AGTL Project Status
and Progress Review
20th January,
2021
INTRODUCTION
Contract Details
Project Name: Design, Supply, Installation, Testing & Commissioning of the Aminbazar-
Gopalganj 400 kV Double Circuit Transmission Line on turnkey basis.
(Contract No: PGCB/ADB/3522/400kV/TL/AGTL)
• Euro : 3,060,618.56
• USD : 42,617,495.36
• BDT : 1,745,619,243.16
Project Value
• 31st March, 2019
Contract Effective
Date
• 19th March, 2021
Finishing Date
• 720 Days
Project Duration
Overview of
AGTL 400kV
Double
Circuit
Total Length: 75.24 Km
• Part – 1 Gopalganj S/S - Jajira: 33.221 Km (94 Towers)
• Part – 2 Maowa – Aminbazar S/S: 41.538 Km (119 Towers)
Total Tower: 213 Nos
Tower Type: 4DL, 4D1, 4D25, 4D45, 4DT6
4DL: 135
4D1: 18
4D25: 36
4D45: 15
4DT6: 9
Total Route Map
TT-1 to TT-2.kmz
Top Issues
• Confidence Steel couldn’t supply the tower materials as per our
requirement which has hampered our tower erection work and
also stringing plan.
Tower Supply
• We have BDT 186,452,963.98 as outstanding.
PGCB Payment
• LS cable has not been approved yet and by this time if ZTT gets
clearance from the ADB (which they are in progress) then we
also have them as other option.
OPGW Vendor
Problem
DISCUSSION OF
LAST MPR
Key Discussion of Last MPR
SL No
Discussion Points
Summary
Decision/Deliverables Action by Status
1 EoT update
Meeting has been done with PD and PD told that PGCB will take decision
regarding the EoT in Feb-21. PD told that they have requested up to Dec-21 to
ADB. Project team have to check whether ADB has submitted NOC or not.
Project team will issue a follow up letter next week.
PM, Contract Dept.
Planner
Official letter has been submitted for
EoT claim.
2 Tower Supply Issue
Project team have communicated with CEO/CSL regarding supply of 4D25
tower and will try to convince him for making the delivery of 4D25 tower
within Jan-21 beyond the contract terms and conditions.
PM have engaged 2 persons to monitor the packing of tower materials. PM
Several meeting have been conducted
and still meetings are going on
3 Insulator Supply Delay
NGK told that they cannot arrange containers before end of Jan-21. After
several negotiation using SEPCO1 and MAX link, NGK is convinced to dispatch
1st Lot by 16th Dec, 20. Negotiation is going on for the early shipment of 2nd
Lot also.
Project will have insulator for 10 km in the Lot-1.
PM, Mr. Kuddush
Insulator Lot-1 already arrived and
waiting for customs clearance.
4 Tower Erection Plan
Already 7 erection gangs are at site. There are 94 towers at Gopalganj site and
these towers have been planned to complete first within Jan-21. Project team
is concentrating on Gopalganj site first.
Mr. kaiser and Mr.
Omar Faruk
8 gangs were engaged and we had a
good progress in Dec-20
Discussion of Last MPR
SL No
Discussion Points
Summary
Decision/Deliverables Action by Status
5 PG-APG Issue
PGCB has issued the letter regarding PG and APG. Draft has been
prepared and sent to PGCB for checking. It will take 2 days to
transfer the money after getting letter from PGCB. Hopefully,
early of the next week project will get it. Mr. Kuddush, Mr. Niaz
Already solved and amount has
been transferred also
6
Stringing Equipment & Vendor
Selection
Procurement of stringing equipment is not feasible as there is no
upcoming ACCC conductor project. So, project team has decided
not to procure the equipment.
Project team will go for the contract with GS E&C (Korea) for the
stringing work with equipment. Project team is trying to reduce
the price some more. They have 2 sets of equipment among
them one is required to have some maintenace work.
Mr. Khaled & Mr.
Kaiser
Already signed the agreement
with Shohel Engineers (GS Korea)
7 Starting Stringing Work
Stringing work is planning to start from Jan-21 at Gopalganj site.
Firstly, 1 set equipment will be engaged and after fixing the
problem another set will be deployed. Both sets will be used at
Gopalganj site which we target to complete first, then we will
move to Dhaka site.
Mr. kaiser and Mr.
Omar Faruk
Due to unavailability of 4D25
towers stringing schedule has
been delayed
8 OPGW Vendor Change Issue
Project team has submitted technical documents of new vendor
(LS Cables) to PGCB for approval. But PGCB told that this vendor
should be verified by ADB first and then PGCB will approve them.
ADB usually takes too much time in this type issue but PD assured
us to get the feedback from ADB ASAP.
LS assured us that they can supply within Feb-21 af we open LC
now.
Project Team, Project
Control
LS has not been approved yet. We
have another option of ZTT if they
get clearance from ADB asap
Discussion of Last MPR
SL No
Discussion Points
Summary
Decision/Deliverables Action by Status
9 MoM of Meeting with PD
Project office is doing monthly meeting with PD and already sent
the MoM of last meeting which PD did not sign. CEO sir
suggested to send MoM officially.
PM, Contract team
MoM has been sent with a official
letter
10 MSP Schedule
The MSP file with replan and without the resource assignment
need to be prepared within 10-12-2020
Mr. Zakir and Mr.
Shakib
MSP file has been prepared and
tracking has been done. As per
tracking we get the completion
date in Dec-21 which is logical
and based on that we have claim
for EoT up to Dec-21
11 Risk Register
CEO sir suggested Mr. Shaibajit to sit with Mr. Maher regarding
the risk register and justify the mitigation plan.
Mr. Shaibajit and Mr.
Maher
Discussion has been done in this
regard and a new format has been
made for maintaining the risk
register which has been started by
the project team (yet to develop
more for residual financial
impact)
12 Cost Claim
CEO sir suggested to find a way by which project team can assist
PGCB to prove additional cost incur so that those amount can be
considered into RDPP. Project Team
Project team has communicated
with PD regarding this and PD told
to not think about cost claim at
this stage. Firstly, try for the EoT
as required
13 Pending MRR
CEO sir asked to check with accounts that why the pending MRR
is so much.
Mr. Shaibajit, AGTL
Accounts
As ERP has been implemented
1.5yrs later, that’s why pending
MRR is showing high value. Now,
day by day it is coming under
control
SAFETY
&
PROGRESS
Safety Status
Trend Nov, 2020 Dec, 2020
Up to
Dec-2020
Rolling LTIFR (Indicative) 0 0
Number of Lost Time Injuries
(LTI)
0 0
Rolling TRIFR 0 0 3.48
Number of Total Recordable
Injuries (TRI)
0 0
No. of Man-hours worked 120,000 132,000 1,293,760
No. of Non-Lost Time Injuries 0 0
No. of Fatal Accidents 0 0
LTIFR is expressed thus: No. of LTI ÷ Manhour (Within the period in assessment) × 1000000
TRIFR : No. of TRI ÷ Manhour (Within the period in assessment) × 1000000
INCIDENT TYPE Dec-20
PTD (Up to
Dec-2020)
Near Miss 0
First Aid 0
Medical Aid 0
Lost Time
Accident
0
Environmental
Spills
0
Progress
Sl. No. Description
Total Weightage Work Completed as on (Weightage) Plan
Qty. Unit
Weightage
(%)
Qty. Unit
Weightage
(%)
Weightage
(%)
1
Survey including submission
of plan and profile, soil test.
75.24 km 5% 75.24 km 5.00% 5.00%
2
Design, approval and tower
test.
5 Nos. 5% 5 No 5.00% 5.00%
3 Foundation Pile. 213 Lot 15% 182 Lot 12.82% 13.02%
4 Pile Cap. 213 Lot 10% 103 Lot 4.84% 4.97%
5 Supply. 213 Lot 35% Lot 11.84% 24.28%
6 Tower Erection. 213 Lot 15% 47 Lot 3.31% 3.38%
7 Stringing. 213 km 10% km 0.00% 0.00%
8 Testing and Commissioning. 75.24 km 5% km 0.00% 0.00%
Total Work 100% 42.46% 55.65%
Variance -13.19%
Plan Vs Actual Graph
• Overall Progress
27.43%
29.41%
42.42%
55.65%
67.69%
76.94%
82.69%
87.91%
93.76%
98.00%
100.00%
1.41%
1.70%
3.60%
5.45%
8.45%
10.95%
13.63%
14.03%
16.45%
22.09%
24.88%
24.88%
24.88%
25.08%
25.37%
25.70%
26.99%
27.78%
35.06%
42.46%
0.79%
1.30%
2.68%
4.05%
6.11%
8.94%
11.96%
15.56%
20.16%
24.75%
30.00%
39.70%
40.50%
40.60%
42.50%
49.75%
37.84%
45.09%
60.05%
69.66%
76.23%
79.23%
83.03%
88.24%
90.91%
97.50%
100.00%
0.00%
20.00%
40.00%
60.00%
80.00%
100.00%
Overall Progress
Replan Actual Plan (Baseline)
Plan Vs Actual Graph
• Design (completed)
2.00%
7.00%
12.85%
22.35%
31.85%
41.35%
51.10%
61.25%
71.50%
82.00%
88.00%
93.00%
97.00% 98.00% 99.00% 100.00%
0.00%
3.00%
6.50%
12.00%
19.25%
29.75%
41.40%
53.25%
64.50%
77.15%
86.50%
91.00%
93.00%
96.00%
98.50% 100.00%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
Apr/19 May/19 Jun/19 Jul/19 Aug/19 Sep/19 Oct/19 Nov/19 Dec/19 Jan/20 Feb/20 Mar/20 Apr/20 May/20 Jun/20 Jul/20
Design Phase overall curve
cumulative Planned cumulative Actual
Plan Vs Actual Graph
• Civil Works
57.24%
67.56%
82.88%
92.12%
100.00%
0.20% 0.70% 1.20% 1.95%
6.95%
18.71%
27.91%
38.20% 38.20% 38.20%
44.96%
51.24% 51.24%
53.43%
55.88%
58.60%
70.64%
0.80% 2.00% 3.60%
5.60%
8.60%
19.60%
31.60%
47.60% 47.60% 47.60%
51.20%
56.20%
61.20%
53.43%
56.43%
61.31%
71.95%
84.16%
95.62%
100.00%
0.00%
20.00%
40.00%
60.00%
80.00%
100.00%
120.00%
Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21
Civil Work Progress
cumulative Plan (Baseline) cumulative Actual cumulative Replan
Plan Vs Actual Graph
• Tower Erection
0.94% 1.88% 1.41%
6.10%
22.53%
34.27%
50.71%
69.49%
87.79%
100.00%
0.00% 0.47% 0.94%
4.70%
22.07%
0.94% 1.88%
9.39%
21.13%
34.27%
48.36%
64.79%
81.22%
100.00%
0.00%
20.00%
40.00%
60.00%
80.00%
100.00%
Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21
Tower Erection
cumulative Replan cumulative Actual cumulative Plan (Baseline)
Plan Vs Actual Graph
• Supply
15.33% 14.75%
46.22%
72.83%
90.32%
100.00%
1.73%
9.49% 11.33% 11.42% 11.42%
27.77%
33.83%
0.00%
0.35%
0.35%
1.11%
1.11%
1.11%
2.43%
11.42%
13.35%
34.08%
44.37%
77.23%
91.51%
95.51%
100.00%
0.00%
20.00%
40.00%
60.00%
80.00%
100.00%
120.00%
Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21
Supply of Materials
cumulative Replan cumulative Actual cumulative Plan (Baseline)
LC STATUS
Vendor Contract & LC Status
Product Name Company Name Contract Status Contract Sign Date LC Status Remarks
Towers
Confidence Steel Ltd.,
Bangladesh
Signed 20-10-19
Opened on
16-09-2020
Conductor & Earthwire
Sterlite Power Transmission
Ltd., India
Signed 23-05-19
Opened on
08-03-20
Advance Payment has
been released
Insulator
Sumitomo Corporation power
and Mobility Co. Ltd., Japan
Signed 01-10-19
Opened on
20-09-20
Conductor, Insulator &
Earthwire Fittings
Dervaux S.A, France Signed 01-06-19
Opened on
02-09-2020
OPGW & Fittings
Jiangsu Tongguang Optical Fiber
Company Ltd., China
Signed
29-07-20
Opened on
17-09-2020
Details Overview of LC
Sl.
No.
Items Supplier Name
Lot
No.
Jan-
2020
Feb-2020 Mar-2020
Apr-20 –
Aug-20
Sep-2020 Oct-2020 Nov-2020 Dec-2020 Jan-2021 Feb-2021 Total
Total Material
wise LC Value
1 TOWER
Confidence Steel
Ltd. (Bangladesh)
Lot - 1
USD
4,464,742.65
USD
4,464,742.65 USD
10,299,704.67
Lot - 2
USD
2,537,643.01
USD
3,297,319.01
USD
1,010,718.62
USD
5,834,962.02
2 CONDUCTOR
Sterlite Power
Transmission Ltd.
(India)
Lot - 1
USD
9,329,742.00
USD
9,329,742.00
USD
22,318,208.41
Lot -
2
USD
11,830,280.00
USD
11,830,280.00
Lot-3
USD
1,158,186.00
USD
1,158,186.00
3 FITTINGS Dervaux (France)
Lot - 1
EUR
1,375,423.29
EUR
1,375,720.60 EUR
3,060,618.60
Lot - 2
EUR
1,684,898.00
EUR
1,684,898.00
4 INSULATORS
Sumitomo
Corporation Power
& Mobility Co., Ltd.
(Japan)
Lot - 1
USD
4,417,500.00
USD
4,417,500.00
USD
7,717,500.00
Lot - 2
Lot - 3
USD
3,170,415.00
USD
3,170,415.00
Lot - 4
5 OPGW Jiangshu Tonguang
USD
211,009.15
USD
211,009.15
USD
211,009.15
USD 4,464,742.65 13,747,242.00 2,787,643.00 18,427,599.01 39,427,226.66
EURO 1,375,720.60 1,684,898.00 3,060,618.6
CONSTRUCTION
STATUS & PLAN
Up to Nov/20 Up to Dec/20
Replan Actual Variance Replan Actual Variance
Nos. of
Completed
Tower
169 164 -5 184 182 -2
% 79.34 77 86.38 85.45
Piling
Up to Nov/20 Up to Dec/20
Replan Actual Variance Replan Actual Variance
Nos. of
Completed
Tower
85 73 -12 105 103 -2
% 39.91 34.27 49.29 48.36
Piling Cap
Construction Status
Up to Nov/20 Up to Dec/20
Replan Actual Variance Replan Actual Variance
Nos. of
Completed
Tower
13 10 -3 31 34 3
% 6.10 4.70 14.55 15.96
Tower
Erection
Construction Status
Construction Status
Construction Plan (Including Lag Recovery)
Sl. Work Total Unit
Up to Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21
May-
21
Jun-21 Jul-21
Planned Actual
Varianc
e
Planne
d
Actual
Varianc
e
Planne
d
Planne
d
Planne
d
Planne
d
Planne
d
Planne
d
Planne
d
Nos. Nos. % Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos.
1 Piling
Location
Plan 213 Nos.
Replan Nos. 169 164 77% -5 16 14 -2 20 15
Pile
Plan 4216 Nos.
Replan Nos. 3331 3271 78% -60 288 304 -16 405 236
2 Pile Cap
Location
Plan 213 Nos.
Replan Nos. 79 73 34% -6 22 20 -2 40 40 40
Cap
Plan 852 Nos.
Replan Nos. 316 292 34% -24 88 80 8 160 160 160
3 Tower Erection Location
Plan 213 Nos.
Replan Nos. 12 7 3% -5 20 27 7 35 35 40 40 29
4 Stringing Route KM 75 KM 7 10 18 20 20
5
Line Checking &
Commissioning
Route KM 75 KM 15 30 30
Recovery Strategy of Construction Lag
Piling
•Already engaged 3 new subcon and more
rigs are in mobilization stage
Pile Cap
•Already engaged 1 new subcon and nos. of
gang has also been increased
Tower
Erection
•Engaged total 8 teams which is adequate to
achieve the monthly plan
Stringing Plan
Section
Route Length
(KM)
Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
TT1 - T39 2.355 Complete
T39 - T40 2.517 Complete
T40 - T40A 2.669 Complete
T40A - T41A 2.754 Complete
T41A - T43A 2.686 Complete
T43A - T45 2.826 Complete
T45 - T46 2.553 Complete
T46 - T47A 2.871 Complete
T47A - T48 3.105 Complete
T48 - T49 3.2 Complete
T49 - T50A 2.075 Complete
T50A - T52 3.013 Complete
T-53 - T54 0.224 Complete
T-54 - T57 2.741 Complete
T57 - T59 4.309 Complete
T59 - T61 3.928 Complete
T61 - T63 5.567 Complete
T63 - T64 2.965 Complete
Total Route Length (KM) 52.358
Stringing Vendor Selection Status
Contract Price
No. Description Special Note Unit Quantity
Unit Rate
per Km in BDT
Amount
In BDT
For 400kV
1 Stringing Work
Scope of work is
including the supply of
equipments and
machinery
Km 75.297 1,415,000.00 106,545,255.00
2 Mid Span Joint pc 50 20,000.00 1,000,000.00
Total 107,545,255.00
RESOURCE PLAN
Foreign Material Procurement Plan
Sl. Work Total Unit
Up to Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21
Plan Actual Variance Plan Actual Variance Plan Plan Plan Plan Plan
Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos.
1 Tower 213 Nos. 64 49 -15 40 15 -35 35 50 40 24
2 Conductor 1800 KM
Plan
Replan 788 788 441 571
3
Hardware
Fittings
213 Nos.
Plan
Replan 106 106 107
4 Insulator 213 Nos.
Plan
Replan 142 0 -142 71
5
OPGW & OPGW
Fittings
75 KM 0 0 0 75
Local Material Procurement Plan
Local Material Procurement Plan.xlsx
Sl. Work Unit
Dec-20 Jan-21 Feb-21 Mar-21
Total Plan
Planned Actual Variance Planned Planned Planned
Nos. Nos. Nos. Nos. Nos. Nos.
1 Cement Bag
Plan
14,000.00
Replan 16000 14800 -1200 8000 4000 2000
2 Sand CFT
Plan
7,000.00
Replan 11500 11441 -59 5000 2000
3 Stone CFT
Plan
12,000.00
Replan 15000 13889 -1111 7000 5000
4 Rebar MT
Plan
1,300.00
Replan 600 400 -200 600 400 300
Subcon Plan
Sl. Work Unit
Dec -20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
Plan Actual Variance Plan Plan Plan Plan Plan Plan
Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos.
1 Piling
Subcon Nos. 5 5 0 5 4
Rig Nos. 24 14 -10 14 8
2 Pile Cap
Subcon Nos. 6 6 0 10 10 7
Gang Nos. 14 14 0 18 20 22
3 Tower Erection
Subcon Nos. 5 4 -1 6 6 7 7 7
Gang Nos. 8 8 0 10 10 12 12 12
4 Stringing
Subcon Nos. 1 1 1 1 1
Gang Nos. 1 1 2 2 2
Subcon Plan (Aggressive).xlsx
New Procurement Schedule
NewProcurement Schedule (AGTL)_Dec-20.xlsx
SL
Material
s Type
Materials Name
Unit
(UOM)
Procure
ment
Type
(Local /
Foreign
)
SCM
Respo
nsible
person
Delivery
Location
Requis
ition
Initial
date
Requisiti
on
Availabil
ity
Lead
Time (up
to Site
delivery)
Inventory
Department
Up to Planned
Data by Project
Remaining Schedule w.r.t. Project's plan (n nos.
mon)
Material Requirement Plan From
Site
Target
date (if
requis. is
unavaila
ble)
Days
Qty
Deliver
ed to
Date
Stock
in
Hand
Total
Requir
ed Qty
Remain
ing Qty
for
Purcha
se
Size of
Deliver
y Batch
- Target
Frequency of
delivery
Progress status Dec-20 Jan-21 Feb-21 Mar-21
A B C D E F G H I J K L
M = L -
J
N O S T U V
1
Construc
tion
Cement Bag Local
Mr.
Soyeb
Uddin
Surjanagar
& Dhaka
Submi
tted
2
14,800 474 16,000 1,200
Partly As per req.
Delivered as per
site requirement
16000 8000 4000 2000
Sand CFT Local
Surjanagar
& Dhaka
Submi
tted
3
11,441 23,093 11,500 59
Partly As per req.
waiting for request
from Construction
Department
11500 5000 2000
Stone CFT Local
Surjanagar
& Dhaka
Submi
tted
3
13,889 8,748 15,000 1,111
Partly As per req.
Delivered as per
site requirement
15000 7000 5000
Rebar MT Local
Surjanagar
& Dhaka
Submi
tted
3
400 66 600 200
Partly As per req.
Delivered as per
site requirement
600 600 400 300
New Subcon Schedule
NewSub-Con Schedule_AGTL_Dec-20.xlsx
Site/PC team Sub-Con team Site/PC team PC Team
Remark
s
Sl. Work location
Type of
Work
Whether
the item
is
payable
from
Client
Site
status
Sub-con
selection
status
Dead line for
Sub-con
selection
Work
order type
Manpowe
r nos. as
per
commitm
ent
Sub-con
requiremen
t date as
per Project
Mnapower
mobilizatio
n agreed
date as per
WO
Present Status
Sub-con plan from the Project
Dec-20 Jan-21 Feb-21
Sub-con
nos.
Manpo
wer
nos.
Sub-con
nos.
Manpo
wer
require
d
Sub-con
nos.
Manpo
wer
require
d
Sub-con
nos.
Manpo
wer
require
d
A B C D E F G H J K L M N
1
Gopalganj
Substation
Gantry
to
Aminbazar
Substation
Gantry
Piling Yes WIP Selected N/A
Subcontrac
t
15/gang 01-08-19 25-07-19 5 210 5 360 5 210 5 210
Piling +
Pile
Cap:
1. MRE-
BBC;
AGTL-
SUBCO
NTRACT
-
FOUND
ATION-
01
Productivity Comparison (Concrete)
NewAGTL_Productivity Comparison Report (Pile + Cap)_Dec-2020.xlsx
Sub-con name Tower ID
Asking
productivity
Task-1 detail: Piling
work qty days req.
Worker per
day
Worker total Productivity
Produc.
Variance
Z A B C D=B*C E=A/D F=E-Z
MRE-BBC T44/1 31.03 21456.32 26 17 442 48.54 17.52
GECL T44/3 31.03 1940.95 3 17 51 38.06 7.03
RSE T64,T64/1,T65/1,T66 31.03 17397.97 26 45 1170 14.87 -16.16
Naif T70 31.03 3776.03 12 15 180 20.98 -10.05
Starlink T77A,T77A/1,T77B 31.03 24985.32 24 26 624 40.04 9.01
Machill T61 31.03 1517.47 4 15 60 25.29 -5.73
Ontel T66/3,T66/4,T67,T67/7 31.03 12386.79 20 27 540 22.94 -8.09
Sheikh T71/2 31.03 2682.04 7 15 105 25.54 -5.48
Global T74/1 31.03 7058.00 13 15 195 36.19 5.17
FU T51/1 31.03 7834.38 19 15 285 27.49 -3.54
Tany T58 31.03 8116.70 16 15 240 33.82 2.79
Mahbub T56 31.03 3034.94 11 15 165 18.39 -12.63
Productivity Comparison (Rebar Fabrication)
Sub-con name Tower ID
Asking
productivity
Task-1 detail: Piling
work qty days req.
Worker per
day
Worker total Productivity
Produc.
Variance
Z A B C D=B*C E=A/D F=E-Z
MRE-BBC T44/1 268.89 154030 26 15 390 394.95 126.06
GECL T44/3 268.89 13058 3 15 45 290.18 21.29
RSE T64,T64/1,T65/1,T66 268.89 47460 15 15 225 210.93 -57.96
Naif T70 268.89 10945 10 6 60 182.42 -86.47
Starlink T77A,T77A/1,T77B 268.89 66176 20 12 240 275.73 6.84
Machill T61 268.89 3765 4 5 20 188.25 -80.64
Ontel T66/3,T66/4,T67,T67/7 268.89 42271 15 15 225 187.87 -81.02
Sheikh T71/2 268.89 8516 7 5 35 243.31 -25.57
Global T74/1 268.89 16195 12 5 60 269.92 1.03
FU T51/1 268.89 19125 19 5 95 201.32 -67.57
Tany T58 268.89 28051 16 6 96 292.20 23.31
Mahbub T56 268.89
8279
6
6 36 229.97 -38.92
Productivity Comparison (Shuttering)
Sub-con name Tower ID
Asking
productivity
Task detail: Pile Cap
work qty days req.
Worker per
day
Worker total Productivity
Produc.
Variance
Z A B C D=B*C E=A/D F=E-Z
Zarin T45B,T47A,T50 35.29 3045.08 18 5 90 33.83 -1.46
MRE-BBC TT1 35.29 1366.52 8 5 40 34.16 -1.13
FU T41/2,T43,T45B/1,T46 35.29 3410.92 24 5 120 28.42 -6.87
RSE T68/1,T70/4 35.29 1570.96 14 5 70 22.44 -12.85
Easy T48B/1 35.29 634.84 6 5 30 21.16 -14.13
GECL T45 35.29 1076 8 4 32 33.63 -1.67
Global T72/1 35.29 548.76 6 4 24 22.87 -12.43
Naif T67/8 35.29 548.76 6 5 30 18.29 -17.00
Starlink T75,T76,T76/1 35.29 3206.48 18 5 90 35.63 0.34
Tany T57,T59/1,T59/2 35.29 2528.6 18 5 90 28.10 -7.20
Manpower Plan
Sl. No Designation Department
Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21 Jul-21
Plan Actual Variance Plan Plan Plan Plan Plan Plan Plan
1 Constrution Manager Construction 2 2 0 2 2 2 2 2 2 2
2 Sr Engineer Construction 2 2 0 2 2 2 2 2 2 2
3 Site Engineer Construction 5 5 0 2 2 2 2 2
4 Sr. Executive (HES) Construction 1 1 0 1 1 1 1 1 1 1
5 Safety Supervisor Construction 1 1 0 1 1 1 1 1 1 1
6 Safety Assistant Construction 1 1 0 1 1 1 1 1 1 1
7 Surveyor Construction 2 2 0 2 2 2 2 2 2 2
8 Survey Assistant Construction 2 2 0 2 2 2 2 2 2 2
9 Line man (Erection) Construction 4 2 -3 4 4 4 5 3 2 2
10 Site Supervisor Construction 6 6 0 4 2
11 Lab Assistant Construction 2 2 0 2 1 1 1 1 1 1
12 Sr. Manager Commercial 1 1 0 1 1 1 1 1 1 1
13 Executive, Commercial Commercial 1 1 0 1 1 1 1 1 1 1
14 Deputy Manager Accounts & Finance 1 1 0 1 1 1 1 1 1 1
15 Sr. Accountant Accounts & Finance 1 1 0 1 1 1 1 1 1 1
16 Executive, Accounts Accounts & Finance 2 2 0 2 2 2 2 2 2 2
17 Asst. Manager HR & Admin 1 1 0 1 1 1 1 1 1 1
18 Executive SCM 1 1 0 1 1 1 1 1 1 1
19 Asst. Manager Inventory 1 1 0 1 1 1 1 1 1 1
20 Store Supervisor Inventory 2 2 0 2 2 2 2 2 2 2
21 Jr Executive Inventory 1 1 0 1 1 1 1 1 1 1
22 Store Assistant Inventory 1 1 0 1 1 1 1 1 1 1
23 Engineer Technical 1 1 0 1 1 1 1 1 1 1
24 Asst. Engineer Technical 1 1 0 1 1 1 1 1 1 1
25 Driver Operation 2 2 0 2 2 2 2 2 2 2
26 Office Assistant Operation 1 1 0 1 1 1 1 1 1 1
27 Cook Operation 4 4 0 4 4 4 4 4 4 4
28 Skill Labour Operation 45 45 0 45 45 45 30 30 25 25
29 Security Operation 18 14 -4 18 18 18 18 15 13 10
Total 111 107 -4 108 105 103 89 84 74 71
New Staff Deployment Schedule
NewStaff Deployment Schedule_AGTL (Dec-2020).xls
Sl. Department Designation
Additional
req. in next
month
Requisition
status from
Project HR
Steps taken for additional req.
Reduction
needs in
next month
Steps taken
for
reduction
Present
Status
Staff plan from the Project
Transfer
from other
project
CV
collection
status
Interview
status
Recruiteme
nt date
Jan-21 Feb-21 Mar-21
nos. nos. nos. nos.
A B C D E F G H I J K L
1 Construction
Constrution
Manager
2 2 2 2
Sr Engineer 2 2 2 2
Site Engineer 5 2 2 2
Sr. Executive (HES) 1 1 1 1
Safety Supervisor 1 1 1 1
Safety Assistant 1 1 1 1
Surveyor 2 2 2 2
Survey Assistant 2 2 2 2
Line man
(Erection)
1 In progress done 01-Jan-21 2 4 4 4
Site Supervisor 6 4 2
Lab Assistant 2 2 1 1
Equipment and Vehicle Plan
Sl.
Equipment/Vehi
cle Name
Unit Capacity
Monthly
Rental Charge
(Taka)
Monthly
Fuel
Consumptio
n (Liter)
Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21 Jul-21
Plan Actual Variance Plan Plan Plan Plan Plan Plan Plan
1 Dump Truck Nos. 145-150 CFT
2 Tractor Nos. 125-130 CFT 65,000.00 400.00 3 2 -1 1
3 Excavator Nos. 7.5 CFT 360,000.00 900.00 0 0 0 1
4 Generator Nos. 8KW 3077.00 0 0 0 0 1 1 1 1 1
5 Crane Nos. 15MT 70,000.00 60.00 2 2 0 2 2 2 2 2 1 1
6 Bike Nos. 60.00 12 12 0 12 12 10 10 10 8 5
7 Pick Up Nos. 250.00 2 2 0 3 3 3 3 2 2 2
NewEquipment Schedule_AGTL_Dec-20.xlsx
Material Reconciliation
S.
No.
Materia
l
Procured
Qty
Received
from
other
Projects
Total
Received
Physical
Stock @
Yard
Physical
Stock @ Site
(if any)
Total
Physical
Stock
Actual
Consump
tion
Theoret
ical
Progres
s
Savings
(+)/
Wastage (-
)
% Savings
(+)/
% Wastage
(-)
Remarks
A B C D = B + C E F G = E + F H = D - G I J = I - H K = J / I
1 Cement 119411 0 119411 661 661 118750 117723 -1027 -0.87% Actual pile
length is
about 70%
of design
length
2 Stone 475903 0 475903 18019 18019 457884 457565 -319 -0.07%
3 Sand 187895 0 187895 15725 15725 172170 170923 -1247 -0.73%
Cement, Stone & Sand
Material Reconciliation_New Format.rev1_.xlsx
Material Reconciliation
Rebar
Dia
(mm)
Unit
Receiving Details Physical Stock
Scrap
Actual
Consump
tion
Theoretic
al
Consump
tion
Savings
(+)
% Savings
(+)
% Scrap (-) Remarks
Procured
Qty
Received
from other
Projects
Total
Received
Full
Length @
Yard & site
locations
Fabricated
Steel @
Yard & Site
locations
Usable Cut
Pieces @
Yard & Site
locations
Total
Stock
A B C D E = C + D F G H
I = F + G +
H
J
K = E - (I
+ J)
L
M = L -
K
N = M / L O = J / L
8 Kg 20,000 0 20,000 2,020 0 0 2,020 700
17,280 16,756 (524)
-3.13% 4.18%
Actual pile
length is
about 70%
of design
length
10 Kg 540,351 0 540,351 6,389 340 0 6,729 2,770
530,852 529,500 (1,352)
-0.26% 0.52%
12 Kg 10,680 0 10,680 - 340 0 340 150
10,190 10,060 (130)
-1.29% 1.49%
16 Kg 1,208,899 0 1,208,899 18,600 438 0 19,038 15,000
1,174,861 1,172,141 (2,720)
-0.23% 1.28%
20 Kg 1,449,122 0 1,449,122 25,680 946 0 26,626 13,000
1,409,496 1,408,035 (1,461)
-0.10% 0.92%
25 Kg 326,254 0 326,254 6,240 0 0 6,240 20,000
300,014 298,655 (1,359)
-0.46% 6.70%
32 Kg 177,805 0 177,805 - 0 0 - 500
177,305 176,659 (646)
-0.37% 0.28%
FINANCIAL STATUS
Financial Progress
Budget
Cost (Expenditure) from Finance & Accounts
Amount % of Budget
5,654,974,549 1,881,591,590.57 33.27%
Budget Vs. Cost (Expenditure)
Project Value
Planned Progress Actual Progress Variance Actual Cash Received
BDT
(B)
%
BDT
(C)
%
BDT
(C-B)
%
Mobilization
Advance (BDT)
(D)
Up to Local IPC-8
& Foreign IPC($)-
15 & IPC(€)-1
(E)
Contractual
amount
(A1)
5,640,892,438
2,301,881,930
40.81%
1,670,870,690
29.62%
-631,011,240
-11.19% 549,038,090.97 1,121,832,599.03
Revised
value
(A2)
5,736,238,943 40.13% 29.13% -11.00% 9.73% 19.89%
AGTL Cash Spent Vs Cash In
Cash Flow
Head
Up to
Jun ‘20
Jul'20
(Plan)
Jul'20
(Actual
)
Aug'20
(Plan)
Aug'20
(Actual
)
Sep’20
(Plan)
Sep’20
(Actual)
Oct’20
(Plan)
Oct’20
(Actual)
Nov’20
(Plan)
Nov’20
(Actual)
Dec’20
(Plan)
Dec’20
(Actual)
Total
(Actual)
Remarks
Cash
Received
77.08 8.54 0.00 16.67 0.00 46.87 35.03 12.74 8.21 42.23 0.0 105.33 46.77 167.09
Cash Spent 83.55 6.24 9.82 73.97 0.43 87.97 34.54 10.90 9.98 30.90 8.10 63.43 17.85 188.16
Net Cash
flow
3.53 2.30 -9.82 -73.97 -0.43 -41.10 0.49 1.84 -1.77 11.33 -8.10 41.9 28.92 -21.08
USD Bal:
4,933,241.74
EUR Bal:
28,579.59
BDT Bal:
3,388,863.86
All Amounts are in BDT & Crore
AGTL Cash Spent Vs In
Description TOTAL Remarks
Cash Receivable (in Crore BDT)
(A)
18.64 Foundation Work
Payable (in Crore BDT)
(B)
16.29
Net (in Crore BDT)
(A-B)
2.35
Receivable/ Payable
Budget vs. Expense
Sl.
No.
Segment
Revised Budget (BDT) Expense (BDT)
BOQ Amount
(BDT)
IPC Received
(BDT)
% Financial
Progress
% Physical
Progress
% Planned
Physical
Progress
% of Budget
Consumed
Total
% of Total
Budget
Total
% of Total
Expense
A B = A / ΣA C D = C / ΣC E F G = F / E H = C / A
BOQ Items
1
Plant and Mandatory Parts
Supply
3,819,391,839.86 67.54%
792,706,551.16
42.13%
3,812,160,969.79 671,615,212.80
17.62% 33.82% 47.75% 20.75%
Tower 902,485,873 15.96%
71,267,723.57
3.79%
1,102,341,563.95 110,234,156.40
10.00% 32.02% 44.13% 7.90%
Conductor 1,949,404,297 34.47%
572,318,207.59
30.42%
1,772,446,005.27 820,814,807.15
46.31% 43.78% 43.78% 29.36%
Fittings 351,014,786 6.21%
149,120,620.00
7.93%
319,253,121.99 146,451,541.04
45.87% 50.23% 50.23% 42.48%
Insulator 595,624,383 10.53% - -
596,211,999.86 59,621,199.99
10.00% - 66.67% -
OPGW 20,862,500 0.37% - -
21,908,278.71 2,190,827.87
10.00% - - -
2 Design Services 49,731,243.00 0.88%
43,511,122.00
2.31%
64,371,890.49 6,286,238.80
9.77% 93.20% 100% 87.49%
Overall Financial Status = 21.33% (OCV)
Overall Financial Status= 20.97% (RCV)
Overall Physical Status = 34.52.%
Continue…
Budget vs. Expense
Sl.
No.
Segment
Revised Budget (BDT) Expense (BDT)
BOQ Amount
(BDT)
IPC Received
(BDT)
% Financial
Progress
% Physical
Progress
% Planned
Physical
Progress
% of Budget
Consumed
Total
% of Total
Budget
Total
% of Total
Expense
A B = A / ΣA C D = C / ΣC E F G = F / E H = C / A
BOQ Items
3 Installation and Other Services 1,556,351,465.95 27.52%
892,161,275.67
47.42%
1,774,169,886.64 443,210,009.40
24.98% 56.23% 50.72% 57.32%
Foundation Work 1,326,858,824 23.46%
889,994,318.67
47.30%
1,327,655,111.65 443,210,009.40
33.38% 70.61% 63.57% 67.08%
Testing of Foundations 5,000,000 0.09%
1,456,640.00
0.08%
7,041,540.00
- - 58.33% 66.67% 29.13%
Tower Erection 88,182,641 1.56%
710,317.00
0.04%
351,269,561.19
- - 15.96% 14.55% 0.81%
Conductor Stringing 136,309,999 2.41% - -
88,203,673.80
- - 0.00% 0.00% -
Continue…
Budget vs. Expense
Sl.
No.
Segment
Revised Budget (BDT) Expense (BDT)
BOQ Amount
(BDT)
IPC Received
(BDT)
% Financial
Progress
% Physical
Progress
% of Budget
Consumed
Total
% of Total
Budget
Total
% of Total
Expense
A B = A / ΣA C D = C / ΣC E F G = F / E H = C / A
Non BOQ Items
4 General & Yard Development 10,000,000.00 0.18%
7,590,300.00
0.40% 85.00% 75.90%
5 Salary and Other Allowances 93,000,000.00 1.64%
54,902,081.00
2.92% 75.00% 59.03%
6 Site Overhead 30,500,000.00 0.54%
19,754,712.74
1.05% 75.00% 64.77%
7 Head Office Overhead 10,000,000.00 0.18%
7,138,198.00
0.38% 75.00% 71.38%
8 Financial Expenses 70,000,000.00 1.24%
51,124,176.00
2.72% 75.00% 73.03%
9
Contingency Fund/Miscellaneous
Exp/BP
10,000,000.00 0.18%
8,433,174.00
0.45% 75.00% 84.33%
10
Project Assets (Tools, Plant,
Machinery, IT & Furniture)
6,000,000.00 0.11%
4,270,000.00
0.23% 90.00% 71.17%
Grand Total (BDT): 5,654,974,548.82 100.00% 1,881,591,590.57
Budget vs. Expense (Non BOQ S- Curve)
10.80
11.21
12.18
13.23
14.35
15.79
18.21
19.22
20.10
20.78
21.06
21.33
10.80
11.03
12.10
13.09
13.49
10.00
11.00
12.00
13.00
14.00
15.00
16.00
17.00
18.00
19.00
20.00
21.00
22.00
Up to Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21 Jul-21
Non BOQ Items Plan vs Actual Expense
Plan Actual
Amounts are in Crore
Expense Record
Sl.
No.
Month Expense
Cost (%) in terms of
Budget
Plan (%)
1 Up to Feb-20 702,816,311.5 10.07%
2 Apr-20 30,916,104.00 0.55% 1.71%
3 May-20 54,602,865.00 0.96% 1.12%
4 Jun-20 74,125,278.00 1.31% 1.60%
5 Jul-20 98,199,459.00 1.73% 1.12%
6 Aug-20 4,345,640.00 0.08% 13.08%
7 Sep-20 345,404,588.12 6.11% 15.56%
8 Oct-20 99,751,555 .00 1.79% 1.96%
9 Nov-20 81,021,101.43 1.43% 5.46%
10 Dec-20 178,457,133.00 3.16% 18.62%
Total 1,881,591,590.57 33.27%
Accounts Payable Summary
Sl. No. Description Amount in Taka
1 Cheque in Hand -
2 Accounts Payable 103,722,373
3 Provision for Pending MRR 59,155,950
Total: 162,878,323
Advance Details
Sl. No. Description Amount in Taka
1 Advance for Yard Rent 300,000
2 Advance for House Rent 300,000
3
Advance for Tower (CSL) Supplier 37,258,278
Advance for Conductor (Sterlite) Supplier 286,887,961
4 Advance for Sub Contractor -
Total 324,746,239
Cash Flow Projection Up to Dec-21
All Amounts are in BDT & Crore
Cashflow Head Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21 Jul-21 Aug-21 Sep-21 Oct-21 Nov-21 Dec-21 Total
Net Cash In 40.38 108.11 20.66 11.35 30.58 7.20 6.42 19.40 5.52 4.25 4.49 1.73 365.43
Cash Out 34.69 59.67 21.47 24.89 84.68 5.05 13.89 3.61 3.26 2.54 1.76 1.63 320.56
Net Cashflow 5.70 48.44 -0.81 -13.54 -54.10 2.14 -7.47 15.80 2.26 1.71 2.74 0.10 44.87
Cost To
Complete
(Based on
Aggressive Plan)
SL Items Amount (BDT)
BOQ 2,824,522,348.44
1 Supply 2,276,033,632.01
2 Design 9,540,546.43
3 Installation 538,948,170.00
Non BOQ 844,263,322.02
4 General & Yard Development 1,360,800.00
5 Salary and Other Allowances 35,956,571.25
6 Site Overhead 6,712,000.00
7 Head Office Overhead 940,000.00
8 Financial Expenses 63,000,000.00
9 Contingency Fund/Miscellaneous Exp/BP 4,200,000.00
10 Project Assets (Tools, Plant, Machinery, IT & Furniture) 697,100.00
11 Accounts Payable
731,396,850.77
Total 3,668,785,670.46
CTC.xlsx
Variation From Original Contract
Description of Variation Unit Variation Quantity Rate Amount impact
A B C D E=C x D
Total Route Length KM 2.24 39,344,236.61 88,131,090.01
3 Additional Piling per tower 3 2,405,138.33 7,215,415.00
Total 95,346,505.01
Profit Margin
Profit
Margin
SL Description Amount (BDT)
% of Contract
(incl. variation)
A Contract Amount 5,640,892,438
B Expense till Dec-20 1,881,591,591
C CTC 3,668,785,670
D Profit Margin (A-B-C) 90,515,177 1.60%
E Add Variation D+95346505 185,861,682 3.29%
F (Add) Claim Adjustment E+137698915 323,560,597 5.74%
G (Deduct) Risk Adjustment F-682851235 -359,290,638 -6.37%
Thanks………..

More Related Content

Similar to AGTL Project Status and Progress_20-01-2021.pptx

Similar to AGTL Project Status and Progress_20-01-2021.pptx (20)

FQUP PPT.pptx
FQUP PPT.pptxFQUP PPT.pptx
FQUP PPT.pptx
 
PPT_14.03.2022.pptx
PPT_14.03.2022.pptxPPT_14.03.2022.pptx
PPT_14.03.2022.pptx
 
A valuable journey proposal
A valuable journey proposalA valuable journey proposal
A valuable journey proposal
 
EPCM-WORK-PROFILE_+_+(EPCM-WORK-PROFILE)
EPCM-WORK-PROFILE_+_+(EPCM-WORK-PROFILE)EPCM-WORK-PROFILE_+_+(EPCM-WORK-PROFILE)
EPCM-WORK-PROFILE_+_+(EPCM-WORK-PROFILE)
 
PMDP Presentation Sep-22_Final dt 27.10.2022.pptx
PMDP Presentation Sep-22_Final  dt 27.10.2022.pptxPMDP Presentation Sep-22_Final  dt 27.10.2022.pptx
PMDP Presentation Sep-22_Final dt 27.10.2022.pptx
 
Bgl solar update210614
Bgl solar update210614Bgl solar update210614
Bgl solar update210614
 
Training PPT
Training PPTTraining PPT
Training PPT
 
Key to a successful EGTL Site
Key to a successful EGTL SiteKey to a successful EGTL Site
Key to a successful EGTL Site
 
Presentation 1
Presentation 1Presentation 1
Presentation 1
 
Mitigtion Plan Presentation
Mitigtion Plan PresentationMitigtion Plan Presentation
Mitigtion Plan Presentation
 
Summer training @ L&T
Summer training @ L&TSummer training @ L&T
Summer training @ L&T
 
Review of PH-16 With CRB.pptx
Review of PH-16 With CRB.pptxReview of PH-16 With CRB.pptx
Review of PH-16 With CRB.pptx
 
Ranjith cv
Ranjith cvRanjith cv
Ranjith cv
 
SABER CV
SABER CVSABER CV
SABER CV
 
updated CV
updated CVupdated CV
updated CV
 
Hossam salah-cv
Hossam salah-cvHossam salah-cv
Hossam salah-cv
 
CV PMG
CV PMGCV PMG
CV PMG
 
r_1
r_1r_1
r_1
 
Yahya Khan CV(1)
Yahya Khan CV(1)Yahya Khan CV(1)
Yahya Khan CV(1)
 
Project Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.pptProject Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.ppt
 

Recently uploaded

Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfAdmir Softic
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756dollysharma2066
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfAmzadHosen3
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with CultureSeta Wicaksana
 

Recently uploaded (20)

Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdf
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 

AGTL Project Status and Progress_20-01-2021.pptx

  • 1. AGTL Project Status and Progress Review 20th January, 2021
  • 3. Contract Details Project Name: Design, Supply, Installation, Testing & Commissioning of the Aminbazar- Gopalganj 400 kV Double Circuit Transmission Line on turnkey basis. (Contract No: PGCB/ADB/3522/400kV/TL/AGTL) • Euro : 3,060,618.56 • USD : 42,617,495.36 • BDT : 1,745,619,243.16 Project Value • 31st March, 2019 Contract Effective Date • 19th March, 2021 Finishing Date • 720 Days Project Duration
  • 4. Overview of AGTL 400kV Double Circuit Total Length: 75.24 Km • Part – 1 Gopalganj S/S - Jajira: 33.221 Km (94 Towers) • Part – 2 Maowa – Aminbazar S/S: 41.538 Km (119 Towers) Total Tower: 213 Nos Tower Type: 4DL, 4D1, 4D25, 4D45, 4DT6 4DL: 135 4D1: 18 4D25: 36 4D45: 15 4DT6: 9
  • 5. Total Route Map TT-1 to TT-2.kmz
  • 6. Top Issues • Confidence Steel couldn’t supply the tower materials as per our requirement which has hampered our tower erection work and also stringing plan. Tower Supply • We have BDT 186,452,963.98 as outstanding. PGCB Payment • LS cable has not been approved yet and by this time if ZTT gets clearance from the ADB (which they are in progress) then we also have them as other option. OPGW Vendor Problem
  • 8. Key Discussion of Last MPR SL No Discussion Points Summary Decision/Deliverables Action by Status 1 EoT update Meeting has been done with PD and PD told that PGCB will take decision regarding the EoT in Feb-21. PD told that they have requested up to Dec-21 to ADB. Project team have to check whether ADB has submitted NOC or not. Project team will issue a follow up letter next week. PM, Contract Dept. Planner Official letter has been submitted for EoT claim. 2 Tower Supply Issue Project team have communicated with CEO/CSL regarding supply of 4D25 tower and will try to convince him for making the delivery of 4D25 tower within Jan-21 beyond the contract terms and conditions. PM have engaged 2 persons to monitor the packing of tower materials. PM Several meeting have been conducted and still meetings are going on 3 Insulator Supply Delay NGK told that they cannot arrange containers before end of Jan-21. After several negotiation using SEPCO1 and MAX link, NGK is convinced to dispatch 1st Lot by 16th Dec, 20. Negotiation is going on for the early shipment of 2nd Lot also. Project will have insulator for 10 km in the Lot-1. PM, Mr. Kuddush Insulator Lot-1 already arrived and waiting for customs clearance. 4 Tower Erection Plan Already 7 erection gangs are at site. There are 94 towers at Gopalganj site and these towers have been planned to complete first within Jan-21. Project team is concentrating on Gopalganj site first. Mr. kaiser and Mr. Omar Faruk 8 gangs were engaged and we had a good progress in Dec-20
  • 9. Discussion of Last MPR SL No Discussion Points Summary Decision/Deliverables Action by Status 5 PG-APG Issue PGCB has issued the letter regarding PG and APG. Draft has been prepared and sent to PGCB for checking. It will take 2 days to transfer the money after getting letter from PGCB. Hopefully, early of the next week project will get it. Mr. Kuddush, Mr. Niaz Already solved and amount has been transferred also 6 Stringing Equipment & Vendor Selection Procurement of stringing equipment is not feasible as there is no upcoming ACCC conductor project. So, project team has decided not to procure the equipment. Project team will go for the contract with GS E&C (Korea) for the stringing work with equipment. Project team is trying to reduce the price some more. They have 2 sets of equipment among them one is required to have some maintenace work. Mr. Khaled & Mr. Kaiser Already signed the agreement with Shohel Engineers (GS Korea) 7 Starting Stringing Work Stringing work is planning to start from Jan-21 at Gopalganj site. Firstly, 1 set equipment will be engaged and after fixing the problem another set will be deployed. Both sets will be used at Gopalganj site which we target to complete first, then we will move to Dhaka site. Mr. kaiser and Mr. Omar Faruk Due to unavailability of 4D25 towers stringing schedule has been delayed 8 OPGW Vendor Change Issue Project team has submitted technical documents of new vendor (LS Cables) to PGCB for approval. But PGCB told that this vendor should be verified by ADB first and then PGCB will approve them. ADB usually takes too much time in this type issue but PD assured us to get the feedback from ADB ASAP. LS assured us that they can supply within Feb-21 af we open LC now. Project Team, Project Control LS has not been approved yet. We have another option of ZTT if they get clearance from ADB asap
  • 10. Discussion of Last MPR SL No Discussion Points Summary Decision/Deliverables Action by Status 9 MoM of Meeting with PD Project office is doing monthly meeting with PD and already sent the MoM of last meeting which PD did not sign. CEO sir suggested to send MoM officially. PM, Contract team MoM has been sent with a official letter 10 MSP Schedule The MSP file with replan and without the resource assignment need to be prepared within 10-12-2020 Mr. Zakir and Mr. Shakib MSP file has been prepared and tracking has been done. As per tracking we get the completion date in Dec-21 which is logical and based on that we have claim for EoT up to Dec-21 11 Risk Register CEO sir suggested Mr. Shaibajit to sit with Mr. Maher regarding the risk register and justify the mitigation plan. Mr. Shaibajit and Mr. Maher Discussion has been done in this regard and a new format has been made for maintaining the risk register which has been started by the project team (yet to develop more for residual financial impact) 12 Cost Claim CEO sir suggested to find a way by which project team can assist PGCB to prove additional cost incur so that those amount can be considered into RDPP. Project Team Project team has communicated with PD regarding this and PD told to not think about cost claim at this stage. Firstly, try for the EoT as required 13 Pending MRR CEO sir asked to check with accounts that why the pending MRR is so much. Mr. Shaibajit, AGTL Accounts As ERP has been implemented 1.5yrs later, that’s why pending MRR is showing high value. Now, day by day it is coming under control
  • 12. Safety Status Trend Nov, 2020 Dec, 2020 Up to Dec-2020 Rolling LTIFR (Indicative) 0 0 Number of Lost Time Injuries (LTI) 0 0 Rolling TRIFR 0 0 3.48 Number of Total Recordable Injuries (TRI) 0 0 No. of Man-hours worked 120,000 132,000 1,293,760 No. of Non-Lost Time Injuries 0 0 No. of Fatal Accidents 0 0 LTIFR is expressed thus: No. of LTI ÷ Manhour (Within the period in assessment) × 1000000 TRIFR : No. of TRI ÷ Manhour (Within the period in assessment) × 1000000 INCIDENT TYPE Dec-20 PTD (Up to Dec-2020) Near Miss 0 First Aid 0 Medical Aid 0 Lost Time Accident 0 Environmental Spills 0
  • 13. Progress Sl. No. Description Total Weightage Work Completed as on (Weightage) Plan Qty. Unit Weightage (%) Qty. Unit Weightage (%) Weightage (%) 1 Survey including submission of plan and profile, soil test. 75.24 km 5% 75.24 km 5.00% 5.00% 2 Design, approval and tower test. 5 Nos. 5% 5 No 5.00% 5.00% 3 Foundation Pile. 213 Lot 15% 182 Lot 12.82% 13.02% 4 Pile Cap. 213 Lot 10% 103 Lot 4.84% 4.97% 5 Supply. 213 Lot 35% Lot 11.84% 24.28% 6 Tower Erection. 213 Lot 15% 47 Lot 3.31% 3.38% 7 Stringing. 213 km 10% km 0.00% 0.00% 8 Testing and Commissioning. 75.24 km 5% km 0.00% 0.00% Total Work 100% 42.46% 55.65% Variance -13.19%
  • 14. Plan Vs Actual Graph • Overall Progress 27.43% 29.41% 42.42% 55.65% 67.69% 76.94% 82.69% 87.91% 93.76% 98.00% 100.00% 1.41% 1.70% 3.60% 5.45% 8.45% 10.95% 13.63% 14.03% 16.45% 22.09% 24.88% 24.88% 24.88% 25.08% 25.37% 25.70% 26.99% 27.78% 35.06% 42.46% 0.79% 1.30% 2.68% 4.05% 6.11% 8.94% 11.96% 15.56% 20.16% 24.75% 30.00% 39.70% 40.50% 40.60% 42.50% 49.75% 37.84% 45.09% 60.05% 69.66% 76.23% 79.23% 83.03% 88.24% 90.91% 97.50% 100.00% 0.00% 20.00% 40.00% 60.00% 80.00% 100.00% Overall Progress Replan Actual Plan (Baseline)
  • 15. Plan Vs Actual Graph • Design (completed) 2.00% 7.00% 12.85% 22.35% 31.85% 41.35% 51.10% 61.25% 71.50% 82.00% 88.00% 93.00% 97.00% 98.00% 99.00% 100.00% 0.00% 3.00% 6.50% 12.00% 19.25% 29.75% 41.40% 53.25% 64.50% 77.15% 86.50% 91.00% 93.00% 96.00% 98.50% 100.00% 0.00% 10.00% 20.00% 30.00% 40.00% 50.00% 60.00% 70.00% 80.00% 90.00% 100.00% Apr/19 May/19 Jun/19 Jul/19 Aug/19 Sep/19 Oct/19 Nov/19 Dec/19 Jan/20 Feb/20 Mar/20 Apr/20 May/20 Jun/20 Jul/20 Design Phase overall curve cumulative Planned cumulative Actual
  • 16. Plan Vs Actual Graph • Civil Works 57.24% 67.56% 82.88% 92.12% 100.00% 0.20% 0.70% 1.20% 1.95% 6.95% 18.71% 27.91% 38.20% 38.20% 38.20% 44.96% 51.24% 51.24% 53.43% 55.88% 58.60% 70.64% 0.80% 2.00% 3.60% 5.60% 8.60% 19.60% 31.60% 47.60% 47.60% 47.60% 51.20% 56.20% 61.20% 53.43% 56.43% 61.31% 71.95% 84.16% 95.62% 100.00% 0.00% 20.00% 40.00% 60.00% 80.00% 100.00% 120.00% Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Civil Work Progress cumulative Plan (Baseline) cumulative Actual cumulative Replan
  • 17. Plan Vs Actual Graph • Tower Erection 0.94% 1.88% 1.41% 6.10% 22.53% 34.27% 50.71% 69.49% 87.79% 100.00% 0.00% 0.47% 0.94% 4.70% 22.07% 0.94% 1.88% 9.39% 21.13% 34.27% 48.36% 64.79% 81.22% 100.00% 0.00% 20.00% 40.00% 60.00% 80.00% 100.00% Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Tower Erection cumulative Replan cumulative Actual cumulative Plan (Baseline)
  • 18. Plan Vs Actual Graph • Supply 15.33% 14.75% 46.22% 72.83% 90.32% 100.00% 1.73% 9.49% 11.33% 11.42% 11.42% 27.77% 33.83% 0.00% 0.35% 0.35% 1.11% 1.11% 1.11% 2.43% 11.42% 13.35% 34.08% 44.37% 77.23% 91.51% 95.51% 100.00% 0.00% 20.00% 40.00% 60.00% 80.00% 100.00% 120.00% Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Supply of Materials cumulative Replan cumulative Actual cumulative Plan (Baseline)
  • 20. Vendor Contract & LC Status Product Name Company Name Contract Status Contract Sign Date LC Status Remarks Towers Confidence Steel Ltd., Bangladesh Signed 20-10-19 Opened on 16-09-2020 Conductor & Earthwire Sterlite Power Transmission Ltd., India Signed 23-05-19 Opened on 08-03-20 Advance Payment has been released Insulator Sumitomo Corporation power and Mobility Co. Ltd., Japan Signed 01-10-19 Opened on 20-09-20 Conductor, Insulator & Earthwire Fittings Dervaux S.A, France Signed 01-06-19 Opened on 02-09-2020 OPGW & Fittings Jiangsu Tongguang Optical Fiber Company Ltd., China Signed 29-07-20 Opened on 17-09-2020
  • 21. Details Overview of LC Sl. No. Items Supplier Name Lot No. Jan- 2020 Feb-2020 Mar-2020 Apr-20 – Aug-20 Sep-2020 Oct-2020 Nov-2020 Dec-2020 Jan-2021 Feb-2021 Total Total Material wise LC Value 1 TOWER Confidence Steel Ltd. (Bangladesh) Lot - 1 USD 4,464,742.65 USD 4,464,742.65 USD 10,299,704.67 Lot - 2 USD 2,537,643.01 USD 3,297,319.01 USD 1,010,718.62 USD 5,834,962.02 2 CONDUCTOR Sterlite Power Transmission Ltd. (India) Lot - 1 USD 9,329,742.00 USD 9,329,742.00 USD 22,318,208.41 Lot - 2 USD 11,830,280.00 USD 11,830,280.00 Lot-3 USD 1,158,186.00 USD 1,158,186.00 3 FITTINGS Dervaux (France) Lot - 1 EUR 1,375,423.29 EUR 1,375,720.60 EUR 3,060,618.60 Lot - 2 EUR 1,684,898.00 EUR 1,684,898.00 4 INSULATORS Sumitomo Corporation Power & Mobility Co., Ltd. (Japan) Lot - 1 USD 4,417,500.00 USD 4,417,500.00 USD 7,717,500.00 Lot - 2 Lot - 3 USD 3,170,415.00 USD 3,170,415.00 Lot - 4 5 OPGW Jiangshu Tonguang USD 211,009.15 USD 211,009.15 USD 211,009.15 USD 4,464,742.65 13,747,242.00 2,787,643.00 18,427,599.01 39,427,226.66 EURO 1,375,720.60 1,684,898.00 3,060,618.6
  • 23. Up to Nov/20 Up to Dec/20 Replan Actual Variance Replan Actual Variance Nos. of Completed Tower 169 164 -5 184 182 -2 % 79.34 77 86.38 85.45 Piling Up to Nov/20 Up to Dec/20 Replan Actual Variance Replan Actual Variance Nos. of Completed Tower 85 73 -12 105 103 -2 % 39.91 34.27 49.29 48.36 Piling Cap Construction Status
  • 24. Up to Nov/20 Up to Dec/20 Replan Actual Variance Replan Actual Variance Nos. of Completed Tower 13 10 -3 31 34 3 % 6.10 4.70 14.55 15.96 Tower Erection Construction Status
  • 26. Construction Plan (Including Lag Recovery) Sl. Work Total Unit Up to Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May- 21 Jun-21 Jul-21 Planned Actual Varianc e Planne d Actual Varianc e Planne d Planne d Planne d Planne d Planne d Planne d Planne d Nos. Nos. % Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. 1 Piling Location Plan 213 Nos. Replan Nos. 169 164 77% -5 16 14 -2 20 15 Pile Plan 4216 Nos. Replan Nos. 3331 3271 78% -60 288 304 -16 405 236 2 Pile Cap Location Plan 213 Nos. Replan Nos. 79 73 34% -6 22 20 -2 40 40 40 Cap Plan 852 Nos. Replan Nos. 316 292 34% -24 88 80 8 160 160 160 3 Tower Erection Location Plan 213 Nos. Replan Nos. 12 7 3% -5 20 27 7 35 35 40 40 29 4 Stringing Route KM 75 KM 7 10 18 20 20 5 Line Checking & Commissioning Route KM 75 KM 15 30 30
  • 27. Recovery Strategy of Construction Lag Piling •Already engaged 3 new subcon and more rigs are in mobilization stage Pile Cap •Already engaged 1 new subcon and nos. of gang has also been increased Tower Erection •Engaged total 8 teams which is adequate to achieve the monthly plan
  • 28. Stringing Plan Section Route Length (KM) Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21 TT1 - T39 2.355 Complete T39 - T40 2.517 Complete T40 - T40A 2.669 Complete T40A - T41A 2.754 Complete T41A - T43A 2.686 Complete T43A - T45 2.826 Complete T45 - T46 2.553 Complete T46 - T47A 2.871 Complete T47A - T48 3.105 Complete T48 - T49 3.2 Complete T49 - T50A 2.075 Complete T50A - T52 3.013 Complete T-53 - T54 0.224 Complete T-54 - T57 2.741 Complete T57 - T59 4.309 Complete T59 - T61 3.928 Complete T61 - T63 5.567 Complete T63 - T64 2.965 Complete Total Route Length (KM) 52.358
  • 29. Stringing Vendor Selection Status Contract Price No. Description Special Note Unit Quantity Unit Rate per Km in BDT Amount In BDT For 400kV 1 Stringing Work Scope of work is including the supply of equipments and machinery Km 75.297 1,415,000.00 106,545,255.00 2 Mid Span Joint pc 50 20,000.00 1,000,000.00 Total 107,545,255.00
  • 31. Foreign Material Procurement Plan Sl. Work Total Unit Up to Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Plan Actual Variance Plan Actual Variance Plan Plan Plan Plan Plan Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. 1 Tower 213 Nos. 64 49 -15 40 15 -35 35 50 40 24 2 Conductor 1800 KM Plan Replan 788 788 441 571 3 Hardware Fittings 213 Nos. Plan Replan 106 106 107 4 Insulator 213 Nos. Plan Replan 142 0 -142 71 5 OPGW & OPGW Fittings 75 KM 0 0 0 75
  • 32. Local Material Procurement Plan Local Material Procurement Plan.xlsx Sl. Work Unit Dec-20 Jan-21 Feb-21 Mar-21 Total Plan Planned Actual Variance Planned Planned Planned Nos. Nos. Nos. Nos. Nos. Nos. 1 Cement Bag Plan 14,000.00 Replan 16000 14800 -1200 8000 4000 2000 2 Sand CFT Plan 7,000.00 Replan 11500 11441 -59 5000 2000 3 Stone CFT Plan 12,000.00 Replan 15000 13889 -1111 7000 5000 4 Rebar MT Plan 1,300.00 Replan 600 400 -200 600 400 300
  • 33. Subcon Plan Sl. Work Unit Dec -20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21 Plan Actual Variance Plan Plan Plan Plan Plan Plan Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. 1 Piling Subcon Nos. 5 5 0 5 4 Rig Nos. 24 14 -10 14 8 2 Pile Cap Subcon Nos. 6 6 0 10 10 7 Gang Nos. 14 14 0 18 20 22 3 Tower Erection Subcon Nos. 5 4 -1 6 6 7 7 7 Gang Nos. 8 8 0 10 10 12 12 12 4 Stringing Subcon Nos. 1 1 1 1 1 Gang Nos. 1 1 2 2 2 Subcon Plan (Aggressive).xlsx
  • 34. New Procurement Schedule NewProcurement Schedule (AGTL)_Dec-20.xlsx SL Material s Type Materials Name Unit (UOM) Procure ment Type (Local / Foreign ) SCM Respo nsible person Delivery Location Requis ition Initial date Requisiti on Availabil ity Lead Time (up to Site delivery) Inventory Department Up to Planned Data by Project Remaining Schedule w.r.t. Project's plan (n nos. mon) Material Requirement Plan From Site Target date (if requis. is unavaila ble) Days Qty Deliver ed to Date Stock in Hand Total Requir ed Qty Remain ing Qty for Purcha se Size of Deliver y Batch - Target Frequency of delivery Progress status Dec-20 Jan-21 Feb-21 Mar-21 A B C D E F G H I J K L M = L - J N O S T U V 1 Construc tion Cement Bag Local Mr. Soyeb Uddin Surjanagar & Dhaka Submi tted 2 14,800 474 16,000 1,200 Partly As per req. Delivered as per site requirement 16000 8000 4000 2000 Sand CFT Local Surjanagar & Dhaka Submi tted 3 11,441 23,093 11,500 59 Partly As per req. waiting for request from Construction Department 11500 5000 2000 Stone CFT Local Surjanagar & Dhaka Submi tted 3 13,889 8,748 15,000 1,111 Partly As per req. Delivered as per site requirement 15000 7000 5000 Rebar MT Local Surjanagar & Dhaka Submi tted 3 400 66 600 200 Partly As per req. Delivered as per site requirement 600 600 400 300
  • 35. New Subcon Schedule NewSub-Con Schedule_AGTL_Dec-20.xlsx Site/PC team Sub-Con team Site/PC team PC Team Remark s Sl. Work location Type of Work Whether the item is payable from Client Site status Sub-con selection status Dead line for Sub-con selection Work order type Manpowe r nos. as per commitm ent Sub-con requiremen t date as per Project Mnapower mobilizatio n agreed date as per WO Present Status Sub-con plan from the Project Dec-20 Jan-21 Feb-21 Sub-con nos. Manpo wer nos. Sub-con nos. Manpo wer require d Sub-con nos. Manpo wer require d Sub-con nos. Manpo wer require d A B C D E F G H J K L M N 1 Gopalganj Substation Gantry to Aminbazar Substation Gantry Piling Yes WIP Selected N/A Subcontrac t 15/gang 01-08-19 25-07-19 5 210 5 360 5 210 5 210 Piling + Pile Cap: 1. MRE- BBC; AGTL- SUBCO NTRACT - FOUND ATION- 01
  • 36. Productivity Comparison (Concrete) NewAGTL_Productivity Comparison Report (Pile + Cap)_Dec-2020.xlsx Sub-con name Tower ID Asking productivity Task-1 detail: Piling work qty days req. Worker per day Worker total Productivity Produc. Variance Z A B C D=B*C E=A/D F=E-Z MRE-BBC T44/1 31.03 21456.32 26 17 442 48.54 17.52 GECL T44/3 31.03 1940.95 3 17 51 38.06 7.03 RSE T64,T64/1,T65/1,T66 31.03 17397.97 26 45 1170 14.87 -16.16 Naif T70 31.03 3776.03 12 15 180 20.98 -10.05 Starlink T77A,T77A/1,T77B 31.03 24985.32 24 26 624 40.04 9.01 Machill T61 31.03 1517.47 4 15 60 25.29 -5.73 Ontel T66/3,T66/4,T67,T67/7 31.03 12386.79 20 27 540 22.94 -8.09 Sheikh T71/2 31.03 2682.04 7 15 105 25.54 -5.48 Global T74/1 31.03 7058.00 13 15 195 36.19 5.17 FU T51/1 31.03 7834.38 19 15 285 27.49 -3.54 Tany T58 31.03 8116.70 16 15 240 33.82 2.79 Mahbub T56 31.03 3034.94 11 15 165 18.39 -12.63
  • 37. Productivity Comparison (Rebar Fabrication) Sub-con name Tower ID Asking productivity Task-1 detail: Piling work qty days req. Worker per day Worker total Productivity Produc. Variance Z A B C D=B*C E=A/D F=E-Z MRE-BBC T44/1 268.89 154030 26 15 390 394.95 126.06 GECL T44/3 268.89 13058 3 15 45 290.18 21.29 RSE T64,T64/1,T65/1,T66 268.89 47460 15 15 225 210.93 -57.96 Naif T70 268.89 10945 10 6 60 182.42 -86.47 Starlink T77A,T77A/1,T77B 268.89 66176 20 12 240 275.73 6.84 Machill T61 268.89 3765 4 5 20 188.25 -80.64 Ontel T66/3,T66/4,T67,T67/7 268.89 42271 15 15 225 187.87 -81.02 Sheikh T71/2 268.89 8516 7 5 35 243.31 -25.57 Global T74/1 268.89 16195 12 5 60 269.92 1.03 FU T51/1 268.89 19125 19 5 95 201.32 -67.57 Tany T58 268.89 28051 16 6 96 292.20 23.31 Mahbub T56 268.89 8279 6 6 36 229.97 -38.92
  • 38. Productivity Comparison (Shuttering) Sub-con name Tower ID Asking productivity Task detail: Pile Cap work qty days req. Worker per day Worker total Productivity Produc. Variance Z A B C D=B*C E=A/D F=E-Z Zarin T45B,T47A,T50 35.29 3045.08 18 5 90 33.83 -1.46 MRE-BBC TT1 35.29 1366.52 8 5 40 34.16 -1.13 FU T41/2,T43,T45B/1,T46 35.29 3410.92 24 5 120 28.42 -6.87 RSE T68/1,T70/4 35.29 1570.96 14 5 70 22.44 -12.85 Easy T48B/1 35.29 634.84 6 5 30 21.16 -14.13 GECL T45 35.29 1076 8 4 32 33.63 -1.67 Global T72/1 35.29 548.76 6 4 24 22.87 -12.43 Naif T67/8 35.29 548.76 6 5 30 18.29 -17.00 Starlink T75,T76,T76/1 35.29 3206.48 18 5 90 35.63 0.34 Tany T57,T59/1,T59/2 35.29 2528.6 18 5 90 28.10 -7.20
  • 39. Manpower Plan Sl. No Designation Department Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21 Jul-21 Plan Actual Variance Plan Plan Plan Plan Plan Plan Plan 1 Constrution Manager Construction 2 2 0 2 2 2 2 2 2 2 2 Sr Engineer Construction 2 2 0 2 2 2 2 2 2 2 3 Site Engineer Construction 5 5 0 2 2 2 2 2 4 Sr. Executive (HES) Construction 1 1 0 1 1 1 1 1 1 1 5 Safety Supervisor Construction 1 1 0 1 1 1 1 1 1 1 6 Safety Assistant Construction 1 1 0 1 1 1 1 1 1 1 7 Surveyor Construction 2 2 0 2 2 2 2 2 2 2 8 Survey Assistant Construction 2 2 0 2 2 2 2 2 2 2 9 Line man (Erection) Construction 4 2 -3 4 4 4 5 3 2 2 10 Site Supervisor Construction 6 6 0 4 2 11 Lab Assistant Construction 2 2 0 2 1 1 1 1 1 1 12 Sr. Manager Commercial 1 1 0 1 1 1 1 1 1 1 13 Executive, Commercial Commercial 1 1 0 1 1 1 1 1 1 1 14 Deputy Manager Accounts & Finance 1 1 0 1 1 1 1 1 1 1 15 Sr. Accountant Accounts & Finance 1 1 0 1 1 1 1 1 1 1 16 Executive, Accounts Accounts & Finance 2 2 0 2 2 2 2 2 2 2 17 Asst. Manager HR & Admin 1 1 0 1 1 1 1 1 1 1 18 Executive SCM 1 1 0 1 1 1 1 1 1 1 19 Asst. Manager Inventory 1 1 0 1 1 1 1 1 1 1 20 Store Supervisor Inventory 2 2 0 2 2 2 2 2 2 2 21 Jr Executive Inventory 1 1 0 1 1 1 1 1 1 1 22 Store Assistant Inventory 1 1 0 1 1 1 1 1 1 1 23 Engineer Technical 1 1 0 1 1 1 1 1 1 1 24 Asst. Engineer Technical 1 1 0 1 1 1 1 1 1 1 25 Driver Operation 2 2 0 2 2 2 2 2 2 2 26 Office Assistant Operation 1 1 0 1 1 1 1 1 1 1 27 Cook Operation 4 4 0 4 4 4 4 4 4 4 28 Skill Labour Operation 45 45 0 45 45 45 30 30 25 25 29 Security Operation 18 14 -4 18 18 18 18 15 13 10 Total 111 107 -4 108 105 103 89 84 74 71
  • 40. New Staff Deployment Schedule NewStaff Deployment Schedule_AGTL (Dec-2020).xls Sl. Department Designation Additional req. in next month Requisition status from Project HR Steps taken for additional req. Reduction needs in next month Steps taken for reduction Present Status Staff plan from the Project Transfer from other project CV collection status Interview status Recruiteme nt date Jan-21 Feb-21 Mar-21 nos. nos. nos. nos. A B C D E F G H I J K L 1 Construction Constrution Manager 2 2 2 2 Sr Engineer 2 2 2 2 Site Engineer 5 2 2 2 Sr. Executive (HES) 1 1 1 1 Safety Supervisor 1 1 1 1 Safety Assistant 1 1 1 1 Surveyor 2 2 2 2 Survey Assistant 2 2 2 2 Line man (Erection) 1 In progress done 01-Jan-21 2 4 4 4 Site Supervisor 6 4 2 Lab Assistant 2 2 1 1
  • 41. Equipment and Vehicle Plan Sl. Equipment/Vehi cle Name Unit Capacity Monthly Rental Charge (Taka) Monthly Fuel Consumptio n (Liter) Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21 Jul-21 Plan Actual Variance Plan Plan Plan Plan Plan Plan Plan 1 Dump Truck Nos. 145-150 CFT 2 Tractor Nos. 125-130 CFT 65,000.00 400.00 3 2 -1 1 3 Excavator Nos. 7.5 CFT 360,000.00 900.00 0 0 0 1 4 Generator Nos. 8KW 3077.00 0 0 0 0 1 1 1 1 1 5 Crane Nos. 15MT 70,000.00 60.00 2 2 0 2 2 2 2 2 1 1 6 Bike Nos. 60.00 12 12 0 12 12 10 10 10 8 5 7 Pick Up Nos. 250.00 2 2 0 3 3 3 3 2 2 2 NewEquipment Schedule_AGTL_Dec-20.xlsx
  • 42. Material Reconciliation S. No. Materia l Procured Qty Received from other Projects Total Received Physical Stock @ Yard Physical Stock @ Site (if any) Total Physical Stock Actual Consump tion Theoret ical Progres s Savings (+)/ Wastage (- ) % Savings (+)/ % Wastage (-) Remarks A B C D = B + C E F G = E + F H = D - G I J = I - H K = J / I 1 Cement 119411 0 119411 661 661 118750 117723 -1027 -0.87% Actual pile length is about 70% of design length 2 Stone 475903 0 475903 18019 18019 457884 457565 -319 -0.07% 3 Sand 187895 0 187895 15725 15725 172170 170923 -1247 -0.73% Cement, Stone & Sand Material Reconciliation_New Format.rev1_.xlsx
  • 43. Material Reconciliation Rebar Dia (mm) Unit Receiving Details Physical Stock Scrap Actual Consump tion Theoretic al Consump tion Savings (+) % Savings (+) % Scrap (-) Remarks Procured Qty Received from other Projects Total Received Full Length @ Yard & site locations Fabricated Steel @ Yard & Site locations Usable Cut Pieces @ Yard & Site locations Total Stock A B C D E = C + D F G H I = F + G + H J K = E - (I + J) L M = L - K N = M / L O = J / L 8 Kg 20,000 0 20,000 2,020 0 0 2,020 700 17,280 16,756 (524) -3.13% 4.18% Actual pile length is about 70% of design length 10 Kg 540,351 0 540,351 6,389 340 0 6,729 2,770 530,852 529,500 (1,352) -0.26% 0.52% 12 Kg 10,680 0 10,680 - 340 0 340 150 10,190 10,060 (130) -1.29% 1.49% 16 Kg 1,208,899 0 1,208,899 18,600 438 0 19,038 15,000 1,174,861 1,172,141 (2,720) -0.23% 1.28% 20 Kg 1,449,122 0 1,449,122 25,680 946 0 26,626 13,000 1,409,496 1,408,035 (1,461) -0.10% 0.92% 25 Kg 326,254 0 326,254 6,240 0 0 6,240 20,000 300,014 298,655 (1,359) -0.46% 6.70% 32 Kg 177,805 0 177,805 - 0 0 - 500 177,305 176,659 (646) -0.37% 0.28%
  • 45. Financial Progress Budget Cost (Expenditure) from Finance & Accounts Amount % of Budget 5,654,974,549 1,881,591,590.57 33.27% Budget Vs. Cost (Expenditure) Project Value Planned Progress Actual Progress Variance Actual Cash Received BDT (B) % BDT (C) % BDT (C-B) % Mobilization Advance (BDT) (D) Up to Local IPC-8 & Foreign IPC($)- 15 & IPC(€)-1 (E) Contractual amount (A1) 5,640,892,438 2,301,881,930 40.81% 1,670,870,690 29.62% -631,011,240 -11.19% 549,038,090.97 1,121,832,599.03 Revised value (A2) 5,736,238,943 40.13% 29.13% -11.00% 9.73% 19.89%
  • 46. AGTL Cash Spent Vs Cash In Cash Flow Head Up to Jun ‘20 Jul'20 (Plan) Jul'20 (Actual ) Aug'20 (Plan) Aug'20 (Actual ) Sep’20 (Plan) Sep’20 (Actual) Oct’20 (Plan) Oct’20 (Actual) Nov’20 (Plan) Nov’20 (Actual) Dec’20 (Plan) Dec’20 (Actual) Total (Actual) Remarks Cash Received 77.08 8.54 0.00 16.67 0.00 46.87 35.03 12.74 8.21 42.23 0.0 105.33 46.77 167.09 Cash Spent 83.55 6.24 9.82 73.97 0.43 87.97 34.54 10.90 9.98 30.90 8.10 63.43 17.85 188.16 Net Cash flow 3.53 2.30 -9.82 -73.97 -0.43 -41.10 0.49 1.84 -1.77 11.33 -8.10 41.9 28.92 -21.08 USD Bal: 4,933,241.74 EUR Bal: 28,579.59 BDT Bal: 3,388,863.86 All Amounts are in BDT & Crore
  • 47. AGTL Cash Spent Vs In Description TOTAL Remarks Cash Receivable (in Crore BDT) (A) 18.64 Foundation Work Payable (in Crore BDT) (B) 16.29 Net (in Crore BDT) (A-B) 2.35 Receivable/ Payable
  • 48. Budget vs. Expense Sl. No. Segment Revised Budget (BDT) Expense (BDT) BOQ Amount (BDT) IPC Received (BDT) % Financial Progress % Physical Progress % Planned Physical Progress % of Budget Consumed Total % of Total Budget Total % of Total Expense A B = A / ΣA C D = C / ΣC E F G = F / E H = C / A BOQ Items 1 Plant and Mandatory Parts Supply 3,819,391,839.86 67.54% 792,706,551.16 42.13% 3,812,160,969.79 671,615,212.80 17.62% 33.82% 47.75% 20.75% Tower 902,485,873 15.96% 71,267,723.57 3.79% 1,102,341,563.95 110,234,156.40 10.00% 32.02% 44.13% 7.90% Conductor 1,949,404,297 34.47% 572,318,207.59 30.42% 1,772,446,005.27 820,814,807.15 46.31% 43.78% 43.78% 29.36% Fittings 351,014,786 6.21% 149,120,620.00 7.93% 319,253,121.99 146,451,541.04 45.87% 50.23% 50.23% 42.48% Insulator 595,624,383 10.53% - - 596,211,999.86 59,621,199.99 10.00% - 66.67% - OPGW 20,862,500 0.37% - - 21,908,278.71 2,190,827.87 10.00% - - - 2 Design Services 49,731,243.00 0.88% 43,511,122.00 2.31% 64,371,890.49 6,286,238.80 9.77% 93.20% 100% 87.49% Overall Financial Status = 21.33% (OCV) Overall Financial Status= 20.97% (RCV) Overall Physical Status = 34.52.% Continue…
  • 49. Budget vs. Expense Sl. No. Segment Revised Budget (BDT) Expense (BDT) BOQ Amount (BDT) IPC Received (BDT) % Financial Progress % Physical Progress % Planned Physical Progress % of Budget Consumed Total % of Total Budget Total % of Total Expense A B = A / ΣA C D = C / ΣC E F G = F / E H = C / A BOQ Items 3 Installation and Other Services 1,556,351,465.95 27.52% 892,161,275.67 47.42% 1,774,169,886.64 443,210,009.40 24.98% 56.23% 50.72% 57.32% Foundation Work 1,326,858,824 23.46% 889,994,318.67 47.30% 1,327,655,111.65 443,210,009.40 33.38% 70.61% 63.57% 67.08% Testing of Foundations 5,000,000 0.09% 1,456,640.00 0.08% 7,041,540.00 - - 58.33% 66.67% 29.13% Tower Erection 88,182,641 1.56% 710,317.00 0.04% 351,269,561.19 - - 15.96% 14.55% 0.81% Conductor Stringing 136,309,999 2.41% - - 88,203,673.80 - - 0.00% 0.00% - Continue…
  • 50. Budget vs. Expense Sl. No. Segment Revised Budget (BDT) Expense (BDT) BOQ Amount (BDT) IPC Received (BDT) % Financial Progress % Physical Progress % of Budget Consumed Total % of Total Budget Total % of Total Expense A B = A / ΣA C D = C / ΣC E F G = F / E H = C / A Non BOQ Items 4 General & Yard Development 10,000,000.00 0.18% 7,590,300.00 0.40% 85.00% 75.90% 5 Salary and Other Allowances 93,000,000.00 1.64% 54,902,081.00 2.92% 75.00% 59.03% 6 Site Overhead 30,500,000.00 0.54% 19,754,712.74 1.05% 75.00% 64.77% 7 Head Office Overhead 10,000,000.00 0.18% 7,138,198.00 0.38% 75.00% 71.38% 8 Financial Expenses 70,000,000.00 1.24% 51,124,176.00 2.72% 75.00% 73.03% 9 Contingency Fund/Miscellaneous Exp/BP 10,000,000.00 0.18% 8,433,174.00 0.45% 75.00% 84.33% 10 Project Assets (Tools, Plant, Machinery, IT & Furniture) 6,000,000.00 0.11% 4,270,000.00 0.23% 90.00% 71.17% Grand Total (BDT): 5,654,974,548.82 100.00% 1,881,591,590.57
  • 51. Budget vs. Expense (Non BOQ S- Curve) 10.80 11.21 12.18 13.23 14.35 15.79 18.21 19.22 20.10 20.78 21.06 21.33 10.80 11.03 12.10 13.09 13.49 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 18.00 19.00 20.00 21.00 22.00 Up to Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21 Jul-21 Non BOQ Items Plan vs Actual Expense Plan Actual Amounts are in Crore
  • 52. Expense Record Sl. No. Month Expense Cost (%) in terms of Budget Plan (%) 1 Up to Feb-20 702,816,311.5 10.07% 2 Apr-20 30,916,104.00 0.55% 1.71% 3 May-20 54,602,865.00 0.96% 1.12% 4 Jun-20 74,125,278.00 1.31% 1.60% 5 Jul-20 98,199,459.00 1.73% 1.12% 6 Aug-20 4,345,640.00 0.08% 13.08% 7 Sep-20 345,404,588.12 6.11% 15.56% 8 Oct-20 99,751,555 .00 1.79% 1.96% 9 Nov-20 81,021,101.43 1.43% 5.46% 10 Dec-20 178,457,133.00 3.16% 18.62% Total 1,881,591,590.57 33.27%
  • 53. Accounts Payable Summary Sl. No. Description Amount in Taka 1 Cheque in Hand - 2 Accounts Payable 103,722,373 3 Provision for Pending MRR 59,155,950 Total: 162,878,323
  • 54. Advance Details Sl. No. Description Amount in Taka 1 Advance for Yard Rent 300,000 2 Advance for House Rent 300,000 3 Advance for Tower (CSL) Supplier 37,258,278 Advance for Conductor (Sterlite) Supplier 286,887,961 4 Advance for Sub Contractor - Total 324,746,239
  • 55. Cash Flow Projection Up to Dec-21 All Amounts are in BDT & Crore Cashflow Head Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21 Jul-21 Aug-21 Sep-21 Oct-21 Nov-21 Dec-21 Total Net Cash In 40.38 108.11 20.66 11.35 30.58 7.20 6.42 19.40 5.52 4.25 4.49 1.73 365.43 Cash Out 34.69 59.67 21.47 24.89 84.68 5.05 13.89 3.61 3.26 2.54 1.76 1.63 320.56 Net Cashflow 5.70 48.44 -0.81 -13.54 -54.10 2.14 -7.47 15.80 2.26 1.71 2.74 0.10 44.87
  • 56. Cost To Complete (Based on Aggressive Plan) SL Items Amount (BDT) BOQ 2,824,522,348.44 1 Supply 2,276,033,632.01 2 Design 9,540,546.43 3 Installation 538,948,170.00 Non BOQ 844,263,322.02 4 General & Yard Development 1,360,800.00 5 Salary and Other Allowances 35,956,571.25 6 Site Overhead 6,712,000.00 7 Head Office Overhead 940,000.00 8 Financial Expenses 63,000,000.00 9 Contingency Fund/Miscellaneous Exp/BP 4,200,000.00 10 Project Assets (Tools, Plant, Machinery, IT & Furniture) 697,100.00 11 Accounts Payable 731,396,850.77 Total 3,668,785,670.46 CTC.xlsx
  • 57. Variation From Original Contract Description of Variation Unit Variation Quantity Rate Amount impact A B C D E=C x D Total Route Length KM 2.24 39,344,236.61 88,131,090.01 3 Additional Piling per tower 3 2,405,138.33 7,215,415.00 Total 95,346,505.01
  • 58. Profit Margin Profit Margin SL Description Amount (BDT) % of Contract (incl. variation) A Contract Amount 5,640,892,438 B Expense till Dec-20 1,881,591,591 C CTC 3,668,785,670 D Profit Margin (A-B-C) 90,515,177 1.60% E Add Variation D+95346505 185,861,682 3.29% F (Add) Claim Adjustment E+137698915 323,560,597 5.74% G (Deduct) Risk Adjustment F-682851235 -359,290,638 -6.37%