This document provides an outline and summary of an internship completed at a 01MW solar power plant in Dhrangandhra from January 13th to April 12th 2022. The internship covered various components of the solar power system including solar panels, inverters, SCADA systems, transformers and more. The intern gained experience in maintenance, testing and operation of the different parts of the solar power plant over the 3 month duration.
Filters for Electromagnetic Compatibility Applications
Presentation 19 04 2022.pdf
1. PRESENTATION FOR COURSE SUMMER INTERNSHIP (3170001)
An Industrial Internship
At
01MW SOLAR POWER PLANT AT MIL STN DHRANGANDHRA
Organis:shree ram laxman sthapatya co.
COMPLETEDAT
(Duration: 13/01/2022 TO 12/04/2022)
PRESENTEDBY: KANJARIYA RAM M. EN. NO. ( 180150109053)
EXTERNAL GUIDE: Mr.HITESHBHAI ROJASRA
INTERNAL GUIDE: PROF.(MS) K. A. SONAGRA
DATE OF PRESENTATION:21/04/2022
DEPARTMENT: ELECTRICAL DEPARTMENT
2. Outline:
1.INTRODUCTION
2.SOLAR SYSTEM
3. SOLAR PANEL
4.S. C. B
5.INVERTER
6.SCADA SYSTEM
7. METER PANEL
8. TRANSFORMER
9.VCB
10. ADVANTAGE AND DISADVANTAGE
3. Sr.No Duration
01 Solar module
construction and working
20/01/2022 To 05/02/2022
02 Use of scb 07/02/2022 To 12/02/2022
03 Inverter operating and
mentanence
14/02/2022 To 26/02/2022
04 SCADA system 28/02/2022 To 05/03/2022
05 Transformer details 07/03/2022 To 12/03/2022
06 Vcb 14/03/2022 To 19/03/2022
07 Inverter operating 21/03/2022 To 12/04/2022
4. INTRODUCTION
Solar power plant is based on the conversionelectricity, using photovoltaic
(PV), or indirectlyusing concentrated solar power (CSP).
Concentrated solar power systems use lenses or mirrors and tracking
systems to focus a large area of sunlight into a small beam.
Photovoltaic into of sunlight into either directly converts light electric
current using the photoelectric effect.
Concentrated solar power plants first appeared in the 1980s
8. Continue
PH-4 Battery Bank 1&2
Priventive Maintenance
Work.
What Is Dynamically
Balanced Siren And Not
Working So Problem
Solved.
3 Phase Induction Motor
Name Plate See And
Understanding.
13. Overview Of 330 Mw Main Plant.
Unit 1 To 4 Pilots Cells
Voltage&Specific Gravity
Measurements For Unit 1 To 4.
DG-2A Priventive Maintenance
HT Switchgear Room Coal Mill-
2B Modification Work Spare T.B.
Adding.
Asynchronous Motor O/H Work
Bearing Damege Problem
330 MW Main Plant E-M-D.
14. Sr.No Department Duration
08 EMD-660 MW Main Plant 28/03/2022 To 03/04/2022
09 Testing Department 07/03/2022 To 13/03/2022
10 220 KV Switchyard 06/01/2022 To 09/01/2022
11 220 KV Switchyard 10/01/2022 To 16/01/2022
12 220 KV Switchyard 17/01/2022 To 23/01/2022
13 220 KV Switchyard 24/01/2022 To 30/01/2022
14 ±500 KV Switchyard 04/04/2022 To 05/04/2022
15. 660 MW MAIN PLANT
LT Motor Priventive Maintenance.
Root Fan Motor Not Working Check The Motor.
Generator Name Plate See And Understanding.
What Is HT Switch Gear.
Which Type Using Voltage Uses.
17. 220 KV SWITCHYARD
Overview : Switch
Yard
Type Of X’Mer :
GT,UAT,ST
Transformer All Part
See And
Understanding
Physical.
18. Continue
UAT-4B Oil purification.
Transformer oil Filtration Plant Capacity
600 LPH
•UAT-4B Taken To the oil sample And
Sending test Lab.
UAT-4A Oil Low Leval ( ¼) This
Minimum Oil Leval so Fill up The Tank
(½) Process.
20. Continue
Phase-1 ConditionMonitoring
Current&Capacitive Voltage Transformer CM Lighting Arrester
CM
Phase-1 Switchyard All Transformer Bushing Oil Leval Indication
Check
Phase-1 Switchyard Transformer C.M
GT,UAT,ST
21. TESTING DEPARTMENT
Current Transformer Testing.
Tapper -1, Tapper-2, Outgoing Line.
CT Anylzer Kit, Ten Delta Kit, Megger.
Capacity Voltage Transformer
Testing.
R Phase PT, Y Phase PT,B Phase PT.
23. ±500 KV HVDC
Basic Knowledge Gain HVDC.
6 Feeder Coming To HVAC.
Different HVAC And HVDC Switchyard
Equipment.
What Is Converter Transformer.
Voltage Divider Test.
SF 6 Q Anylzer.