SlideShare a Scribd company logo
Description Unit
Earthwork, Stone/Brick Work, Wood Work/Sunshadem3
Surface/Shallow Excavation m2
Pointing, Soling, DPC, Plastering m2
Steel/Iron Work kg/Quintel
Dressing of stone/Half Brick wall/partition wall m2
Painting Work/Distemper/Colour Washing/Jali Workm2
Degree ofAccuracy:WoodWork: 2mm,Weight – 1 kg, length
– 1 cm,Area – 0.01 m2
, Volume – 0.01 m3
 Purpose of Valuation
(a) Taxation– (10–14%)
(b) Rent fixation – (6 –10% of total value)
Outgoing: (a) Repairness – (10 – 15)% of total Income
(b) Management and collection Charge – (5 – 10)% of total
Income.
Scrap Value: It is about 10% of total value. It is the value of
Dismental Material.
Salvage Value: It is value at the end of Utility period without
being this dismental.
Sinking Fund:Annual Installment (I) = C
n
S.i.
I .S
(1 i) 1

 
(a) Straight line Method: Assume depreciation by same
amount D=
C S
n

(b) Constant percentage Method: Also called Balancing
Decline Method. It assume depreciation by same
percentage. D =
1/ n
S
1
C
 
 
 
General Overhead Cost Job Overhead Cost
Telephone Bill Salary Delay
Travelling charges Establishment of a New Office
Printing, Post office Compensation
Description Quantity
Work in foundation with Mud Mortar 1.5 m3
Work in foundation with Lime/Cement Mortar 1.25 m2
Work in Superstructure with Lime/Cement Mortar1 m3
Work in Superstructure mud Mortar 1.25 m3
Distemper (1 coat) 35 m2
White Washing/Colour Washing (3 Coat) 70 m2
White Washing/Colour Washing (1 Coat) 200 m2
RCC Work 3m3
Half Brick wall/Partition Wall 5 m2
Lime concrete in Roof 6 m3
Lime Concrete in foundation/Floring 8.5 m3
12 mm Plastering with cement/Lime Mortar 8 m2
Degree of Accuracy (descreasing order)
Detailed > Cube rate > Plinth area > Rough estimate
Area
Plinth area Floor area
Circulation area Carpet area
Vertical circulation area
Horizontal circulation area
(Staircase, Lift) (Varandaha, Passes)
4-5% of P.A. 10-15% of P.A.
 F.A. = Plinth area – area occupiedby walls/Intermediate sup-
ports
 Courtyard, play ground, unclosed Balcony, cantilever porch
is not included in plinth area.
 CarpetArea:Useable area/Living area
 C.A. =Totalfloorarea – (circulation area + Non-useablearea)
 C.A. in residential area (50 – 65)% and in commercial area
(60 – 75)%.
Work % of Estimate
Departmental charges (centage charge) (10 – 15)
Contractor charge 10
Labour Charge 25
Electrification 8
Electric fan 4
Saniatory and Water Supply Charge 8
Contigences Charges (3 – 5)
Work Charge Establishment (1.5 – 2)
Tools and Plants (1 – 1.5)
Security money is about 10% of total contract including Earnest
Money.
Security money and Earnest Money are refundable after some
time Without Any Interest.
 Types of Contract: Lumsum, unit price, cost plus contract.
 TypesofTrap:P,Q, S(Shape), Intercepting,Gully,Floor(Pur-
pose)
 Chief Engineer is theAdministrative Head of Department &
Directly responsible to the govt.
 Plastering Work:
(a) Volume is increased by 30% (if thickness 12 mm ) &
20% (if thickness 20 mm) due to uneven surface.
(b) Above calculated vol. is increased by 25% for dry vol.
calculation.
 Flooring Work:
(a) Volume is increased by 10% due to uneven surface.
(b) Above calculated vol. is increased by 50% for dry vol.
calculation.
 Cement Concrete Work: In C.C. mixture, we divide 1.52 by
sum of ratio of material and multiply it with respective
quantity ratio which will give yourespective quantity.
 Brick Work:
(a) Volume is increased by 15% due to frog filling, bonding/
jointing, wastage etc.
(b) Above calculated vol. is increased by 25% for dry vol.
calculation.
Event: It is an instant of time at which some specific milestone
has been achieved. It denotes the start or completion of an activity,
& it is represented by nodes of different shapes like rectangular,
circular, square or oval. An event does not consumes any time or
resource.
CIVIL ENGINEERING
ROCKET CHART
FOR QUICK REVISION
BY
S.SOROUT: 9255624029
Dummy Activity: It is an artificial activity represented by
dashed arrows which neither consumes any time nor resources.
Activity G is dummy activity. Dummies maintain the logic of
network diagram & keeps the numbering system of the network
unique.
Slack: It is associated with an event. It is the difference between
the latest allowable occurrence time & earliest expected
occurrence time of the event. It is the excess time by which
occurence of an event can be delayed without affecting the project
completion time.
Types of Slack -
(a) Positive slack ( S >0 ) - Ts
> TE
(b) Zero slack ( S = 0 ) - Ts
= TE
(c) Negative slack ( S < 0 ) - Ts
< TE
( (
(
(
 ij
Activity Name (EST, EFT)
(i) (j)
t x days (LST, LFT)

 Float is associated with An activity.
1. Total Float: It is the difference between maximum time
available & actual time required for the completion of the
activity.
2. Free Float: It is the amount of time by which an activity
can be delayed without affecting the EST of the succeeding
activity
3. Independent Float: It is the excess of minimum available
time over the required activity duration.
4. Interfering Float: It is the difference of total float & free
float of an activity. It is also equal to the slack of head event of
an activity.
Types of float -
(a) Negative total float (FT
< 0 ) - If maximum available time for an
activity is less than the activity time, then total float will be a
negative value. Such activities are called super-critical
activities.They need extra deployment of resources.
(b) Total float zero (FT
= 0 ) - If maximum available time for an
activity is equal to the activity time, then total float will be
zero. Such activities are called critical activities.In them, no
freedom of delay is allowed.
(c) Positive total float (FT
> 0 ) - If maximum available time for an
activity is more than the activity time, then total float will be
a positive value. Such activities are called sub-critical
activities.They demand normal attention but allowing them
some freedom of action.
PERT absorbs uncertainties into the time estimates for activity
& project duration. Following are 3 time estimate -
(a) Optimistic Time Estimate (to
) - It is the minimum time
required for an activity if everything occurs perfectly right without
any problems or adverse conditions developed during completetion
of the activity.
(b) Pessimistic Time Estimate (tp
) - It is the maximum time
required for an activity if everything goes wrong & abnormal
conditions prevail. It does not include possible effects of major
catastrophes like as earthquakes, flood, fire etc.
(c) Most Likely Time Estimate (tm
) - It lie in between pessimistic
& optimistic time estimate. It is time required to complete the
activity if normal conditions prevail.
 Mean time  
x :
1 2 3 n
x x x ...... x
x
n
 
 =
x
n

 Deviation (): x x
  
 Variance :
 2
2
2 x x
n n
 

  
PERT CPM
1.Probabilistic approach 1. Deterministic approach
2.Three time estimate 2. Single time estimate
3.Event oriented 3. Activity oriented.
4.Cost is proportional to time 4. Cost model is developed
5.-distribution 5. Normal distribution
6.Concept of slack 6. Concept of float
7.Critical path by joining 7. Critical path by joining
critical events critical activities.
Crashing: The process of reduction of the total project duration
along the longest path (time wise) of the network (along the critical
path to obtain the optimum project cost & optimum duration.)
Updating : It is the process of reviewing the progress of project,
execution & redrafting the network according to latest
requirements
Cost slope =
c n
n c
C C
t t


Cost
Crash
time
Optimum
time
Normal
time
Overheads
Outage cost
Indirect cost
Direct cost
Total cost
Resource Smoothing: ·In this, the total project duration is not
changed but the activities having float are rescheduled in such a
way that a uniform demand for the resources is achieved. In it, the
resources are considered to be limited & the critical path of the
project remains unchanged.
Resource Levelling: In it, the activities are so rescheduled in such
a way that maximum or peak demand of the resource does not
exceed the availability of resources. In it, the resource are
unlimited & the critical path may get changed (so project
duration may also get changed). Uniform demand of resources
is achieved.
CIVIL BOOSTER - Dnt trust us, Just Check it’s content &
ThenGoforit-(LEAVETHEREST,GETTHEBEST). Available
on amazon flipkart. Zero Error bookwithBEST Content

More Related Content

Similar to ESTIMATE COSTING.pdf

Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
Mr. Ramesh Nayaka
 
Project management
Project managementProject management
Project management
Kwesi Kissiedu
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
Akaresh Jose Kaviyil JY
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
Debanjan15
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gert
Raj J Das
 
Pert, cpm & gert
Pert, cpm & gertPert, cpm & gert
Pert, cpm & gert
Pranav Krishna
 
Ch 06 - CPM PERT (1).pptx
Ch 06 - CPM  PERT (1).pptxCh 06 - CPM  PERT (1).pptx
Ch 06 - CPM PERT (1).pptx
sitinorhafizabintiab1
 
Cpmprt
CpmprtCpmprt
PERT-CPM PPT.pptx
PERT-CPM PPT.pptxPERT-CPM PPT.pptx
PERT-CPM PPT.pptx
DhesinghRajaLekha
 
Chapter-2 Solved examples.ppt
Chapter-2 Solved examples.pptChapter-2 Solved examples.ppt
Chapter-2 Solved examples.ppt
BetshaTizazu2
 
PERT.pptx
PERT.pptxPERT.pptx
PERT.pptx
Snehal Athawale
 
Operation research's CPM techniques
Operation research's CPM techniques Operation research's CPM techniques
Operation research's CPM techniques
Mohammad Younus
 
construction resource optimization 1.pptx
construction resource optimization 1.pptxconstruction resource optimization 1.pptx
construction resource optimization 1.pptx
kimkov119
 
Critical path method
Critical path methodCritical path method
Critical path method
Dushyant Nasit
 
criticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfcriticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdf
Salahudin Babar
 
Program Evaluation and Review Technique
Program Evaluation and Review TechniqueProgram Evaluation and Review Technique
Program Evaluation and Review Technique
Raymund Sanchez
 
Pert Analysis
Pert AnalysisPert Analysis
Pert Analysis
Kaizer Dave
 
P E R T
P E R TP E R T
P E R T
Vikas Verma
 
Construction Management
Construction ManagementConstruction Management
Construction Management
BENTHOMASOOMMEN
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
SimranGrewal33
 

Similar to ESTIMATE COSTING.pdf (20)

Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Project management
Project managementProject management
Project management
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gert
 
Pert, cpm & gert
Pert, cpm & gertPert, cpm & gert
Pert, cpm & gert
 
Ch 06 - CPM PERT (1).pptx
Ch 06 - CPM  PERT (1).pptxCh 06 - CPM  PERT (1).pptx
Ch 06 - CPM PERT (1).pptx
 
Cpmprt
CpmprtCpmprt
Cpmprt
 
PERT-CPM PPT.pptx
PERT-CPM PPT.pptxPERT-CPM PPT.pptx
PERT-CPM PPT.pptx
 
Chapter-2 Solved examples.ppt
Chapter-2 Solved examples.pptChapter-2 Solved examples.ppt
Chapter-2 Solved examples.ppt
 
PERT.pptx
PERT.pptxPERT.pptx
PERT.pptx
 
Operation research's CPM techniques
Operation research's CPM techniques Operation research's CPM techniques
Operation research's CPM techniques
 
construction resource optimization 1.pptx
construction resource optimization 1.pptxconstruction resource optimization 1.pptx
construction resource optimization 1.pptx
 
Critical path method
Critical path methodCritical path method
Critical path method
 
criticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfcriticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdf
 
Program Evaluation and Review Technique
Program Evaluation and Review TechniqueProgram Evaluation and Review Technique
Program Evaluation and Review Technique
 
Pert Analysis
Pert AnalysisPert Analysis
Pert Analysis
 
P E R T
P E R TP E R T
P E R T
 
Construction Management
Construction ManagementConstruction Management
Construction Management
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
 

Recently uploaded

Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
Exception Handling notes in java exception
Exception Handling notes in java exceptionException Handling notes in java exception
Exception Handling notes in java exception
Ratnakar Mikkili
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
awadeshbabu
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
PauloRodrigues104553
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
JamalHussainArman
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
ssuser36d3051
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
Mukeshwaran Balu
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
nooriasukmaningtyas
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
mamunhossenbd75
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 

Recently uploaded (20)

Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
Exception Handling notes in java exception
Exception Handling notes in java exceptionException Handling notes in java exception
Exception Handling notes in java exception
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 

ESTIMATE COSTING.pdf

  • 1. Description Unit Earthwork, Stone/Brick Work, Wood Work/Sunshadem3 Surface/Shallow Excavation m2 Pointing, Soling, DPC, Plastering m2 Steel/Iron Work kg/Quintel Dressing of stone/Half Brick wall/partition wall m2 Painting Work/Distemper/Colour Washing/Jali Workm2 Degree ofAccuracy:WoodWork: 2mm,Weight – 1 kg, length – 1 cm,Area – 0.01 m2 , Volume – 0.01 m3  Purpose of Valuation (a) Taxation– (10–14%) (b) Rent fixation – (6 –10% of total value) Outgoing: (a) Repairness – (10 – 15)% of total Income (b) Management and collection Charge – (5 – 10)% of total Income. Scrap Value: It is about 10% of total value. It is the value of Dismental Material. Salvage Value: It is value at the end of Utility period without being this dismental. Sinking Fund:Annual Installment (I) = C n S.i. I .S (1 i) 1    (a) Straight line Method: Assume depreciation by same amount D= C S n  (b) Constant percentage Method: Also called Balancing Decline Method. It assume depreciation by same percentage. D = 1/ n S 1 C       General Overhead Cost Job Overhead Cost Telephone Bill Salary Delay Travelling charges Establishment of a New Office Printing, Post office Compensation Description Quantity Work in foundation with Mud Mortar 1.5 m3 Work in foundation with Lime/Cement Mortar 1.25 m2 Work in Superstructure with Lime/Cement Mortar1 m3 Work in Superstructure mud Mortar 1.25 m3 Distemper (1 coat) 35 m2 White Washing/Colour Washing (3 Coat) 70 m2 White Washing/Colour Washing (1 Coat) 200 m2 RCC Work 3m3 Half Brick wall/Partition Wall 5 m2 Lime concrete in Roof 6 m3 Lime Concrete in foundation/Floring 8.5 m3 12 mm Plastering with cement/Lime Mortar 8 m2 Degree of Accuracy (descreasing order) Detailed > Cube rate > Plinth area > Rough estimate Area Plinth area Floor area Circulation area Carpet area Vertical circulation area Horizontal circulation area (Staircase, Lift) (Varandaha, Passes) 4-5% of P.A. 10-15% of P.A.  F.A. = Plinth area – area occupiedby walls/Intermediate sup- ports  Courtyard, play ground, unclosed Balcony, cantilever porch is not included in plinth area.  CarpetArea:Useable area/Living area  C.A. =Totalfloorarea – (circulation area + Non-useablearea)  C.A. in residential area (50 – 65)% and in commercial area (60 – 75)%. Work % of Estimate Departmental charges (centage charge) (10 – 15) Contractor charge 10 Labour Charge 25 Electrification 8 Electric fan 4 Saniatory and Water Supply Charge 8 Contigences Charges (3 – 5) Work Charge Establishment (1.5 – 2) Tools and Plants (1 – 1.5) Security money is about 10% of total contract including Earnest Money. Security money and Earnest Money are refundable after some time Without Any Interest.  Types of Contract: Lumsum, unit price, cost plus contract.  TypesofTrap:P,Q, S(Shape), Intercepting,Gully,Floor(Pur- pose)  Chief Engineer is theAdministrative Head of Department & Directly responsible to the govt.  Plastering Work: (a) Volume is increased by 30% (if thickness 12 mm ) & 20% (if thickness 20 mm) due to uneven surface. (b) Above calculated vol. is increased by 25% for dry vol. calculation.  Flooring Work: (a) Volume is increased by 10% due to uneven surface. (b) Above calculated vol. is increased by 50% for dry vol. calculation.  Cement Concrete Work: In C.C. mixture, we divide 1.52 by sum of ratio of material and multiply it with respective quantity ratio which will give yourespective quantity.  Brick Work: (a) Volume is increased by 15% due to frog filling, bonding/ jointing, wastage etc. (b) Above calculated vol. is increased by 25% for dry vol. calculation. Event: It is an instant of time at which some specific milestone has been achieved. It denotes the start or completion of an activity, & it is represented by nodes of different shapes like rectangular, circular, square or oval. An event does not consumes any time or resource. CIVIL ENGINEERING ROCKET CHART FOR QUICK REVISION BY S.SOROUT: 9255624029 Dummy Activity: It is an artificial activity represented by dashed arrows which neither consumes any time nor resources. Activity G is dummy activity. Dummies maintain the logic of network diagram & keeps the numbering system of the network unique. Slack: It is associated with an event. It is the difference between the latest allowable occurrence time & earliest expected occurrence time of the event. It is the excess time by which occurence of an event can be delayed without affecting the project completion time. Types of Slack - (a) Positive slack ( S >0 ) - Ts > TE (b) Zero slack ( S = 0 ) - Ts = TE (c) Negative slack ( S < 0 ) - Ts < TE ( ( ( (  ij Activity Name (EST, EFT) (i) (j) t x days (LST, LFT)   Float is associated with An activity. 1. Total Float: It is the difference between maximum time available & actual time required for the completion of the activity. 2. Free Float: It is the amount of time by which an activity can be delayed without affecting the EST of the succeeding activity 3. Independent Float: It is the excess of minimum available time over the required activity duration. 4. Interfering Float: It is the difference of total float & free float of an activity. It is also equal to the slack of head event of an activity. Types of float - (a) Negative total float (FT < 0 ) - If maximum available time for an activity is less than the activity time, then total float will be a negative value. Such activities are called super-critical activities.They need extra deployment of resources. (b) Total float zero (FT = 0 ) - If maximum available time for an activity is equal to the activity time, then total float will be zero. Such activities are called critical activities.In them, no freedom of delay is allowed. (c) Positive total float (FT > 0 ) - If maximum available time for an activity is more than the activity time, then total float will be a positive value. Such activities are called sub-critical activities.They demand normal attention but allowing them some freedom of action. PERT absorbs uncertainties into the time estimates for activity & project duration. Following are 3 time estimate - (a) Optimistic Time Estimate (to ) - It is the minimum time required for an activity if everything occurs perfectly right without any problems or adverse conditions developed during completetion of the activity. (b) Pessimistic Time Estimate (tp ) - It is the maximum time required for an activity if everything goes wrong & abnormal conditions prevail. It does not include possible effects of major catastrophes like as earthquakes, flood, fire etc. (c) Most Likely Time Estimate (tm ) - It lie in between pessimistic & optimistic time estimate. It is time required to complete the activity if normal conditions prevail.  Mean time   x : 1 2 3 n x x x ...... x x n    = x n   Deviation (): x x     Variance :  2 2 2 x x n n       PERT CPM 1.Probabilistic approach 1. Deterministic approach 2.Three time estimate 2. Single time estimate 3.Event oriented 3. Activity oriented. 4.Cost is proportional to time 4. Cost model is developed 5.-distribution 5. Normal distribution 6.Concept of slack 6. Concept of float 7.Critical path by joining 7. Critical path by joining critical events critical activities. Crashing: The process of reduction of the total project duration along the longest path (time wise) of the network (along the critical path to obtain the optimum project cost & optimum duration.) Updating : It is the process of reviewing the progress of project, execution & redrafting the network according to latest requirements Cost slope = c n n c C C t t   Cost Crash time Optimum time Normal time Overheads Outage cost Indirect cost Direct cost Total cost Resource Smoothing: ·In this, the total project duration is not changed but the activities having float are rescheduled in such a way that a uniform demand for the resources is achieved. In it, the resources are considered to be limited & the critical path of the project remains unchanged. Resource Levelling: In it, the activities are so rescheduled in such a way that maximum or peak demand of the resource does not exceed the availability of resources. In it, the resource are unlimited & the critical path may get changed (so project duration may also get changed). Uniform demand of resources is achieved. CIVIL BOOSTER - Dnt trust us, Just Check it’s content & ThenGoforit-(LEAVETHEREST,GETTHEBEST). Available on amazon flipkart. Zero Error bookwithBEST Content