SlideShare a Scribd company logo
PROJECT REPORT ON
“ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND
MACADAM ROAD (WBM)’’
This project work is submitted in partial fulfilled the requirement for the award of
diploma in
CIVIL ENGINEERING
BOARD OF TECHNICAL EDUCATION MUMBAI
UNDER THE GUIDANCE OF
MRS. N. A. KRIPAN
(Lecturer in CIVIL ENGG. Dept.)
SUBMITTED BY
HITENDRA PENDAM
TEJAS MANE
HEMANT NEWARE
DEPARTMENT OF CIVIL ENGINEERING
GOVT. POLYTECHNIC, GONDIA
DIST. GONDIA PIN-441601
GOVERNMENT POLYTECHNIC GONDIA
2020-2021
A
PROJECT REPORT ON
“ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND
MACADAM ROAD (WBM)’’
SUBMITTED BY
HITENDRA PENDAM
TEJAS MANE
HEMANT NEWARE
Project Guide H. O. D. Principal
Mrs. N. A. Kripan Mr. C. R. Sahu Dr. C. D. Golghate
DEPARTMENT OF CIVIL ENGINEERING
MAHARASTRA STATE BOARD OF TECHNICAL EDUCATION,
MUMBAI
GOVERNMENT POLYTECHNIC GONDIA
Academic Year 2020-2021
Department of Civil Engineering
CERTIFICATE
This is to certify that the project report on “Estimate the construction procedure of
water-bound macadam road (WBM)’’ submitted by Hitendra Pendam, Tejas Mane, Hemant
Neware, partially fulfilled the requirement for the Diploma in Civil Engineering (CE) to the
Maharashtra State Board of Technical Education, Mumbai. This is their original work done by
them under my supervision and guidance by Lecturer N. A. Kripan and has undergone the
requisite hour of practical prescribed by the university for project work.
To the best of my knowledge, the matter presented in this report has not been submitted
earlier for a similar diploma.
Project Guide H. O. D. Principal
Mrs. N. A. Kripan Mr. C. R. Sahu Dr. C. D. Golghate
Date: -
Place: - Gondia
GOVERNMENT POLYTECHNIC GONDIA
Academic Year 2020-2021
EXAMINER'S CERTIFICATE
This is to certify that the student of final year Civil Engineering of Government Polytechnic
Gondia has completed the project entitled as….
“ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND
MACADAM ROAD (WBM)’’
HITENDRA PENDAM
TEJAS MANE
HEMANT NEWARE
As prescribed by the Maharashtra State Board of Technical Education Mumbai (MSBTE)
as partial fulfillment for the award of civil engineering during the academic year 2020-2021
Signature Project Guide
Internal examiner Mrs. N. A. Kripan
Date: -
DEPARTMENT OF CIVIL ENGINEERING
ACKNOWLEDGMENT
We avail this opportunity to express our deep sense of gratitude and wholehearted
thanks to our guide Mrs. N. A. Kripan for his guidance and encouragement to embark on this
project.
We are thankful to our Head of the Department, Mr. R. Sahu Civil Engineering.
Whole esteem suggestions and encouragement from time to time have always been unparalleled
stimuli for us to travel eventually toward completion of the project.
We are also thankful to our Honorable Principal Dr. C. D. Golghate who inspired
us a lot to achieve the highest goal.
Last but not least we would like to thank all faculty of the civil department and our
friends who helped us directly or indirectly for the success of our project.
PROJECTEES….
HITENDRA PENDAM
TEJAS MANE
HEMANT NEWARE
CONTENTS
1. INTRODUCTION
2. MATERIAL REQUIRED FOR WBM ROAD
3. CONSTRUCTION OF WBM ROAD
4. MAINTENANCE OF WBM ROAD
5. REMEDIES OF DAMAGE WBM ROAD
6. ADVANTAGES AND DISADVANTAGES OF WBM ROAD
7. COST ESTIMATE OF WBM ROAD
8. CONCLUSION
9. REFERENCE
INTRODUCTION
The road has its wearing surface consisting of a clean, crushed aggregate, which is mechanically
rolled, bound together with filler material (screening), and the water laid on the finished base
course is called a WBM Roads.
The wearing surface is shaped by cleaned, crushed aggregates that are spread and rolled by
sprinkling water.
The pavement base course is made of crushed or broken aggregates interlocked by rolling and
voids filled with water-assisted screening and binding materials.
WBM means water-bound macadam, the term macadam is Scottish engineer John L, and the name
came from macadam.
MATERIAL REQUIRED FOR WBM ROAD:
1. COURSE AGGREGATES:
Coarse aggregates that are commonly used in WBM road construction include crushed aggregates
or broken stones. Coarse aggregates for each layer of construction must be accepted as one of three
gradings. Coarse aggregates used in the construction of WBM roads should be
• Durable, Hard.
• Free from flaky and elongated particles
• Acceptable shape.
• IRC has specified the physical requirements of coarse aggregation for WBM road
construction throughout test values of the three pavement layers.
2. SCREENINGS:
Screening materials are usually small-sized aggregates of the same material as the coarse
aggregates.
To reduce the cost of WBM road construction, the IRC recommends the use of non-plastic
materials such as kankar nodules, murum, or gravel.
Such material satisfies the following requirements as follows:
• The liquid limit is less than 20%.
• The plasticity index is less than 6%.
• The portion of fines passing 0.075 mm size sieve is less than 10%.
3. BINDING MATERIAL:
The binding material used for WBM road construction should include an engineer-approved
suitable material with a plasticity index value of less than 6. It may not be necessary when the
screening used is a crushable type, i.e. murum or gravel.
CONSTRUCTION OF WBM ROAD:
1. PREPARATION OF FOUNDATION FOR RECEIVING THE WBM
COURSE:
Subgrade or base courses are prepared for the required grades and camber. Depressions and pot-
holes are filled on the existing road surface. The corrugations are eliminated by scarifying and
reshaping the surface to the required grade and camber as essential. If the WBM road is to be
supplied on the existing surface, the furrows of depth 50 mm and width 50 mm are minimized at
intervals of 1 meter and at the center of the carriageway at 45 degrees earlier than laying the coarse
aggregate.
2. PROVISION OF LATERAL CONFINEMENT:
To provide lateral confinement of the aggregates, a shoulder with a thickness equal to the
compacted WBM layer must be constructed in advance. Good earth or murum can be used in the
construction of shoulders. They are prepared and rolled to maintain the road structure between
them. The practice of building WBM in the bench section excavated in the finished formation
should be completely discouraged.
3. SPREADING OF COURSE AGGREGATES:
Aggregates that are stored along the road are then spread evenly and uniformly on the required
amount of prepared base. The number of layers and the total thickness of the WBM road will
depend on the details of the design of the pavement. For ordinary roads, a layer of compact
thickness 75 mm is sufficient. For critical roads, two layers of equivalent 150 mm compact
thickness may be provided. If a grading number set is used, it is compacted to a thickness of 100
mm.
4. ROLLING:
After the aggregates are dispersed, rolling is carried out for compaction. This can be done with the
help of a three-wheel power roller of 6 to 10 tons capacity or an equivalent vibratory roller. The
rolling process is an efficient operation and depends on the proper completion of the WBM road
surface. The roller should pass evenly over the entire surface and its speed should be slow and
uniform. Rolling should start from the side of the road and carry it up to the crown. Each successive
strip must overlap the preceding strip to avoid the formation of weak points.
The effect of defective rolling as follows:
• There is the formation of corrugations on a road surface.
• There is an unequal finish of the road surface.
• The road starts wearing out very fast at places where the metal is not properly deposited.
On the super-elevated section of the wbm road, rolling starts from the inner or lower edge and
moves slowly towards the outer or upper edges of the pavement.
5. APPLICATION OF SCREENINGS:
• After the compaction of course aggregates, screening is applied to fill the interstices.
• Screening is applied in three or more layers.
• Each layer is compacted by dry rolling.
• Screening has to be spread evenly.
• The rolling and sweeping of each layer of screening must be done carefully.
6. SPRINKLING AND GROUTING:
After the application of screening, the wbm road surface is sprayed with plenty of water. It is then
swept and rolled. Hand sweep is used to clean wet screening in the wedge. Additional screening
is applied and rolled until the coarse aggregates are well bonded and set firmly.
7. APPLICATION OF BINDING MATERIAL:
The bonding material is then applied at a uniform and slow rate in two or more layers. After each
application of binding material, the surface is sprayed with plenty of water. Wet slurry is used to
fill with hand rooms or mechanical rooms. It is then rolled with a 6 to 10-ton roller. During rolling,
water is applied to the wheel of the rollers to wash the binding material that is stocked on the
surface of the roller.
8. SETTING AND DRYING:
The wbm road surface is allowed to cure or set the night after final rolling. If depressions are found
the next day, they are filled with screening or binding material, if necessary, water is sprayed and
the surface is rolled.
9. PREPARATION OF SHOULDER:
During curing, the shoulders are prepared by filling the earth at the specified cross slope. These
are then correctly compacted by rolling or tamping.
10. OPENING TO TRAFFIC:
After drying, the street is opened to traffic. Traffic should be well distributed over the entire width
of the road by placing long obstacles in the form of drums, tree branches, etc. on the road surface.
Maintenance of WBM Road
WBM is the basic stage of the planned improvement of road surfacing. Wbm roads are damaged
rapidly due to heavy traffic and adverse climatic conditions?
The steel-tired bullock carts cause serves wear and tear to the WBM surface. In dry weather, dust
is formed and in the rainy season, mud is formed on WBM road. Fine particles are sucked up by
fast-moving vehicles from the road surface resulting in loss of binding particles in the surface. In
the rainy season, the rain is soaked by the surface which makes the surface soft. In such conditions,
the movement of vehicles makes the layer of the surface lose. In this situation, some aggregate
gets displaced from their position causing ruts and potholes on the surface.
Remedies of Damage WBM Road
To prevent aggregate from getting loose from the surface course, a thin layer of moist soil should
be spread over the surface periodically, particularly after the rainy season. The dust nuisance can
be effectively eliminated by providing a surface dressing of bituminous materials.
ADVANTAGES OF WBM ROAD:
1. The cracks do not form on the surface of bituminous roads.
2. Maintenance costs are low.
3. The surface of these roads is non-slippery.
4. Such roads are waterproof roads.
5. It provides a smooth, durable and comfortable road surface for traffic.
6. Such roads eliminate dust infiltration.
7. It can resist the adverse effects of rain, changes in temperature, and wind.
8. The cost of construction is low.
9. No skilled laborers are required.
10. Made from locally available material.
11. If maintained in good condition, it can carry a traffic load of about 900 tons per lane per
day.
DISADVANTAGES OF WBM ROAD:
1. Maintenance costs are high.
2. Life is short.
3. If the WBM road surface is poorly maintained, it causes inconvenience and hazard to the
traffic.
4. They are permeable to rainwater and leads to softening and yield of subsoil.
5. If the bituminous material exceeds the optimal value for a given mixture, it proves
detrimental to the good performance of the bituminous road.
6. The viscosity of the bitumen aggregate mixture plays an excellent role in determining the
COST ESTIMATE OF WBM ROAD
▪ Assume, the cost of construction will be measured for a water bound macadam road having
length one kilometer and width 3.5 meters. The road contains 20 cm base of 10 to 20 cm.
The road contains 20 cm base supported with 10 to 20 cm size stone boulders as well as 10
cm dense road metal of 1.5 to 3 cm size crushed stone.
1. ABSTRACT OF QUANTITIES?
SOLUTION: -
2. ABSTRACT OF COST?
SOLUTION: -
CONCLUSION:
As the population is increasing day-to-day, we have to enhance our roads for higher
effectiveness in transportation. The wbm road constructed by keeping in mind the future aspects
to full fill the requirements of road users.
REFERENCE
• www.engineer.com
• www.wikipedia.com
• www.slideshare.in

More Related Content

What's hot

Design flexible and rigid pavements
Design flexible and rigid pavementsDesign flexible and rigid pavements
DIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITS
DIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITSDIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITS
DIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITS
Asaru Champ
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
pjainrahul
 
Well foundations notes
 Well foundations notes Well foundations notes
Well foundations notes
PRASANTHI PETLURU
 
Coffer dam and its type
Coffer dam and its typeCoffer dam and its type
Coffer dam and its type
Gaurang Kakadiya
 
Dense Bituminous macadam
Dense Bituminous macadamDense Bituminous macadam
Dense Bituminous macadam
pradip dangar
 
Caissons
Caissons Caissons
Roads design as per IRC 37
Roads design as per IRC 37Roads design as per IRC 37
Roads design as per IRC 37
Amardeep Singh
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniques
jamali husain
 
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
VATSAL PATEL
 
Well foundation
Well foundationWell foundation
ppt foundation.pptx
ppt foundation.pptxppt foundation.pptx
ppt foundation.pptx
AnshuBarmase
 
Determining equivalent single wheel load.(ESWL)
Determining equivalent single wheel load.(ESWL) Determining equivalent single wheel load.(ESWL)
Determining equivalent single wheel load.(ESWL)
Imran Nawaz
 
Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavementsHARITSEHRAWAT
 
Railway Engineering: Turnouts
Railway Engineering: TurnoutsRailway Engineering: Turnouts
Railway Engineering: Turnouts
Vijai Krishnan V
 
Field control of compaction and compaction Equipment
Field control of compaction and compaction EquipmentField control of compaction and compaction Equipment
Field control of compaction and compaction Equipment
aishgup
 
Canal Fall
Canal FallCanal Fall
Canal Fall
GAURAV. H .TANDON
 
Well foundations
Well foundationsWell foundations
Well foundations
ganesh6561
 
Pile foundation ppt
Pile foundation pptPile foundation ppt
Pile foundation ppt
Surat Construction PVT LTD
 
2.7 BRIDGE LAUNCHING.ppt
2.7 BRIDGE LAUNCHING.ppt2.7 BRIDGE LAUNCHING.ppt
2.7 BRIDGE LAUNCHING.ppt
PrasannaRaniB
 

What's hot (20)

Design flexible and rigid pavements
Design flexible and rigid pavementsDesign flexible and rigid pavements
Design flexible and rigid pavements
 
DIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITS
DIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITSDIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITS
DIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITS
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
 
Well foundations notes
 Well foundations notes Well foundations notes
Well foundations notes
 
Coffer dam and its type
Coffer dam and its typeCoffer dam and its type
Coffer dam and its type
 
Dense Bituminous macadam
Dense Bituminous macadamDense Bituminous macadam
Dense Bituminous macadam
 
Caissons
Caissons Caissons
Caissons
 
Roads design as per IRC 37
Roads design as per IRC 37Roads design as per IRC 37
Roads design as per IRC 37
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniques
 
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
 
Well foundation
Well foundationWell foundation
Well foundation
 
ppt foundation.pptx
ppt foundation.pptxppt foundation.pptx
ppt foundation.pptx
 
Determining equivalent single wheel load.(ESWL)
Determining equivalent single wheel load.(ESWL) Determining equivalent single wheel load.(ESWL)
Determining equivalent single wheel load.(ESWL)
 
Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavements
 
Railway Engineering: Turnouts
Railway Engineering: TurnoutsRailway Engineering: Turnouts
Railway Engineering: Turnouts
 
Field control of compaction and compaction Equipment
Field control of compaction and compaction EquipmentField control of compaction and compaction Equipment
Field control of compaction and compaction Equipment
 
Canal Fall
Canal FallCanal Fall
Canal Fall
 
Well foundations
Well foundationsWell foundations
Well foundations
 
Pile foundation ppt
Pile foundation pptPile foundation ppt
Pile foundation ppt
 
2.7 BRIDGE LAUNCHING.ppt
2.7 BRIDGE LAUNCHING.ppt2.7 BRIDGE LAUNCHING.ppt
2.7 BRIDGE LAUNCHING.ppt
 

Similar to ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD

ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdfROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
DanielWisman1
 
MD NEHAL 8TH SEM PPT- 2pptx.pptx
MD NEHAL 8TH SEM PPT- 2pptx.pptxMD NEHAL 8TH SEM PPT- 2pptx.pptx
MD NEHAL 8TH SEM PPT- 2pptx.pptx
nehal103998
 
Road bridge & railway construction pdf
Road bridge & railway construction pdfRoad bridge & railway construction pdf
Road bridge & railway construction pdf
Saqib Imran
 
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
hitendra pendam
 
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURESProject:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Malay Talaviya
 
CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROAD
GLA University
 
RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)
Anil Gupta
 
Industrial training abhi edited.pdf
Industrial training abhi edited.pdfIndustrial training abhi edited.pdf
Industrial training abhi edited.pdf
Abhi858562
 
Construction of Water Bound Macadam (WBM) roads
Construction of Water Bound Macadam (WBM) roadsConstruction of Water Bound Macadam (WBM) roads
Construction of Water Bound Macadam (WBM) roads
ssuserdcb186
 
1 transportation engineering i-bce5012
1 transportation engineering i-bce50121 transportation engineering i-bce5012
1 transportation engineering i-bce5012
SRMUBarabanki
 
Anshuman.pptx
Anshuman.pptxAnshuman.pptx
Anshuman.pptx
Devanshumangal1
 
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxCONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
JaySinghchib1
 
summertraining-1809301ajskelasfkj61205.pptx
summertraining-1809301ajskelasfkj61205.pptxsummertraining-1809301ajskelasfkj61205.pptx
summertraining-1809301ajskelasfkj61205.pptx
Rajni769849
 
123 VIKASH.pptx
123 VIKASH.pptx123 VIKASH.pptx
123 VIKASH.pptx
Rajni769849
 
final ppt.pptx
final ppt.pptxfinal ppt.pptx
final ppt.pptx
DigambarShete
 
Roadconstructionequipment pptx2-130310150329-phpapp01 - copy (2)
Roadconstructionequipment pptx2-130310150329-phpapp01 - copy (2)Roadconstructionequipment pptx2-130310150329-phpapp01 - copy (2)
Roadconstructionequipment pptx2-130310150329-phpapp01 - copy (2)
Purna Mallick
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
pradip dangar
 
Construction of rigid pavement
Construction of rigid pavement Construction of rigid pavement
Construction of rigid pavement
chiranjeevulu chinthala
 
ppt on pwd cement concrete road pavement
ppt on pwd cement concrete road pavementppt on pwd cement concrete road pavement
ppt on pwd cement concrete road pavement
NIWASHISH VISWAS
 

Similar to ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD (20)

ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdfROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
 
MD NEHAL 8TH SEM PPT- 2pptx.pptx
MD NEHAL 8TH SEM PPT- 2pptx.pptxMD NEHAL 8TH SEM PPT- 2pptx.pptx
MD NEHAL 8TH SEM PPT- 2pptx.pptx
 
Road bridge & railway construction pdf
Road bridge & railway construction pdfRoad bridge & railway construction pdf
Road bridge & railway construction pdf
 
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
 
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURESProject:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
 
CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROAD
 
RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)
 
Industrial training abhi edited.pdf
Industrial training abhi edited.pdfIndustrial training abhi edited.pdf
Industrial training abhi edited.pdf
 
Construction of Water Bound Macadam (WBM) roads
Construction of Water Bound Macadam (WBM) roadsConstruction of Water Bound Macadam (WBM) roads
Construction of Water Bound Macadam (WBM) roads
 
1 transportation engineering i-bce5012
1 transportation engineering i-bce50121 transportation engineering i-bce5012
1 transportation engineering i-bce5012
 
AVNEET TRAINING
AVNEET TRAININGAVNEET TRAINING
AVNEET TRAINING
 
Anshuman.pptx
Anshuman.pptxAnshuman.pptx
Anshuman.pptx
 
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxCONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 
summertraining-1809301ajskelasfkj61205.pptx
summertraining-1809301ajskelasfkj61205.pptxsummertraining-1809301ajskelasfkj61205.pptx
summertraining-1809301ajskelasfkj61205.pptx
 
123 VIKASH.pptx
123 VIKASH.pptx123 VIKASH.pptx
123 VIKASH.pptx
 
final ppt.pptx
final ppt.pptxfinal ppt.pptx
final ppt.pptx
 
Roadconstructionequipment pptx2-130310150329-phpapp01 - copy (2)
Roadconstructionequipment pptx2-130310150329-phpapp01 - copy (2)Roadconstructionequipment pptx2-130310150329-phpapp01 - copy (2)
Roadconstructionequipment pptx2-130310150329-phpapp01 - copy (2)
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
 
Construction of rigid pavement
Construction of rigid pavement Construction of rigid pavement
Construction of rigid pavement
 
ppt on pwd cement concrete road pavement
ppt on pwd cement concrete road pavementppt on pwd cement concrete road pavement
ppt on pwd cement concrete road pavement
 

Recently uploaded

block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 

Recently uploaded (20)

block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 

ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD

  • 1. PROJECT REPORT ON “ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD (WBM)’’ This project work is submitted in partial fulfilled the requirement for the award of diploma in CIVIL ENGINEERING BOARD OF TECHNICAL EDUCATION MUMBAI UNDER THE GUIDANCE OF MRS. N. A. KRIPAN (Lecturer in CIVIL ENGG. Dept.) SUBMITTED BY HITENDRA PENDAM TEJAS MANE HEMANT NEWARE DEPARTMENT OF CIVIL ENGINEERING GOVT. POLYTECHNIC, GONDIA DIST. GONDIA PIN-441601
  • 2. GOVERNMENT POLYTECHNIC GONDIA 2020-2021 A PROJECT REPORT ON “ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD (WBM)’’ SUBMITTED BY HITENDRA PENDAM TEJAS MANE HEMANT NEWARE Project Guide H. O. D. Principal Mrs. N. A. Kripan Mr. C. R. Sahu Dr. C. D. Golghate DEPARTMENT OF CIVIL ENGINEERING
  • 3. MAHARASTRA STATE BOARD OF TECHNICAL EDUCATION, MUMBAI GOVERNMENT POLYTECHNIC GONDIA Academic Year 2020-2021 Department of Civil Engineering CERTIFICATE This is to certify that the project report on “Estimate the construction procedure of water-bound macadam road (WBM)’’ submitted by Hitendra Pendam, Tejas Mane, Hemant Neware, partially fulfilled the requirement for the Diploma in Civil Engineering (CE) to the Maharashtra State Board of Technical Education, Mumbai. This is their original work done by them under my supervision and guidance by Lecturer N. A. Kripan and has undergone the requisite hour of practical prescribed by the university for project work. To the best of my knowledge, the matter presented in this report has not been submitted earlier for a similar diploma. Project Guide H. O. D. Principal Mrs. N. A. Kripan Mr. C. R. Sahu Dr. C. D. Golghate Date: - Place: - Gondia
  • 4. GOVERNMENT POLYTECHNIC GONDIA Academic Year 2020-2021 EXAMINER'S CERTIFICATE This is to certify that the student of final year Civil Engineering of Government Polytechnic Gondia has completed the project entitled as…. “ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD (WBM)’’ HITENDRA PENDAM TEJAS MANE HEMANT NEWARE As prescribed by the Maharashtra State Board of Technical Education Mumbai (MSBTE) as partial fulfillment for the award of civil engineering during the academic year 2020-2021 Signature Project Guide Internal examiner Mrs. N. A. Kripan Date: -
  • 5. DEPARTMENT OF CIVIL ENGINEERING ACKNOWLEDGMENT We avail this opportunity to express our deep sense of gratitude and wholehearted thanks to our guide Mrs. N. A. Kripan for his guidance and encouragement to embark on this project. We are thankful to our Head of the Department, Mr. R. Sahu Civil Engineering. Whole esteem suggestions and encouragement from time to time have always been unparalleled stimuli for us to travel eventually toward completion of the project. We are also thankful to our Honorable Principal Dr. C. D. Golghate who inspired us a lot to achieve the highest goal. Last but not least we would like to thank all faculty of the civil department and our friends who helped us directly or indirectly for the success of our project. PROJECTEES…. HITENDRA PENDAM TEJAS MANE HEMANT NEWARE
  • 6. CONTENTS 1. INTRODUCTION 2. MATERIAL REQUIRED FOR WBM ROAD 3. CONSTRUCTION OF WBM ROAD 4. MAINTENANCE OF WBM ROAD 5. REMEDIES OF DAMAGE WBM ROAD 6. ADVANTAGES AND DISADVANTAGES OF WBM ROAD 7. COST ESTIMATE OF WBM ROAD 8. CONCLUSION 9. REFERENCE
  • 7. INTRODUCTION The road has its wearing surface consisting of a clean, crushed aggregate, which is mechanically rolled, bound together with filler material (screening), and the water laid on the finished base course is called a WBM Roads. The wearing surface is shaped by cleaned, crushed aggregates that are spread and rolled by sprinkling water. The pavement base course is made of crushed or broken aggregates interlocked by rolling and voids filled with water-assisted screening and binding materials. WBM means water-bound macadam, the term macadam is Scottish engineer John L, and the name came from macadam.
  • 8. MATERIAL REQUIRED FOR WBM ROAD: 1. COURSE AGGREGATES: Coarse aggregates that are commonly used in WBM road construction include crushed aggregates or broken stones. Coarse aggregates for each layer of construction must be accepted as one of three gradings. Coarse aggregates used in the construction of WBM roads should be • Durable, Hard. • Free from flaky and elongated particles • Acceptable shape. • IRC has specified the physical requirements of coarse aggregation for WBM road construction throughout test values of the three pavement layers. 2. SCREENINGS: Screening materials are usually small-sized aggregates of the same material as the coarse aggregates. To reduce the cost of WBM road construction, the IRC recommends the use of non-plastic materials such as kankar nodules, murum, or gravel.
  • 9. Such material satisfies the following requirements as follows: • The liquid limit is less than 20%. • The plasticity index is less than 6%. • The portion of fines passing 0.075 mm size sieve is less than 10%. 3. BINDING MATERIAL: The binding material used for WBM road construction should include an engineer-approved suitable material with a plasticity index value of less than 6. It may not be necessary when the screening used is a crushable type, i.e. murum or gravel. CONSTRUCTION OF WBM ROAD: 1. PREPARATION OF FOUNDATION FOR RECEIVING THE WBM COURSE: Subgrade or base courses are prepared for the required grades and camber. Depressions and pot- holes are filled on the existing road surface. The corrugations are eliminated by scarifying and reshaping the surface to the required grade and camber as essential. If the WBM road is to be supplied on the existing surface, the furrows of depth 50 mm and width 50 mm are minimized at intervals of 1 meter and at the center of the carriageway at 45 degrees earlier than laying the coarse aggregate.
  • 10. 2. PROVISION OF LATERAL CONFINEMENT: To provide lateral confinement of the aggregates, a shoulder with a thickness equal to the compacted WBM layer must be constructed in advance. Good earth or murum can be used in the construction of shoulders. They are prepared and rolled to maintain the road structure between them. The practice of building WBM in the bench section excavated in the finished formation should be completely discouraged. 3. SPREADING OF COURSE AGGREGATES: Aggregates that are stored along the road are then spread evenly and uniformly on the required amount of prepared base. The number of layers and the total thickness of the WBM road will depend on the details of the design of the pavement. For ordinary roads, a layer of compact thickness 75 mm is sufficient. For critical roads, two layers of equivalent 150 mm compact thickness may be provided. If a grading number set is used, it is compacted to a thickness of 100 mm.
  • 11. 4. ROLLING: After the aggregates are dispersed, rolling is carried out for compaction. This can be done with the help of a three-wheel power roller of 6 to 10 tons capacity or an equivalent vibratory roller. The rolling process is an efficient operation and depends on the proper completion of the WBM road surface. The roller should pass evenly over the entire surface and its speed should be slow and uniform. Rolling should start from the side of the road and carry it up to the crown. Each successive strip must overlap the preceding strip to avoid the formation of weak points.
  • 12. The effect of defective rolling as follows: • There is the formation of corrugations on a road surface. • There is an unequal finish of the road surface. • The road starts wearing out very fast at places where the metal is not properly deposited. On the super-elevated section of the wbm road, rolling starts from the inner or lower edge and moves slowly towards the outer or upper edges of the pavement. 5. APPLICATION OF SCREENINGS: • After the compaction of course aggregates, screening is applied to fill the interstices. • Screening is applied in three or more layers. • Each layer is compacted by dry rolling. • Screening has to be spread evenly. • The rolling and sweeping of each layer of screening must be done carefully.
  • 13. 6. SPRINKLING AND GROUTING: After the application of screening, the wbm road surface is sprayed with plenty of water. It is then swept and rolled. Hand sweep is used to clean wet screening in the wedge. Additional screening is applied and rolled until the coarse aggregates are well bonded and set firmly. 7. APPLICATION OF BINDING MATERIAL: The bonding material is then applied at a uniform and slow rate in two or more layers. After each application of binding material, the surface is sprayed with plenty of water. Wet slurry is used to fill with hand rooms or mechanical rooms. It is then rolled with a 6 to 10-ton roller. During rolling, water is applied to the wheel of the rollers to wash the binding material that is stocked on the surface of the roller. 8. SETTING AND DRYING: The wbm road surface is allowed to cure or set the night after final rolling. If depressions are found the next day, they are filled with screening or binding material, if necessary, water is sprayed and the surface is rolled. 9. PREPARATION OF SHOULDER: During curing, the shoulders are prepared by filling the earth at the specified cross slope. These are then correctly compacted by rolling or tamping. 10. OPENING TO TRAFFIC: After drying, the street is opened to traffic. Traffic should be well distributed over the entire width of the road by placing long obstacles in the form of drums, tree branches, etc. on the road surface.
  • 14. Maintenance of WBM Road WBM is the basic stage of the planned improvement of road surfacing. Wbm roads are damaged rapidly due to heavy traffic and adverse climatic conditions? The steel-tired bullock carts cause serves wear and tear to the WBM surface. In dry weather, dust is formed and in the rainy season, mud is formed on WBM road. Fine particles are sucked up by fast-moving vehicles from the road surface resulting in loss of binding particles in the surface. In the rainy season, the rain is soaked by the surface which makes the surface soft. In such conditions, the movement of vehicles makes the layer of the surface lose. In this situation, some aggregate gets displaced from their position causing ruts and potholes on the surface. Remedies of Damage WBM Road To prevent aggregate from getting loose from the surface course, a thin layer of moist soil should be spread over the surface periodically, particularly after the rainy season. The dust nuisance can be effectively eliminated by providing a surface dressing of bituminous materials.
  • 15. ADVANTAGES OF WBM ROAD: 1. The cracks do not form on the surface of bituminous roads. 2. Maintenance costs are low. 3. The surface of these roads is non-slippery. 4. Such roads are waterproof roads. 5. It provides a smooth, durable and comfortable road surface for traffic. 6. Such roads eliminate dust infiltration. 7. It can resist the adverse effects of rain, changes in temperature, and wind. 8. The cost of construction is low. 9. No skilled laborers are required. 10. Made from locally available material. 11. If maintained in good condition, it can carry a traffic load of about 900 tons per lane per day. DISADVANTAGES OF WBM ROAD: 1. Maintenance costs are high. 2. Life is short. 3. If the WBM road surface is poorly maintained, it causes inconvenience and hazard to the traffic. 4. They are permeable to rainwater and leads to softening and yield of subsoil. 5. If the bituminous material exceeds the optimal value for a given mixture, it proves detrimental to the good performance of the bituminous road. 6. The viscosity of the bitumen aggregate mixture plays an excellent role in determining the
  • 16. COST ESTIMATE OF WBM ROAD ▪ Assume, the cost of construction will be measured for a water bound macadam road having length one kilometer and width 3.5 meters. The road contains 20 cm base of 10 to 20 cm. The road contains 20 cm base supported with 10 to 20 cm size stone boulders as well as 10 cm dense road metal of 1.5 to 3 cm size crushed stone. 1. ABSTRACT OF QUANTITIES?
  • 18. 2. ABSTRACT OF COST?
  • 20. CONCLUSION: As the population is increasing day-to-day, we have to enhance our roads for higher effectiveness in transportation. The wbm road constructed by keeping in mind the future aspects to full fill the requirements of road users.