SlideShare a Scribd company logo
1 of 17
Paradip Refinery
Plant Building In FQUP
Paradip Refinery – The Energy Gateway to Eastern India 2
Expansion of CISF Colony
Township
Contract detail -Plant Buildings IN FQUP (BSVI)
Building Contract Value Agency Contract Detail
Main Substation 340S
30,35,21,791.30
M/s SIL,
PO No. 27995509
PMC/EIC- tkIS
Award Date : 20-Jul-22
Completion Date : 26-Aug-23
Duration : 13 Months
SRR, 823
15,66,44,241.11
M/s SIL,
PO No. 27081977
PMC/EIC- tkIS
Award Date : 05-Jul-21
Completion Date : 04-May-22
Duration : 10 Months
GIS 300 Extn 5,14,45,614.12
M/s RKS,
PO No. 27011865
PMC/EIC- tkIS
Award Date : 13-Sep-21
Completion Date : 12-Apr-22
Duration : 7 Months
Paradip Refinery – The Energy Gateway to Eastern India 3
Expansion of CISF Colony
Township
Physical Progress status
Building CDD in Months Time Elapsed In Months
Physical
Progress
Achieved in
Percentage
Main Substation 340S 13 Months from 27.07.2022 4 Months 10 Days 12%
SRR, 823
10 Months from 05.07.2021 17 Months 2 Days 68%
GIS 300 Extn 07 Months from 13.09.2021 14 Months 24 Days 66%
Paradip Refinery – The Energy Gateway to Eastern India 4
Building Agency
Contract Detail
Unit
Scope
Qty
Complet
ed Qty
Balance
Qty
Remarks
Main
Substation,
SS340S
Stonehenge
Award Date : 20-Jul-22
Completion Date : 26-aug-23
Duration : 14 Months
Cum 4209 727.00 3482.00
1st Floor ready by 29.03.22
Expected completion of civil
works in all respect: 26.08.2023.
SRR, 823
Stonehenge
Award Date : 05-Jul-21
Completion Date : 04-May-22
Duration : 10 Months
Cum 3445 3379 66
Expected completion of civil
works: 28.02.2023.
GIS 300 Extn.
RKS
Award Date : 13-Sep-21
Completion Date : 12-Apr-22
Duration : 7 Months
Cum 661 560.00 101.00
Expected completion of civil
works: 31.12.2022.
Paradip Refinery – The Energy Gateway to Eastern India 5
GIS 300(Gas Insulated Switchgear)Extension Building-66KV
Building Size (850 Sqm)
Level
Milestones to be
achieved
RCC (Cum) Steel (MT) Brickwork (Cum) Outlook
Scope Status Scope Status Scope Status
Ground Floor (EL 0.44) Grade Slab
137
112 cum
completed
5
4.75 MT
completed
101.40
Completed
1st Floor (EL 3.74)
Roof Slab (at EL
8.49)
111.4 Completed
35
Completed
221.25
completed
Completed
Roof Slab (at EL
13..84)
195.4 Completed Completed
14.11.2022
15.12.2022
(Material
removing and
area cleaning)
Waterproofing 1104.558 Sqm Order placed to Sika, material not yet reached 31.12.2022
False ceiling 144.167 Sqm Order placed to Llyod, material not yet reached, Expected delivery at site 20.12.2022
22.10.2022
31.12.2022
AR Lining 89.025 Sqm Completed
Ironite flooring 1500.000 Sqm
550 sqm.
completed In Progress
Vitrified / Ceramic 71.57 Sqm Sample approved, material not yet reached, Expected delivery at site 20.12.2022 31.12.2022
Paradip Refinery – The Energy Gateway to Eastern India 6
GIS Extn Bldg. 300 (Ground Floor)
)
Ground Floor
Cellar Area Status Outlook
Ironite Flooring In progress 15.12.22
Cable Trench Completed
Reactor Area Status Outlook
Cable Trench Completed
Ironite Flooring In progress 31.12.22
Electrical fittings/ items- No data available from Contractor
Paradip Refinery – The Energy Gateway to Eastern India 7
GIS Extn Bldg.300 (First Floor at EL 3.74 m)
)
Battery Charger Room
Flooring & painting work completed, false
ceiling & door fixing yet to be start (Target
to complete within 1.12.2022 31.12.2022)
HVAC Room
Flooring, Putty work completed, painting
work started (One span brick wall
dismantled as per tkIS/IOCL instruction due
to HVAC panels shifting) 13.11.2022
First Floor (Roof Level EL 8.49m)
Battery Room
Flooring & painting work completed, false
ceiling & door fixing yet to be start (Target
to complete within 31.10.2022 31.12.2022)
Paradip Refinery – The Energy Gateway to Eastern India 8
GIS Extn Bldg.300
)
Shifting GIS Panels Status Outlook
Shuttering and Staging removal Completed
Balance brickwork In progress 21.11.2022 15.12.22
Internal Plaster In progress 21.11.2022 20.12.22
Ironite Flooring (Generation area) To be started 18.12.2022 23.12.22
Ironite Flooring (Distribution area) To be started 18.12.2022 31.12.22
Fire Door Fixing (9 Nos)
7 Nos completed(2 no’s hampered due to
existing toilet at First Floor) 14.12.2022 31.12.22
Concern
 Rectification of GIS plates.
 Delivery and Erection of EOT crane .
 Delivery and Erection of Mono Rail, Structural steel for truss material.
 Fire fighting sleepers and trench.
First Floor (Roof Level EL 13.84m)
 Other jobs like Fire door (installation started), waterproofing, aluminum partition in corridor, etc. will be
taken up in parallel
Paradip Refinery – The Energy Gateway to Eastern India 9
Paradip Refinery – The Energy Gateway to Eastern India 10
SRR-823 (Satellite Rack Room)
Building Size (2700 Sqm)
Level
Milestones to be
achieved
RCC (Cum) Steel (MT) Brickwork (Cum) Outlook
Scope Status Scope Status Scope Status
Ground Floor Grade Slab
Completed Completed 524
350 Cum
completed, rest
is in progress 21.12.22
Ground Floor Slab (El
107.25) Roof Slab
1800 Completed 251 Completed NA NA
Waterproofing 3202 SQM 1000 Sqm completed, rest i/p
30.11.22
31.12.22
Plumbing & Sanitary Work Not yet started 15.01.23
Plastering Work 7037 SQM 1000 completed, rest i/p
31.12.22
31.01.23
False ceiling 1935.183 SQM Order placed, material yet to came 31.01.23
False Flooring 775 SQM Order placed, material yet to came (Subject to fixing of Panel Frames) 28.02.23
Ironite flooring 340 SQM Will be started after plastering work 28.02.23
Vitrified / Ceramic 950 SQM Target to submission of Physical sample on 31.12.2022 28.02.23
AR Lining 145 SQM Material yet to came 28.02.23
AL Partitions 450 SQM Material yet to came 17.02.23
Electrical Works Order placed for GI conduit, Material yet to came 28.02.23
Paradip Refinery – The Energy Gateway to Eastern India 11
 Water proofing is under progress
Paradip Refinery – The Energy Gateway to Eastern India 12
Main Substation Building (MSS 340)
Building Size
(3200 Sqm)
Level
Milestones to be
achieved
RCC (Cum) Steel (MT) Brickwork (Cum) Outlook
Scope Status Scope Status Scope Status
Ground Floor
Grade Slab and
Cable trench
950
665 cum
completed, rest
is in progress
26
25 MT
completed,
rest is in
progress
485
94 cum
completed
18.11.22
10.12.22
1st Slab (at EL
105.4)
504
Shuttering &
Reinforcement
work i/p
83+24 In progress
10.12.22
10.01.23
1st Floor (EL
105.4)
2nd Slab (at EL
111.5)
596 Pending 78 Pending 689 Pending
31.01.23
28.02.23
Paradip Refinery – The Energy Gateway to Eastern India 13
Ground Floor Status Outlook
Cable trench In progress 07.12.22
Grade Slab In progress 10.12.22
Staging for Slab 1st Part completed 2nd Part -15.12.22
Steel reinforcement 1st Part – In progress 1st Part : 18.12.22 // 2nd Part : 08.01.23
Slab Casting 1st Part : 20.12.22 // 2nd Part : 10.01.23
Shuttering removal 1st part : 15.01.23 // 2nd part : 09.01.23 31.01.23
Brickwork 1st part : 25.01.23 // 2nd part : 20.01.23 10.02.23
Plaster 31.01.23 20.02.23
Flooring 13.02.23 23.02.23
Electrical conduit 11.02.23 28.02.23
Transformer Foundation In progress 25.01.23 (4 out of 12 no's front available)
Transformer Platform 01.02.23
Transformer area Brickwork and Plaster 20.02.23
Paradip Refinery – The Energy Gateway to Eastern India 14
1st Floor Status Outlook
Column lifting 06.01.23 25.01.23
Staging for Slab 14.01.23 31.01.23
Steel reinforcement 30.01.2022 03.02.23
Slab Casting 31.01.23 05.02.2023
Shuttering removal 01.03.23
Brickwork 12.03.23
Plaster 19.03.23
Flooring 29.03.23
False ceiling 31.03.23
Electrical conduit 15.03.23
Inside painting 24.03.23
Paradip Refinery – The Energy Gateway to Eastern India 15
Paradip Refinery – The Energy Gateway to Eastern India 16
Points of Concern
 Porta Cabin / Container to be shifted by IOCL to provide the work front for B&R, TEL ( Compo) and
subsequently to M/s. Stonehenge for transformer foundations.
 Resource / Manpower Augmentation
 Procurement of TMT and Structural steel ( Corner Angles)
Paradip Refinery – The Energy Gateway to Eastern India 17

More Related Content

Similar to FQUP PPT.pptx

Design Status.pptx
Design Status.pptxDesign Status.pptx
Design Status.pptxssuser73884b
 
New Persentation
New PersentationNew Persentation
New PersentationTarek Fagal
 
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Allan Leyte
 
AGTL Project Status and Progress_20-01-2021.pptx
AGTL Project Status and Progress_20-01-2021.pptxAGTL Project Status and Progress_20-01-2021.pptx
AGTL Project Status and Progress_20-01-2021.pptxMdAbuNaser13
 
Al Qasr Mall presentation
Al Qasr Mall presentationAl Qasr Mall presentation
Al Qasr Mall presentationMamdouh Attia
 
Project management report of stadium
Project management report of stadiumProject management report of stadium
Project management report of stadiumSLIIT, Sri Lanka
 
Guidetosolarprojectimplementation 140323073210-phpapp01
Guidetosolarprojectimplementation 140323073210-phpapp01Guidetosolarprojectimplementation 140323073210-phpapp01
Guidetosolarprojectimplementation 140323073210-phpapp01Kiran Singh
 
A seminar report on stps by ashok khoja
A seminar report on stps by ashok khojaA seminar report on stps by ashok khoja
A seminar report on stps by ashok khojaASHOK KHOJA
 
Complete Report Of Nelum Jehlum Hydro Electric Project
Complete Report Of Nelum Jehlum Hydro Electric ProjectComplete Report Of Nelum Jehlum Hydro Electric Project
Complete Report Of Nelum Jehlum Hydro Electric ProjectEngr_Emad Khan
 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptxTalebAlfihan
 
Virat Vanijya_ Vishwakarma Industrial Park_r.pptx
Virat Vanijya_  Vishwakarma Industrial Park_r.pptxVirat Vanijya_  Vishwakarma Industrial Park_r.pptx
Virat Vanijya_ Vishwakarma Industrial Park_r.pptxSomSaha1
 
QUATRZ DRILLING AND LAB COMPANY PROFILE.pdf
QUATRZ DRILLING AND LAB COMPANY PROFILE.pdfQUATRZ DRILLING AND LAB COMPANY PROFILE.pdf
QUATRZ DRILLING AND LAB COMPANY PROFILE.pdfNeerajOjha17
 
Presentation Fatehpur Substation TL Final 22.09.2021.pptx
Presentation Fatehpur Substation  TL Final 22.09.2021.pptxPresentation Fatehpur Substation  TL Final 22.09.2021.pptx
Presentation Fatehpur Substation TL Final 22.09.2021.pptxabhishek357916
 
A valuable journey proposal
A valuable journey proposalA valuable journey proposal
A valuable journey proposalkjanand
 

Similar to FQUP PPT.pptx (20)

Design Status.pptx
Design Status.pptxDesign Status.pptx
Design Status.pptx
 
New Persentation
New PersentationNew Persentation
New Persentation
 
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
 
AGTL Project Status and Progress_20-01-2021.pptx
AGTL Project Status and Progress_20-01-2021.pptxAGTL Project Status and Progress_20-01-2021.pptx
AGTL Project Status and Progress_20-01-2021.pptx
 
Al Qasr Mall presentation
Al Qasr Mall presentationAl Qasr Mall presentation
Al Qasr Mall presentation
 
Project management report of stadium
Project management report of stadiumProject management report of stadium
Project management report of stadium
 
Final Year Review
Final Year ReviewFinal Year Review
Final Year Review
 
Training PPT
Training PPTTraining PPT
Training PPT
 
Guidetosolarprojectimplementation 140323073210-phpapp01
Guidetosolarprojectimplementation 140323073210-phpapp01Guidetosolarprojectimplementation 140323073210-phpapp01
Guidetosolarprojectimplementation 140323073210-phpapp01
 
Guide to Solar Project Implementation
Guide to Solar Project ImplementationGuide to Solar Project Implementation
Guide to Solar Project Implementation
 
A seminar report on stps by ashok khoja
A seminar report on stps by ashok khojaA seminar report on stps by ashok khoja
A seminar report on stps by ashok khoja
 
Complete Report Of Nelum Jehlum Hydro Electric Project
Complete Report Of Nelum Jehlum Hydro Electric ProjectComplete Report Of Nelum Jehlum Hydro Electric Project
Complete Report Of Nelum Jehlum Hydro Electric Project
 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptx
 
1Malaysia Cabin
1Malaysia Cabin1Malaysia Cabin
1Malaysia Cabin
 
Virat Vanijya_ Vishwakarma Industrial Park_r.pptx
Virat Vanijya_  Vishwakarma Industrial Park_r.pptxVirat Vanijya_  Vishwakarma Industrial Park_r.pptx
Virat Vanijya_ Vishwakarma Industrial Park_r.pptx
 
QUATRZ DRILLING AND LAB COMPANY PROFILE.pdf
QUATRZ DRILLING AND LAB COMPANY PROFILE.pdfQUATRZ DRILLING AND LAB COMPANY PROFILE.pdf
QUATRZ DRILLING AND LAB COMPANY PROFILE.pdf
 
sn-ladakh.pdf
sn-ladakh.pdfsn-ladakh.pdf
sn-ladakh.pdf
 
Presentation 19 04 2022.pdf
Presentation 19 04 2022.pdfPresentation 19 04 2022.pdf
Presentation 19 04 2022.pdf
 
Presentation Fatehpur Substation TL Final 22.09.2021.pptx
Presentation Fatehpur Substation  TL Final 22.09.2021.pptxPresentation Fatehpur Substation  TL Final 22.09.2021.pptx
Presentation Fatehpur Substation TL Final 22.09.2021.pptx
 
A valuable journey proposal
A valuable journey proposalA valuable journey proposal
A valuable journey proposal
 

Recently uploaded

Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 

Recently uploaded (20)

Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 

FQUP PPT.pptx

  • 2. Paradip Refinery – The Energy Gateway to Eastern India 2 Expansion of CISF Colony Township Contract detail -Plant Buildings IN FQUP (BSVI) Building Contract Value Agency Contract Detail Main Substation 340S 30,35,21,791.30 M/s SIL, PO No. 27995509 PMC/EIC- tkIS Award Date : 20-Jul-22 Completion Date : 26-Aug-23 Duration : 13 Months SRR, 823 15,66,44,241.11 M/s SIL, PO No. 27081977 PMC/EIC- tkIS Award Date : 05-Jul-21 Completion Date : 04-May-22 Duration : 10 Months GIS 300 Extn 5,14,45,614.12 M/s RKS, PO No. 27011865 PMC/EIC- tkIS Award Date : 13-Sep-21 Completion Date : 12-Apr-22 Duration : 7 Months
  • 3. Paradip Refinery – The Energy Gateway to Eastern India 3 Expansion of CISF Colony Township Physical Progress status Building CDD in Months Time Elapsed In Months Physical Progress Achieved in Percentage Main Substation 340S 13 Months from 27.07.2022 4 Months 10 Days 12% SRR, 823 10 Months from 05.07.2021 17 Months 2 Days 68% GIS 300 Extn 07 Months from 13.09.2021 14 Months 24 Days 66%
  • 4. Paradip Refinery – The Energy Gateway to Eastern India 4 Building Agency Contract Detail Unit Scope Qty Complet ed Qty Balance Qty Remarks Main Substation, SS340S Stonehenge Award Date : 20-Jul-22 Completion Date : 26-aug-23 Duration : 14 Months Cum 4209 727.00 3482.00 1st Floor ready by 29.03.22 Expected completion of civil works in all respect: 26.08.2023. SRR, 823 Stonehenge Award Date : 05-Jul-21 Completion Date : 04-May-22 Duration : 10 Months Cum 3445 3379 66 Expected completion of civil works: 28.02.2023. GIS 300 Extn. RKS Award Date : 13-Sep-21 Completion Date : 12-Apr-22 Duration : 7 Months Cum 661 560.00 101.00 Expected completion of civil works: 31.12.2022.
  • 5. Paradip Refinery – The Energy Gateway to Eastern India 5 GIS 300(Gas Insulated Switchgear)Extension Building-66KV Building Size (850 Sqm) Level Milestones to be achieved RCC (Cum) Steel (MT) Brickwork (Cum) Outlook Scope Status Scope Status Scope Status Ground Floor (EL 0.44) Grade Slab 137 112 cum completed 5 4.75 MT completed 101.40 Completed 1st Floor (EL 3.74) Roof Slab (at EL 8.49) 111.4 Completed 35 Completed 221.25 completed Completed Roof Slab (at EL 13..84) 195.4 Completed Completed 14.11.2022 15.12.2022 (Material removing and area cleaning) Waterproofing 1104.558 Sqm Order placed to Sika, material not yet reached 31.12.2022 False ceiling 144.167 Sqm Order placed to Llyod, material not yet reached, Expected delivery at site 20.12.2022 22.10.2022 31.12.2022 AR Lining 89.025 Sqm Completed Ironite flooring 1500.000 Sqm 550 sqm. completed In Progress Vitrified / Ceramic 71.57 Sqm Sample approved, material not yet reached, Expected delivery at site 20.12.2022 31.12.2022
  • 6. Paradip Refinery – The Energy Gateway to Eastern India 6 GIS Extn Bldg. 300 (Ground Floor) ) Ground Floor Cellar Area Status Outlook Ironite Flooring In progress 15.12.22 Cable Trench Completed Reactor Area Status Outlook Cable Trench Completed Ironite Flooring In progress 31.12.22 Electrical fittings/ items- No data available from Contractor
  • 7. Paradip Refinery – The Energy Gateway to Eastern India 7 GIS Extn Bldg.300 (First Floor at EL 3.74 m) ) Battery Charger Room Flooring & painting work completed, false ceiling & door fixing yet to be start (Target to complete within 1.12.2022 31.12.2022) HVAC Room Flooring, Putty work completed, painting work started (One span brick wall dismantled as per tkIS/IOCL instruction due to HVAC panels shifting) 13.11.2022 First Floor (Roof Level EL 8.49m) Battery Room Flooring & painting work completed, false ceiling & door fixing yet to be start (Target to complete within 31.10.2022 31.12.2022)
  • 8. Paradip Refinery – The Energy Gateway to Eastern India 8 GIS Extn Bldg.300 ) Shifting GIS Panels Status Outlook Shuttering and Staging removal Completed Balance brickwork In progress 21.11.2022 15.12.22 Internal Plaster In progress 21.11.2022 20.12.22 Ironite Flooring (Generation area) To be started 18.12.2022 23.12.22 Ironite Flooring (Distribution area) To be started 18.12.2022 31.12.22 Fire Door Fixing (9 Nos) 7 Nos completed(2 no’s hampered due to existing toilet at First Floor) 14.12.2022 31.12.22 Concern  Rectification of GIS plates.  Delivery and Erection of EOT crane .  Delivery and Erection of Mono Rail, Structural steel for truss material.  Fire fighting sleepers and trench. First Floor (Roof Level EL 13.84m)  Other jobs like Fire door (installation started), waterproofing, aluminum partition in corridor, etc. will be taken up in parallel
  • 9. Paradip Refinery – The Energy Gateway to Eastern India 9
  • 10. Paradip Refinery – The Energy Gateway to Eastern India 10 SRR-823 (Satellite Rack Room) Building Size (2700 Sqm) Level Milestones to be achieved RCC (Cum) Steel (MT) Brickwork (Cum) Outlook Scope Status Scope Status Scope Status Ground Floor Grade Slab Completed Completed 524 350 Cum completed, rest is in progress 21.12.22 Ground Floor Slab (El 107.25) Roof Slab 1800 Completed 251 Completed NA NA Waterproofing 3202 SQM 1000 Sqm completed, rest i/p 30.11.22 31.12.22 Plumbing & Sanitary Work Not yet started 15.01.23 Plastering Work 7037 SQM 1000 completed, rest i/p 31.12.22 31.01.23 False ceiling 1935.183 SQM Order placed, material yet to came 31.01.23 False Flooring 775 SQM Order placed, material yet to came (Subject to fixing of Panel Frames) 28.02.23 Ironite flooring 340 SQM Will be started after plastering work 28.02.23 Vitrified / Ceramic 950 SQM Target to submission of Physical sample on 31.12.2022 28.02.23 AR Lining 145 SQM Material yet to came 28.02.23 AL Partitions 450 SQM Material yet to came 17.02.23 Electrical Works Order placed for GI conduit, Material yet to came 28.02.23
  • 11. Paradip Refinery – The Energy Gateway to Eastern India 11  Water proofing is under progress
  • 12. Paradip Refinery – The Energy Gateway to Eastern India 12 Main Substation Building (MSS 340) Building Size (3200 Sqm) Level Milestones to be achieved RCC (Cum) Steel (MT) Brickwork (Cum) Outlook Scope Status Scope Status Scope Status Ground Floor Grade Slab and Cable trench 950 665 cum completed, rest is in progress 26 25 MT completed, rest is in progress 485 94 cum completed 18.11.22 10.12.22 1st Slab (at EL 105.4) 504 Shuttering & Reinforcement work i/p 83+24 In progress 10.12.22 10.01.23 1st Floor (EL 105.4) 2nd Slab (at EL 111.5) 596 Pending 78 Pending 689 Pending 31.01.23 28.02.23
  • 13. Paradip Refinery – The Energy Gateway to Eastern India 13 Ground Floor Status Outlook Cable trench In progress 07.12.22 Grade Slab In progress 10.12.22 Staging for Slab 1st Part completed 2nd Part -15.12.22 Steel reinforcement 1st Part – In progress 1st Part : 18.12.22 // 2nd Part : 08.01.23 Slab Casting 1st Part : 20.12.22 // 2nd Part : 10.01.23 Shuttering removal 1st part : 15.01.23 // 2nd part : 09.01.23 31.01.23 Brickwork 1st part : 25.01.23 // 2nd part : 20.01.23 10.02.23 Plaster 31.01.23 20.02.23 Flooring 13.02.23 23.02.23 Electrical conduit 11.02.23 28.02.23 Transformer Foundation In progress 25.01.23 (4 out of 12 no's front available) Transformer Platform 01.02.23 Transformer area Brickwork and Plaster 20.02.23
  • 14. Paradip Refinery – The Energy Gateway to Eastern India 14 1st Floor Status Outlook Column lifting 06.01.23 25.01.23 Staging for Slab 14.01.23 31.01.23 Steel reinforcement 30.01.2022 03.02.23 Slab Casting 31.01.23 05.02.2023 Shuttering removal 01.03.23 Brickwork 12.03.23 Plaster 19.03.23 Flooring 29.03.23 False ceiling 31.03.23 Electrical conduit 15.03.23 Inside painting 24.03.23
  • 15. Paradip Refinery – The Energy Gateway to Eastern India 15
  • 16. Paradip Refinery – The Energy Gateway to Eastern India 16 Points of Concern  Porta Cabin / Container to be shifted by IOCL to provide the work front for B&R, TEL ( Compo) and subsequently to M/s. Stonehenge for transformer foundations.  Resource / Manpower Augmentation  Procurement of TMT and Structural steel ( Corner Angles)
  • 17. Paradip Refinery – The Energy Gateway to Eastern India 17