PMP EXAM
SAMPLE Q & A
You are about to start planning for a large and complex project. Due to the size of the project along with
the regulatory and environmental considerations, the development of a detailed project management
plan will be critical.
As a starting point for initial project planning, what is the first thing you should do?
A. Conduct a project kick-off meeting to inform and engage stakeholders and gain commitment
B. Review the project charter to understand the high-level information about the project
C. Begin the process of identifying stakeholders so they can be engaged as necessary for project planning
D. Share the project scope statement with the project team for a common understanding of project
deliverables
HINT: The Initiating Process Group has been completed, and the Planning Process Group is about to
begin.
Question
The correct answer is B
The question states that project planning is about to begin which suggests that project initiation
has been completed. The project charter is created during the Develop Project Charter process as
part of project initiation. The project team uses the project charter as a starting point for initial
project planning. The type and amount of information in the project charter varies depending on
the complexity of the project and the information known at the time of its creation. At a
minimum, the project charter should define the high-level information about the project that will
be elaborated in the various components of the project management plan.
Answer
All our questions are updated to the latest 
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.


Stop by at free.pm-exam-simulator.com/ and try the
PM Exam Simulator free for 7 days.


We are a trusted and experienced education provider.

Free PMP Sample Q & A

  • 1.
  • 2.
    You are aboutto start planning for a large and complex project. Due to the size of the project along with the regulatory and environmental considerations, the development of a detailed project management plan will be critical. As a starting point for initial project planning, what is the first thing you should do? A. Conduct a project kick-off meeting to inform and engage stakeholders and gain commitment B. Review the project charter to understand the high-level information about the project C. Begin the process of identifying stakeholders so they can be engaged as necessary for project planning D. Share the project scope statement with the project team for a common understanding of project deliverables HINT: The Initiating Process Group has been completed, and the Planning Process Group is about to begin. Question
  • 3.
    The correct answeris B The question states that project planning is about to begin which suggests that project initiation has been completed. The project charter is created during the Develop Project Charter process as part of project initiation. The project team uses the project charter as a starting point for initial project planning. The type and amount of information in the project charter varies depending on the complexity of the project and the information known at the time of its creation. At a minimum, the project charter should define the high-level information about the project that will be elaborated in the various components of the project management plan. Answer
  • 4.
    All our questionsare updated to the latest  A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days. We are a trusted and experienced education provider.