SlideShare a Scribd company logo
Executing Process Group – PMP/CAPM (PMBOK 6)
The Executing Process Group consists of those processes performed to
complete the work defined in the project management plan to satisfy the
project requirements. PMBOK6
The processes in Executing Process Group deal with the completion of the work defined in the Project
Management Plan which is completed and approved by the stakeholders at the end of the project planning
phase. It involves coordinating resources like people, equipment and resources to get the work done
efficiently and effectively so that the project keeps delivering the promised objective.
The most important output here is Deliverable, which is produced in line with the defined Project
Management Plan.
This process is where most of the work is carried out, and where products and deliverables are built,
assembled, constructed, and created.
Behind every successful project is a great team and a good team is a direct result of the good environment
which is based on trust and competencies and capabilities rather than anything else. The team has to be
acquired, managed and cultivated for performance. Conflicts, they are healthy if solved amicably by using
the right conflict resolution method
The Executing process group utilizes the most project time and resources, and as a result, costs are usually
highest during the Executing process.
10 Process – 31% of Exam Questions: Isn’t this a reason to motivate you to dive quickly in these 10
processes and get 62 questions correct.
During the execution process, Changes will also be implemented but only those which are Approved by
the management or change control board or by the steering committee.
Don’t forget that Deliverables should be quality oriented to make sure here we do the things right i.e
quality assurance process.
In short, the Executing process involves coordinating people and resources, as well as integrating and
performing the activities of the project in accordance with the project plan. The main outputs the project
deliverables and producing these will be the responsibility of the project team who will be working to the
project plan.
Purpose of Executing Process Groups
ï‚· Produce the deliverables as per the plan by Coordinating people and resources
ï‚· Managing stakeholder expectation
ï‚· Integrating and performing the project activities
This is the stage where deliverables are created and completed. This
frequently refers to the meat of the project because multiple tasks are
happeningduringthis period such as status information and conferences,
growth updates, and performance reports. Here an important meeting
typically marks the beginningof the Project Execution phase where the project
management team is informed about theirresponsibilities. Some of the key
tasks completed in this phase include develop a team, assign resources,
implement project management plans, and procurement management if
required.
Tasks in Executing Process Groups
ï‚· Implement the procurement of project resources
ï‚· Execute tasks/project defined in the project management plan
ï‚· Implement quality management plan
ï‚· Implement approved changes and corrective actions
ï‚· Implement Risk Mitigation and Response approved action
ï‚· Ensure common understanding and set expectations
ï‚· Keep Stakeholders engaged through Communication
Processes in Executing Process Groups (10 Processes)
1. Direct and Manage Project Work ⇒ Project Integration Management
is the process of using existing knowledge and creating new knowledge to achieve the project’s
objectives and contribute to organizational learning
2. Manage Project Knowledge (Project Integration Management)
is the process of using existing knowledge and creating new knowledge to achieve the project’s
objectives and contribute to organizational learning.
3. Manage Quality ⇒ Project Quality Management
is the process of translating the quality management plan into executable quality activities that
incorporate the organization’s quality policies into the project.
4. Acquire Resource ⇒ Project Resource Management
is the process of obtaining team members, facilities, equipment, materials, supplies, and other resources
necessary to complete project work
5. Develop Team (Project Resource Management)
is the process of improving competencies, team member interaction, and overall team environment to
enhance project performance.
6. Manage Team (Project Resource Management)
Manage Team is the process of tracking team member performance, providing feedback, resolving
issues, and managing team changes to optimize project performance.
7. Manage Communications ⇒ Project Communication Management
is the process of ensuring timely and appropriate collection, creation, distribution, storage, retrieval,
management, monitoring, and the ultimate disposition of project information
8. Implement Risk Responses ⇒ Project Risk Management
Implement Risk Responses is the process of implementing agreed-upon risk response plans
9. Conduct Procurements ⇒ Project Procurement Management
Conduct Procurements is the process of obtaining seller responses, selecting a seller, and awarding a
contract.
10. Manage Stakeholder EEngagement ⇒ Project Stakeholder Management
Manage Stakeholder Engagement is the process of communicating and working with stakeholders to
meet their needs and expectations, address issues, and foster appropriate stakeholder involvement
Further Readings
ï‚· Project Life Cycle vs Product Life Cycle vs Project Management Phases

More Related Content

What's hot

PgMP - Introduction to Program Management
PgMP -  Introduction to Program ManagementPgMP -  Introduction to Program Management
PgMP - Introduction to Program Management
Issah Abdul-Wahab, MCTS, PMP, PgMP, PfMP
 
R&D Project Management
R&D Project ManagementR&D Project Management
R&D Project Management
kevinlu
 
PgMP 02 - Program Performance Domainv1
PgMP 02 - Program Performance Domainv1PgMP 02 - Program Performance Domainv1
PgMP 02 - Program Performance Domainv1
Issah Abdul-Wahab, MCTS, PMP, PgMP, PfMP
 
R&D Project Management
R&D Project ManagementR&D Project Management
R&D Project Managementafrinaafrose
 
Introduction to Management & Project Management By Pravin Minde
Introduction to Management & Project Management By Pravin MindeIntroduction to Management & Project Management By Pravin Minde
Introduction to Management & Project Management By Pravin Minde
Pravin Minde
 
Pmp Course Outline
Pmp Course OutlinePmp Course Outline
Pmp Course Outline
quahance
 
Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full course
Marten Schoonman
 
Strategies for successful_engineering_management
Strategies for successful_engineering_managementStrategies for successful_engineering_management
Strategies for successful_engineering_management
Society of Women Engineers
 
Improving sales and operations (S&0P) in fmcg companies
Improving sales and operations (S&0P) in fmcg companiesImproving sales and operations (S&0P) in fmcg companies
Improving sales and operations (S&0P) in fmcg companies
Issah Abdul-Wahab, MCTS, PMP, PgMP, PfMP
 
Art of Project Management - Make Things Done On Time
Art of Project Management - Make Things Done On TimeArt of Project Management - Make Things Done On Time
Art of Project Management - Make Things Done On Time
calvinbiz0514
 
01 3 day elearning executing process v2
01 3 day elearning executing process v201 3 day elearning executing process v2
01 3 day elearning executing process v2
Joyce Wong
 
Understand PMBOK 6TH GUIDE
Understand PMBOK 6TH GUIDEUnderstand PMBOK 6TH GUIDE
Understand PMBOK 6TH GUIDE
Amr Miqdadi
 
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
Muzette Charles, PMP
 
Project management pocket skills
Project management   pocket skillsProject management   pocket skills
Project management pocket skills
rdlteam
 
Project Management Pocket Skills Guide
Project Management Pocket Skills GuideProject Management Pocket Skills Guide
Project Management Pocket Skills Guide
Emily Robinson
 
Process Improvement and Change Management, 29th October 2015
Process Improvement and Change Management, 29th October 2015Process Improvement and Change Management, 29th October 2015
Process Improvement and Change Management, 29th October 2015
Association for Project Management
 
Programs and Portfolios - Multi-project Management
Programs and Portfolios - Multi-project ManagementPrograms and Portfolios - Multi-project Management
Programs and Portfolios - Multi-project Management
Bryan Fenech
 
CCP_SEC5_ Project Management
CCP_SEC5_ Project ManagementCCP_SEC5_ Project Management
CCP_SEC5_ Project Management
Hisham Haridy MBA, PMP®, RMP®, SP®
 
Setting up a pmo
Setting up a pmoSetting up a pmo
Setting up a pmo
crmackenzie
 

What's hot (20)

041006-Program Management PMI NB - PMI Logo
041006-Program Management PMI NB - PMI Logo041006-Program Management PMI NB - PMI Logo
041006-Program Management PMI NB - PMI Logo
 
PgMP - Introduction to Program Management
PgMP -  Introduction to Program ManagementPgMP -  Introduction to Program Management
PgMP - Introduction to Program Management
 
R&D Project Management
R&D Project ManagementR&D Project Management
R&D Project Management
 
PgMP 02 - Program Performance Domainv1
PgMP 02 - Program Performance Domainv1PgMP 02 - Program Performance Domainv1
PgMP 02 - Program Performance Domainv1
 
R&D Project Management
R&D Project ManagementR&D Project Management
R&D Project Management
 
Introduction to Management & Project Management By Pravin Minde
Introduction to Management & Project Management By Pravin MindeIntroduction to Management & Project Management By Pravin Minde
Introduction to Management & Project Management By Pravin Minde
 
Pmp Course Outline
Pmp Course OutlinePmp Course Outline
Pmp Course Outline
 
Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full course
 
Strategies for successful_engineering_management
Strategies for successful_engineering_managementStrategies for successful_engineering_management
Strategies for successful_engineering_management
 
Improving sales and operations (S&0P) in fmcg companies
Improving sales and operations (S&0P) in fmcg companiesImproving sales and operations (S&0P) in fmcg companies
Improving sales and operations (S&0P) in fmcg companies
 
Art of Project Management - Make Things Done On Time
Art of Project Management - Make Things Done On TimeArt of Project Management - Make Things Done On Time
Art of Project Management - Make Things Done On Time
 
01 3 day elearning executing process v2
01 3 day elearning executing process v201 3 day elearning executing process v2
01 3 day elearning executing process v2
 
Understand PMBOK 6TH GUIDE
Understand PMBOK 6TH GUIDEUnderstand PMBOK 6TH GUIDE
Understand PMBOK 6TH GUIDE
 
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
 
Project management pocket skills
Project management   pocket skillsProject management   pocket skills
Project management pocket skills
 
Project Management Pocket Skills Guide
Project Management Pocket Skills GuideProject Management Pocket Skills Guide
Project Management Pocket Skills Guide
 
Process Improvement and Change Management, 29th October 2015
Process Improvement and Change Management, 29th October 2015Process Improvement and Change Management, 29th October 2015
Process Improvement and Change Management, 29th October 2015
 
Programs and Portfolios - Multi-project Management
Programs and Portfolios - Multi-project ManagementPrograms and Portfolios - Multi-project Management
Programs and Portfolios - Multi-project Management
 
CCP_SEC5_ Project Management
CCP_SEC5_ Project ManagementCCP_SEC5_ Project Management
CCP_SEC5_ Project Management
 
Setting up a pmo
Setting up a pmoSetting up a pmo
Setting up a pmo
 

Similar to Executing process group

Planning process group
Planning process groupPlanning process group
Planning process group
Mudassir Iqbal
 
Pm training 1 18
Pm training 1 18Pm training 1 18
Pm training 1 18
Nawzad Bilal
 
Pmp study-notes
Pmp study-notesPmp study-notes
Pmp study-notes
Krishna Murthy RVN
 
Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3
Amr Miqdadi
 
2) PMT & PIM.pptx
2) PMT & PIM.pptx2) PMT & PIM.pptx
2) PMT & PIM.pptx
MuhammadAmanAzam
 
PMBOK(Project Management Body of Knowledge)
PMBOK(Project Management Body of Knowledge)PMBOK(Project Management Body of Knowledge)
PMBOK(Project Management Body of Knowledge)
Mohammad Mohammadi
 
Project Management V1
Project Management V1Project Management V1
Project Management V1Rebecca Keating
 
Project management
Project managementProject management
Project management
Er. BHUSHAN SARISE
 
ICT4GOV PROJECT MANAGEMENT
ICT4GOV PROJECT MANAGEMENTICT4GOV PROJECT MANAGEMENT
ICT4GOV PROJECT MANAGEMENTJohn Macasio
 
PPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxPPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptx
SabrinaScott22
 
The Art Of Project Management
The Art Of Project ManagementThe Art Of Project Management
The Art Of Project Management
hatemk
 
PMP.pdf
PMP.pdfPMP.pdf
PMP.pdf
DineshKumar4470
 
Online PMP Prep Material for PMP Exam - Project management process groups
Online PMP Prep Material for PMP Exam - Project management process groupsOnline PMP Prep Material for PMP Exam - Project management process groups
Online PMP Prep Material for PMP Exam - Project management process groups
GlobalSkillup
 
Answer sheet project management
Answer sheet project managementAnswer sheet project management
Answer sheet project management
PMlynda17
 
Day 1 framework
Day 1 frameworkDay 1 framework
Day 1 framework
Ahmed Elgazzar
 
Project management
Project managementProject management
Project management
Biswa Prusty
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkejlp12
 
Pmbok Training for pmo
Pmbok Training for pmoPmbok Training for pmo
Pmbok Training for pmo
Erin Jones
 
Project Management Methodologies
Project Management MethodologiesProject Management Methodologies
Project Management Methodologies
Monief Eid,Prince2,Prosci, Lean Six Sigma &ITIL
 
project management concepts
project management conceptsproject management concepts
project management concepts
Aswin prakash i , Xantus Technologies
 

Similar to Executing process group (20)

Planning process group
Planning process groupPlanning process group
Planning process group
 
Pm training 1 18
Pm training 1 18Pm training 1 18
Pm training 1 18
 
Pmp study-notes
Pmp study-notesPmp study-notes
Pmp study-notes
 
Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3
 
2) PMT & PIM.pptx
2) PMT & PIM.pptx2) PMT & PIM.pptx
2) PMT & PIM.pptx
 
PMBOK(Project Management Body of Knowledge)
PMBOK(Project Management Body of Knowledge)PMBOK(Project Management Body of Knowledge)
PMBOK(Project Management Body of Knowledge)
 
Project Management V1
Project Management V1Project Management V1
Project Management V1
 
Project management
Project managementProject management
Project management
 
ICT4GOV PROJECT MANAGEMENT
ICT4GOV PROJECT MANAGEMENTICT4GOV PROJECT MANAGEMENT
ICT4GOV PROJECT MANAGEMENT
 
PPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxPPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptx
 
The Art Of Project Management
The Art Of Project ManagementThe Art Of Project Management
The Art Of Project Management
 
PMP.pdf
PMP.pdfPMP.pdf
PMP.pdf
 
Online PMP Prep Material for PMP Exam - Project management process groups
Online PMP Prep Material for PMP Exam - Project management process groupsOnline PMP Prep Material for PMP Exam - Project management process groups
Online PMP Prep Material for PMP Exam - Project management process groups
 
Answer sheet project management
Answer sheet project managementAnswer sheet project management
Answer sheet project management
 
Day 1 framework
Day 1 frameworkDay 1 framework
Day 1 framework
 
Project management
Project managementProject management
Project management
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to framework
 
Pmbok Training for pmo
Pmbok Training for pmoPmbok Training for pmo
Pmbok Training for pmo
 
Project Management Methodologies
Project Management MethodologiesProject Management Methodologies
Project Management Methodologies
 
project management concepts
project management conceptsproject management concepts
project management concepts
 

More from Mudassir Iqbal

Quality assurance and control quality - PMP/CAPM by PMI
Quality assurance and control quality - PMP/CAPM by PMIQuality assurance and control quality - PMP/CAPM by PMI
Quality assurance and control quality - PMP/CAPM by PMI
Mudassir Iqbal
 
Residual risk and secondary risk - PMP/CAPM from PMI
Residual risk and secondary risk - PMP/CAPM from PMIResidual risk and secondary risk - PMP/CAPM from PMI
Residual risk and secondary risk - PMP/CAPM from PMI
Mudassir Iqbal
 
Free float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMIFree float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMI
Mudassir Iqbal
 
Event and Non-Event Risk - PMP/CAPM from PMI
Event and Non-Event Risk  - PMP/CAPM from PMIEvent and Non-Event Risk  - PMP/CAPM from PMI
Event and Non-Event Risk - PMP/CAPM from PMI
Mudassir Iqbal
 
EEF and OPA - PMP/CAPM from PMI
EEF and OPA - PMP/CAPM from PMIEEF and OPA - PMP/CAPM from PMI
EEF and OPA - PMP/CAPM from PMI
Mudassir Iqbal
 
Control account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMIControl account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMI
Mudassir Iqbal
 
Budget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMIBudget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMI
Mudassir Iqbal
 
Project scope Management - PMP/CAPM
Project scope Management - PMP/CAPMProject scope Management - PMP/CAPM
Project scope Management - PMP/CAPM
Mudassir Iqbal
 
Project schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPMProject schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPM
Mudassir Iqbal
 
Project Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPMProject Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPM
Mudassir Iqbal
 
Project procurement Management - PMP/CAPM
Project procurement  Management - PMP/CAPMProject procurement  Management - PMP/CAPM
Project procurement Management - PMP/CAPM
Mudassir Iqbal
 
Closing process group
Closing process groupClosing process group
Closing process group
Mudassir Iqbal
 
Master schedule and milestone schedule
Master schedule and milestone scheduleMaster schedule and milestone schedule
Master schedule and milestone schedule
Mudassir Iqbal
 
Quality and Grade
Quality and GradeQuality and Grade
Quality and Grade
Mudassir Iqbal
 
Cost baseline and cost budget
Cost baseline and cost budgetCost baseline and cost budget
Cost baseline and cost budget
Mudassir Iqbal
 
Babok2 chapter9 daxko
Babok2 chapter9 daxko Babok2 chapter9 daxko
Babok2 chapter9 daxko Mudassir Iqbal
 

More from Mudassir Iqbal (16)

Quality assurance and control quality - PMP/CAPM by PMI
Quality assurance and control quality - PMP/CAPM by PMIQuality assurance and control quality - PMP/CAPM by PMI
Quality assurance and control quality - PMP/CAPM by PMI
 
Residual risk and secondary risk - PMP/CAPM from PMI
Residual risk and secondary risk - PMP/CAPM from PMIResidual risk and secondary risk - PMP/CAPM from PMI
Residual risk and secondary risk - PMP/CAPM from PMI
 
Free float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMIFree float and total float - PMP/CAPM from PMI
Free float and total float - PMP/CAPM from PMI
 
Event and Non-Event Risk - PMP/CAPM from PMI
Event and Non-Event Risk  - PMP/CAPM from PMIEvent and Non-Event Risk  - PMP/CAPM from PMI
Event and Non-Event Risk - PMP/CAPM from PMI
 
EEF and OPA - PMP/CAPM from PMI
EEF and OPA - PMP/CAPM from PMIEEF and OPA - PMP/CAPM from PMI
EEF and OPA - PMP/CAPM from PMI
 
Control account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMIControl account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMI
 
Budget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMIBudget and cost estimates - PMP/CAPM from PMI
Budget and cost estimates - PMP/CAPM from PMI
 
Project scope Management - PMP/CAPM
Project scope Management - PMP/CAPMProject scope Management - PMP/CAPM
Project scope Management - PMP/CAPM
 
Project schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPMProject schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPM
 
Project Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPMProject Cost Management - PMP/CAPM
Project Cost Management - PMP/CAPM
 
Project procurement Management - PMP/CAPM
Project procurement  Management - PMP/CAPMProject procurement  Management - PMP/CAPM
Project procurement Management - PMP/CAPM
 
Closing process group
Closing process groupClosing process group
Closing process group
 
Master schedule and milestone schedule
Master schedule and milestone scheduleMaster schedule and milestone schedule
Master schedule and milestone schedule
 
Quality and Grade
Quality and GradeQuality and Grade
Quality and Grade
 
Cost baseline and cost budget
Cost baseline and cost budgetCost baseline and cost budget
Cost baseline and cost budget
 
Babok2 chapter9 daxko
Babok2 chapter9 daxko Babok2 chapter9 daxko
Babok2 chapter9 daxko
 

Recently uploaded

Enterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdfEnterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdf
KaiNexus
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
Operational Excellence Consulting
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
uae taxgpt
 
Mastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnapMastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnap
Norma Mushkat Gaffin
 
LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024
Lital Barkan
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
Cynthia Clay
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
Bojamma2
 
Authentically Social Presented by Corey Perlman
Authentically Social Presented by Corey PerlmanAuthentically Social Presented by Corey Perlman
Authentically Social Presented by Corey Perlman
Corey Perlman, Social Media Speaker and Consultant
 
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdfModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
fisherameliaisabella
 
Bài tập - Tiếng anh 11 Global Success UNIT 1 - Bản HS.doc
Bài tập - Tiếng anh 11 Global Success UNIT 1 - Bản HS.docBài tập - Tiếng anh 11 Global Success UNIT 1 - Bản HS.doc
Bài tập - Tiếng anh 11 Global Success UNIT 1 - Bản HS.doc
daothibichhang1
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Arihant Webtech Pvt. Ltd
 
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdfikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
agatadrynko
 
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdfikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
agatadrynko
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
creerey
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Lviv Startup Club
 
Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...
Lviv Startup Club
 
Call 7735293663 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...
Call 7735293663 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...Call 7735293663 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...
Call 7735293663 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...
bosssp10
 
Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
HARSHITHV26
 
The key differences between the MDR and IVDR in the EU
The key differences between the MDR and IVDR in the EUThe key differences between the MDR and IVDR in the EU
The key differences between the MDR and IVDR in the EU
Allensmith572606
 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
LR1709MUSIC
 

Recently uploaded (20)

Enterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdfEnterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdf
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
 
Mastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnapMastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnap
 
LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
 
Authentically Social Presented by Corey Perlman
Authentically Social Presented by Corey PerlmanAuthentically Social Presented by Corey Perlman
Authentically Social Presented by Corey Perlman
 
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdfModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
 
Bài tập - Tiếng anh 11 Global Success UNIT 1 - Bản HS.doc
Bài tập - Tiếng anh 11 Global Success UNIT 1 - Bản HS.docBài tập - Tiếng anh 11 Global Success UNIT 1 - Bản HS.doc
Bài tập - Tiếng anh 11 Global Success UNIT 1 - Bản HS.doc
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
 
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdfikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
 
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdfikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
 
Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...
 
Call 7735293663 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...
Call 7735293663 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...Call 7735293663 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...
Call 7735293663 Satta Matka Dpboss Matka Guessing Satta batta Matka 420 Satta...
 
Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
 
The key differences between the MDR and IVDR in the EU
The key differences between the MDR and IVDR in the EUThe key differences between the MDR and IVDR in the EU
The key differences between the MDR and IVDR in the EU
 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
 

Executing process group

  • 1. Executing Process Group – PMP/CAPM (PMBOK 6) The Executing Process Group consists of those processes performed to complete the work defined in the project management plan to satisfy the project requirements. PMBOK6 The processes in Executing Process Group deal with the completion of the work defined in the Project Management Plan which is completed and approved by the stakeholders at the end of the project planning phase. It involves coordinating resources like people, equipment and resources to get the work done efficiently and effectively so that the project keeps delivering the promised objective. The most important output here is Deliverable, which is produced in line with the defined Project Management Plan. This process is where most of the work is carried out, and where products and deliverables are built, assembled, constructed, and created. Behind every successful project is a great team and a good team is a direct result of the good environment which is based on trust and competencies and capabilities rather than anything else. The team has to be acquired, managed and cultivated for performance. Conflicts, they are healthy if solved amicably by using the right conflict resolution method The Executing process group utilizes the most project time and resources, and as a result, costs are usually highest during the Executing process. 10 Process – 31% of Exam Questions: Isn’t this a reason to motivate you to dive quickly in these 10 processes and get 62 questions correct. During the execution process, Changes will also be implemented but only those which are Approved by the management or change control board or by the steering committee. Don’t forget that Deliverables should be quality oriented to make sure here we do the things right i.e quality assurance process.
  • 2. In short, the Executing process involves coordinating people and resources, as well as integrating and performing the activities of the project in accordance with the project plan. The main outputs the project deliverables and producing these will be the responsibility of the project team who will be working to the project plan. Purpose of Executing Process Groups ï‚· Produce the deliverables as per the plan by Coordinating people and resources ï‚· Managing stakeholder expectation ï‚· Integrating and performing the project activities This is the stage where deliverables are created and completed. This frequently refers to the meat of the project because multiple tasks are happeningduringthis period such as status information and conferences, growth updates, and performance reports. Here an important meeting typically marks the beginningof the Project Execution phase where the project management team is informed about theirresponsibilities. Some of the key tasks completed in this phase include develop a team, assign resources, implement project management plans, and procurement management if required. Tasks in Executing Process Groups ï‚· Implement the procurement of project resources ï‚· Execute tasks/project defined in the project management plan ï‚· Implement quality management plan ï‚· Implement approved changes and corrective actions ï‚· Implement Risk Mitigation and Response approved action ï‚· Ensure common understanding and set expectations ï‚· Keep Stakeholders engaged through Communication Processes in Executing Process Groups (10 Processes)
  • 3. 1. Direct and Manage Project Work ⇒ Project Integration Management is the process of using existing knowledge and creating new knowledge to achieve the project’s objectives and contribute to organizational learning 2. Manage Project Knowledge (Project Integration Management) is the process of using existing knowledge and creating new knowledge to achieve the project’s objectives and contribute to organizational learning. 3. Manage Quality ⇒ Project Quality Management is the process of translating the quality management plan into executable quality activities that incorporate the organization’s quality policies into the project. 4. Acquire Resource ⇒ Project Resource Management is the process of obtaining team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work 5. Develop Team (Project Resource Management) is the process of improving competencies, team member interaction, and overall team environment to enhance project performance. 6. Manage Team (Project Resource Management) Manage Team is the process of tracking team member performance, providing feedback, resolving issues, and managing team changes to optimize project performance. 7. Manage Communications ⇒ Project Communication Management is the process of ensuring timely and appropriate collection, creation, distribution, storage, retrieval, management, monitoring, and the ultimate disposition of project information 8. Implement Risk Responses ⇒ Project Risk Management Implement Risk Responses is the process of implementing agreed-upon risk response plans 9. Conduct Procurements ⇒ Project Procurement Management Conduct Procurements is the process of obtaining seller responses, selecting a seller, and awarding a contract. 10. Manage Stakeholder EEngagement ⇒ Project Stakeholder Management Manage Stakeholder Engagement is the process of communicating and working with stakeholders to meet their needs and expectations, address issues, and foster appropriate stakeholder involvement Further Readings
  • 4. ï‚· Project Life Cycle vs Product Life Cycle vs Project Management Phases