approch to Climate Finance
Aldo Baietti
 
Status of GCF support, review criteria and observations from progress to date
Status of GCF support, review criteria and observations from progress to dateStatus of GCF support, review criteria and observations from progress to date
Status of GCF support, review criteria and observations from progress to date
NAP Global Network
 
Developing projects and programs in a strategic manner: Adaptation Investment...
Developing projects and programs in a strategic manner: Adaptation Investment...Developing projects and programs in a strategic manner: Adaptation Investment...
Developing projects and programs in a strategic manner: Adaptation Investment...
NAP Global Network
 
Climate finance aoki (gef)scale up&replication-gef perspectives-ccxg gf march...
Climate finance aoki (gef)scale up&replication-gef perspectives-ccxg gf march...Climate finance aoki (gef)scale up&replication-gef perspectives-ccxg gf march...
Climate finance aoki (gef)scale up&replication-gef perspectives-ccxg gf march...
OECD Environment
 
Financial Inclusion Strategies: Global Trends and Lessons Learned from the AF...
Financial Inclusion Strategies: Global Trends and Lessons Learned from the AF...Financial Inclusion Strategies: Global Trends and Lessons Learned from the AF...
Financial Inclusion Strategies: Global Trends and Lessons Learned from the AF...
Alliance for Financial Inclusion
 
11 wectorial work group
11 wectorial work group11 wectorial work group
11 wectorial work group
PROCASUR Corporation
 
Plan Implementation
Plan ImplementationPlan Implementation
Plan Implementation
Jo Balucanag - Bitonio
 
Investment planning and public investment plans: Inssues and Best Practices
Investment planning and public investment plans: Inssues and Best PracticesInvestment planning and public investment plans: Inssues and Best Practices
Investment planning and public investment plans: Inssues and Best Practices
Jean-Marc Lepain
 
Talking Points on GCF’s Support for NAPs
Talking Points on GCF’s Support for NAPs Talking Points on GCF’s Support for NAPs
Talking Points on GCF’s Support for NAPs
NAP Events
 
1. Roger Garrini - good governance guidance GOV011015
1. Roger Garrini - good governance guidance GOV0110151. Roger Garrini - good governance guidance GOV011015
1. Roger Garrini - good governance guidance GOV011015
Association for Project Management
 
MR12CD Tuesday 13h00 - Sayed
MR12CD Tuesday 13h00 - SayedMR12CD Tuesday 13h00 - Sayed
MR12CD Tuesday 13h00 - Sayed
7391456
 
Energy Efficiency financing & evaluation criteria
Energy Efficiency  financing & evaluation criteriaEnergy Efficiency  financing & evaluation criteria
Energy Efficiency financing & evaluation criteria
ZAINI ABDUL WAHAB
 
GEF's Support and Experience on Capacity Building for Transparency GEF''s, Du...
GEF's Support and Experience on Capacity Building for Transparency GEF''s, Du...GEF's Support and Experience on Capacity Building for Transparency GEF''s, Du...
GEF's Support and Experience on Capacity Building for Transparency GEF''s, Du...
OECD Environment
 
Session 5.1: Programatic approach in building resilience
Session 5.1: Programatic approach in building resilienceSession 5.1: Programatic approach in building resilience
Session 5.1: Programatic approach in building resilience
NAP Events
 
Retirement Plan News | Fall 2016
Retirement Plan News | Fall 2016Retirement Plan News | Fall 2016
Retirement Plan News | Fall 2016
CBIZ, Inc.
 

Similar to GEF policies (20)

Programmatic approach
Programmatic approach Programmatic approach
Programmatic approach
 
Programmatic approach
Programmatic approach Programmatic approach
Programmatic approach
 
Gfatm 081208 partnership forum arnsa pres v9
Gfatm 081208 partnership forum arnsa pres v9Gfatm 081208 partnership forum arnsa pres v9
Gfatm 081208 partnership forum arnsa pres v9
 
FPS FUNDING REPORT nov 2015
FPS FUNDING REPORT nov 2015 FPS FUNDING REPORT nov 2015
FPS FUNDING REPORT nov 2015
 
Progress towards Results: Overall Performance Study of the GEF (IWC5 Presenta...
Progress towards Results: Overall Performance Study of the GEF (IWC5 Presenta...Progress towards Results: Overall Performance Study of the GEF (IWC5 Presenta...
Progress towards Results: Overall Performance Study of the GEF (IWC5 Presenta...
 
A Public Private Partnership Approch to Climate Finance
A Public Private Partnership Approch to Climate FinanceA Public Private Partnership Approch to Climate Finance
A Public Private Partnership Approch to Climate Finance
 
Status of GCF support, review criteria and observations from progress to date
Status of GCF support, review criteria and observations from progress to dateStatus of GCF support, review criteria and observations from progress to date
Status of GCF support, review criteria and observations from progress to date
 
Developing projects and programs in a strategic manner: Adaptation Investment...
Developing projects and programs in a strategic manner: Adaptation Investment...Developing projects and programs in a strategic manner: Adaptation Investment...
Developing projects and programs in a strategic manner: Adaptation Investment...
 
Climate finance aoki (gef)scale up&replication-gef perspectives-ccxg gf march...
Climate finance aoki (gef)scale up&replication-gef perspectives-ccxg gf march...Climate finance aoki (gef)scale up&replication-gef perspectives-ccxg gf march...
Climate finance aoki (gef)scale up&replication-gef perspectives-ccxg gf march...
 
Financial Inclusion Strategies: Global Trends and Lessons Learned from the AF...
Financial Inclusion Strategies: Global Trends and Lessons Learned from the AF...Financial Inclusion Strategies: Global Trends and Lessons Learned from the AF...
Financial Inclusion Strategies: Global Trends and Lessons Learned from the AF...
 
11 wectorial work group
11 wectorial work group11 wectorial work group
11 wectorial work group
 
Plan Implementation
Plan ImplementationPlan Implementation
Plan Implementation
 
Investment planning and public investment plans: Inssues and Best Practices
Investment planning and public investment plans: Inssues and Best PracticesInvestment planning and public investment plans: Inssues and Best Practices
Investment planning and public investment plans: Inssues and Best Practices
 
Talking Points on GCF’s Support for NAPs
Talking Points on GCF’s Support for NAPs Talking Points on GCF’s Support for NAPs
Talking Points on GCF’s Support for NAPs
 
1. Roger Garrini - good governance guidance GOV011015
1. Roger Garrini - good governance guidance GOV0110151. Roger Garrini - good governance guidance GOV011015
1. Roger Garrini - good governance guidance GOV011015
 
MR12CD Tuesday 13h00 - Sayed
MR12CD Tuesday 13h00 - SayedMR12CD Tuesday 13h00 - Sayed
MR12CD Tuesday 13h00 - Sayed
 
Energy Efficiency financing & evaluation criteria
Energy Efficiency  financing & evaluation criteriaEnergy Efficiency  financing & evaluation criteria
Energy Efficiency financing & evaluation criteria
 
GEF's Support and Experience on Capacity Building for Transparency GEF''s, Du...
GEF's Support and Experience on Capacity Building for Transparency GEF''s, Du...GEF's Support and Experience on Capacity Building for Transparency GEF''s, Du...
GEF's Support and Experience on Capacity Building for Transparency GEF''s, Du...
 
Session 5.1: Programatic approach in building resilience
Session 5.1: Programatic approach in building resilienceSession 5.1: Programatic approach in building resilience
Session 5.1: Programatic approach in building resilience
 
Retirement Plan News | Fall 2016
Retirement Plan News | Fall 2016Retirement Plan News | Fall 2016
Retirement Plan News | Fall 2016
 

More from IFAD International Fund for Agricultural Development

Happy facts
Happy factsHappy facts
3 bsp awards-gfrd2015
3 bsp    awards-gfrd20153 bsp    awards-gfrd2015
Gfrd awards world remit
Gfrd awards world remitGfrd awards world remit
Marco nicoli greenback
Marco nicoli   greenbackMarco nicoli   greenback
Malaysia greenback project june 2015 alison ang
Malaysia greenback project june 2015 alison angMalaysia greenback project june 2015 alison ang
Malaysia greenback project june 2015 alison ang
IFAD International Fund for Agricultural Development
 
Pedro de vasconcelos
Pedro de vasconcelosPedro de vasconcelos
Tomas miller fomin
Tomas miller fominTomas miller fomin
David khoudour
David khoudourDavid khoudour
Bela hovy
Bela hovy Bela hovy
Dilip ratha
Dilip rathaDilip ratha
Josephine cervero
Josephine cerveroJosephine cervero
Nicolaas de zwager 10.1 b
Nicolaas de zwager 10.1 bNicolaas de zwager 10.1 b
Lee sorensen shuraako
Lee sorensen shuraakoLee sorensen shuraako
Sierra leone stats chuwku
Sierra leone stats chuwkuSierra leone stats chuwku
1 kinglsey
1 kinglsey1 kinglsey
Sabasaba mosinghi
Sabasaba mosinghiSabasaba mosinghi
De zwager iasci 7.1 b
De zwager iasci 7.1 bDe zwager iasci 7.1 b
Gfrd pinci v2
Gfrd pinci v2Gfrd pinci v2
Simone di castro gsma
Simone di castro gsmaSimone di castro gsma

More from IFAD International Fund for Agricultural Development (20)

Happy facts
Happy factsHappy facts
Happy facts
 
3 bsp awards-gfrd2015
3 bsp    awards-gfrd20153 bsp    awards-gfrd2015
3 bsp awards-gfrd2015
 
Gfrd awards world remit
Gfrd awards world remitGfrd awards world remit
Gfrd awards world remit
 
Marco nicoli greenback
Marco nicoli   greenbackMarco nicoli   greenback
Marco nicoli greenback
 
Malaysia greenback project june 2015 alison ang
Malaysia greenback project june 2015 alison angMalaysia greenback project june 2015 alison ang
Malaysia greenback project june 2015 alison ang
 
Pedro de vasconcelos
Pedro de vasconcelosPedro de vasconcelos
Pedro de vasconcelos
 
Tomas miller fomin
Tomas miller fominTomas miller fomin
Tomas miller fomin
 
David khoudour
David khoudourDavid khoudour
David khoudour
 
Bela hovy
Bela hovy Bela hovy
Bela hovy
 
Dilip ratha
Dilip rathaDilip ratha
Dilip ratha
 
Josephine cervero
Josephine cerveroJosephine cervero
Josephine cervero
 
Nicolaas de zwager 10.1 b
Nicolaas de zwager 10.1 bNicolaas de zwager 10.1 b
Nicolaas de zwager 10.1 b
 
Mai anonuevo
Mai anonuevoMai anonuevo
Mai anonuevo
 
Lee sorensen shuraako
Lee sorensen shuraakoLee sorensen shuraako
Lee sorensen shuraako
 
Sierra leone stats chuwku
Sierra leone stats chuwkuSierra leone stats chuwku
Sierra leone stats chuwku
 
1 kinglsey
1 kinglsey1 kinglsey
1 kinglsey
 
Sabasaba mosinghi
Sabasaba mosinghiSabasaba mosinghi
Sabasaba mosinghi
 
De zwager iasci 7.1 b
De zwager iasci 7.1 bDe zwager iasci 7.1 b
De zwager iasci 7.1 b
 
Gfrd pinci v2
Gfrd pinci v2Gfrd pinci v2
Gfrd pinci v2
 
Simone di castro gsma
Simone di castro gsmaSimone di castro gsma
Simone di castro gsma
 

Recently uploaded

Enhanced action and stakeholder engagement for sustainable peatland management
Enhanced action and stakeholder engagement for sustainable peatland managementEnhanced action and stakeholder engagement for sustainable peatland management
Enhanced action and stakeholder engagement for sustainable peatland management
Global Landscapes Forum (GLF)
 
Global Peatlands Map and Hotspot Explanation Atlas
Global Peatlands Map and Hotspot Explanation AtlasGlobal Peatlands Map and Hotspot Explanation Atlas
Global Peatlands Map and Hotspot Explanation Atlas
Global Landscapes Forum (GLF)
 
原版制作(Newcastle毕业证书)纽卡斯尔大学毕业证在读证明一模一样
原版制作(Newcastle毕业证书)纽卡斯尔大学毕业证在读证明一模一样原版制作(Newcastle毕业证书)纽卡斯尔大学毕业证在读证明一模一样
原版制作(Newcastle毕业证书)纽卡斯尔大学毕业证在读证明一模一样
p2npnqp
 
world-environment-day-2024-240601103559-14f4c0b4.pptx
world-environment-day-2024-240601103559-14f4c0b4.pptxworld-environment-day-2024-240601103559-14f4c0b4.pptx
world-environment-day-2024-240601103559-14f4c0b4.pptx
mfasna35
 
在线办理(lboro毕业证书)拉夫堡大学毕业证学历证书一模一样
在线办理(lboro毕业证书)拉夫堡大学毕业证学历证书一模一样在线办理(lboro毕业证书)拉夫堡大学毕业证学历证书一模一样
在线办理(lboro毕业证书)拉夫堡大学毕业证学历证书一模一样
pjq9n1lk
 
原版制作(Manitoba毕业证书)曼尼托巴大学毕业证学位证一模一样
原版制作(Manitoba毕业证书)曼尼托巴大学毕业证学位证一模一样原版制作(Manitoba毕业证书)曼尼托巴大学毕业证学位证一模一样
原版制作(Manitoba毕业证书)曼尼托巴大学毕业证学位证一模一样
mvrpcz6
 
Environment Conservation Rules 2023 (ECR)-2023.pptx
Environment Conservation Rules 2023 (ECR)-2023.pptxEnvironment Conservation Rules 2023 (ECR)-2023.pptx
Environment Conservation Rules 2023 (ECR)-2023.pptx
neilsencassidy
 
Peatlands of Latin America and the Caribbean
Peatlands of Latin America and the CaribbeanPeatlands of Latin America and the Caribbean
Peatlands of Latin America and the Caribbean
Global Landscapes Forum (GLF)
 
Overview of the Global Peatlands Assessment
Overview of the Global Peatlands AssessmentOverview of the Global Peatlands Assessment
Overview of the Global Peatlands Assessment
Global Landscapes Forum (GLF)
 
Epcon is One of the World's leading Manufacturing Companies.
Epcon is One of the World's leading Manufacturing Companies.Epcon is One of the World's leading Manufacturing Companies.
Epcon is One of the World's leading Manufacturing Companies.
EpconLP
 
Improving the viability of probiotics by encapsulation methods for developmen...
Improving the viability of probiotics by encapsulation methods for developmen...Improving the viability of probiotics by encapsulation methods for developmen...
Improving the viability of probiotics by encapsulation methods for developmen...
Open Access Research Paper
 
Improving the Management of Peatlands and the Capacities of Stakeholders in I...
Improving the Management of Peatlands and the Capacities of Stakeholders in I...Improving the Management of Peatlands and the Capacities of Stakeholders in I...
Improving the Management of Peatlands and the Capacities of Stakeholders in I...
Global Landscapes Forum (GLF)
 
Kinetic studies on malachite green dye adsorption from aqueous solutions by A...
Kinetic studies on malachite green dye adsorption from aqueous solutions by A...Kinetic studies on malachite green dye adsorption from aqueous solutions by A...
Kinetic studies on malachite green dye adsorption from aqueous solutions by A...
Open Access Research Paper
 
Promoting Multilateral Cooperation for Sustainable Peatland management
Promoting Multilateral Cooperation for Sustainable Peatland managementPromoting Multilateral Cooperation for Sustainable Peatland management
Promoting Multilateral Cooperation for Sustainable Peatland management
Global Landscapes Forum (GLF)
 
Evolving Lifecycles with High Resolution Site Characterization (HRSC) and 3-D...
Evolving Lifecycles with High Resolution Site Characterization (HRSC) and 3-D...Evolving Lifecycles with High Resolution Site Characterization (HRSC) and 3-D...
Evolving Lifecycles with High Resolution Site Characterization (HRSC) and 3-D...
Joshua Orris
 
Wildlife-AnIntroduction.pdf so that you know more about our environment
Wildlife-AnIntroduction.pdf so that you know more about our environmentWildlife-AnIntroduction.pdf so that you know more about our environment
Wildlife-AnIntroduction.pdf so that you know more about our environment
amishajha2407
 
Peatland Management in Indonesia, Science to Policy and Knowledge Education
Peatland Management in Indonesia, Science to Policy and Knowledge EducationPeatland Management in Indonesia, Science to Policy and Knowledge Education
Peatland Management in Indonesia, Science to Policy and Knowledge Education
Global Landscapes Forum (GLF)
 
Lessons from operationalizing integrated landscape approaches
Lessons from operationalizing integrated landscape approachesLessons from operationalizing integrated landscape approaches
Lessons from operationalizing integrated landscape approaches
CIFOR-ICRAF
 
Microbial characterisation and identification, and potability of River Kuywa ...
Microbial characterisation and identification, and potability of River Kuywa ...Microbial characterisation and identification, and potability of River Kuywa ...
Microbial characterisation and identification, and potability of River Kuywa ...
Open Access Research Paper
 
RoHS stands for Restriction of Hazardous Substances, which is also known as t...
RoHS stands for Restriction of Hazardous Substances, which is also known as t...RoHS stands for Restriction of Hazardous Substances, which is also known as t...
RoHS stands for Restriction of Hazardous Substances, which is also known as t...
vijaykumar292010
 

Recently uploaded (20)

Enhanced action and stakeholder engagement for sustainable peatland management
Enhanced action and stakeholder engagement for sustainable peatland managementEnhanced action and stakeholder engagement for sustainable peatland management
Enhanced action and stakeholder engagement for sustainable peatland management
 
Global Peatlands Map and Hotspot Explanation Atlas
Global Peatlands Map and Hotspot Explanation AtlasGlobal Peatlands Map and Hotspot Explanation Atlas
Global Peatlands Map and Hotspot Explanation Atlas
 
原版制作(Newcastle毕业证书)纽卡斯尔大学毕业证在读证明一模一样
原版制作(Newcastle毕业证书)纽卡斯尔大学毕业证在读证明一模一样原版制作(Newcastle毕业证书)纽卡斯尔大学毕业证在读证明一模一样
原版制作(Newcastle毕业证书)纽卡斯尔大学毕业证在读证明一模一样
 
world-environment-day-2024-240601103559-14f4c0b4.pptx
world-environment-day-2024-240601103559-14f4c0b4.pptxworld-environment-day-2024-240601103559-14f4c0b4.pptx
world-environment-day-2024-240601103559-14f4c0b4.pptx
 
在线办理(lboro毕业证书)拉夫堡大学毕业证学历证书一模一样
在线办理(lboro毕业证书)拉夫堡大学毕业证学历证书一模一样在线办理(lboro毕业证书)拉夫堡大学毕业证学历证书一模一样
在线办理(lboro毕业证书)拉夫堡大学毕业证学历证书一模一样
 
原版制作(Manitoba毕业证书)曼尼托巴大学毕业证学位证一模一样
原版制作(Manitoba毕业证书)曼尼托巴大学毕业证学位证一模一样原版制作(Manitoba毕业证书)曼尼托巴大学毕业证学位证一模一样
原版制作(Manitoba毕业证书)曼尼托巴大学毕业证学位证一模一样
 
Environment Conservation Rules 2023 (ECR)-2023.pptx
Environment Conservation Rules 2023 (ECR)-2023.pptxEnvironment Conservation Rules 2023 (ECR)-2023.pptx
Environment Conservation Rules 2023 (ECR)-2023.pptx
 
Peatlands of Latin America and the Caribbean
Peatlands of Latin America and the CaribbeanPeatlands of Latin America and the Caribbean
Peatlands of Latin America and the Caribbean
 
Overview of the Global Peatlands Assessment
Overview of the Global Peatlands AssessmentOverview of the Global Peatlands Assessment
Overview of the Global Peatlands Assessment
 
Epcon is One of the World's leading Manufacturing Companies.
Epcon is One of the World's leading Manufacturing Companies.Epcon is One of the World's leading Manufacturing Companies.
Epcon is One of the World's leading Manufacturing Companies.
 
Improving the viability of probiotics by encapsulation methods for developmen...
Improving the viability of probiotics by encapsulation methods for developmen...Improving the viability of probiotics by encapsulation methods for developmen...
Improving the viability of probiotics by encapsulation methods for developmen...
 
Improving the Management of Peatlands and the Capacities of Stakeholders in I...
Improving the Management of Peatlands and the Capacities of Stakeholders in I...Improving the Management of Peatlands and the Capacities of Stakeholders in I...
Improving the Management of Peatlands and the Capacities of Stakeholders in I...
 
Kinetic studies on malachite green dye adsorption from aqueous solutions by A...
Kinetic studies on malachite green dye adsorption from aqueous solutions by A...Kinetic studies on malachite green dye adsorption from aqueous solutions by A...
Kinetic studies on malachite green dye adsorption from aqueous solutions by A...
 
Promoting Multilateral Cooperation for Sustainable Peatland management
Promoting Multilateral Cooperation for Sustainable Peatland managementPromoting Multilateral Cooperation for Sustainable Peatland management
Promoting Multilateral Cooperation for Sustainable Peatland management
 
Evolving Lifecycles with High Resolution Site Characterization (HRSC) and 3-D...
Evolving Lifecycles with High Resolution Site Characterization (HRSC) and 3-D...Evolving Lifecycles with High Resolution Site Characterization (HRSC) and 3-D...
Evolving Lifecycles with High Resolution Site Characterization (HRSC) and 3-D...
 
Wildlife-AnIntroduction.pdf so that you know more about our environment
Wildlife-AnIntroduction.pdf so that you know more about our environmentWildlife-AnIntroduction.pdf so that you know more about our environment
Wildlife-AnIntroduction.pdf so that you know more about our environment
 
Peatland Management in Indonesia, Science to Policy and Knowledge Education
Peatland Management in Indonesia, Science to Policy and Knowledge EducationPeatland Management in Indonesia, Science to Policy and Knowledge Education
Peatland Management in Indonesia, Science to Policy and Knowledge Education
 
Lessons from operationalizing integrated landscape approaches
Lessons from operationalizing integrated landscape approachesLessons from operationalizing integrated landscape approaches
Lessons from operationalizing integrated landscape approaches
 
Microbial characterisation and identification, and potability of River Kuywa ...
Microbial characterisation and identification, and potability of River Kuywa ...Microbial characterisation and identification, and potability of River Kuywa ...
Microbial characterisation and identification, and potability of River Kuywa ...
 
RoHS stands for Restriction of Hazardous Substances, which is also known as t...
RoHS stands for Restriction of Hazardous Substances, which is also known as t...RoHS stands for Restriction of Hazardous Substances, which is also known as t...
RoHS stands for Restriction of Hazardous Substances, which is also known as t...
 

GEF policies

  • 1. GEF-6 Policies IFAD and FAO Learning Event on GEF Rome, Italy December 10-12, 2014
  • 2. 2 Overview Background: GEF Policies are usually submitted to Council for approval via Council papers but do not capture discussions/views of Council during the meeting. GEF Policy Framework: In GEF-6: Types and Hierarchy of Policy and Procedure Framework was established Policy: A statement of principles or values approved by the GEF Council that mandates or constrains activities undertaken to achieve the institutional goals of the GEF Secretariat. A Policy’s legal power is higher than that of procedures and guidelines. Procedures: A set of instructions or process that must be followed to adhere to a particular Policy or to accomplish an operational function or a specific task. Procedures are approved by the GEF CEO with the responsibility for the relevant Policy or relevant operational area or subject matter. Guideline: Additional information to help explain or implement a particular policy. Guidelines are approved by the CEO or by Team Leaders with responsibility of the relevant Policy or relevant operational area or subject matter. Guidelines have the lowest power in the strata of Policies, Procedures and Guidelines.
  • 3. 3 Overview…………(2) 1. GEF Programmatic Approach, 47th Council Meeting 2. Update on Project Cancellation Policy, 47th Council Meeting 3. Co-financing Policy, 46th Council Meeting 4. Non-Grant Instrument, 47th Council Meeting 5. Policy on Gender Mainstreaming, 47th Council Meeting 6. Public Involvement Policy, 7th Council Meeting
  • 4. 4 Programmatic Approach  Key document = a Program Framework Document (PFD) submitted in a work program for Council approval;  Program can be single-Agency or multi-Agency; single focal area or mutli-focal area, single trust fund or multi-trust fund;  For multi-Agency program, a Lead Agency will be identified to manage the program in all related administrative matters;  Extensive upstream consultation among relevant stakeholders;  Key Features in a PFD: • Discuss program objectives; • Describe all child project contributions to the program objective; • Establish a program commitment deadline.
  • 5. 5 Project Cancellation Policy Objectives:  to improve the GEF’s operational efficiency, particularly in the amount of time it takes to prepare and deliver projects;  to ensure that GEF-financed projects remain relevant to the objectives and priorities of the GEF and recipient countries. Using Phased approach to implement the policy: • After 12 months of Council approval of PIF, a notification will be sent to the Agency and OFP of the recipient country to alert them of the remaining 6 months for submission of project for CEO endorsement; • After 18 months, the Secretariat informs all relevant stakeholders on the cancellation of the project. • The Secretariat will consider exception to the above cancellation only on extraordinary events, and if agreed, will notify Council. • Cancelled projects maybe resubmitted within a year for consideration of CEO endorsement if resources are available.
  • 6. 6 Project Cancellation Policy……..(2) Cancellation of child projects under a program and unused program amount: • All child projects should be submitted for CEO endorsement by the program commitment deadline. • Six months before the program commitment deadline, if there are still program funds of child projects not yet CEO endorsed, the Secretariat sends a notification to the Lead Agency notifying it of the upcoming cancellation of such program funds. • After the passing of the program commitment deadline, the CEO notifies the relevant Lead Agency and the Trustee of the cancellation for the remaining program funds.
  • 7. 7 GEF Co-financing Policy • Approved by Council in May 2014, which has been posted as Policy FI/PL/01. This Policy:  establishes the objectives for co-financing in GEF-financed projects;  Defines co-financing for GEF-financed projects and programs; and  Provides rules/requirements on co-financing for GEF-financed projects and programs. • Applies to GEF Trust Fund and the Nagoya Protocol Implementation Fund (GEF-financed projects) financed projects and programs but not to LDCF or SCCF financed projects. • Council Document that proposed the Policy to the Council (Document GEF/C.20/6/Rev.1, Co-financing) contains helpful background and guidance on how it will be implemented.
  • 8. 8 GEF Co-financing Policy……..(2) • Objective: “to attain adequate levels of co-financing as a means to:  enhance the effectiveness and sustainability of the GEF in achieving global environmental benefits;  strengthen partnerships with recipient country governments, multilateral and bilateral financing entities, the private sector, and civil society.” • Includes “an ambition for the overall GEF portfolio to reach a co-financing ratio of at least 6:1, with expectations for greater co-financing in upper-middle income countries that are not SIDs.”  This is a portfolio ambition, not project-by-project.  GEF Secretariat “will not impose minimum thresholds and/or specific co-financing sources in the review of individual projects or work programs.”
  • 9. 9 GEF Co-financing Policy……..(3) • Definition: “resources that are additional to the GEF grant1 and that are provided by the GEF Partner Agency itself and/or by other non-GEF sources that support the implementation of the GEF-financed project and the achievement of its objectives.” • Co-financing is required for all GEF full-sized and medium-sized projects and programmatic approaches (PAs). Optional for enabling activities.  PIFs & PAs must list indicative co-financing for work program inclusion.  For CEO endorsement, Agencies must confirm co-financing and provide evidence.  Agencies must list co-financing by source and type.  Secretariat reviews proposals for consistency with Policy. ____________ 1 GEF financing (e.g. the GEF grants) is determined on the basis of the agreed incremental cost principle.
  • 10. 10 GEF Co-financing Policy……..(4) Council Document GEF/C.20/6/Rev.1 also notes that the Secretariat will “continue to review project co-financing as part of its assessment of whether the project is supported by an adequate financing package in light of the needs of the project.” (Paragraph 16) • GEF Secretariat will also monitor portfolio co-financing and report to Council through Annual Monitoring Review (AMR). • Agencies to report on materialized co-financing during implementation and project closure (per GEF PIR and TER-Terminal Evaluation Report) • Evaluation Office may evaluate co-financing through Overall Performance Studies. Link to the paper: http://www.thegef.org/gef/policy/co-financing
  • 11. 11 Non-Grant Instrument GEF’s experience to date suggests that non-grant instruments can make an important contribution to the achievement of the GEF’s objectives. They have helped deliver innovative projects and catalytic partnerships. GEF-6 Policy Recommendations: expand the use of non-grant instruments, in view of the contributions these can make to leverage capital from private sector, to long-term financial sustainability through their potential for generating reflows, as well as the usefulness of assessing the demand for non-grant instruments for the public sector in GEF recipient countries.
  • 12. 12 Non-Grant Instrument…………(2) • Since the GEF’s inception, a total of 86 projects have been recorded as having utilized a “non-grant” instrument, totaling $715 million of GEF financing (about 6% of the GEF’s total programmed amount); • Co-financing ratio of these projects has trended high over time, and is well above co-financing levels of GEF grant programming; • The largest share of projects has been in the CCM focal area (80% of the funds). 7 projects have been in the BD; • Debt instruments and risk mitigation products are the most frequently used non-grant instruments (71 % of the funds)
  • 13. 13 GEF-6 Non-Grant Pilot • will play a key role in supporting the GEF’s efforts to leverage significant capital from the private sector through the use of innovative and flexible financial instruments. • will expand the range of tools available to the GEF and allow the GEF to assess the demand and applicability of GEF non-grant instruments for public sector recipients. • By demonstrating and validating successful models for the use of non-grant instruments, the GEF can help catalyze large-scale changes through broader adoption and generate experiences which may also be useful for other international environmental funding mechanisms such as the Green Climate Fund. • by focusing the Pilot on non-grant instruments that have the potential to generate reflows, the Pilot can make a contribution to the GEF Trust Fund’s financial sustainability.
  • 14. 14 NGI Pilot: Implementation • A set-aside of $110 million for the Non-Grant Pilot. • The maximum amount of funding for each project is approximately $15 million. • Proposals must be submitted by one of the GEF Partner Agencies on behalf of the potential project proponent. Interested parties are encouraged to contact the relevant GEF Partner Agency focal point. • Only proposals using non-grant instruments with a potential for reflows to the GEF Trust Fund will be funded under the Pilot. • Consistent with the Policy on Non-Grant Instruments, a broad and flexible range of debt, equity and guarantee instruments will be supported under the Pilot. For projects/programs with public sector recipients, instruments include concessional loans and guarantee instruments; an emphasis on concessional loans is expected.
  • 15. 15 NGI Pilot Implementation – Selection Criteria • Project proposals are eligible as long as they contribute GEBs as per GEF’s strategic programming under GEF-6. • The Pilot will seek to fund a diversity of recipient countries, regions, and Focal Areas. Proposals for both full-sized projects and medium-sized projects will be considered. • The Pilot will support capacity building, technical assistance, and advisory services only if they are included as part of the overall investment using the non-grant instrument and if the overall investment has potential for reflow to the GEF Trust Fund.
  • 16. 16 Implementation – Selection Criteria Following elements are especially encouraged: • demonstrate innovative application of financial mechanisms and partnerships that may be broadly adopted and can be scaled-up; • demonstrate use of non-grant instruments in areas other than CC; • deliver innovative engagement with the private sector and innovative business models; • deliver high levels of co-financing.
  • 17. 17 Implementation – Financing Terms……(1) • For projects with private sector, the GEF Partner Agency will negotiate an appropriate lending rate or return on investment that is consistent with the Agency’s standard practices; • Ensures a minimum level of concessionality; • Avoids displacing other finance; • Catalyzes other investments; • The maximum maturity for private sector loans is twenty years; the exit date for equity investments will be negotiated case by case.
  • 18. 18 Implementation – Financing Terms……(2) For projects/programs with loans to public sector recipients, the Pilot will use differentiated terms: softer concessional terms will be offered to LDCs and SIDS, while harder concessional terms will be offered to other countries as follows: GEF concessional loans under the Pilot Maturity (Years) Grace Period (Years) Annual Principal Repayment Years 11-20 (% of initial principal) Annual Principal Repayment Years 21-40 (% of initial principal) Interest To LDCs and SIDS 40 10 2% 4% 0.25% To Other Recipient Countries 20 10 10% NA 0.75%
  • 19. 19 Implementation – Financing Terms ………..(3) • Consistent with MDB standard lending practice, the GEF Agencies will not seek any guarantee or security for lending to sovereign governments under the Pilot. If a GEF loan under the Pilot is made to a sub-national entity, the beneficiary country will be required to guarantee the loan if the GEF Partner Agency requires such guarantees for sub-sovereign lending. • In case of the use of guarantee instruments for public sector entities, the reflow schedule and fees will be negotiated on a case-by-case basis by the GEF Partner Agency. There will be no requirement for sovereign government indemnity for any guarantee product
  • 20. 20 Implementation - Application Schedule: • It is anticipated that funds under the Pilot could be allocated rapidly -- the Pilot aspires to be fully programed by the end of the calendar year 2015. This will facilitate early compilation of lessons learned that might be useful for GEF-7 and for other interested parties. • The first opportunity for FSPs will open in Nov 2014 . Agencies are encouraged to submit projects/programs in time for consideration by Council in the June 2015 WP. The second opportunity for FSPs will open in July 2015. • Medium-sized projects can be submitted for CEO consideration under the Pilot on a rolling basis, consistent with regular processing of medium-sized projects.
  • 21. 21 Gender Mainstreaming Policy on Gender Mainstreaming (PL/SD/02) was adopted in 2011 • GEF’s commitment to enhancing gender equality through GEF operations. • The Policy calls on the GEF Agencies to have policies, strategies, or action plans that meet the seven minimum standards: 1) Institutional capacity for gender mainstreaming 2) Consideration of gender elements in project design, implementation and review 3) Undertake project gender analysis 4) Measures to minimize/mitigate adverse gender impacts 5) Integration of gender sensitive activities 6) Monitoring and evaluation of gender mainstreaming progress 7) Inclusion of gender experts in projects
  • 22. 22 Gender Equality Action Plan To operationalize the Policy on Gender Mainstreaming, a Gender Equality Action Plan was approved by Council in the October 2014 meeting where the following was established: • Concrete road map to implement the GEF Policy on Gender Mainstreaming that builds on the existing and planned gender strategies and plans of the GEF Agencies • Goal: to operationalize the mainstreaming of gender in GEF policy and programming to advance both the GEF’s goals for attaining GEBs and the goal of gender equality and women’s empowerment. • Initially serves during the GEF-6 period (FY15-18).
  • 23. 23 Key Elements 1. Project Cycle • Develop a Guideline on Mainstreaming Gender in GEF Project Cycle • Incorporate in Project Templates and Guidelines 2. Programming and Policies • Support gender responsive projects, based on country demand and GEF-6 Strategy • Mainstream gender in key GEF Strategy and Policy documents. 3. Knowledge Management • Enhance KM on gender equality, in line with new KM strategy (Knowledge products, webpage, etc) 4. Results Based Management • Strengthen GEF-wide accountability for gender mainstreaming by having Corporate and Focal Area level indicators and targets. 5. Capacity Development • Strengthen capacity at GEFSEC institution and staff levels, OFPs and partners at the country level
  • 24. 24 GEF-6 Core Gender Indicators 1. Percentage of projects that have conducted gender analysis during project preparation. 2. Percentage of projects that have incorporated gender responsive project results framework (e.g. gender responsive output, outcome, indicator, budget, etc). 3. Share of women and men as direct beneficiaries of project. 4. Share of convention related national reports incorporated gender dimensions (e.g. NBSAP, NAPA, TDA/SAP, etc.). 5. Percentage of monitoring and evaluation reports that incorporates gender equality/women’s empowerment issues and assess results/progress.
  • 25. 25 Public Involvement Policy Policy: Public Involvement in GEF Projects, GEF/PL/SD/01 http://www.thegef.org/gef/content/public-involvement-policy • Approved by GEF Council in April 1996, based on paragraph 5 of the GEF Instrument. • Effective public involvement is critical to the success of GEF-financed projects, with emphasis on local participation. • Includes five principles and related requirements that all GEF Partner Agencies are required to follow to ensure public involvement in the design, implementation, and evaluation of GEF-financed projects. • GEF Partner Agencies must describe (in PIF and CEO endorsement) how they have ensured public involvement in project design and will continue during implementation.
  • 26. 26 The Rationale for Public Involvement in GEF-financed Projects Public involvement improves the performance and impact of projects by: • Enhancing recipient country ownership of, and accountability for, project outcomes • Addressing the social and economic needs of affected people • Building partnerships among project executing agencies and stakeholders • Making use of skills, experiences, and knowledge, specifically of non-governmental organizations (NGOs), community and local groups, and the private sector in the design, implementation and evaluation of project activities.
  • 27. 27 Public Involvement Guidelines: Overview  Information Dissemination  Consultation for Setting Priorities  Consultation for Project/Program Design and Implementation  Reporting, Monitoring and Evaluation
  • 28. 28 Action Plan for Implementing Public Involvement Policy and Guidelines  Information Dissemination  Design of programs and projects  Knowledge Management  Monitoring  Capacity Development  Policy and Guidelines  Conflict Resolution
  • 29. 29 Related Council Paper Links GEF website: www.thegef.org for all relevant project cycle papers for more detailed policies and procedures. GEF/C.38/05/Rev.1 Streamlining the Project Cycle and Refining the Programmatic Approach GEF/C.39/Inf.03 GEF Project and Programmatic Approach Cycles GEF/C.43/06 Streamlining of Project Cycle GEF/C.47/07 Improving the GEF Project Cycle GEF/C.46/09 Co-financing Policy, http://www.thegef.org/gef/policy/co-financing For GEF Policies and Strategies, http://www.thegef.org/gef/policies For key GEF Policy and Procedure Documents: http://www.thegef.org/gef/policies_procedures
  • 30. 30 . Thank you for your attention! Questions? Lily Uy Hale (Lhale@thegef.org) Sr. Operations Officer Operations and Business Strategy, GEF 17