1. Introduction
Quartz Drilling and Lab (QDL) Pvt. Ltd. is an registered engineering investigation firm
established under the act no. 18 of the year 2063 (2006) with the aim at providing engineering
related investigation services. We deliver wide range of services that satisfy clients’ needs for
progressive geotechnical engineering, soil testing, core drilling, ERT survey developments
works.
QDL has aimed to provide pragmatic and disruptive technology and cost-effective solutions to
its clients. This in turn has helped QDL to earn reputation and business excellence in a very
short period. QDL has highly qualified and experienced professionals on its rolls.
2. Services:
QDL provides core drilling and laboratory services for soil and rocks in order to evaluate the
engineering properties of the sub-surface materials.
Drilling works:
QDL carry out the drilling works in every development works both in soil and rocks. We have
two rotary drilling machines; one is XY-150, DW100, DW-50 and Voltas 35. XY-150, a Chinese
rotary drilling machine can drill up to 150 meters. Likewise, Voltas 35 can easily drill up to 200m
into the Himalayan rocks. Similarly, QDL has few percussion machines and Auger Boring
Machines along with the accessories. Percussion machines are generally used to drill the soft
sub surface materials mainly in the terai region and valley fill sediments.
E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624
Laboratory Tests:
QDL aims to provide highly credible results for its clients that ultimately helps them to design a
strong sub and super structures. Highly qualified and experienced lab technicians under the
supervision of engineers, geotechnical engineers and geologist test the soil/rock materials in
order to calculate the engineering properties of the sub surface materials.
We provide lab services for:
 Index Properties of Soil / Rock
 Standard and Modified Proctor
 California Bearing Ratio (CBR)
 Field CBR test
 UCS Test
 Point Load test
 Plate Load Test
In- situ tests
 Unconfined Compression
 Direct Shear Test
 Consolidation
 Permeability
We provide in-situ tests for,
 SPT/DCPT
 Permeability (constant and falling head) tests for soil.
 Lugeon tests (Water pressure tests) for rocks.
 SPT for road
 Field CBR tests
E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624
3. Electrical Resistivity Tomography (ERT) Survey
QDL Provides electrical resistivity survey for the delineation of sub-surface geology, mineral layer
identification, hydrological investigation, differentiate the overburden and bed rock. We had
Geomative 10 (GD10) brand machine having 1200m long cable. We can reveal the sub-surface data
up to 300m depth from the surface.
GD-10 Series Geo-electrical System
GD-10 series is a new electrical geophysical exploration system with highly engineered & cutting
edge technology with a revolutionary change. It is promoted to market focusing the best solution to
meet emerging technological advancements, cost affordability, flexibility in field practices, the
greatest accuracy in geo-electrical exploration, the enduring sustainability for a basic user to a
progressive researcher.
GD-10 series supports 1D VES, 2D ERI and 3D ERT Resistivity/IP measurement, which are the
versatile geophysical method apply for a broad range of applications, as groundwater and mineral
exploration, infrastructure site investigations and so on.
Feature:
 Can measure the resistivity, time domain induced polarization method (IP) and spontaneous
potential (SP);
 High power, wide range, high precision;
 Transmitter and receiver designed in one unit, light and portable;
 The unique sub-level centralized cable system realized the electrode switching by CL-10 cable
leader, no electrode limit on measurement, which features light, low cost and easy operation.
 Using a unique scrolling technology, which can detects deeper than comparable instruments
with no repeated measuring point. And the scrolling function is realized during detection, which
improve the working efficiency.
 The data management platform, Geomative Studio, breaks through the bottleneck of traditional
embedded software, which enrich the software function greatly;
 Designed with built-in GPS, can accurately determine the measurement coordinates;
 Multi-electrode cable with bi-direction design and dual take-outs enable the parallel electrodes
for high power applications;
 Powerful self-checking function for the high-quality data during measurement, including
Grounding R test, switcher test and cable leader test.
 Communication port for USB data transfer;
 Real-time data valuation, the time window can be set in IP survey;
 High reliability, security and robustness, can use in extremely harsh weather.
E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624
GD-10 Advanced 2D Multi-electrode Res Imaging System is the 2D ERI system with functions of SP
survey, 1D Resistivity/IP sounding survey and 2D Resistivity Imaging survey. The mainframe
including GD-10 mainframe and CS-60 multi-electrode switching box.
Power: 800V/1600Vp-p, 4A, 3200W
E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624
4. Working Areas:
We are expert in working different disciplines of development works.
Some defined working areas have been outlined below.
 Drilling and in-situ testing for Hydropower
 Drilling and in-situ testing for Mines
 Drilling and in-situ testing for Bridges and Buildings
 Transmission lines tower foundation soil testing
 Sub-station site soil testing
 Soil resistivity measurement of TL tower foundation
 Mine investigation and Quarry site investigation
 Geological and engineering geological mapping
 Electrical Resistivity tomography (ERT) survey for Hydropowers, Mines, Bridges, Slopes
 Soil and Rock testing laboratory.
E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624
5. Completed Projects
General Construction Experience
Starting
Month
Year
Ending
Month
Year
Year Contract Identification and Name and
address of Employer Brief Description of
the Works Executed by the Bidder
Client
Nov Dec 2022 ERT survey of Mugu Karnali
Hydroelectric Project, Mugu
Department of Electricity
Development (DOED),
Nepal
April Dec 2022 Core drilling and geotechnical
investigation work of Super
Budhigandaki Hydroelectric Project,
Gorkha
Department of Electricity
Development (DOED),
Nepal
May Dec 2022 Core drilling and geotechnical
investigation work of Tom Dogar
Hydroelectric Project, Gorkha
Department of Electricity
Development (DOED),
Nepal
Aug Oct 2022 Geotechnical Investigation of
Kaligandaki-Ridi 132kV Transmission
Line Project, Palpa
Nepal Electricity Authority
June Aug 2022 ERT survey of Upper Mugu Karnali
Hydropower Project, Mugu
Golyan Group
July Aug 2022 ERT survey of Super Budhigandaki
Hydroelectric project, Gorkha
Department of Electricity
Development (DOED),
Nepal
Mar May 2022 ERT Survey of Tom Dogar Hydroelectric
project, Gorkha
Department of Electricity
Development (DOED),
Nepal
July Aug 2022 Core drilling and geotechnical
investigation work of Bhotekoshi-1
Hydropower Project, Sindhupalchok
Shailung Power Company
Limited
July July 2022 ERT and MASW survey of Myagdi Khola
Hyropower Project, Myagdi
Hydro Village Pvt. Ltd.
E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624
June June 2022 ERT survey of Daraudi Khola
Hydropower Project, Gorkha
Epicenter Engineering
Solution Pvt. Ltd.
June June 2022 ERT survey of Daraudi Khola
Hydropower Project, Gorkha
Epicenter Engineering
Solution Pvt. Ltd.
April June 2022 Geological Mapping and ERT survey of
Bakan Khola Hydropower Project,
Shankhuwasabha
Epicenter Engineering
Solution Pvt. Ltd.
April June 2022 Geological Mapping and ERT survey of
Chujung Khola Hydropower Project,
Shankhuwasabha
Epicenter Engineering
Solution Pvt. Ltd.
May May 2022 Geotechnical investigation of Tribhuvan
International Airport Terminal Building,
Kathmandu
Tribhuvan International
Airport Authority, Nepal
Mar May 2022 Geological mapping and report
preparation of Super Budhigandaki
Hydroelectric project, Gorkha
Department of Electricity
Development (DOED),
Nepal
Mar May 2022 Geological mapping and report
preparation of Tom Dogar Hydroelectric
project, Gorkha
Department of Electricity
Development (DOED),
Nepal
Mar Apr 2022 Core drilling work of Madhya Mailung
Javidhyut Ayojana, Rasuwa
Mathillo Mailung Khola
Jalvidhyut Limited
Feb Mar 2022 Electrical Resistivity Tomography (ERT)
survey of Bhotekoshi-1 Hydropower
Project, Sindhupalchok
Shailung Power Company
Limited
Jan Feb 2022 Core drilling work of Mathillo Mailung
‘B’ Javidhyut Ayojana, Rasuwa
Mathillo Mailung Khola
Jalvidhyut Limited
Aug Sep 2021 Electrical Resistivity Tomography (ERT)
survey of Rauje Khola Hydropower
Project, Solukhumbu
Cepad Hydroconsultants
Pvt. Ltd.
E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624
July Aug 2021 Electrical Resistivity Tomography (ERT)
survey of Luja Khola Hydropower
Project, Solukhumbu
Silk Power Pvt. Ltd.
Feb May 2021 Geotechnical Investigation of Balefi-
Bahrabise 132 kV Transmission Line
Project, Sindhupalchok
Nepal Electricity Authority
Jan June 2021 Core drilling work of Lower Apsuwa
Khola Hydropower Project,
Shankhuwasabha
Golyan Group
Jan Jan 2021 ERT survey and Geotechnical
investigation of Zipline foundation and
YoYo Resort, Bhaktpur
YoYo Zipline Pvt. Ltd.
Jan Jan 2021 ERT Survey of Bhujung Khola
Hydropower Project, Lamjung
Bhujung Hydropower
Company Pvt. Ltd.
Dec Dec 2021 ERT Survey of Dar Khola Hydropower
Project, Myagdi
Dar Khola Hydropower
Company Pvt. Ltd.
Nov Nov 2021 ERT Survey of Khani Khola Dolakha
Hydropower Project, Dolakha
SASA Engineering
Company Pvt. Ltd.
Sep Nov 2020 Geotechnical Investigation of Mainhiya-
Sampatiya 132 kV Transmission Line
Project, Nepal Electricity Authority
Nepal Electricity Authority
June Aug 2020 Geotechnical Investigation of Burtibang
Paudi-Amarai Tamghas Sandhikharka
Gorushinge 132 kV Transmission Line
Project, Nepal Electricity Authority,
Contract No. BPTSG-074/75-01
Nepal Electricity Authority
Sep Oct 2020 Electrical Resistivity Survey of Upper
Brahmayani Hydropower Project,
Sindhupalchok
Ekikrit Byapar Company
Pvt. Ltd.
March May 2020 Geotechnical Investigation of Hitar-
Sitalpati (Arun Coridor) 400 kV
Transmission Line Project
RGPCL
February March 2020 Core drilling works of Lower Likhu
Hydropower Project, Ramechhap
Swet Ganga Hydropower
and Construction Limited
E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624
August September 2019 Geotechnical Investigation of Proposed
Building Foundation at Jarankhu,
Kathmandu
School
July August 2019 Geotechnical Investigation of Proposed
Building Foundation at Boudha,
Kathmandu
Kapan Gumba
March April 2019 Geotechnical Investigation of Proposed
Chitwan Rangshala Foundation at
Ratnanagar, Chitwan
District Sports
Development Committee
May June 2019 Geotechnical Investigation of Proposed
Building Foundation at Kuleshwor,
Kathmandu
Sunrays Trading Pvt. Ltd.
Jan Feb 2019 Geotechnical Investigation of Likhu IV-
New Tamakoshi 220 kV Transmission
Line Project, Green Ventures Pvt. Ltd.
Contract No. Likhu-IV/GVN/Package
05/2018
Green Ventures Pvt. Ltd.
March May 2019 Geotechnical Investigation of Burtibang
Paudi-Amarai Tamghas Sandhikharka
Gorushinge 132 kV Transmission Line
Project, Nepal Electricity Authority,
Contract No. BPTSG-074/75-01
Nepal Electricity Authority
August October 2019 Resitivity Survey of Soti Khola
Hydropower Project, Manang
Cepad Hydro Consultants
Pvt. Ltd.
November December 2019 Elecrical Resistivity Survey of Rauje
Khola Hydropower Project, Solukhumbu
Cepad Hydro Consultants
Pvt. Ltd.
October June 2019 Core Drilling works of Khara Limesone
Deposit, Rolpa
Samrat Cement Pvt. Ltd.
May July 2019 Electrical Resistivity Survey of
Brahmayani Hydropower Project,
Sindhupalchok
Ekikrit Byapar Company
Pvt. Ltd.
March September 2018 Core Drilling works of Thara Limestone
Deposit, Dang
Samrat Cement Pvt. Ltd.
March July 2018 Geotechnical Investigation of Hongu
Khola Hydropower Project, Solukhumbu
CEBDL Hydro Fund Limited
August September 2018 Electrical Resitivity Survey of Chepe
Khola Hydropower Project, Lamjung
November December 2018 Resitivity Survey of Richet Khola
Hydropower Project, Gorkha
Richet Khola Hydropower
Company Pvt. Ltd.
E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624
October October 2018 Electrical Restivity Survey and
Geotechnical Investigation of
Dudhkunda Khola Hydropower Project,
Solukhumbu
Cepad Hydro Consultants
Pvt. Ltd.
August December 2017 Geotechnical Investigation of
Dudhkoshi-6, Dudhkoshi-9 and
Dudhkoshi-10 Hydropower Project,
Solukhumbu
Cepad Hydro Consultants
Pvt. Ltd.
July August 2017 Geotechnical Investigation of Proposed
Medical Building at Tandi, Chitwan
Bakulahar Ratnanagar
Hospital
June August 2017 Geotechnical Investigation of Middle
Marsyandi-Dumre-Damauli 132kV
Transmission Line & Substation Project,
Nepal Electricity Authority, Contract No.
MMDD/NCB/73-74/TL-1
Nepal Electricity Authority
August September 2016 Geotechnical Investigation of Proposed
Residential Building at Sitapaila-5,
Kathmandu
January May 2016 Geotechnical Investigation of Liping
Khola Hydropower Project,
Sindhupalchok
Swacha Urja Pvt. Ltd.
6. Ongoing Projects
1. Geo-technical investigation of proposed building foundation at Bhaktpur
2. Geo-technical investigation of proposed building foundation at Maharajgunj
3. ERT survey of Salque Khola Hydropower Project, Manang
E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624
7. Manpower
Manju Kandel Managing Director
Dilandra Raj Pathak Senior Geologist
Bishow Bastakoti Geotechnical Engineer
Gyanendra Raj Sapkota Engineering Geologist
Ramesh Joshi Civil Engineer
Subash Pousel Civil Engineer
Manoj Damai Accountant
Urmila Rana Lab Technician
Suraj Pathak Administration
Lila Bahadur Rana Magar Driller
Krishna Nagarkoti Shrestha Driller
Ram Nagarkoti Shrestha Driller
Nabin Magar Driller
Ram Lal Tamang Driller
Bikash Tamang Driller
Krishna Thapa Driller
Shukra Thapa Magar Driller
E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624
Drilling work in Different sites
E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624
E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624
E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624
ERT Survey at different sites
E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624
E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624

More Related Content

Similar to QUATRZ DRILLING AND LAB COMPANY PROFILE.pdf

Similar to QUATRZ DRILLING AND LAB COMPANY PROFILE.pdf (20)

Land Surveyor Akmal Khan
Land Surveyor Akmal KhanLand Surveyor Akmal Khan
Land Surveyor Akmal Khan
 
Rajib Ali CV (Final)
Rajib Ali CV (Final)Rajib Ali CV (Final)
Rajib Ali CV (Final)
 
VK-Resume
VK-ResumeVK-Resume
VK-Resume
 
V. SRINIVASA RAO CV
V. SRINIVASA RAO CVV. SRINIVASA RAO CV
V. SRINIVASA RAO CV
 
Narender_Geologist cum Shift Engg. Resume
Narender_Geologist cum Shift Engg. ResumeNarender_Geologist cum Shift Engg. Resume
Narender_Geologist cum Shift Engg. Resume
 
GIRIRAJAN
GIRIRAJANGIRIRAJAN
GIRIRAJAN
 
Sourav Cv
Sourav CvSourav Cv
Sourav Cv
 
Project Route Map - OMC South Kaliapani Chromite UG Mine
Project Route Map - OMC South Kaliapani Chromite UG MineProject Route Map - OMC South Kaliapani Chromite UG Mine
Project Route Map - OMC South Kaliapani Chromite UG Mine
 
haq_(3)
haq_(3)haq_(3)
haq_(3)
 
Engineering Geologist
Engineering GeologistEngineering Geologist
Engineering Geologist
 
Vivencio Atienza updated resume 2016
Vivencio Atienza updated resume 2016Vivencio Atienza updated resume 2016
Vivencio Atienza updated resume 2016
 
LINGAM
LINGAMLINGAM
LINGAM
 
CFF.CV_10.07.2016
CFF.CV_10.07.2016CFF.CV_10.07.2016
CFF.CV_10.07.2016
 
GOPAL
GOPALGOPAL
GOPAL
 
NACE CP LEVEL II ENGINEER
NACE CP LEVEL II ENGINEERNACE CP LEVEL II ENGINEER
NACE CP LEVEL II ENGINEER
 
anindya maity-cv
anindya maity-cvanindya maity-cv
anindya maity-cv
 
TonyCV updated5dec16

TonyCV updated5dec16
TonyCV updated5dec16

TonyCV updated5dec16

 
GDRPL Company Profile - .pptx
GDRPL Company Profile - .pptxGDRPL Company Profile - .pptx
GDRPL Company Profile - .pptx
 
VEERAPANDIAN CV.doc1
VEERAPANDIAN CV.doc1VEERAPANDIAN CV.doc1
VEERAPANDIAN CV.doc1
 
V.BASKAR CV
V.BASKAR CVV.BASKAR CV
V.BASKAR CV
 

More from NeerajOjha17

पाठ्यवस्तु समायोजन ढांचा (कक्षा ९-१०).pdf
पाठ्यवस्तु समायोजन ढांचा (कक्षा ९-१०).pdfपाठ्यवस्तु समायोजन ढांचा (कक्षा ९-१०).pdf
पाठ्यवस्तु समायोजन ढांचा (कक्षा ९-१०).pdfNeerajOjha17
 
Staff commitment.doc
Staff commitment.docStaff commitment.doc
Staff commitment.docNeerajOjha17
 
Affidavit of Surya B Gurung.docx
Affidavit of Surya B Gurung.docxAffidavit of Surya B Gurung.docx
Affidavit of Surya B Gurung.docxNeerajOjha17
 
AFFIDAVIT ON EXTRAORDINARY BY A PETITIONER-1.docx
AFFIDAVIT ON EXTRAORDINARY BY A PETITIONER-1.docxAFFIDAVIT ON EXTRAORDINARY BY A PETITIONER-1.docx
AFFIDAVIT ON EXTRAORDINARY BY A PETITIONER-1.docxNeerajOjha17
 
Affidavit Ghosh.docx
Affidavit Ghosh.docxAffidavit Ghosh.docx
Affidavit Ghosh.docxNeerajOjha17
 
affidvit.Cjitrakar,Nalina.doc
affidvit.Cjitrakar,Nalina.docaffidvit.Cjitrakar,Nalina.doc
affidvit.Cjitrakar,Nalina.docNeerajOjha17
 
affidvit.Cjitrakar,Nalina_1.doc
affidvit.Cjitrakar,Nalina_1.docaffidvit.Cjitrakar,Nalina_1.doc
affidvit.Cjitrakar,Nalina_1.docNeerajOjha17
 
Affidavit.COV.docx
Affidavit.COV.docxAffidavit.COV.docx
Affidavit.COV.docxNeerajOjha17
 
Affidavit of Plaintiff.docx
Affidavit of Plaintiff.docxAffidavit of Plaintiff.docx
Affidavit of Plaintiff.docxNeerajOjha17
 
Affidavit of Regularity_1.docx
Affidavit of Regularity_1.docxAffidavit of Regularity_1.docx
Affidavit of Regularity_1.docxNeerajOjha17
 
Supporting Letter.EB-1,Ghosh, Mampi (BhattaLawFirm's conflicted copy 2011-11-...
Supporting Letter.EB-1,Ghosh, Mampi (BhattaLawFirm's conflicted copy 2011-11-...Supporting Letter.EB-1,Ghosh, Mampi (BhattaLawFirm's conflicted copy 2011-11-...
Supporting Letter.EB-1,Ghosh, Mampi (BhattaLawFirm's conflicted copy 2011-11-...NeerajOjha17
 
Affidavit Ghosh.docx
Affidavit Ghosh.docxAffidavit Ghosh.docx
Affidavit Ghosh.docxNeerajOjha17
 
Proof of Service (2).docx
Proof of Service (2).docxProof of Service (2).docx
Proof of Service (2).docxNeerajOjha17
 
MY FORMAT ULTRA PRO MAX (1).docx
MY FORMAT  ULTRA PRO MAX (1).docxMY FORMAT  ULTRA PRO MAX (1).docx
MY FORMAT ULTRA PRO MAX (1).docxNeerajOjha17
 
Sailesh CV_Cist.docx
Sailesh CV_Cist.docxSailesh CV_Cist.docx
Sailesh CV_Cist.docxNeerajOjha17
 
1-A-Define the health system and describe the functions and elements of healt...
1-A-Define the health system and describe the functions and elements of healt...1-A-Define the health system and describe the functions and elements of healt...
1-A-Define the health system and describe the functions and elements of healt...NeerajOjha17
 
1-B-Models of Health System.ppt
1-B-Models of Health System.ppt1-B-Models of Health System.ppt
1-B-Models of Health System.pptNeerajOjha17
 
2-A-Brief Hisory of HSD in Nepal.pptx
2-A-Brief Hisory of HSD in Nepal.pptx2-A-Brief Hisory of HSD in Nepal.pptx
2-A-Brief Hisory of HSD in Nepal.pptxNeerajOjha17
 

More from NeerajOjha17 (20)

पाठ्यवस्तु समायोजन ढांचा (कक्षा ९-१०).pdf
पाठ्यवस्तु समायोजन ढांचा (कक्षा ९-१०).pdfपाठ्यवस्तु समायोजन ढांचा (कक्षा ९-१०).pdf
पाठ्यवस्तु समायोजन ढांचा (कक्षा ९-१०).pdf
 
Staff commitment.doc
Staff commitment.docStaff commitment.doc
Staff commitment.doc
 
Affidavit of Surya B Gurung.docx
Affidavit of Surya B Gurung.docxAffidavit of Surya B Gurung.docx
Affidavit of Surya B Gurung.docx
 
AFFIDAVIT ON EXTRAORDINARY BY A PETITIONER-1.docx
AFFIDAVIT ON EXTRAORDINARY BY A PETITIONER-1.docxAFFIDAVIT ON EXTRAORDINARY BY A PETITIONER-1.docx
AFFIDAVIT ON EXTRAORDINARY BY A PETITIONER-1.docx
 
Affidavit Ghosh.docx
Affidavit Ghosh.docxAffidavit Ghosh.docx
Affidavit Ghosh.docx
 
affidvit.Cjitrakar,Nalina.doc
affidvit.Cjitrakar,Nalina.docaffidvit.Cjitrakar,Nalina.doc
affidvit.Cjitrakar,Nalina.doc
 
affidvit.Cjitrakar,Nalina_1.doc
affidvit.Cjitrakar,Nalina_1.docaffidvit.Cjitrakar,Nalina_1.doc
affidvit.Cjitrakar,Nalina_1.doc
 
Affidavit.COV.docx
Affidavit.COV.docxAffidavit.COV.docx
Affidavit.COV.docx
 
Affidavit of Plaintiff.docx
Affidavit of Plaintiff.docxAffidavit of Plaintiff.docx
Affidavit of Plaintiff.docx
 
Affidavit of Regularity_1.docx
Affidavit of Regularity_1.docxAffidavit of Regularity_1.docx
Affidavit of Regularity_1.docx
 
Supporting Letter.EB-1,Ghosh, Mampi (BhattaLawFirm's conflicted copy 2011-11-...
Supporting Letter.EB-1,Ghosh, Mampi (BhattaLawFirm's conflicted copy 2011-11-...Supporting Letter.EB-1,Ghosh, Mampi (BhattaLawFirm's conflicted copy 2011-11-...
Supporting Letter.EB-1,Ghosh, Mampi (BhattaLawFirm's conflicted copy 2011-11-...
 
Affidavit Ghosh.docx
Affidavit Ghosh.docxAffidavit Ghosh.docx
Affidavit Ghosh.docx
 
Proof of Service (2).docx
Proof of Service (2).docxProof of Service (2).docx
Proof of Service (2).docx
 
MY FORMAT ULTRA PRO MAX (1).docx
MY FORMAT  ULTRA PRO MAX (1).docxMY FORMAT  ULTRA PRO MAX (1).docx
MY FORMAT ULTRA PRO MAX (1).docx
 
mamata.doc
mamata.docmamata.doc
mamata.doc
 
Sailesh CV_Cist.docx
Sailesh CV_Cist.docxSailesh CV_Cist.docx
Sailesh CV_Cist.docx
 
Sristi.docx
Sristi.docxSristi.docx
Sristi.docx
 
1-A-Define the health system and describe the functions and elements of healt...
1-A-Define the health system and describe the functions and elements of healt...1-A-Define the health system and describe the functions and elements of healt...
1-A-Define the health system and describe the functions and elements of healt...
 
1-B-Models of Health System.ppt
1-B-Models of Health System.ppt1-B-Models of Health System.ppt
1-B-Models of Health System.ppt
 
2-A-Brief Hisory of HSD in Nepal.pptx
2-A-Brief Hisory of HSD in Nepal.pptx2-A-Brief Hisory of HSD in Nepal.pptx
2-A-Brief Hisory of HSD in Nepal.pptx
 

Recently uploaded

Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...amitlee9823
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...allensay1
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...amitlee9823
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...Anamikakaur10
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfAdmir Softic
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptxnandhinijagan9867
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperityhemanthkumar470700
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with CultureSeta Wicaksana
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableSeo
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...daisycvs
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876dlhescort
 

Recently uploaded (20)

Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 
Falcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in indiaFalcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in india
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
 

QUATRZ DRILLING AND LAB COMPANY PROFILE.pdf

  • 1. E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624 COMPANY PROFILE FOR Quartz Drilling and Lab Pvt. Ltd. (Geotechnical and Geophysical Investigations) Kirtipur, Kathmandu Email: quartz2072@gmail.com Phone: 014384642, 9851022075, Po Box. 25117 NEPAL 2015
  • 2. E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624 1. Introduction Quartz Drilling and Lab (QDL) Pvt. Ltd. is an registered engineering investigation firm established under the act no. 18 of the year 2063 (2006) with the aim at providing engineering related investigation services. We deliver wide range of services that satisfy clients’ needs for progressive geotechnical engineering, soil testing, core drilling, ERT survey developments works. QDL has aimed to provide pragmatic and disruptive technology and cost-effective solutions to its clients. This in turn has helped QDL to earn reputation and business excellence in a very short period. QDL has highly qualified and experienced professionals on its rolls. 2. Services: QDL provides core drilling and laboratory services for soil and rocks in order to evaluate the engineering properties of the sub-surface materials. Drilling works: QDL carry out the drilling works in every development works both in soil and rocks. We have two rotary drilling machines; one is XY-150, DW100, DW-50 and Voltas 35. XY-150, a Chinese rotary drilling machine can drill up to 150 meters. Likewise, Voltas 35 can easily drill up to 200m into the Himalayan rocks. Similarly, QDL has few percussion machines and Auger Boring Machines along with the accessories. Percussion machines are generally used to drill the soft sub surface materials mainly in the terai region and valley fill sediments.
  • 3. E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624 Laboratory Tests: QDL aims to provide highly credible results for its clients that ultimately helps them to design a strong sub and super structures. Highly qualified and experienced lab technicians under the supervision of engineers, geotechnical engineers and geologist test the soil/rock materials in order to calculate the engineering properties of the sub surface materials. We provide lab services for:  Index Properties of Soil / Rock  Standard and Modified Proctor  California Bearing Ratio (CBR)  Field CBR test  UCS Test  Point Load test  Plate Load Test In- situ tests  Unconfined Compression  Direct Shear Test  Consolidation  Permeability We provide in-situ tests for,  SPT/DCPT  Permeability (constant and falling head) tests for soil.  Lugeon tests (Water pressure tests) for rocks.  SPT for road  Field CBR tests
  • 4. E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624 3. Electrical Resistivity Tomography (ERT) Survey QDL Provides electrical resistivity survey for the delineation of sub-surface geology, mineral layer identification, hydrological investigation, differentiate the overburden and bed rock. We had Geomative 10 (GD10) brand machine having 1200m long cable. We can reveal the sub-surface data up to 300m depth from the surface. GD-10 Series Geo-electrical System GD-10 series is a new electrical geophysical exploration system with highly engineered & cutting edge technology with a revolutionary change. It is promoted to market focusing the best solution to meet emerging technological advancements, cost affordability, flexibility in field practices, the greatest accuracy in geo-electrical exploration, the enduring sustainability for a basic user to a progressive researcher. GD-10 series supports 1D VES, 2D ERI and 3D ERT Resistivity/IP measurement, which are the versatile geophysical method apply for a broad range of applications, as groundwater and mineral exploration, infrastructure site investigations and so on. Feature:  Can measure the resistivity, time domain induced polarization method (IP) and spontaneous potential (SP);  High power, wide range, high precision;  Transmitter and receiver designed in one unit, light and portable;  The unique sub-level centralized cable system realized the electrode switching by CL-10 cable leader, no electrode limit on measurement, which features light, low cost and easy operation.  Using a unique scrolling technology, which can detects deeper than comparable instruments with no repeated measuring point. And the scrolling function is realized during detection, which improve the working efficiency.  The data management platform, Geomative Studio, breaks through the bottleneck of traditional embedded software, which enrich the software function greatly;  Designed with built-in GPS, can accurately determine the measurement coordinates;  Multi-electrode cable with bi-direction design and dual take-outs enable the parallel electrodes for high power applications;  Powerful self-checking function for the high-quality data during measurement, including Grounding R test, switcher test and cable leader test.  Communication port for USB data transfer;  Real-time data valuation, the time window can be set in IP survey;  High reliability, security and robustness, can use in extremely harsh weather.
  • 5. E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624 GD-10 Advanced 2D Multi-electrode Res Imaging System is the 2D ERI system with functions of SP survey, 1D Resistivity/IP sounding survey and 2D Resistivity Imaging survey. The mainframe including GD-10 mainframe and CS-60 multi-electrode switching box. Power: 800V/1600Vp-p, 4A, 3200W
  • 6. E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624 4. Working Areas: We are expert in working different disciplines of development works. Some defined working areas have been outlined below.  Drilling and in-situ testing for Hydropower  Drilling and in-situ testing for Mines  Drilling and in-situ testing for Bridges and Buildings  Transmission lines tower foundation soil testing  Sub-station site soil testing  Soil resistivity measurement of TL tower foundation  Mine investigation and Quarry site investigation  Geological and engineering geological mapping  Electrical Resistivity tomography (ERT) survey for Hydropowers, Mines, Bridges, Slopes  Soil and Rock testing laboratory.
  • 7. E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624 5. Completed Projects General Construction Experience Starting Month Year Ending Month Year Year Contract Identification and Name and address of Employer Brief Description of the Works Executed by the Bidder Client Nov Dec 2022 ERT survey of Mugu Karnali Hydroelectric Project, Mugu Department of Electricity Development (DOED), Nepal April Dec 2022 Core drilling and geotechnical investigation work of Super Budhigandaki Hydroelectric Project, Gorkha Department of Electricity Development (DOED), Nepal May Dec 2022 Core drilling and geotechnical investigation work of Tom Dogar Hydroelectric Project, Gorkha Department of Electricity Development (DOED), Nepal Aug Oct 2022 Geotechnical Investigation of Kaligandaki-Ridi 132kV Transmission Line Project, Palpa Nepal Electricity Authority June Aug 2022 ERT survey of Upper Mugu Karnali Hydropower Project, Mugu Golyan Group July Aug 2022 ERT survey of Super Budhigandaki Hydroelectric project, Gorkha Department of Electricity Development (DOED), Nepal Mar May 2022 ERT Survey of Tom Dogar Hydroelectric project, Gorkha Department of Electricity Development (DOED), Nepal July Aug 2022 Core drilling and geotechnical investigation work of Bhotekoshi-1 Hydropower Project, Sindhupalchok Shailung Power Company Limited July July 2022 ERT and MASW survey of Myagdi Khola Hyropower Project, Myagdi Hydro Village Pvt. Ltd.
  • 8. E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624 June June 2022 ERT survey of Daraudi Khola Hydropower Project, Gorkha Epicenter Engineering Solution Pvt. Ltd. June June 2022 ERT survey of Daraudi Khola Hydropower Project, Gorkha Epicenter Engineering Solution Pvt. Ltd. April June 2022 Geological Mapping and ERT survey of Bakan Khola Hydropower Project, Shankhuwasabha Epicenter Engineering Solution Pvt. Ltd. April June 2022 Geological Mapping and ERT survey of Chujung Khola Hydropower Project, Shankhuwasabha Epicenter Engineering Solution Pvt. Ltd. May May 2022 Geotechnical investigation of Tribhuvan International Airport Terminal Building, Kathmandu Tribhuvan International Airport Authority, Nepal Mar May 2022 Geological mapping and report preparation of Super Budhigandaki Hydroelectric project, Gorkha Department of Electricity Development (DOED), Nepal Mar May 2022 Geological mapping and report preparation of Tom Dogar Hydroelectric project, Gorkha Department of Electricity Development (DOED), Nepal Mar Apr 2022 Core drilling work of Madhya Mailung Javidhyut Ayojana, Rasuwa Mathillo Mailung Khola Jalvidhyut Limited Feb Mar 2022 Electrical Resistivity Tomography (ERT) survey of Bhotekoshi-1 Hydropower Project, Sindhupalchok Shailung Power Company Limited Jan Feb 2022 Core drilling work of Mathillo Mailung ‘B’ Javidhyut Ayojana, Rasuwa Mathillo Mailung Khola Jalvidhyut Limited Aug Sep 2021 Electrical Resistivity Tomography (ERT) survey of Rauje Khola Hydropower Project, Solukhumbu Cepad Hydroconsultants Pvt. Ltd.
  • 9. E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624 July Aug 2021 Electrical Resistivity Tomography (ERT) survey of Luja Khola Hydropower Project, Solukhumbu Silk Power Pvt. Ltd. Feb May 2021 Geotechnical Investigation of Balefi- Bahrabise 132 kV Transmission Line Project, Sindhupalchok Nepal Electricity Authority Jan June 2021 Core drilling work of Lower Apsuwa Khola Hydropower Project, Shankhuwasabha Golyan Group Jan Jan 2021 ERT survey and Geotechnical investigation of Zipline foundation and YoYo Resort, Bhaktpur YoYo Zipline Pvt. Ltd. Jan Jan 2021 ERT Survey of Bhujung Khola Hydropower Project, Lamjung Bhujung Hydropower Company Pvt. Ltd. Dec Dec 2021 ERT Survey of Dar Khola Hydropower Project, Myagdi Dar Khola Hydropower Company Pvt. Ltd. Nov Nov 2021 ERT Survey of Khani Khola Dolakha Hydropower Project, Dolakha SASA Engineering Company Pvt. Ltd. Sep Nov 2020 Geotechnical Investigation of Mainhiya- Sampatiya 132 kV Transmission Line Project, Nepal Electricity Authority Nepal Electricity Authority June Aug 2020 Geotechnical Investigation of Burtibang Paudi-Amarai Tamghas Sandhikharka Gorushinge 132 kV Transmission Line Project, Nepal Electricity Authority, Contract No. BPTSG-074/75-01 Nepal Electricity Authority Sep Oct 2020 Electrical Resistivity Survey of Upper Brahmayani Hydropower Project, Sindhupalchok Ekikrit Byapar Company Pvt. Ltd. March May 2020 Geotechnical Investigation of Hitar- Sitalpati (Arun Coridor) 400 kV Transmission Line Project RGPCL February March 2020 Core drilling works of Lower Likhu Hydropower Project, Ramechhap Swet Ganga Hydropower and Construction Limited
  • 10. E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624 August September 2019 Geotechnical Investigation of Proposed Building Foundation at Jarankhu, Kathmandu School July August 2019 Geotechnical Investigation of Proposed Building Foundation at Boudha, Kathmandu Kapan Gumba March April 2019 Geotechnical Investigation of Proposed Chitwan Rangshala Foundation at Ratnanagar, Chitwan District Sports Development Committee May June 2019 Geotechnical Investigation of Proposed Building Foundation at Kuleshwor, Kathmandu Sunrays Trading Pvt. Ltd. Jan Feb 2019 Geotechnical Investigation of Likhu IV- New Tamakoshi 220 kV Transmission Line Project, Green Ventures Pvt. Ltd. Contract No. Likhu-IV/GVN/Package 05/2018 Green Ventures Pvt. Ltd. March May 2019 Geotechnical Investigation of Burtibang Paudi-Amarai Tamghas Sandhikharka Gorushinge 132 kV Transmission Line Project, Nepal Electricity Authority, Contract No. BPTSG-074/75-01 Nepal Electricity Authority August October 2019 Resitivity Survey of Soti Khola Hydropower Project, Manang Cepad Hydro Consultants Pvt. Ltd. November December 2019 Elecrical Resistivity Survey of Rauje Khola Hydropower Project, Solukhumbu Cepad Hydro Consultants Pvt. Ltd. October June 2019 Core Drilling works of Khara Limesone Deposit, Rolpa Samrat Cement Pvt. Ltd. May July 2019 Electrical Resistivity Survey of Brahmayani Hydropower Project, Sindhupalchok Ekikrit Byapar Company Pvt. Ltd. March September 2018 Core Drilling works of Thara Limestone Deposit, Dang Samrat Cement Pvt. Ltd. March July 2018 Geotechnical Investigation of Hongu Khola Hydropower Project, Solukhumbu CEBDL Hydro Fund Limited August September 2018 Electrical Resitivity Survey of Chepe Khola Hydropower Project, Lamjung November December 2018 Resitivity Survey of Richet Khola Hydropower Project, Gorkha Richet Khola Hydropower Company Pvt. Ltd.
  • 11. E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624 October October 2018 Electrical Restivity Survey and Geotechnical Investigation of Dudhkunda Khola Hydropower Project, Solukhumbu Cepad Hydro Consultants Pvt. Ltd. August December 2017 Geotechnical Investigation of Dudhkoshi-6, Dudhkoshi-9 and Dudhkoshi-10 Hydropower Project, Solukhumbu Cepad Hydro Consultants Pvt. Ltd. July August 2017 Geotechnical Investigation of Proposed Medical Building at Tandi, Chitwan Bakulahar Ratnanagar Hospital June August 2017 Geotechnical Investigation of Middle Marsyandi-Dumre-Damauli 132kV Transmission Line & Substation Project, Nepal Electricity Authority, Contract No. MMDD/NCB/73-74/TL-1 Nepal Electricity Authority August September 2016 Geotechnical Investigation of Proposed Residential Building at Sitapaila-5, Kathmandu January May 2016 Geotechnical Investigation of Liping Khola Hydropower Project, Sindhupalchok Swacha Urja Pvt. Ltd. 6. Ongoing Projects 1. Geo-technical investigation of proposed building foundation at Bhaktpur 2. Geo-technical investigation of proposed building foundation at Maharajgunj 3. ERT survey of Salque Khola Hydropower Project, Manang
  • 12. E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624 7. Manpower Manju Kandel Managing Director Dilandra Raj Pathak Senior Geologist Bishow Bastakoti Geotechnical Engineer Gyanendra Raj Sapkota Engineering Geologist Ramesh Joshi Civil Engineer Subash Pousel Civil Engineer Manoj Damai Accountant Urmila Rana Lab Technician Suraj Pathak Administration Lila Bahadur Rana Magar Driller Krishna Nagarkoti Shrestha Driller Ram Nagarkoti Shrestha Driller Nabin Magar Driller Ram Lal Tamang Driller Bikash Tamang Driller Krishna Thapa Driller Shukra Thapa Magar Driller
  • 13. E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624 Drilling work in Different sites
  • 14. E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624
  • 15. E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624
  • 16. E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624 ERT Survey at different sites
  • 17. E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624
  • 18. E-mail: quartz2072@gmail.com, Po Box No.: 25117, Phone: 014384624