NOBLE FIRE PRODUCTIVITY 
IMPROVEMENTS & SAVINGS 
by Julian Kalac P.Eng 
November 12, 2012
Capacity Issues & Report 
• On October 6, 2012 –asked to assess Noble Fire 
production capacity & make recommendations for 
improvement 
• October 9th I prepared a formal Engineering report 
on Production Capacity 
• October 19th was asked to implement the needed 
improvements
Noble Fire Productivity Improvements 
Within 2 weeks (Oct. 16 to Nov 2, 2012) 
• increase productivity by 15% w/o new equipment 
(from 2,189 to 2,317 outlets/Week) 
• completed DVP&R and Approval new SPRINKLER 
OUTLETS for a pilot run build of 1000pcs 
• New ANSI Outlets reduced Safety Field repairs by 95% 
• The biggest improvement has been seen on the 
NOGEO machine over 40% (17-24/hr)== $175K/Year 
• We have reduced the NOGEO m/c cycle time from 2:36 
to <2 min/outlet (by implementing a M/C PM
Labour Cost/Outlet 
• The plant is working OT 55hrs/week to 
maintain the customer deliveries 
• Since Oct 19 we have Reduced Labor Cost by 
$1.48/Outlet in less than 1 month 
• Developed a capacity plan that will save 
$230K/Year in Plant OVERTIME COSTS within 
3-4 months 
• Total labour savings= $230,000/Year
2012 Noble Fire Production Capacity per month 
$481.00 
$364.00 
$598.00 
$483.00 
$482.00 
$686.00 
$579.00 
$448.00 
$579.00 
$522.00 
$625.00 
$550.00 
$800.00 
$700.00 
$600.00 
$500.00 
$400.00 
$300.00 
$200.00 
$100.00 
$- 
2012 Avg= $534K 
When I started to help 
Jan Feb March April May June July August Sept Oct Nov Dec
OUTLETS/HR AND LABOUR COST 
M/C Outlets 
Producti 
on Hrs 
3 DAYS USING NEW OUTLETS 
DT Hrs PPMH % DT 
LAB COST 
@40HR 
OT COST 
TOTAL 
LABOUR 
COST 
LABOUR 
COST/OUTLET 
WB #1 748 54 10 13.9 18.5% $ 1,600.00 $ 840.00 $ 2,440.00 $ 3.26 
WB #2 517 54 9.5 9.6 19.0% $ 1,600.00 $ 600.00 $ 2,200.00 $ 4.26 
NOGEO M/C 1052 54 7 19.48 24.1% 
$ 1,600.00 $ 840.00 $ 2,440.00 $ 2.32 
TOTAL PRODUCTION 2317 158 32.5 14.3 20.6% $ 9.82 
% NOGEO Production 45.4% 
M/C Outlets 
Producti 
on Hrs 
DT Hrs PPMH % DT 
WB #1 589 32.25 10 18.26 31.0% 
WB #2 357 32.25 9.5 11.07 29.5% 
NOGEO M/C 789 32.25 4 24.47 12.4% 
TOTAL PRODUCTION 1735 96.75 23.5 17.9 20.6% 
% NOGEO Production 45.5% 
3 Days Only 
Oct 29 - Nov 2 Production (5 days) 
MON-WED WITH NEW OUTLETS
$250,000 
$200,000 
$150,000 
$100,000 
$50,000 
$- 
OCTOBER ACTUAL CAPACITY BY WEEK 
Max Sales Capacity ACTUAL SALES PRODUCTION 
~20% Increase in sales (new outlets) 
Week 1 Week 2 Week 3 Week 4 
Week
CYPRESS AUTOMTED BURN & WELD 
FUTURE LABOUR COSTS WITH AUTOMATED CYPRESS CW-5 & CBP-1 BURNER 
Min Oulets/Hr Labour Cost/Outlet Outlets/8Hr Day Outlet/40Hr week Outlets/month OUTLETS/YEAR 
50 $ 0.80 400 2000 8000 96000 
WITH OT@ 60 Hrs/week 
Max Outlets/Hr AVG LAB COST Max Outlets/Day Max Outlets/Week Max Outlets/Month Max Outlets/Year (9000 Lab Hrs) 
41 $ 3.89 440.8 2203.8 8815 105780 
NEW TOTAL CAPACITY 
OUTLETS/HR NEW LABOUR COST @$120/HR OUTLETS/8HR DAY Outlet/40Hr week Outlets/month OUTLETS/YEAR 
91 $ 1.32 728 3640 14560 174,720.0 
Min Sales @ 
$600K/month 
Max sales @ 
$1Mil/Month 
% Increased Productivity 
ANNUAL SAVINGS Min OUTLETS/YEAR Max OUTLETS/YEAR 91% 
90000 150000 
CURRENT Avg Labour 
Cost/Outlet $ 3.89 CURRENT COST $ 350,528.30 $ 584,213.84 
FUTURE COST/OUTLET $ 1.32 FUTURE COST $ 118,681.32 $ 197,802.20 
SAVINGS/OUTLET= $ 2.58 
DIRECT LABOUR 
SAVINGS $ 231,846.98 $ 386,411.64 
$ 231,847 
MIN LABOUR SAVINGS/YEAR =
NOGEO CYCLE TIME IMPROVEMENTS 
OLD OUTLETS NEW OUTLETS 
CYCLE TIME (Min) CYCLE TIME (Min) 
1 OUTLET 2.76 2 
Outlets/Hr 21.739 30 
Outlets/8 Hrs 173.9 240.0 
Outlets/Week 870 1200 
Outlets/Month 3478 4800 
Outlets/Year 41739 57600 
15861 
Labour rate $ 40.0 $ 40.0 
Normal Labour cost/Outlet $ 1.84 $ 1.33 
Labour rate $ 60.00 $ 60.00 
OT Labour Cost $ 2.76 $ 2.00 
$ 21,147.83 
0.95 
$ 22,260.87 
Improvement in Outlets/Year = 
MIN DIRECT LABOUR SAVINGS YTD= 
NEW OUTLET $0.05 LESS THAN OLD ONE 
MIN YTD SAVINGS WITH NEW OUTLETS=
Total Outlets Produced by Week 
Started to use new Outlets 
Oct 8-12 Oct 15-26 Oct 29-Nov 2 
2350 
2300 
2250 
2200 
2150 
2100 
2050 
Outlets 
Total Outlets 2181 2149 2317
Avg Outlets per Hr 
13 
With new Outlets 
13.6 
15.2 
Oct 8-12 Oct 15-26 Oct 29-Nov 2
% Downtime by M/C 
% Donwtime, 
24.1% 
30.0% 
25.0% 
20.0% 
15.0% 
10.0% 
5.0% 
0.0% 
WB #1 WB #2 NOGEO M/C 
Axis Title 
% Donwtime
Recommendations next step 
• Fix/replace the chuck drive stalling issue to 
reduce the cycle time from 2 min to < 1.5 min 
• Rebuild/Replace the weld unit 
• Fix the magnet issue 
• Replace all worn air cylinders 
• Develop a spare parts list of most critical items 
• Schedule 1-2hrs/week for regular machine 
maintenance and inspect/replace worn parts
Questions?

Fire productivity savings

  • 1.
    NOBLE FIRE PRODUCTIVITY IMPROVEMENTS & SAVINGS by Julian Kalac P.Eng November 12, 2012
  • 2.
    Capacity Issues &Report • On October 6, 2012 –asked to assess Noble Fire production capacity & make recommendations for improvement • October 9th I prepared a formal Engineering report on Production Capacity • October 19th was asked to implement the needed improvements
  • 3.
    Noble Fire ProductivityImprovements Within 2 weeks (Oct. 16 to Nov 2, 2012) • increase productivity by 15% w/o new equipment (from 2,189 to 2,317 outlets/Week) • completed DVP&R and Approval new SPRINKLER OUTLETS for a pilot run build of 1000pcs • New ANSI Outlets reduced Safety Field repairs by 95% • The biggest improvement has been seen on the NOGEO machine over 40% (17-24/hr)== $175K/Year • We have reduced the NOGEO m/c cycle time from 2:36 to <2 min/outlet (by implementing a M/C PM
  • 4.
    Labour Cost/Outlet •The plant is working OT 55hrs/week to maintain the customer deliveries • Since Oct 19 we have Reduced Labor Cost by $1.48/Outlet in less than 1 month • Developed a capacity plan that will save $230K/Year in Plant OVERTIME COSTS within 3-4 months • Total labour savings= $230,000/Year
  • 5.
    2012 Noble FireProduction Capacity per month $481.00 $364.00 $598.00 $483.00 $482.00 $686.00 $579.00 $448.00 $579.00 $522.00 $625.00 $550.00 $800.00 $700.00 $600.00 $500.00 $400.00 $300.00 $200.00 $100.00 $- 2012 Avg= $534K When I started to help Jan Feb March April May June July August Sept Oct Nov Dec
  • 6.
    OUTLETS/HR AND LABOURCOST M/C Outlets Producti on Hrs 3 DAYS USING NEW OUTLETS DT Hrs PPMH % DT LAB COST @40HR OT COST TOTAL LABOUR COST LABOUR COST/OUTLET WB #1 748 54 10 13.9 18.5% $ 1,600.00 $ 840.00 $ 2,440.00 $ 3.26 WB #2 517 54 9.5 9.6 19.0% $ 1,600.00 $ 600.00 $ 2,200.00 $ 4.26 NOGEO M/C 1052 54 7 19.48 24.1% $ 1,600.00 $ 840.00 $ 2,440.00 $ 2.32 TOTAL PRODUCTION 2317 158 32.5 14.3 20.6% $ 9.82 % NOGEO Production 45.4% M/C Outlets Producti on Hrs DT Hrs PPMH % DT WB #1 589 32.25 10 18.26 31.0% WB #2 357 32.25 9.5 11.07 29.5% NOGEO M/C 789 32.25 4 24.47 12.4% TOTAL PRODUCTION 1735 96.75 23.5 17.9 20.6% % NOGEO Production 45.5% 3 Days Only Oct 29 - Nov 2 Production (5 days) MON-WED WITH NEW OUTLETS
  • 7.
    $250,000 $200,000 $150,000 $100,000 $50,000 $- OCTOBER ACTUAL CAPACITY BY WEEK Max Sales Capacity ACTUAL SALES PRODUCTION ~20% Increase in sales (new outlets) Week 1 Week 2 Week 3 Week 4 Week
  • 8.
    CYPRESS AUTOMTED BURN& WELD FUTURE LABOUR COSTS WITH AUTOMATED CYPRESS CW-5 & CBP-1 BURNER Min Oulets/Hr Labour Cost/Outlet Outlets/8Hr Day Outlet/40Hr week Outlets/month OUTLETS/YEAR 50 $ 0.80 400 2000 8000 96000 WITH OT@ 60 Hrs/week Max Outlets/Hr AVG LAB COST Max Outlets/Day Max Outlets/Week Max Outlets/Month Max Outlets/Year (9000 Lab Hrs) 41 $ 3.89 440.8 2203.8 8815 105780 NEW TOTAL CAPACITY OUTLETS/HR NEW LABOUR COST @$120/HR OUTLETS/8HR DAY Outlet/40Hr week Outlets/month OUTLETS/YEAR 91 $ 1.32 728 3640 14560 174,720.0 Min Sales @ $600K/month Max sales @ $1Mil/Month % Increased Productivity ANNUAL SAVINGS Min OUTLETS/YEAR Max OUTLETS/YEAR 91% 90000 150000 CURRENT Avg Labour Cost/Outlet $ 3.89 CURRENT COST $ 350,528.30 $ 584,213.84 FUTURE COST/OUTLET $ 1.32 FUTURE COST $ 118,681.32 $ 197,802.20 SAVINGS/OUTLET= $ 2.58 DIRECT LABOUR SAVINGS $ 231,846.98 $ 386,411.64 $ 231,847 MIN LABOUR SAVINGS/YEAR =
  • 9.
    NOGEO CYCLE TIMEIMPROVEMENTS OLD OUTLETS NEW OUTLETS CYCLE TIME (Min) CYCLE TIME (Min) 1 OUTLET 2.76 2 Outlets/Hr 21.739 30 Outlets/8 Hrs 173.9 240.0 Outlets/Week 870 1200 Outlets/Month 3478 4800 Outlets/Year 41739 57600 15861 Labour rate $ 40.0 $ 40.0 Normal Labour cost/Outlet $ 1.84 $ 1.33 Labour rate $ 60.00 $ 60.00 OT Labour Cost $ 2.76 $ 2.00 $ 21,147.83 0.95 $ 22,260.87 Improvement in Outlets/Year = MIN DIRECT LABOUR SAVINGS YTD= NEW OUTLET $0.05 LESS THAN OLD ONE MIN YTD SAVINGS WITH NEW OUTLETS=
  • 10.
    Total Outlets Producedby Week Started to use new Outlets Oct 8-12 Oct 15-26 Oct 29-Nov 2 2350 2300 2250 2200 2150 2100 2050 Outlets Total Outlets 2181 2149 2317
  • 11.
    Avg Outlets perHr 13 With new Outlets 13.6 15.2 Oct 8-12 Oct 15-26 Oct 29-Nov 2
  • 12.
    % Downtime byM/C % Donwtime, 24.1% 30.0% 25.0% 20.0% 15.0% 10.0% 5.0% 0.0% WB #1 WB #2 NOGEO M/C Axis Title % Donwtime
  • 13.
    Recommendations next step • Fix/replace the chuck drive stalling issue to reduce the cycle time from 2 min to < 1.5 min • Rebuild/Replace the weld unit • Fix the magnet issue • Replace all worn air cylinders • Develop a spare parts list of most critical items • Schedule 1-2hrs/week for regular machine maintenance and inspect/replace worn parts
  • 14.