DURGAPUR STEEL PLANT
Status as on 12.10.22
SUMMARY OF ASSIGNMENTS
Area RMHP
CO &
BP
SPs BFs SMS MILLs W&A U & S Misc. Total
Cost
(In Rs Cr)
Stage II 1 4 1 2 6 3 3 1 4 25 478
Stage I 0 2 0 4 2 0 0 3 4 15 115
Reports
submitted
0 9 6 3 1 4 4 6 8 41 6230
Reports to
be
submitted
0 0 0 0 0 0 0 1 3 4 140
Total 1 15 7 9 9 7 7 11 19 85 6963
STAGE – II APPROVED
Slide 2
8.Replacement of Charging car #14 for COB#3, DSP (04/DE/4276)
(Stage II Approved) (Sheet – 1 of 1)
Slide 3of 117
Description Current Status
Date of Acceptance 03.01.2017 Contract signed on 12.10.20 with effective date
of contract 23.09.20.
Engineering complete. Supply complete except
drive. MOM dtd 12.02.22- two quadrant drive
accepted by DSP with suitable adjustment for
differential price. Drive received at DSP.
Hot trial run from 4th June,22.
PAC issued on 02.07.22.
Commissioning trial started from 21.07.22 and
completed.
Commissioning certificate issued on 26.08.22.,
where date of completion: 24.07.22.
PG is due for the following
i)M/s BEC shall supply an A/C to the Charging car. Ii)
Also the hopper gate mechanism is repeatedly failing..
FAC to follow after PG completion
Date of
Submission
FR & TS 31.03.2017 FR(R=0)
04.10.2018 TS(R=2)
D/o Stage I & Cost (Rs. In Cr) 14.09.2018 7.54 Crore
D/o Stage II & Cost (Rs. In Cr) 28.08.2020 7.92 Crore
No. of Packages 1
Date of NIT 08.10.2018
TOD 07.01.19, 04.02.19
Date of TER 02.05.2019
PBE 17.06.2020
Contractor BEC TFL & LS Sushil Kumar, mech. ,FROM DSC-KC
Value of Package 7.92 Crore Status of Design Engineering
Effective date of Contract 23.09.20 Scope Submitted Cleared* Commented U/s
Schedule of BE 22.05.21 BE 15 15 15 0 0
Schedule of DE 22.11.21 DE 78 78 78 1 0
Schedule D/o completion 22.03.22
9.Replacement of 3 nos. ETP in 1.6Mt CCP of DSP(04/DE/4350)
(Stage II Approved) (Sheet – 1 of 1)
Slide 4of 117
Description---- Current Status
Date of Acceptance 04.07.2017 EC(R-0) & EC(R-1) issued on 08.06.20 & 11.02.21.
RA of 1st tender failed due to sealed bid price was
98.24% higher than package cost. Tender cancelled.
Revised EC(R-1) based on TS(R-3) issued on 03.02.22
along with Bidder’s profile. PAG held on 16.03.22
Tendered out for 2nd time. RA held on 30.08.22
M/s OEPL is the L-1 bidder
LOA: Ref. No.DSP/PROJPUR/COCC/ETP/SC /659/ LOA
issued on 29.10.22
Technical Draft contract along with input for
commercial volume sent on 10.11.2022
Contract Agreement signed on 14.12.2022
KOM held on 15.12.2022. MDL is under preparation
Date of
Submission
FR 25.10.17(R=0), 03.06.20 (R=1)
07.11.20(R=2), 07.02.22(R=3)
TS 30.10.17(R=0), 05.06.20(R=1)
07.11.20(R=2), (R=3)
D/o Stage I & Cost
(Rs. In Cr)
18.03.21 & Rs. 5.01 Cr (R=2)
21.04.22 & Rs. 11.62 Cr (R=3)
D/o Stage II & Cost
(Rs. In Cr)
01.11.22 & Rs. 12.33 Cr
No. of Packages One
Date of NIT 02.04.21(R=0), 28.04.22(R=1)
TOD 10.06.20 (R=0) ,
27.05.22 & 27.06.22 (R=1)
Tender Discussion 30.06.21(R=0) & 18.07.22(R=1)
Date of TER 29.07.21(R=0) & 27.07.22(R=1)
PBE 03.09.22
Contractor Oriental EPC Private Limited TFL & LS Jyoti Dayal, C,C&C
DSC: KC
Value of Package Rs. 10.16 crores Status of Design Engineering
Effective date of Contract 29.11.22 Scope Submitted Cleared* Commented U/s
10.Rebuilding of Salt Handling section in Ammonium Sulphate Plant of Coal Chemical Plant ,
DSP(04/DE/4405)
(Stage II Approved) (Sheet – 1 of 1)
Slide 5of 117
Description Current Status
Date of Acceptance 14.11.2017 LOA issued to P & Sen construction co
on 19.09.20.
Contract(Tech.) signed on 16.10.20.
Design & engineering not completed.
Site Activities: Job comprised of two phases.
Phase -1 job completed.
The conveyor circuit of Phase-1 shall be restored
of during shutdown of plant.
Dismantling of phase-II has started. Concrete
structure of composite building is demolished.
Steel structure
Steam Dryer towards CHP side has been taken out
of operation. Dismantling for relocation is in
progress.
Date of
Submission
FR & TS 03.02.18, FR R0
20.11.18, FR R3
09.02.18, TS R0
20.11.18, TS R3
D/o Stage I & Cost (Rs. In Cr) 23.04.2019 6.17 Crore
D/o Stage II & Cost (Rs. In Cr) 18.09.2020 5.8 Crore
No. of Packages 1
Date of NIT 13.07.2019
TOD 13.08.2019/03.09.2019
Date of TER 23.10.2019
PBE
Contractor P & Sen construction co. TFL & LS Suresh Vechalapu (C, C & C), FROM
DSC- NHM, KC
value of Package 5.8 Crore Status of Design Engineering
Effective date of Contract 16.10.20 Scope Submitted Cleared* Commented U/s
Schedule of BE 13.02.21 BE 12 12 11 1 0
32. Re-circulation of waste water from outfall #1,2 &3 at DSP (04/DE/4562) (Package –II)
(Stage II Approved) (Sheet – 1 of 1)
Slide 6of 117
Description---- Current Status
Date of Acceptance 28.11.18 LOA placed on Eastern Metec on 21.04.21. KOM held on
21.05.2021. Draft contract sent on 18.05.2021
Work order issued on 02.06.2021
Pit Cleaning completed. Laying of u/g pipeline from
wheel shop, axle shop, forge shop to water pit
completed. Pump foundation construction and pump
motor installation completed. Laying of cables and
electrical panel erection completed. Supply & erection of
portable drainage pump completed.
PAC done on 27.05.22.
Hot trial done. Defect list liquidation completed.
Commissioning done on11.06.22
PG test held up to due to modification carried out in
order to encounter the water hammering issue
Date of
Submission
FR
TS
17.01.19(R0)
30.04.19(R1)
26.11.19(R2)
D/o Stage I & Cost (Rs. In Cr) 05.12.2020 & 1.06
D/o Stage II & Cost (Rs. In Cr) 2.74 (Pkg II)
No. of Packages 3
Date of NIT 14.01.2021
TOD 04.02.2021
Date of TER 03.03.2021
PBE 03.04.2021
Contractor Eastern Metec TFL & LS A. Trivedi (U&S)
value of Package Rs. 68.55 Crore Status of Design Engineering
Effective date of Contract 20.05.21 Scope Submitted Cleared* Commented U/s
Schedule of BE BE 8 8 8 0 0
Schedule of DE DE 16 12 12 0 0
33. Re-circulation of waste water from outfall #1,2 &3 at DSP (04/DE/4562) (Package –II, for BF-3)
(Stage II Approved) (Sheet – 1 of 1)
Slide 7of 117
Description--- Current Status
Date of Acceptance 28.11.18 LOA: 22.05.21
Work order placed on 11.06.2021. KOM held on 28.05.2021.
Pipe route for treated water and pit water along with new
trestle location finalized after joint site visit. Pipe bridge of
length 30 meters to be envisaged to avoid trestle construction
at the entry of Hi line bunker
Recovery pit cleaning completed. Pump Motor pedestal
foundation and erection of pump motor completed.
Construction of slurry holding tank and erection of agitator
completed. Construction of cooling tower pump house and
erection of Recirculation Pump motor completed. Foundation &
erection of centrifugal separator completed. Cooling tower cold
basin & wall erection construction completed whereas
construction of hot basin of cooling tower is in progress.
Centrifuge separator has been supplied at site.
Fabrication and erection of 21 nos. trestles completed.
Fabrication work & erection of 20 nos of pipe bridge
completed, only 2 are remaining. Pipeline trestles erection
completed. MS ERW Pipeline layout completed by 260 mtr
completed, 80 meters is left out. Total DI pipe line laying of 320
meters left out
Date of
Submission
FR
TS
17.01.19(R0)
30.04.19(R1)
26.11.19(R2)
D/o Stage I & Cost
(Rs. In Cr)
05.12.2020 & 1.06
D/o Stage II & Cost
(Rs. In Cr)
2.74 (Pkg II)
No. of Packages 3
Date of NIT 14.01.2021
TOD 04.02.2021
Date of TER 03.03.2021
PBE 03.04.2021
Contrac
tor
Eastern Metec TFL & LS A. Trivedi (U&S)
15.Implementation of zero liquid discharge at Coke ovens , DSP(04/DE/4619)
(Stage II Approved) (Sheet – 1 of 1)
Slide 8of 117
Description----IPU PROJECT Current Status
Date of Acceptance 01.06.19 LOA issued to M/s P Sen on 30.06.21.
Contract signed: 31.07.21.
Contract price: 2.997 Cr.
Implementation period: 14 months from the date of
contract.
• Civil work related to Cooling tower, tank and pump
house completed
• Equipment erection like pump, valves & cooling tower
fan completed.
• Trestles and pipeline layout completed by 200 meters
about 150meters left out.
• Erection of electric panels, cable layout and agitator
in tank left out
Date of
Submission
AN
FR
TS
22.08.19
13.02.20(R0)
18.06.20(R1)
14.09.20(R1)
D/o Stage I & Cost (Rs. In Cr) 01.12.20, 6 Cr.
D/o Stage II & Cost (Rs. In Cr) 05.07.21, 3.56 Cr.
No. of Packages
Date of NIT 13.01.2021
TOD 01.03.2021.
Date of TER 20.03.21.
PBE 12.05.2021.
Contractor P &Sen TFL & LS S C Choudhary(C,C&C),K.P. Jayakumar(C,C&C)
FROM DSC- KC
value of Package 2.997 Crore Status of Design Engineering
Effective date of Contract 30.07.21 Scope Submitted Cleared* Commented U/s
Schedule of BE BE 7 7 7 0 0
Schedule of DE 27.12.21 DE 51 45 38 7 0
Schedule D/o completion 29.09.22(14m)
27. Installation of two nos. of additional Pressure Reducing and De-superheating unit (PRDU) in
power plant at DSP (04/DE/4735)(Stage II Approved) (Sheet – 1 of 1)
Slide 9of 117
Description---- Current Status
Date of Acceptance 30.04.2020 Kick-off meeting held on 16.02.22.
Engineering started.
Contract signed on 16.02.22.
Design & Engineering is in progress. Delay in DE
due to improper submission of document
IBR clearance received on 13-06-22
Site Activity:
Pipes of sizes 65NB for water spray line, 150NB
& 200NB for steam lines supplied.
Ordering of Bought out item like PRDS and 8”
isolation valve completed. Supply is delayed
likely to be delivered by Mid Dec’22. Cable,
cable tray, UPS, PRV starter supplied to the site.
Date of
Submission
FR
TS
27.07.2020(R0)
27.07.2020(R0)
D/o Stage I & Cost (Rs. In Cr) 17.03.21, 1.54Cr.
D/o Stage II & Cost (Rs. In Cr) 20.12.21, 2.26Cr.
No. of Packages 1
Date of NIT 12.04.21
TOD 11.05.21, 30.07.21
Date of TER 13.08.21
PBE 10.09.21
Contractor Shailaja Enterprise TFL & LS K.Choudhury, DSC
value of Package 1.85 Crore Status of Design Engineering
Effective date of Contract 15.01.22 Scope Submitted Cleared* Commented U/s
Schedule of BE 16.04.22 BE 9 9 9 0 0
Schedule of DE 16.04.22 DE 57 53 53 0 0
Schedule D/o completion 15.09.22,8m
24. Installation of a new Gas Booster House for Rolling Mills in DSP (04/DE/4737)
(Stage II Approved) (Sheet – 1 of 1)
Slide 10of 117
Description---- Current Status
Date of Acceptance 06.05.2020 LOA placed on 31.01.22. Contract signed on
09.03.22.
Kick – off meeting on 16.03.22.
Engineering has been completed.
Civil work for Electrical & control room completed
Earthwork for Gas Booster room & trestle in progress.
Bought-out out items like MGV, CV, pipelines, flanges,
instruments and field devices supplied, overhead
crane , booster fan and motor supplied. Incoming
cables (80%) laid and MCC, PDB, VFD panel installed.
49T of structural steel is supplied. Another 30% to is
in transit. Fabrication of the structural steel started.
Supply of PLC panel, instrument panel .
Site-work stalled due to fatal accident.
Date of
Submission
FR
TS
31.08.20
31.08.20
D/o Stage I & Cost (Rs. In Cr) 06.07.21, 10.41 Cr.
D/o Stage II & Cost (Rs. In Cr)
No. of Packages
Date of NIT 06.08.21
TOD 29.09.21
Date of TER 28.10.21
PBE 04.12.21
Contractor TLT Engg. India Pvt. Ltd. TFL & LS M.K.Yadav , DSC: Kaustav Choudhury
value of Package 11.93 Crore Status of Design Engineering
Effective date of Contract 03.03.22 Scope Submitted Cleared* Commented U/s
Schedule of BE BE 11 11 11 0 0
Schedule of DE DE 75 75 75 0 0
Schedule D/o completion 02.02.23(11m)
18. Replacement of two nos. of Electric Loco of COB-3, DSP(04/DE/4782)
(Stage II Approved) (Sheet – 1 of 1)
Slide 11of 117
Description---- Current Status
Date of Acceptance 21.09.2020 LOA placed on 16.12.21.
Kick off meeting held 22.02.22.
Contract No. DSP/PROJ-PUR/CO&CC/Electric
Loco/AS/570 signed on 22.02.2022
• Design & Engineering completed
100% of fabrication/manufacturing work
completed, 3 consignments reached and 1
consignment is in transit.
100% bought out items have been ordered. Like to
be supplied by end of Jan’23
Site activity like Leveling of the site area,
unloading of consignment started
Date of
Submission
CE
TS
10.11.20
10.11.20(R0)
06.01.2021(R1)
D/o Stage I & Cost (Rs. In Cr) 18.03.21, 5.42
D/o Stage II & Cost (Rs. In Cr) 16.12.21, 8.14
No. of Packages 1
Date of NIT 04.05.21
TOD 04.06.21, 10.07.21
Date of TER 06.08.21
PBE 24.09.21
Contractor Bhilai Engineering Corporation Ltd TFL & LS
TFM CTEB
Sushil Kumar(Mech.),
DSC: KC
value of Package 7.13 Crore Status of Design Engineering
Effective date of Contract 15.01.22 Scope Submitted Cleared* Commented U/s
Schedule of BE BE 7 7 7 0 0
Schedule of DE DE 36 36 36 0 0
Schedule D/o completion 15.12.22(12m)
STAGE – I APPROVED
Slide 12
17. Rebuilding of COB No.4 at DSP (04/DE/4747) (Stage I Approved)
Slide 13of 117
Description: Rebuilding of
COB No.4 at DSP
(04/DE/4747)
-CORPORATE PROJECT
Current Status
Date of
Acceptance
29.06.2020 Draft Investment Proposal (DIP) along with Annexures issued to DSP on
28.06.22.Calculation sheet of NPV and IRR sent to DSP on 28.06.22. Plant
PAG held on 28.06.22.
EC & Bidder’s profile on PKG-I issued on 26.07.22
COD:08.08.22. Reply to observations on COD sent on 20.08.22
Reply on EMD’s observation were sent on 20.08.22 to DTE. COD
observation were incorporated in Draft Agenda Note and sent on
26.08.22
Corporate PAG: 08.09.22. Reply to CO PAG observation sent on 15.09.22.
Battery Proper Package-1 TS(R=0) issued on 09.09.22.
Coke Oven Machine Package-2 TS(R=0) issued on 30.08.22
EC & Bidder’s profile on PKG-II issued on 14.09.22
Project DTE asked for views of Dir. Finance on cost comparison with COB#
2 RSP scheme for 41% Cost escalation which has accordingly being replied
by CET on 10.10.2022.
Board Sub committee held on 19.10.22. Board Meeting held on 20.10.22
and cleared
TS for Pkg-I (R=2) issued on 27.10.22 & Pkg-II (R=1) issued on 21.10.22.
Open Global Tender for Pkg-I vide Ref. no. DSP/PROJ-PUR/COCC/COB4-
1/SC/713 dated 14.11.22 has been floated.
Open Indigenous Tender for Pkg-II vide Ref. no. DSP/PROJ-
Date of
Subm.
FR 10.09.20(R0)
31.05.22(R1)
08.07.22(R2)
TS Pkg-I 27.10.22(R=2)
Pkg-II 21.10.22(R=1)
Date of
Stage I
20.10.22
Stage I cost
(Rs. in crore)
Rs. 673.15 cr
No. of Package 2
NIT Pkg-I : 14.11.22
Pkg-II 14.11.22
TOD Pkg-I : 15.12.22,
01.02.23
Pkg-II: 12.12.22,
19.01.23
Tender
21. Complete waste water treatment at outfall #1,2&3 at DSP (04/DE/4817)
(Stage I Approved)
Slide 14of 117
Description Complete waste
water treatment at outfall #
1,2&3 at DSP (04/DE/4817)
Current Status
Date of
Acceptance
25.01.21 Three Packages
Pkg. No. 1A- Soil Inv. & Survey: Report submitted by SS Solution on 15.03.22
& cleared on 29.06.22.
Pkg. No. 1B:UG Mapping-Report issued on 11.02.22 by Gaveshana
Geosciences Limited & cleared on .
Main Package
Plant PAG held on 02.07.22.PAG queries replied on 04.07.22.
Updated cost issued on 04.07.22.
COD held on 08.08.22.
TS(R=1) issued on 13-08-22. EC(R=1) issued on 22.08.22.
Draft agenda note updated on basis of COD’s & Project DTE’s observation
on 26.08.22 and 01.09.22 respectively.
Corporate PAG: 08.09.22. Outcome of CO PAG and comparative study of
proposed ZLD at DSP vis-à-vis ZLD Scheme #3 at ISP were sent on 23.09.22
The queries raised by CO in the Agenda Note regarding O&M contract &
comparison of total CAPEX & OPEX for RO and Ion Exchange processes, with
due consideration of tertiary system were sent to CO on 17.10.22 &
19.10.22. Board Sub committee held on 19.10.22.
Board Meeting held on 20.10.22 and the proposal was cleared. Bidder’s
profile sent on 15.11.22
Open Indigenous Tender for Main Pkg-II vide Ref. no. DSP/PROJ-
Date of
submssn
FR 23.04.21(R=0)
23.03.22 (R=1)
TS 15.05. 21(R=0)
12.08.22(R=1)
Date of Stage I 20.10.22
Stage I cost
(Rs. in crore)
Rs. 63.33 cr
No. of Package Three (3)
NIT 12.11.22
TOD 13.12.22,
20.01.23
Tender
discussions
Date of TER
Date of PBE
TFL & LS A. Trivedi (U&S)
18. INSTALLATION OF 1 NEW PUSHER CAR FOR COB#3 IN CO&CC
(Stage I Approved)
Slide 15of 117
Description ----INSTALLATION OF 1 NEW
PUSHER CAR FOR COB#3 IN CO&CC
(04/DE/4901)
Current Status
Date of Acceptance 01.11.21 EC (R=0) submitted on 27.07.22 & (R=1)
submitted on 14.09.22
Bidders’ Profile submitted on 27.07.22 & 14.09.22
Plant PAG held on 27.09.22. Reply to DSP’s PAG
deliberation sent on 06.10.22. Accordingly EC
revised & EC (R=2) submitted on 13.10.22.
For tendering purpose, CET’s reply to clarification
were sent on 09.11.22 to DSP
Tender No. DSP/PROJ-PUR/CO&CC/PC-
COB#3/AS/716 dated 17.11.22 was raised on
open indigenous tender enquiry basis.
Three bidders participated. i) GAME ii) BEC iii)
Gourika India Enterprise.
TER submitted on 12.01.2023
Tender cancelled on 31.01.2023 due to less than
X+2 bidders and changes to be done in the TS and
Eligibility Criteria as per amendment of SBD 2020
Date of
submission
FR 29.01.22(R0), 30.06.22(R1)
TS 10.02.22(R0), 29.06.22(R1)
Date of Stage I 01.11.22
Stage I cost
(Rs. in crore)
17.82
No. of Package 1
NIT 17.11.22
TOD 16.12.22
Tender discussions 03.01.22 & 05.01.22
Date of TER 18.01.2023
Date of PBE
TFL & LS A.Tirkey, Mech. Ranchi
TFM(From DSC) &CTE K.Choudhury, Anup Kr
17. 2ND CIRCULAR SAW WITH ALLIED FACILITIES IN WHEEL AXLE PLANT(04/DE/4908)
(Stage I Approved)
Slide 16of 117
Description ----IPU PROJECT Current Status
Date of Acceptance 22.11.22 EC(R=0) issued on 23.03.22.
Contact details of probable supplier for
indigenous bid has been sent on 18.06.22.
Tender No. DSP/PROJ-
PUR/MM/WAP/CS/AS/673 issued on basis of
open indigenous tender enquiry
Probable bidders raised some queries.
Corrigendum to TS(R=1) issued to DSP on
09.09.22 for change in PG parameters.
TOD extended till 30.09.2022 from 22.08.22. Two
bids from following two suppliers received
i) Consortium of MACO & Linslinger
ii) ITL
Tender opened on 18.11.22. Technical offers of
above two vendors sent to CET-Mech for
evaluation. TER issued on 28.11.2022
Date of
submissi
on
FR 22.02.22(R=0)
TS 22.02.22(R=0)
07.04.22(R=1)
Date of Stage I 28.05.22
Stage I cost
(Rs. in crore)
19.34
No. of Package 1
NIT 18.06.22
TOD 22.08.22 ,30.09.22,
18.11.2022
Tender discussions NA
Date of TER 28.11.2022
Date of PBE
TFL & LS Ajay Kr, Utility
K.Choudhury, Anup Kr
REPORTS SUBMITTED
(having progress)
Slide 17
Sl.N
o.
Description
CORPORATE PROJECT
Current Status
(Reasons of delay, if any)
49 DE-BOTTLENECKING IN AREAS
OF SP1 : REVAMPING OF APC
SYSTEMS (04/DE/4938)
(Four projects: 4288, 4251, 4313, part of 3805 combined to form 4938)
A visit to DSP done by CET on 23.06.2022. A meeting between Sinter plant (Elect),
PMD and CET held to freeze the power supply arrangement.
VC held on 06.07.22 for Power source finalisation.
Site visit done on 13.07.22 for finalization of power source and location of
Electrical building.
Clearance of the proposed location of substation awaited from DSP.
Document Submission date changed to 17.09.2022 due to non receipt of BQ.
FR (R=0) released on 15.09.22.
Comments on FR(R=0) received on 06.10.22
Request for EC & bidder’s profile from plant received on 19.10.22 .
TS(R=0) for Pkg-I issued on 09.11.22
TS(R=0) for Pkg-II issued on 10.11.22
Plant PAG for stage-I approval held on 10.11.22. Reply to Plant deliberation by CET
on 16.11.22
EC & Bidder’s profile issued on 26.12.2022 for Pkg-I &Pkg-II
Reply to DSP’s observation (raised by Dir-I/c) sent by CET on 03.01.23
TFL & LS :
DSC &
CTE :
SOMRAJ
CHAKRAVARTY
(TFL),
KC, Garish Kr.
Date of Acceptance :
23.05.2022
FR 15.09.22(R=0)
TS
Cost of Project : Rs. 128.59
crores
Slide 18 of 127
Reports Submitted
Sl.
No.
Description ---IPU
PROJECT/ CORPORATE
PROJECT
Current Status
(Reasons of delay, if any)
23 Installation of new Wagon
Tipplers/ Track Hopper in
RMHP at DSP (04/DE/ 4826)
Pkg.I-SIS & AS
TS-12.08.21.
Work order issued on 04.03.22 to SS Solution. Value: 4.67 L, duration:2
months
Completed on 11.06.22. Final report cleared on 28.06.22.
Pkg.II-UG:
TS-12.08.21.
Work order issued on 05.03.22 to SS Solution. Value:3.45 L, duration:45 days
Reports submitted on 29.08.22 & CET cleared the same on 03.09.22.
Completion certificates for both package issued on 08.09.22.
Main Pkg:
DSP to appoint external agency for formulating the general layout drawing of
in-haul and out-haul railway track for proposed Wagon Tippler-4. CET issued
new revised layout indicating the new proposed location of wagon tippler
no.4 after site visit of 07.09.2022. TS(R=0) issued on 18.11.2022
Cost Committee for revision of capital cost held on 22.11.22 &FR(R=1) issued
on 06.12.2022
Revised TS(R=1) for Pkg-IA (SIS & AS) & TS(R=1) for PKG-IIA (UG) issued on
28.12.2022 due to change in proposed location of Tippler#4. Block Cost for
Package-IA (Area survey & SIS) & Package-II A (UG) is 5 lakhs and issued on
04.01.23 &11.01.23 respectively
TFL & LS :
TFM & CTE :
Sanjay Kumar
(ME), DSC:KC,
Date of Acceptance:
08.03.2021
FR 05.06.2021(R=0)
06.12.2022(R=1)
TS 18.11.2022(R=0)
Cost of Project : Rs. 67.56 cr
(R=1 cost)
Slide 19 of 127
Reports submitted
Sl.
No.
Description
CORPORATE PROJECT
Current Status
(Reasons of delay, if any)
5 Installation of Micro -
Pellet plant on BOO
basis (04/DE/4951)
DSP requested for draft investment proposal along with block cost estimate on
15.06.22.
Acceptance letter sent on 22.06.22.
DSP on 07.07.11 requested for Soil investigation & Underground mapping of the
proposed site.
On 20.08.22, draft tender document (Part A and Part B) sent to DSP for filling up
the required portions.
Technical basis for preparation of the tender document is on basis of RDCIS report
on Pot sintering experiments with micro pellet condition at SP, ISP
conditions. Micro pellet testing has not been done for DSP conditions since the
source of iron ore and process iron making is same.
TS on SIS & Area Survey submitted on 22.11.2022. Being a green field project UG
mapping is not required. Block Cost of Rs 16 lakhs submitted on 30.11.2022. 5 nos.
of bid for the above package has been received and sent to CET (C&S) for tender
evaluation on 04.01.2023
DSP specified the power source for Micropellet plant & proportioning quantity of
feed materials, chemical analysis of iron bearing waste through e-mail dated
01.12.2022 & 3.12.2022. DSP requirement for provision of handling mill scale and
ESP dust in Sinter plant is not clearly stated in the e-mail dated 3.12.2022
CET requested DSP vide email dated 21.12.2022 to include the balance points in
tender document (like location, nature of land sharing, Minimum guaranteed off-
take value, Battery limit of feed materials, & (physical analysis) quality iron bearing
waste, % LD charges, Earnest Money Deposit and security deposit.
TFL & LS :
TFM &
CTE:
SHYAM JI (I&S)
KC, PK Mishra
Date of Acceptance :
20.06.22
TD Scheduled :23.08.22
Issued :19.08.22
Cost of Project: Rs. 100 cr
Slide 20 of 127
Reports submitted
Sl.
No.
Description Current Status
(Reasons of delay, if any)
10 Installation of Ladle Tilters at
SMS-ISP (03/DE/4991)
1 no. of BQ received from M/s GAME.
Cost Sheet finalized on 26.12.2022. (P&E cost arrived
on basis of combining P&E cost, D&E in BQ with 10%
knockdown & factoring out the normative)
DR held on 29.12.2022
FR(R=0) issued on 29.12.2022
TS(R=0) issued on 30.12.2022
TFL & LS :
TFM & CTE :
:KC & DSC,
RK(CTE)
Date of Acceptance : 29.09.2022
FR & TS Scheduled
:29.12.2022
Cost of Project : Rs. 10.7 cr
Slide 21 of 127
Reports to be submitted
REPORTS TO BE SUBMITTED
Slide 22
Sl.
No.
Description Current Status
(Reasons of delay, if any)
1 PARALLEL CONVEYOR TO
CONVEYOR 5A
(04/DE/4903)
Soil and UG mapping TS submitted on 22.02.22.
Main TS will be submitted after soil report.
DSP sent RA report along with the price break up of the L1
bidder for Soil pkg. Requested for PBE on 18.08.22.
PBE report issued on 23.08.22.
Order placed on SS Solution. Survey completed and final report
submitted on 07.11.22.
CET has commented on survey report related to ”Level, extent
and name of the existing facilities ” which is not mentioned in
the drawing. SS Solution after joint visit on 24.12.2022 with the
Dept. & Proj. has issued the corrected drawing on 30.12.2022.
The same has cleared by DSP on 04.01.23 & sent to CET on
05.01.2023 for further observation.
FR & TS of main pkg are due
TFL & LS :
TFM & CTE :
SK Singh, Mech
DSC: KC , RK Jha
Date of Acceptance : 08.11.21
TS :
Cost of Project : Rs. 8 cr
Slide 23 of 127
Reports to be submitted

More Related Content

Similar to DURGAPUR STEEL PLANT Project Review_07.01.23_KC.pptx

DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)Mohd Zaini Baharum
 
Buildings so r 14 15
Buildings so r 14 15Buildings so r 14 15
Buildings so r 14 15Ptpg Stuc
 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptxTalebAlfihan
 
Status of GNSS Phase II of Package.7 Kadapa.ppt
Status of GNSS Phase II of  Package.7 Kadapa.pptStatus of GNSS Phase II of  Package.7 Kadapa.ppt
Status of GNSS Phase II of Package.7 Kadapa.pptAnil Venkata Nag Kothur
 
LRT3 GS10 - CCC Tracking 22.3.2023.pptx
LRT3 GS10 - CCC Tracking 22.3.2023.pptxLRT3 GS10 - CCC Tracking 22.3.2023.pptx
LRT3 GS10 - CCC Tracking 22.3.2023.pptxNaimRozak
 
Fairgrounds Permit Application Amend Phase 1 11-15-2010
Fairgrounds Permit Application Amend Phase 1 11-15-2010Fairgrounds Permit Application Amend Phase 1 11-15-2010
Fairgrounds Permit Application Amend Phase 1 11-15-2010Adam Cohen
 
Material Cost Estimate of BS 32 BRT ,Peshawar
Material Cost Estimate of BS 32 BRT ,PeshawarMaterial Cost Estimate of BS 32 BRT ,Peshawar
Material Cost Estimate of BS 32 BRT ,PeshawarSyed Qaseem Haider
 
243-249 MANN STREET GOSFORD 1 s
243-249 MANN STREET GOSFORD 1 s243-249 MANN STREET GOSFORD 1 s
243-249 MANN STREET GOSFORD 1 sMike Darwich
 
ABC_2nd Progress Mtg Briefing_011214_final.ppt
ABC_2nd Progress Mtg Briefing_011214_final.pptABC_2nd Progress Mtg Briefing_011214_final.ppt
ABC_2nd Progress Mtg Briefing_011214_final.pptKingHaroldDeLeon
 
Final Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptxFinal Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptxIESGATEWiz
 
CWE Tkd FB more than 01 year old and.ppt
CWE Tkd FB more than 01 year old and.pptCWE Tkd FB more than 01 year old and.ppt
CWE Tkd FB more than 01 year old and.pptSauravAnand68
 
Bhusawal Project(1x660MW)- Taregt Setting Meeting July 23.pptx
Bhusawal Project(1x660MW)- Taregt Setting Meeting July 23.pptxBhusawal Project(1x660MW)- Taregt Setting Meeting July 23.pptx
Bhusawal Project(1x660MW)- Taregt Setting Meeting July 23.pptxssuser8ee2f9
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final AccountKai Yun Pang
 

Similar to DURGAPUR STEEL PLANT Project Review_07.01.23_KC.pptx (20)

DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)
 
Building ssr 2013-14
Building ssr 2013-14Building ssr 2013-14
Building ssr 2013-14
 
Nagpur csr
Nagpur csrNagpur csr
Nagpur csr
 
Buildings so r 14 15
Buildings so r 14 15Buildings so r 14 15
Buildings so r 14 15
 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptx
 
Decision Notice
Decision NoticeDecision Notice
Decision Notice
 
Status of GNSS Phase II of Package.7 Kadapa.ppt
Status of GNSS Phase II of  Package.7 Kadapa.pptStatus of GNSS Phase II of  Package.7 Kadapa.ppt
Status of GNSS Phase II of Package.7 Kadapa.ppt
 
LRT3 GS10 - CCC Tracking 22.3.2023.pptx
LRT3 GS10 - CCC Tracking 22.3.2023.pptxLRT3 GS10 - CCC Tracking 22.3.2023.pptx
LRT3 GS10 - CCC Tracking 22.3.2023.pptx
 
Fairgrounds Permit Application Amend Phase 1 11-15-2010
Fairgrounds Permit Application Amend Phase 1 11-15-2010Fairgrounds Permit Application Amend Phase 1 11-15-2010
Fairgrounds Permit Application Amend Phase 1 11-15-2010
 
Material Cost Estimate of BS 32 BRT ,Peshawar
Material Cost Estimate of BS 32 BRT ,PeshawarMaterial Cost Estimate of BS 32 BRT ,Peshawar
Material Cost Estimate of BS 32 BRT ,Peshawar
 
243-249 MANN STREET GOSFORD 1 s
243-249 MANN STREET GOSFORD 1 s243-249 MANN STREET GOSFORD 1 s
243-249 MANN STREET GOSFORD 1 s
 
ABC_2nd Progress Mtg Briefing_011214_final.ppt
ABC_2nd Progress Mtg Briefing_011214_final.pptABC_2nd Progress Mtg Briefing_011214_final.ppt
ABC_2nd Progress Mtg Briefing_011214_final.ppt
 
sn-ladakh.pdf
sn-ladakh.pdfsn-ladakh.pdf
sn-ladakh.pdf
 
Final Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptxFinal Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptx
 
FINAL VOLUME 2 20.12
FINAL VOLUME 2 20.12FINAL VOLUME 2 20.12
FINAL VOLUME 2 20.12
 
Munger ganga bridge
Munger ganga bridgeMunger ganga bridge
Munger ganga bridge
 
TechTown 1st Floor Renovation
TechTown 1st Floor RenovationTechTown 1st Floor Renovation
TechTown 1st Floor Renovation
 
CWE Tkd FB more than 01 year old and.ppt
CWE Tkd FB more than 01 year old and.pptCWE Tkd FB more than 01 year old and.ppt
CWE Tkd FB more than 01 year old and.ppt
 
Bhusawal Project(1x660MW)- Taregt Setting Meeting July 23.pptx
Bhusawal Project(1x660MW)- Taregt Setting Meeting July 23.pptxBhusawal Project(1x660MW)- Taregt Setting Meeting July 23.pptx
Bhusawal Project(1x660MW)- Taregt Setting Meeting July 23.pptx
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final Account
 

Recently uploaded

CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 
Artificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraArtificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraDeakin University
 
Snow Chain-Integrated Tire for a Safe Drive on Winter Roads
Snow Chain-Integrated Tire for a Safe Drive on Winter RoadsSnow Chain-Integrated Tire for a Safe Drive on Winter Roads
Snow Chain-Integrated Tire for a Safe Drive on Winter RoadsHyundai Motor Group
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j
 
How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?XfilesPro
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAndikSusilo4
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphNeo4j
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesSinan KOZAK
 
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptxMaking_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptxnull - The Open Security Community
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhisoniya singh
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...HostedbyConfluent
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure servicePooja Nehwal
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxOnBoard
 

Recently uploaded (20)

CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 
Vulnerability_Management_GRC_by Sohang Sengupta.pptx
Vulnerability_Management_GRC_by Sohang Sengupta.pptxVulnerability_Management_GRC_by Sohang Sengupta.pptx
Vulnerability_Management_GRC_by Sohang Sengupta.pptx
 
Artificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraArtificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning era
 
Snow Chain-Integrated Tire for a Safe Drive on Winter Roads
Snow Chain-Integrated Tire for a Safe Drive on Winter RoadsSnow Chain-Integrated Tire for a Safe Drive on Winter Roads
Snow Chain-Integrated Tire for a Safe Drive on Winter Roads
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
 
How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & Application
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen Frames
 
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptxMaking_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptx
 

DURGAPUR STEEL PLANT Project Review_07.01.23_KC.pptx

  • 1. DURGAPUR STEEL PLANT Status as on 12.10.22 SUMMARY OF ASSIGNMENTS Area RMHP CO & BP SPs BFs SMS MILLs W&A U & S Misc. Total Cost (In Rs Cr) Stage II 1 4 1 2 6 3 3 1 4 25 478 Stage I 0 2 0 4 2 0 0 3 4 15 115 Reports submitted 0 9 6 3 1 4 4 6 8 41 6230 Reports to be submitted 0 0 0 0 0 0 0 1 3 4 140 Total 1 15 7 9 9 7 7 11 19 85 6963
  • 2. STAGE – II APPROVED Slide 2
  • 3. 8.Replacement of Charging car #14 for COB#3, DSP (04/DE/4276) (Stage II Approved) (Sheet – 1 of 1) Slide 3of 117 Description Current Status Date of Acceptance 03.01.2017 Contract signed on 12.10.20 with effective date of contract 23.09.20. Engineering complete. Supply complete except drive. MOM dtd 12.02.22- two quadrant drive accepted by DSP with suitable adjustment for differential price. Drive received at DSP. Hot trial run from 4th June,22. PAC issued on 02.07.22. Commissioning trial started from 21.07.22 and completed. Commissioning certificate issued on 26.08.22., where date of completion: 24.07.22. PG is due for the following i)M/s BEC shall supply an A/C to the Charging car. Ii) Also the hopper gate mechanism is repeatedly failing.. FAC to follow after PG completion Date of Submission FR & TS 31.03.2017 FR(R=0) 04.10.2018 TS(R=2) D/o Stage I & Cost (Rs. In Cr) 14.09.2018 7.54 Crore D/o Stage II & Cost (Rs. In Cr) 28.08.2020 7.92 Crore No. of Packages 1 Date of NIT 08.10.2018 TOD 07.01.19, 04.02.19 Date of TER 02.05.2019 PBE 17.06.2020 Contractor BEC TFL & LS Sushil Kumar, mech. ,FROM DSC-KC Value of Package 7.92 Crore Status of Design Engineering Effective date of Contract 23.09.20 Scope Submitted Cleared* Commented U/s Schedule of BE 22.05.21 BE 15 15 15 0 0 Schedule of DE 22.11.21 DE 78 78 78 1 0 Schedule D/o completion 22.03.22
  • 4. 9.Replacement of 3 nos. ETP in 1.6Mt CCP of DSP(04/DE/4350) (Stage II Approved) (Sheet – 1 of 1) Slide 4of 117 Description---- Current Status Date of Acceptance 04.07.2017 EC(R-0) & EC(R-1) issued on 08.06.20 & 11.02.21. RA of 1st tender failed due to sealed bid price was 98.24% higher than package cost. Tender cancelled. Revised EC(R-1) based on TS(R-3) issued on 03.02.22 along with Bidder’s profile. PAG held on 16.03.22 Tendered out for 2nd time. RA held on 30.08.22 M/s OEPL is the L-1 bidder LOA: Ref. No.DSP/PROJPUR/COCC/ETP/SC /659/ LOA issued on 29.10.22 Technical Draft contract along with input for commercial volume sent on 10.11.2022 Contract Agreement signed on 14.12.2022 KOM held on 15.12.2022. MDL is under preparation Date of Submission FR 25.10.17(R=0), 03.06.20 (R=1) 07.11.20(R=2), 07.02.22(R=3) TS 30.10.17(R=0), 05.06.20(R=1) 07.11.20(R=2), (R=3) D/o Stage I & Cost (Rs. In Cr) 18.03.21 & Rs. 5.01 Cr (R=2) 21.04.22 & Rs. 11.62 Cr (R=3) D/o Stage II & Cost (Rs. In Cr) 01.11.22 & Rs. 12.33 Cr No. of Packages One Date of NIT 02.04.21(R=0), 28.04.22(R=1) TOD 10.06.20 (R=0) , 27.05.22 & 27.06.22 (R=1) Tender Discussion 30.06.21(R=0) & 18.07.22(R=1) Date of TER 29.07.21(R=0) & 27.07.22(R=1) PBE 03.09.22 Contractor Oriental EPC Private Limited TFL & LS Jyoti Dayal, C,C&C DSC: KC Value of Package Rs. 10.16 crores Status of Design Engineering Effective date of Contract 29.11.22 Scope Submitted Cleared* Commented U/s
  • 5. 10.Rebuilding of Salt Handling section in Ammonium Sulphate Plant of Coal Chemical Plant , DSP(04/DE/4405) (Stage II Approved) (Sheet – 1 of 1) Slide 5of 117 Description Current Status Date of Acceptance 14.11.2017 LOA issued to P & Sen construction co on 19.09.20. Contract(Tech.) signed on 16.10.20. Design & engineering not completed. Site Activities: Job comprised of two phases. Phase -1 job completed. The conveyor circuit of Phase-1 shall be restored of during shutdown of plant. Dismantling of phase-II has started. Concrete structure of composite building is demolished. Steel structure Steam Dryer towards CHP side has been taken out of operation. Dismantling for relocation is in progress. Date of Submission FR & TS 03.02.18, FR R0 20.11.18, FR R3 09.02.18, TS R0 20.11.18, TS R3 D/o Stage I & Cost (Rs. In Cr) 23.04.2019 6.17 Crore D/o Stage II & Cost (Rs. In Cr) 18.09.2020 5.8 Crore No. of Packages 1 Date of NIT 13.07.2019 TOD 13.08.2019/03.09.2019 Date of TER 23.10.2019 PBE Contractor P & Sen construction co. TFL & LS Suresh Vechalapu (C, C & C), FROM DSC- NHM, KC value of Package 5.8 Crore Status of Design Engineering Effective date of Contract 16.10.20 Scope Submitted Cleared* Commented U/s Schedule of BE 13.02.21 BE 12 12 11 1 0
  • 6. 32. Re-circulation of waste water from outfall #1,2 &3 at DSP (04/DE/4562) (Package –II) (Stage II Approved) (Sheet – 1 of 1) Slide 6of 117 Description---- Current Status Date of Acceptance 28.11.18 LOA placed on Eastern Metec on 21.04.21. KOM held on 21.05.2021. Draft contract sent on 18.05.2021 Work order issued on 02.06.2021 Pit Cleaning completed. Laying of u/g pipeline from wheel shop, axle shop, forge shop to water pit completed. Pump foundation construction and pump motor installation completed. Laying of cables and electrical panel erection completed. Supply & erection of portable drainage pump completed. PAC done on 27.05.22. Hot trial done. Defect list liquidation completed. Commissioning done on11.06.22 PG test held up to due to modification carried out in order to encounter the water hammering issue Date of Submission FR TS 17.01.19(R0) 30.04.19(R1) 26.11.19(R2) D/o Stage I & Cost (Rs. In Cr) 05.12.2020 & 1.06 D/o Stage II & Cost (Rs. In Cr) 2.74 (Pkg II) No. of Packages 3 Date of NIT 14.01.2021 TOD 04.02.2021 Date of TER 03.03.2021 PBE 03.04.2021 Contractor Eastern Metec TFL & LS A. Trivedi (U&S) value of Package Rs. 68.55 Crore Status of Design Engineering Effective date of Contract 20.05.21 Scope Submitted Cleared* Commented U/s Schedule of BE BE 8 8 8 0 0 Schedule of DE DE 16 12 12 0 0
  • 7. 33. Re-circulation of waste water from outfall #1,2 &3 at DSP (04/DE/4562) (Package –II, for BF-3) (Stage II Approved) (Sheet – 1 of 1) Slide 7of 117 Description--- Current Status Date of Acceptance 28.11.18 LOA: 22.05.21 Work order placed on 11.06.2021. KOM held on 28.05.2021. Pipe route for treated water and pit water along with new trestle location finalized after joint site visit. Pipe bridge of length 30 meters to be envisaged to avoid trestle construction at the entry of Hi line bunker Recovery pit cleaning completed. Pump Motor pedestal foundation and erection of pump motor completed. Construction of slurry holding tank and erection of agitator completed. Construction of cooling tower pump house and erection of Recirculation Pump motor completed. Foundation & erection of centrifugal separator completed. Cooling tower cold basin & wall erection construction completed whereas construction of hot basin of cooling tower is in progress. Centrifuge separator has been supplied at site. Fabrication and erection of 21 nos. trestles completed. Fabrication work & erection of 20 nos of pipe bridge completed, only 2 are remaining. Pipeline trestles erection completed. MS ERW Pipeline layout completed by 260 mtr completed, 80 meters is left out. Total DI pipe line laying of 320 meters left out Date of Submission FR TS 17.01.19(R0) 30.04.19(R1) 26.11.19(R2) D/o Stage I & Cost (Rs. In Cr) 05.12.2020 & 1.06 D/o Stage II & Cost (Rs. In Cr) 2.74 (Pkg II) No. of Packages 3 Date of NIT 14.01.2021 TOD 04.02.2021 Date of TER 03.03.2021 PBE 03.04.2021 Contrac tor Eastern Metec TFL & LS A. Trivedi (U&S)
  • 8. 15.Implementation of zero liquid discharge at Coke ovens , DSP(04/DE/4619) (Stage II Approved) (Sheet – 1 of 1) Slide 8of 117 Description----IPU PROJECT Current Status Date of Acceptance 01.06.19 LOA issued to M/s P Sen on 30.06.21. Contract signed: 31.07.21. Contract price: 2.997 Cr. Implementation period: 14 months from the date of contract. • Civil work related to Cooling tower, tank and pump house completed • Equipment erection like pump, valves & cooling tower fan completed. • Trestles and pipeline layout completed by 200 meters about 150meters left out. • Erection of electric panels, cable layout and agitator in tank left out Date of Submission AN FR TS 22.08.19 13.02.20(R0) 18.06.20(R1) 14.09.20(R1) D/o Stage I & Cost (Rs. In Cr) 01.12.20, 6 Cr. D/o Stage II & Cost (Rs. In Cr) 05.07.21, 3.56 Cr. No. of Packages Date of NIT 13.01.2021 TOD 01.03.2021. Date of TER 20.03.21. PBE 12.05.2021. Contractor P &Sen TFL & LS S C Choudhary(C,C&C),K.P. Jayakumar(C,C&C) FROM DSC- KC value of Package 2.997 Crore Status of Design Engineering Effective date of Contract 30.07.21 Scope Submitted Cleared* Commented U/s Schedule of BE BE 7 7 7 0 0 Schedule of DE 27.12.21 DE 51 45 38 7 0 Schedule D/o completion 29.09.22(14m)
  • 9. 27. Installation of two nos. of additional Pressure Reducing and De-superheating unit (PRDU) in power plant at DSP (04/DE/4735)(Stage II Approved) (Sheet – 1 of 1) Slide 9of 117 Description---- Current Status Date of Acceptance 30.04.2020 Kick-off meeting held on 16.02.22. Engineering started. Contract signed on 16.02.22. Design & Engineering is in progress. Delay in DE due to improper submission of document IBR clearance received on 13-06-22 Site Activity: Pipes of sizes 65NB for water spray line, 150NB & 200NB for steam lines supplied. Ordering of Bought out item like PRDS and 8” isolation valve completed. Supply is delayed likely to be delivered by Mid Dec’22. Cable, cable tray, UPS, PRV starter supplied to the site. Date of Submission FR TS 27.07.2020(R0) 27.07.2020(R0) D/o Stage I & Cost (Rs. In Cr) 17.03.21, 1.54Cr. D/o Stage II & Cost (Rs. In Cr) 20.12.21, 2.26Cr. No. of Packages 1 Date of NIT 12.04.21 TOD 11.05.21, 30.07.21 Date of TER 13.08.21 PBE 10.09.21 Contractor Shailaja Enterprise TFL & LS K.Choudhury, DSC value of Package 1.85 Crore Status of Design Engineering Effective date of Contract 15.01.22 Scope Submitted Cleared* Commented U/s Schedule of BE 16.04.22 BE 9 9 9 0 0 Schedule of DE 16.04.22 DE 57 53 53 0 0 Schedule D/o completion 15.09.22,8m
  • 10. 24. Installation of a new Gas Booster House for Rolling Mills in DSP (04/DE/4737) (Stage II Approved) (Sheet – 1 of 1) Slide 10of 117 Description---- Current Status Date of Acceptance 06.05.2020 LOA placed on 31.01.22. Contract signed on 09.03.22. Kick – off meeting on 16.03.22. Engineering has been completed. Civil work for Electrical & control room completed Earthwork for Gas Booster room & trestle in progress. Bought-out out items like MGV, CV, pipelines, flanges, instruments and field devices supplied, overhead crane , booster fan and motor supplied. Incoming cables (80%) laid and MCC, PDB, VFD panel installed. 49T of structural steel is supplied. Another 30% to is in transit. Fabrication of the structural steel started. Supply of PLC panel, instrument panel . Site-work stalled due to fatal accident. Date of Submission FR TS 31.08.20 31.08.20 D/o Stage I & Cost (Rs. In Cr) 06.07.21, 10.41 Cr. D/o Stage II & Cost (Rs. In Cr) No. of Packages Date of NIT 06.08.21 TOD 29.09.21 Date of TER 28.10.21 PBE 04.12.21 Contractor TLT Engg. India Pvt. Ltd. TFL & LS M.K.Yadav , DSC: Kaustav Choudhury value of Package 11.93 Crore Status of Design Engineering Effective date of Contract 03.03.22 Scope Submitted Cleared* Commented U/s Schedule of BE BE 11 11 11 0 0 Schedule of DE DE 75 75 75 0 0 Schedule D/o completion 02.02.23(11m)
  • 11. 18. Replacement of two nos. of Electric Loco of COB-3, DSP(04/DE/4782) (Stage II Approved) (Sheet – 1 of 1) Slide 11of 117 Description---- Current Status Date of Acceptance 21.09.2020 LOA placed on 16.12.21. Kick off meeting held 22.02.22. Contract No. DSP/PROJ-PUR/CO&CC/Electric Loco/AS/570 signed on 22.02.2022 • Design & Engineering completed 100% of fabrication/manufacturing work completed, 3 consignments reached and 1 consignment is in transit. 100% bought out items have been ordered. Like to be supplied by end of Jan’23 Site activity like Leveling of the site area, unloading of consignment started Date of Submission CE TS 10.11.20 10.11.20(R0) 06.01.2021(R1) D/o Stage I & Cost (Rs. In Cr) 18.03.21, 5.42 D/o Stage II & Cost (Rs. In Cr) 16.12.21, 8.14 No. of Packages 1 Date of NIT 04.05.21 TOD 04.06.21, 10.07.21 Date of TER 06.08.21 PBE 24.09.21 Contractor Bhilai Engineering Corporation Ltd TFL & LS TFM CTEB Sushil Kumar(Mech.), DSC: KC value of Package 7.13 Crore Status of Design Engineering Effective date of Contract 15.01.22 Scope Submitted Cleared* Commented U/s Schedule of BE BE 7 7 7 0 0 Schedule of DE DE 36 36 36 0 0 Schedule D/o completion 15.12.22(12m)
  • 12. STAGE – I APPROVED Slide 12
  • 13. 17. Rebuilding of COB No.4 at DSP (04/DE/4747) (Stage I Approved) Slide 13of 117 Description: Rebuilding of COB No.4 at DSP (04/DE/4747) -CORPORATE PROJECT Current Status Date of Acceptance 29.06.2020 Draft Investment Proposal (DIP) along with Annexures issued to DSP on 28.06.22.Calculation sheet of NPV and IRR sent to DSP on 28.06.22. Plant PAG held on 28.06.22. EC & Bidder’s profile on PKG-I issued on 26.07.22 COD:08.08.22. Reply to observations on COD sent on 20.08.22 Reply on EMD’s observation were sent on 20.08.22 to DTE. COD observation were incorporated in Draft Agenda Note and sent on 26.08.22 Corporate PAG: 08.09.22. Reply to CO PAG observation sent on 15.09.22. Battery Proper Package-1 TS(R=0) issued on 09.09.22. Coke Oven Machine Package-2 TS(R=0) issued on 30.08.22 EC & Bidder’s profile on PKG-II issued on 14.09.22 Project DTE asked for views of Dir. Finance on cost comparison with COB# 2 RSP scheme for 41% Cost escalation which has accordingly being replied by CET on 10.10.2022. Board Sub committee held on 19.10.22. Board Meeting held on 20.10.22 and cleared TS for Pkg-I (R=2) issued on 27.10.22 & Pkg-II (R=1) issued on 21.10.22. Open Global Tender for Pkg-I vide Ref. no. DSP/PROJ-PUR/COCC/COB4- 1/SC/713 dated 14.11.22 has been floated. Open Indigenous Tender for Pkg-II vide Ref. no. DSP/PROJ- Date of Subm. FR 10.09.20(R0) 31.05.22(R1) 08.07.22(R2) TS Pkg-I 27.10.22(R=2) Pkg-II 21.10.22(R=1) Date of Stage I 20.10.22 Stage I cost (Rs. in crore) Rs. 673.15 cr No. of Package 2 NIT Pkg-I : 14.11.22 Pkg-II 14.11.22 TOD Pkg-I : 15.12.22, 01.02.23 Pkg-II: 12.12.22, 19.01.23 Tender
  • 14. 21. Complete waste water treatment at outfall #1,2&3 at DSP (04/DE/4817) (Stage I Approved) Slide 14of 117 Description Complete waste water treatment at outfall # 1,2&3 at DSP (04/DE/4817) Current Status Date of Acceptance 25.01.21 Three Packages Pkg. No. 1A- Soil Inv. & Survey: Report submitted by SS Solution on 15.03.22 & cleared on 29.06.22. Pkg. No. 1B:UG Mapping-Report issued on 11.02.22 by Gaveshana Geosciences Limited & cleared on . Main Package Plant PAG held on 02.07.22.PAG queries replied on 04.07.22. Updated cost issued on 04.07.22. COD held on 08.08.22. TS(R=1) issued on 13-08-22. EC(R=1) issued on 22.08.22. Draft agenda note updated on basis of COD’s & Project DTE’s observation on 26.08.22 and 01.09.22 respectively. Corporate PAG: 08.09.22. Outcome of CO PAG and comparative study of proposed ZLD at DSP vis-à-vis ZLD Scheme #3 at ISP were sent on 23.09.22 The queries raised by CO in the Agenda Note regarding O&M contract & comparison of total CAPEX & OPEX for RO and Ion Exchange processes, with due consideration of tertiary system were sent to CO on 17.10.22 & 19.10.22. Board Sub committee held on 19.10.22. Board Meeting held on 20.10.22 and the proposal was cleared. Bidder’s profile sent on 15.11.22 Open Indigenous Tender for Main Pkg-II vide Ref. no. DSP/PROJ- Date of submssn FR 23.04.21(R=0) 23.03.22 (R=1) TS 15.05. 21(R=0) 12.08.22(R=1) Date of Stage I 20.10.22 Stage I cost (Rs. in crore) Rs. 63.33 cr No. of Package Three (3) NIT 12.11.22 TOD 13.12.22, 20.01.23 Tender discussions Date of TER Date of PBE TFL & LS A. Trivedi (U&S)
  • 15. 18. INSTALLATION OF 1 NEW PUSHER CAR FOR COB#3 IN CO&CC (Stage I Approved) Slide 15of 117 Description ----INSTALLATION OF 1 NEW PUSHER CAR FOR COB#3 IN CO&CC (04/DE/4901) Current Status Date of Acceptance 01.11.21 EC (R=0) submitted on 27.07.22 & (R=1) submitted on 14.09.22 Bidders’ Profile submitted on 27.07.22 & 14.09.22 Plant PAG held on 27.09.22. Reply to DSP’s PAG deliberation sent on 06.10.22. Accordingly EC revised & EC (R=2) submitted on 13.10.22. For tendering purpose, CET’s reply to clarification were sent on 09.11.22 to DSP Tender No. DSP/PROJ-PUR/CO&CC/PC- COB#3/AS/716 dated 17.11.22 was raised on open indigenous tender enquiry basis. Three bidders participated. i) GAME ii) BEC iii) Gourika India Enterprise. TER submitted on 12.01.2023 Tender cancelled on 31.01.2023 due to less than X+2 bidders and changes to be done in the TS and Eligibility Criteria as per amendment of SBD 2020 Date of submission FR 29.01.22(R0), 30.06.22(R1) TS 10.02.22(R0), 29.06.22(R1) Date of Stage I 01.11.22 Stage I cost (Rs. in crore) 17.82 No. of Package 1 NIT 17.11.22 TOD 16.12.22 Tender discussions 03.01.22 & 05.01.22 Date of TER 18.01.2023 Date of PBE TFL & LS A.Tirkey, Mech. Ranchi TFM(From DSC) &CTE K.Choudhury, Anup Kr
  • 16. 17. 2ND CIRCULAR SAW WITH ALLIED FACILITIES IN WHEEL AXLE PLANT(04/DE/4908) (Stage I Approved) Slide 16of 117 Description ----IPU PROJECT Current Status Date of Acceptance 22.11.22 EC(R=0) issued on 23.03.22. Contact details of probable supplier for indigenous bid has been sent on 18.06.22. Tender No. DSP/PROJ- PUR/MM/WAP/CS/AS/673 issued on basis of open indigenous tender enquiry Probable bidders raised some queries. Corrigendum to TS(R=1) issued to DSP on 09.09.22 for change in PG parameters. TOD extended till 30.09.2022 from 22.08.22. Two bids from following two suppliers received i) Consortium of MACO & Linslinger ii) ITL Tender opened on 18.11.22. Technical offers of above two vendors sent to CET-Mech for evaluation. TER issued on 28.11.2022 Date of submissi on FR 22.02.22(R=0) TS 22.02.22(R=0) 07.04.22(R=1) Date of Stage I 28.05.22 Stage I cost (Rs. in crore) 19.34 No. of Package 1 NIT 18.06.22 TOD 22.08.22 ,30.09.22, 18.11.2022 Tender discussions NA Date of TER 28.11.2022 Date of PBE TFL & LS Ajay Kr, Utility K.Choudhury, Anup Kr
  • 18. Sl.N o. Description CORPORATE PROJECT Current Status (Reasons of delay, if any) 49 DE-BOTTLENECKING IN AREAS OF SP1 : REVAMPING OF APC SYSTEMS (04/DE/4938) (Four projects: 4288, 4251, 4313, part of 3805 combined to form 4938) A visit to DSP done by CET on 23.06.2022. A meeting between Sinter plant (Elect), PMD and CET held to freeze the power supply arrangement. VC held on 06.07.22 for Power source finalisation. Site visit done on 13.07.22 for finalization of power source and location of Electrical building. Clearance of the proposed location of substation awaited from DSP. Document Submission date changed to 17.09.2022 due to non receipt of BQ. FR (R=0) released on 15.09.22. Comments on FR(R=0) received on 06.10.22 Request for EC & bidder’s profile from plant received on 19.10.22 . TS(R=0) for Pkg-I issued on 09.11.22 TS(R=0) for Pkg-II issued on 10.11.22 Plant PAG for stage-I approval held on 10.11.22. Reply to Plant deliberation by CET on 16.11.22 EC & Bidder’s profile issued on 26.12.2022 for Pkg-I &Pkg-II Reply to DSP’s observation (raised by Dir-I/c) sent by CET on 03.01.23 TFL & LS : DSC & CTE : SOMRAJ CHAKRAVARTY (TFL), KC, Garish Kr. Date of Acceptance : 23.05.2022 FR 15.09.22(R=0) TS Cost of Project : Rs. 128.59 crores Slide 18 of 127 Reports Submitted
  • 19. Sl. No. Description ---IPU PROJECT/ CORPORATE PROJECT Current Status (Reasons of delay, if any) 23 Installation of new Wagon Tipplers/ Track Hopper in RMHP at DSP (04/DE/ 4826) Pkg.I-SIS & AS TS-12.08.21. Work order issued on 04.03.22 to SS Solution. Value: 4.67 L, duration:2 months Completed on 11.06.22. Final report cleared on 28.06.22. Pkg.II-UG: TS-12.08.21. Work order issued on 05.03.22 to SS Solution. Value:3.45 L, duration:45 days Reports submitted on 29.08.22 & CET cleared the same on 03.09.22. Completion certificates for both package issued on 08.09.22. Main Pkg: DSP to appoint external agency for formulating the general layout drawing of in-haul and out-haul railway track for proposed Wagon Tippler-4. CET issued new revised layout indicating the new proposed location of wagon tippler no.4 after site visit of 07.09.2022. TS(R=0) issued on 18.11.2022 Cost Committee for revision of capital cost held on 22.11.22 &FR(R=1) issued on 06.12.2022 Revised TS(R=1) for Pkg-IA (SIS & AS) & TS(R=1) for PKG-IIA (UG) issued on 28.12.2022 due to change in proposed location of Tippler#4. Block Cost for Package-IA (Area survey & SIS) & Package-II A (UG) is 5 lakhs and issued on 04.01.23 &11.01.23 respectively TFL & LS : TFM & CTE : Sanjay Kumar (ME), DSC:KC, Date of Acceptance: 08.03.2021 FR 05.06.2021(R=0) 06.12.2022(R=1) TS 18.11.2022(R=0) Cost of Project : Rs. 67.56 cr (R=1 cost) Slide 19 of 127 Reports submitted
  • 20. Sl. No. Description CORPORATE PROJECT Current Status (Reasons of delay, if any) 5 Installation of Micro - Pellet plant on BOO basis (04/DE/4951) DSP requested for draft investment proposal along with block cost estimate on 15.06.22. Acceptance letter sent on 22.06.22. DSP on 07.07.11 requested for Soil investigation & Underground mapping of the proposed site. On 20.08.22, draft tender document (Part A and Part B) sent to DSP for filling up the required portions. Technical basis for preparation of the tender document is on basis of RDCIS report on Pot sintering experiments with micro pellet condition at SP, ISP conditions. Micro pellet testing has not been done for DSP conditions since the source of iron ore and process iron making is same. TS on SIS & Area Survey submitted on 22.11.2022. Being a green field project UG mapping is not required. Block Cost of Rs 16 lakhs submitted on 30.11.2022. 5 nos. of bid for the above package has been received and sent to CET (C&S) for tender evaluation on 04.01.2023 DSP specified the power source for Micropellet plant & proportioning quantity of feed materials, chemical analysis of iron bearing waste through e-mail dated 01.12.2022 & 3.12.2022. DSP requirement for provision of handling mill scale and ESP dust in Sinter plant is not clearly stated in the e-mail dated 3.12.2022 CET requested DSP vide email dated 21.12.2022 to include the balance points in tender document (like location, nature of land sharing, Minimum guaranteed off- take value, Battery limit of feed materials, & (physical analysis) quality iron bearing waste, % LD charges, Earnest Money Deposit and security deposit. TFL & LS : TFM & CTE: SHYAM JI (I&S) KC, PK Mishra Date of Acceptance : 20.06.22 TD Scheduled :23.08.22 Issued :19.08.22 Cost of Project: Rs. 100 cr Slide 20 of 127 Reports submitted
  • 21. Sl. No. Description Current Status (Reasons of delay, if any) 10 Installation of Ladle Tilters at SMS-ISP (03/DE/4991) 1 no. of BQ received from M/s GAME. Cost Sheet finalized on 26.12.2022. (P&E cost arrived on basis of combining P&E cost, D&E in BQ with 10% knockdown & factoring out the normative) DR held on 29.12.2022 FR(R=0) issued on 29.12.2022 TS(R=0) issued on 30.12.2022 TFL & LS : TFM & CTE : :KC & DSC, RK(CTE) Date of Acceptance : 29.09.2022 FR & TS Scheduled :29.12.2022 Cost of Project : Rs. 10.7 cr Slide 21 of 127 Reports to be submitted
  • 22. REPORTS TO BE SUBMITTED Slide 22
  • 23. Sl. No. Description Current Status (Reasons of delay, if any) 1 PARALLEL CONVEYOR TO CONVEYOR 5A (04/DE/4903) Soil and UG mapping TS submitted on 22.02.22. Main TS will be submitted after soil report. DSP sent RA report along with the price break up of the L1 bidder for Soil pkg. Requested for PBE on 18.08.22. PBE report issued on 23.08.22. Order placed on SS Solution. Survey completed and final report submitted on 07.11.22. CET has commented on survey report related to ”Level, extent and name of the existing facilities ” which is not mentioned in the drawing. SS Solution after joint visit on 24.12.2022 with the Dept. & Proj. has issued the corrected drawing on 30.12.2022. The same has cleared by DSP on 04.01.23 & sent to CET on 05.01.2023 for further observation. FR & TS of main pkg are due TFL & LS : TFM & CTE : SK Singh, Mech DSC: KC , RK Jha Date of Acceptance : 08.11.21 TS : Cost of Project : Rs. 8 cr Slide 23 of 127 Reports to be submitted