2. Paradip Refinery – The Energy Gateway to Eastern India 2
Expansion of CISF Colony
Township
Contract detail -Plant Buildings IN FQUP (BSVI)
Building Contract Value Agency Contract Detail
Main Substation 340S
30,35,21,791.30
M/s SIL,
PO No. 27995509
PMC/EIC- tkIS
Award Date : 20-Jul-22
Completion Date : 26-Aug-23
Duration : 13 Months
SRR, 823
15,66,44,241.11
M/s SIL,
PO No. 27081977
PMC/EIC- tkIS
Award Date : 05-Jul-21
Completion Date : 04-May-22
Duration : 10 Months
GIS 300 Extn 5,14,45,614.12
M/s RKS,
PO No. 27011865
PMC/EIC- tkIS
Award Date : 13-Sep-21
Completion Date : 12-Apr-22
Duration : 7 Months
3. Paradip Refinery – The Energy Gateway to Eastern India 3
Expansion of CISF Colony
Township
Physical Progress status
Building CDD in Months Time Elapsed In Months
Physical
Progress
Achieved in
Percentage
Main Substation 340S 13 Months from 27.07.2022 4 Months 10 Days 12%
SRR, 823
10 Months from 05.07.2021 17 Months 2 Days 68%
GIS 300 Extn 07 Months from 13.09.2021 14 Months 24 Days 66%
4. Paradip Refinery – The Energy Gateway to Eastern India 4
Building Agency
Contract Detail
Unit
Scope
Qty
Complet
ed Qty
Balance
Qty
Remarks
Main
Substation,
SS340S
Stonehenge
Award Date : 20-Jul-22
Completion Date : 26-aug-23
Duration : 14 Months
Cum 4209 727.00 3482.00
1st Floor ready by 29.03.22
Expected completion of civil
works in all respect: 26.08.2023.
SRR, 823
Stonehenge
Award Date : 05-Jul-21
Completion Date : 04-May-22
Duration : 10 Months
Cum 3445 3379 66
Expected completion of civil
works: 28.02.2023.
GIS 300 Extn.
RKS
Award Date : 13-Sep-21
Completion Date : 12-Apr-22
Duration : 7 Months
Cum 661 560.00 101.00
Expected completion of civil
works: 31.12.2022.
5. Paradip Refinery – The Energy Gateway to Eastern India 5
GIS 300(Gas Insulated Switchgear)Extension Building-66KV
Building Size (850 Sqm)
Level
Milestones to be
achieved
RCC (Cum) Steel (MT) Brickwork (Cum) Outlook
Scope Status Scope Status Scope Status
Ground Floor (EL 0.44) Grade Slab
137
112 cum
completed
5
4.75 MT
completed
101.40
Completed
1st Floor (EL 3.74)
Roof Slab (at EL
8.49)
111.4 Completed
35
Completed
221.25
completed
Completed
Roof Slab (at EL
13..84)
195.4 Completed Completed
14.11.2022
15.12.2022
(Material
removing and
area cleaning)
Waterproofing 1104.558 Sqm Order placed to Sika, material not yet reached 31.12.2022
False ceiling 144.167 Sqm Order placed to Llyod, material not yet reached, Expected delivery at site 20.12.2022
22.10.2022
31.12.2022
AR Lining 89.025 Sqm Completed
Ironite flooring 1500.000 Sqm
550 sqm.
completed In Progress
Vitrified / Ceramic 71.57 Sqm Sample approved, material not yet reached, Expected delivery at site 20.12.2022 31.12.2022
6. Paradip Refinery – The Energy Gateway to Eastern India 6
GIS Extn Bldg. 300 (Ground Floor)
)
Ground Floor
Cellar Area Status Outlook
Ironite Flooring In progress 15.12.22
Cable Trench Completed
Reactor Area Status Outlook
Cable Trench Completed
Ironite Flooring In progress 31.12.22
Electrical fittings/ items- No data available from Contractor
7. Paradip Refinery – The Energy Gateway to Eastern India 7
GIS Extn Bldg.300 (First Floor at EL 3.74 m)
)
Battery Charger Room
Flooring & painting work completed, false
ceiling & door fixing yet to be start (Target
to complete within 1.12.2022 31.12.2022)
HVAC Room
Flooring, Putty work completed, painting
work started (One span brick wall
dismantled as per tkIS/IOCL instruction due
to HVAC panels shifting) 13.11.2022
First Floor (Roof Level EL 8.49m)
Battery Room
Flooring & painting work completed, false
ceiling & door fixing yet to be start (Target
to complete within 31.10.2022 31.12.2022)
8. Paradip Refinery – The Energy Gateway to Eastern India 8
GIS Extn Bldg.300
)
Shifting GIS Panels Status Outlook
Shuttering and Staging removal Completed
Balance brickwork In progress 21.11.2022 15.12.22
Internal Plaster In progress 21.11.2022 20.12.22
Ironite Flooring (Generation area) To be started 18.12.2022 23.12.22
Ironite Flooring (Distribution area) To be started 18.12.2022 31.12.22
Fire Door Fixing (9 Nos)
7 Nos completed(2 no’s hampered due to
existing toilet at First Floor) 14.12.2022 31.12.22
Concern
Rectification of GIS plates.
Delivery and Erection of EOT crane .
Delivery and Erection of Mono Rail, Structural steel for truss material.
Fire fighting sleepers and trench.
First Floor (Roof Level EL 13.84m)
Other jobs like Fire door (installation started), waterproofing, aluminum partition in corridor, etc. will be
taken up in parallel
10. Paradip Refinery – The Energy Gateway to Eastern India 10
SRR-823 (Satellite Rack Room)
Building Size (2700 Sqm)
Level
Milestones to be
achieved
RCC (Cum) Steel (MT) Brickwork (Cum) Outlook
Scope Status Scope Status Scope Status
Ground Floor Grade Slab
Completed Completed 524
350 Cum
completed, rest
is in progress 21.12.22
Ground Floor Slab (El
107.25) Roof Slab
1800 Completed 251 Completed NA NA
Waterproofing 3202 SQM 1000 Sqm completed, rest i/p
30.11.22
31.12.22
Plumbing & Sanitary Work Not yet started 15.01.23
Plastering Work 7037 SQM 1000 completed, rest i/p
31.12.22
31.01.23
False ceiling 1935.183 SQM Order placed, material yet to came 31.01.23
False Flooring 775 SQM Order placed, material yet to came (Subject to fixing of Panel Frames) 28.02.23
Ironite flooring 340 SQM Will be started after plastering work 28.02.23
Vitrified / Ceramic 950 SQM Target to submission of Physical sample on 31.12.2022 28.02.23
AR Lining 145 SQM Material yet to came 28.02.23
AL Partitions 450 SQM Material yet to came 17.02.23
Electrical Works Order placed for GI conduit, Material yet to came 28.02.23
11. Paradip Refinery – The Energy Gateway to Eastern India 11
Water proofing is under progress
12. Paradip Refinery – The Energy Gateway to Eastern India 12
Main Substation Building (MSS 340)
Building Size
(3200 Sqm)
Level
Milestones to be
achieved
RCC (Cum) Steel (MT) Brickwork (Cum) Outlook
Scope Status Scope Status Scope Status
Ground Floor
Grade Slab and
Cable trench
950
665 cum
completed, rest
is in progress
26
25 MT
completed,
rest is in
progress
485
94 cum
completed
18.11.22
10.12.22
1st Slab (at EL
105.4)
504
Shuttering &
Reinforcement
work i/p
83+24 In progress
10.12.22
10.01.23
1st Floor (EL
105.4)
2nd Slab (at EL
111.5)
596 Pending 78 Pending 689 Pending
31.01.23
28.02.23
13. Paradip Refinery – The Energy Gateway to Eastern India 13
Ground Floor Status Outlook
Cable trench In progress 07.12.22
Grade Slab In progress 10.12.22
Staging for Slab 1st Part completed 2nd Part -15.12.22
Steel reinforcement 1st Part – In progress 1st Part : 18.12.22 // 2nd Part : 08.01.23
Slab Casting 1st Part : 20.12.22 // 2nd Part : 10.01.23
Shuttering removal 1st part : 15.01.23 // 2nd part : 09.01.23 31.01.23
Brickwork 1st part : 25.01.23 // 2nd part : 20.01.23 10.02.23
Plaster 31.01.23 20.02.23
Flooring 13.02.23 23.02.23
Electrical conduit 11.02.23 28.02.23
Transformer Foundation In progress 25.01.23 (4 out of 12 no's front available)
Transformer Platform 01.02.23
Transformer area Brickwork and Plaster 20.02.23
14. Paradip Refinery – The Energy Gateway to Eastern India 14
1st Floor Status Outlook
Column lifting 06.01.23 25.01.23
Staging for Slab 14.01.23 31.01.23
Steel reinforcement 30.01.2022 03.02.23
Slab Casting 31.01.23 05.02.2023
Shuttering removal 01.03.23
Brickwork 12.03.23
Plaster 19.03.23
Flooring 29.03.23
False ceiling 31.03.23
Electrical conduit 15.03.23
Inside painting 24.03.23
16. Paradip Refinery – The Energy Gateway to Eastern India 16
Points of Concern
Porta Cabin / Container to be shifted by IOCL to provide the work front for B&R, TEL ( Compo) and
subsequently to M/s. Stonehenge for transformer foundations.
Resource / Manpower Augmentation
Procurement of TMT and Structural steel ( Corner Angles)