Closing Unit
1-Shear rams open
Shear Rams operation
2-Shear rams closing
Shear Rams operation
3-Shear rams closed
Shear Rams operation
BOP closing unit ( Koomey unit )
SCHEMATIC FOR CLOSING UNIT
2
1
3
5
6
4
7
8
9
10
11
12
13
14
15
16 17 18
19
20
 Accumulators
 Standard bladder type
Each bottle is called ten gallons bottle
3000 psi
1200 psi
Usable fluid
(Recoverable oil)
N
Oil
Accumulator Bottle
The Precharge pressure is 1000 psi for the 3000 psi working
pressure accumulator unit
Minimum working pressure is 200 psi above precharge pressure
1. Bottles to be able to (with pumps off)
- Close annular
- Close all rams
- Open one HCR
- Remaining pressure shall be at least 200 psi above
precharge pressure (1200 psi ).
2. Useable Fluid: Fluid recoverable between operating
pressure (3000 psi) and minimum operating pressure
(1200 psi) or (200 psi) above pre charge pressure.
Information from the API RP53
3. Reservoir Capacity: At least twice useable fluid of
bottles.
4. Accumulator precharge
A. The precharge pressure should be measured each
well
B. Minimum precharge pressure for 3000 psi working
pressure accumulator should be 1000 psi
C. Only nitrogen gas should be used.
5-Pump Systems
•With accumulators isolated pump should be capable of closing
the annular and open the hydraulic choke (HCR) and return
system to normal annular pressure in 2 minutes.
•Electric pump will automatically start when system pressure has
decreased to 90% of system working pressure.
•A pump system consists of one or more pump each pump should
have independent power source.
7. Pressure Test Frequency
Pressure test on well control equipment should be at least:
1. Prior to spud or upon installation.
2. After disconnection or repair of any component
3. Not to exceed 21 days.
6. Closing time RAM Annular
Smaller than 18 ¾” 30 sec max. 30 sec max.
18 ¾” and larger 30 sec max. 45 sec max.
8. Shell or Body Test at manufacturer Shop
1 ½ times BOP rating I.e. 150% of pressure rating.
9. Closing Ratio
Ratio of well head pressure to pressure required to close the BOP.
10. Choke Lines
1. Minimum recommended size for choke line is 2 inches for 3K and
5K arrangements and 3 inch for 10K and 15K.
2. Minimum recommended inside diameter for lines downstream of
choke should be equal to or greater than the connecting lines of
the choke (choke line).
3. The bleed line should be at least equal in diameter to the choke
line this line allows:
a) Circulation of well with preventors closed while
maintaining a minimum back pressure.
b) Permits high volume bleed off of well fluids to relieve
casing pressure with the preventers close.
Remote control panel
Remote control panel
When the BOP ram in the close position close line has 1500 psi.
When the BOP ram in the open position open line has 1500 psi.
When the 4 way valve shifts the micro switch will activate the light to illuminate.
When light illuminates, it tells us that oil on its way to the BOP function.
Rig air
120 psi
4 Way valve and
micro switch
Oil
Indicator Lights on BOP Remote Panel
A micro switch is located at the main unit, it will send a
signal to the indicator lights to change color only when the
4-way valve shifts.
Indicator lights, don’t tell us that the BOP’s function
has completed, but they tell us that the 4-way valve is
already shifted and the oil is flowing under pressure to
move the functions piston to complete the close or open
operations.
indicator lights Problem
while shutting in a well from remote panel
2.If indicator light does not illuminate and pressure gauges
don’t drop, it means that no oil has been used and BOP
piston does not move, the cause could be
a)4-way valve failed to shift.
b)Master control valve is not depressed
with the control valve of the function.
c)No air pressure is going to the remote panel.
1.If indicator light does not illuminate, but gauges drop
and later rise back up which means that oil has been
used to move the piston of the BOP and the function is
completed so the cause is (BULB has blown).
indicator lights Problem
4.If indicator light illuminates and pressure dropped
but not rise back up it means that oil has been
used, function completed but there is LEAK in
hydraulic system.
5.If indicator light illuminates and pressure dropped
then the manifold pressure raised back up to 1500
psi but accumulates pressure did not raise back up to
3000 psi.
3.If indicator light illuminates but pressure gauges do not
drop it means that the 4-way valves has shifted but
hydraulic line between the 4-way valve and the BOP is
plugged.

More Related Content

Similar to (Equip-3(closing unit).ppt Equip closing unit

bnt68 introduction
bnt68 introductionbnt68 introduction
bnt68 introductionMona Lisa
 
Sop of turbine lubrication oil system
Sop of turbine lubrication oil systemSop of turbine lubrication oil system
Sop of turbine lubrication oil systemAjit Kumar
 
Coluna de Calibração _ Milton Roy
Coluna de Calibração _ Milton RoyColuna de Calibração _ Milton Roy
Coluna de Calibração _ Milton RoyVibropac
 
Microsoft PowerPoint - DEV of Dual Filling
Microsoft PowerPoint - DEV of Dual FillingMicrosoft PowerPoint - DEV of Dual Filling
Microsoft PowerPoint - DEV of Dual FillingPRAN-RFL Group
 
Sunward hydraulic system training-SWL.ppt
Sunward hydraulic system training-SWL.pptSunward hydraulic system training-SWL.ppt
Sunward hydraulic system training-SWL.pptadrianpitis
 
BASIC_Hydraulic.ppt
BASIC_Hydraulic.pptBASIC_Hydraulic.ppt
BASIC_Hydraulic.pptJiaJunWang17
 
Inspection, Testing and Maintenance of fire pump
Inspection, Testing and Maintenance of fire pumpInspection, Testing and Maintenance of fire pump
Inspection, Testing and Maintenance of fire pumpklsmani
 
introduccion a los Inyectores para cromatografía de gases
introduccion a los Inyectores para cromatografía de gasesintroduccion a los Inyectores para cromatografía de gases
introduccion a los Inyectores para cromatografía de gasesLgIrvin
 
49539990 burner-management-system
49539990 burner-management-system49539990 burner-management-system
49539990 burner-management-systemMowaten Masry
 
Operation of Centrifugal Pumps
Operation of Centrifugal PumpsOperation of Centrifugal Pumps
Operation of Centrifugal PumpsSahyog Shishodia
 
BASIC Hydraulic-kapil
BASIC Hydraulic-kapilBASIC Hydraulic-kapil
BASIC Hydraulic-kapilkapil dev
 

Similar to (Equip-3(closing unit).ppt Equip closing unit (20)

bnt68 introduction
bnt68 introductionbnt68 introduction
bnt68 introduction
 
Sop of turbine lubrication oil system
Sop of turbine lubrication oil systemSop of turbine lubrication oil system
Sop of turbine lubrication oil system
 
Coluna de Calibração _ Milton Roy
Coluna de Calibração _ Milton RoyColuna de Calibração _ Milton Roy
Coluna de Calibração _ Milton Roy
 
Microsoft PowerPoint - DEV of Dual Filling
Microsoft PowerPoint - DEV of Dual FillingMicrosoft PowerPoint - DEV of Dual Filling
Microsoft PowerPoint - DEV of Dual Filling
 
MVP-07-T-A.pdf
MVP-07-T-A.pdfMVP-07-T-A.pdf
MVP-07-T-A.pdf
 
Valve type-modi-11
Valve type-modi-11Valve type-modi-11
Valve type-modi-11
 
Valve type-modi-11
Valve type-modi-11Valve type-modi-11
Valve type-modi-11
 
Sunward hydraulic system training-SWL.ppt
Sunward hydraulic system training-SWL.pptSunward hydraulic system training-SWL.ppt
Sunward hydraulic system training-SWL.ppt
 
Testing Fuel Injectors
Testing Fuel Injectors Testing Fuel Injectors
Testing Fuel Injectors
 
CARGO OIL PUMPING SYSTEM.pdf
CARGO OIL PUMPING SYSTEM.pdfCARGO OIL PUMPING SYSTEM.pdf
CARGO OIL PUMPING SYSTEM.pdf
 
CARGO OIL PUMPING SYSTEM.pdf
CARGO OIL PUMPING SYSTEM.pdfCARGO OIL PUMPING SYSTEM.pdf
CARGO OIL PUMPING SYSTEM.pdf
 
BASIC_Hydraulic.ppt
BASIC_Hydraulic.pptBASIC_Hydraulic.ppt
BASIC_Hydraulic.ppt
 
Gas street
Gas streetGas street
Gas street
 
Inspection, Testing and Maintenance of fire pump
Inspection, Testing and Maintenance of fire pumpInspection, Testing and Maintenance of fire pump
Inspection, Testing and Maintenance of fire pump
 
introduccion a los Inyectores para cromatografía de gases
introduccion a los Inyectores para cromatografía de gasesintroduccion a los Inyectores para cromatografía de gases
introduccion a los Inyectores para cromatografía de gases
 
Hplpbp
HplpbpHplpbp
Hplpbp
 
LINSample
LINSampleLINSample
LINSample
 
49539990 burner-management-system
49539990 burner-management-system49539990 burner-management-system
49539990 burner-management-system
 
Operation of Centrifugal Pumps
Operation of Centrifugal PumpsOperation of Centrifugal Pumps
Operation of Centrifugal Pumps
 
BASIC Hydraulic-kapil
BASIC Hydraulic-kapilBASIC Hydraulic-kapil
BASIC Hydraulic-kapil
 

More from MahmoudNassar55

FINAL_EAGE_MUD_ENGINEERING_PPT.pptx MUD_ENGINEERING
FINAL_EAGE_MUD_ENGINEERING_PPT.pptx MUD_ENGINEERINGFINAL_EAGE_MUD_ENGINEERING_PPT.pptx MUD_ENGINEERING
FINAL_EAGE_MUD_ENGINEERING_PPT.pptx MUD_ENGINEERINGMahmoudNassar55
 
Ahmed Farouq safety.pptx safetysafetysafety
Ahmed Farouq safety.pptx safetysafetysafetyAhmed Farouq safety.pptx safetysafetysafety
Ahmed Farouq safety.pptx safetysafetysafetyMahmoudNassar55
 
safety.pptx safety.safety.safety.safety.safety.
safety.pptx safety.safety.safety.safety.safety.safety.pptx safety.safety.safety.safety.safety.
safety.pptx safety.safety.safety.safety.safety.MahmoudNassar55
 
nabih exploration.pptx nabih exploration
nabih exploration.pptx nabih explorationnabih exploration.pptx nabih exploration
nabih exploration.pptx nabih explorationMahmoudNassar55
 
tech-drilling-Abnormal Press..ppt Abnormal Press
tech-drilling-Abnormal Press..ppt Abnormal Presstech-drilling-Abnormal Press..ppt Abnormal Press
tech-drilling-Abnormal Press..ppt Abnormal PressMahmoudNassar55
 
07 Fuel Oil Systems (1).ppt Fuel Oil Systems
07 Fuel Oil Systems (1).ppt Fuel Oil Systems07 Fuel Oil Systems (1).ppt Fuel Oil Systems
07 Fuel Oil Systems (1).ppt Fuel Oil SystemsMahmoudNassar55
 
2 Introd to Drlg Flds.ppt Introd to Drlg Flds.ppt
2 Introd to Drlg Flds.ppt Introd to Drlg Flds.ppt2 Introd to Drlg Flds.ppt Introd to Drlg Flds.ppt
2 Introd to Drlg Flds.ppt Introd to Drlg Flds.pptMahmoudNassar55
 
1-Pakinstan IWBS.PPT Pakinstan IWBS.PPTS
1-Pakinstan IWBS.PPT Pakinstan IWBS.PPTS1-Pakinstan IWBS.PPT Pakinstan IWBS.PPTS
1-Pakinstan IWBS.PPT Pakinstan IWBS.PPTSMahmoudNassar55
 

More from MahmoudNassar55 (9)

FINAL_EAGE_MUD_ENGINEERING_PPT.pptx MUD_ENGINEERING
FINAL_EAGE_MUD_ENGINEERING_PPT.pptx MUD_ENGINEERINGFINAL_EAGE_MUD_ENGINEERING_PPT.pptx MUD_ENGINEERING
FINAL_EAGE_MUD_ENGINEERING_PPT.pptx MUD_ENGINEERING
 
Ahmed Farouq safety.pptx safetysafetysafety
Ahmed Farouq safety.pptx safetysafetysafetyAhmed Farouq safety.pptx safetysafetysafety
Ahmed Farouq safety.pptx safetysafetysafety
 
safety.pptx safety.safety.safety.safety.safety.
safety.pptx safety.safety.safety.safety.safety.safety.pptx safety.safety.safety.safety.safety.
safety.pptx safety.safety.safety.safety.safety.
 
nabih exploration.pptx nabih exploration
nabih exploration.pptx nabih explorationnabih exploration.pptx nabih exploration
nabih exploration.pptx nabih exploration
 
tech-drilling-Abnormal Press..ppt Abnormal Press
tech-drilling-Abnormal Press..ppt Abnormal Presstech-drilling-Abnormal Press..ppt Abnormal Press
tech-drilling-Abnormal Press..ppt Abnormal Press
 
07 Fuel Oil Systems (1).ppt Fuel Oil Systems
07 Fuel Oil Systems (1).ppt Fuel Oil Systems07 Fuel Oil Systems (1).ppt Fuel Oil Systems
07 Fuel Oil Systems (1).ppt Fuel Oil Systems
 
2 Introd to Drlg Flds.ppt Introd to Drlg Flds.ppt
2 Introd to Drlg Flds.ppt Introd to Drlg Flds.ppt2 Introd to Drlg Flds.ppt Introd to Drlg Flds.ppt
2 Introd to Drlg Flds.ppt Introd to Drlg Flds.ppt
 
1-Pakinstan IWBS.PPT Pakinstan IWBS.PPTS
1-Pakinstan IWBS.PPT Pakinstan IWBS.PPTS1-Pakinstan IWBS.PPT Pakinstan IWBS.PPTS
1-Pakinstan IWBS.PPT Pakinstan IWBS.PPTS
 
Bit Selection.ppt
Bit Selection.pptBit Selection.ppt
Bit Selection.ppt
 

Recently uploaded

Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...Call Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 

Recently uploaded (20)

Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 

(Equip-3(closing unit).ppt Equip closing unit

  • 3.
  • 4.
  • 5.
  • 6.
  • 7.
  • 8.
  • 9. 1-Shear rams open Shear Rams operation
  • 10. 2-Shear rams closing Shear Rams operation
  • 11. 3-Shear rams closed Shear Rams operation
  • 12.
  • 13.
  • 14.
  • 15.
  • 16.
  • 17.
  • 18. BOP closing unit ( Koomey unit )
  • 19. SCHEMATIC FOR CLOSING UNIT 2 1 3 5 6 4 7 8 9 10 11 12 13 14 15 16 17 18 19 20
  • 21. Each bottle is called ten gallons bottle 3000 psi 1200 psi Usable fluid (Recoverable oil) N Oil Accumulator Bottle The Precharge pressure is 1000 psi for the 3000 psi working pressure accumulator unit Minimum working pressure is 200 psi above precharge pressure
  • 22. 1. Bottles to be able to (with pumps off) - Close annular - Close all rams - Open one HCR - Remaining pressure shall be at least 200 psi above precharge pressure (1200 psi ). 2. Useable Fluid: Fluid recoverable between operating pressure (3000 psi) and minimum operating pressure (1200 psi) or (200 psi) above pre charge pressure. Information from the API RP53
  • 23. 3. Reservoir Capacity: At least twice useable fluid of bottles. 4. Accumulator precharge A. The precharge pressure should be measured each well B. Minimum precharge pressure for 3000 psi working pressure accumulator should be 1000 psi C. Only nitrogen gas should be used.
  • 24. 5-Pump Systems •With accumulators isolated pump should be capable of closing the annular and open the hydraulic choke (HCR) and return system to normal annular pressure in 2 minutes. •Electric pump will automatically start when system pressure has decreased to 90% of system working pressure. •A pump system consists of one or more pump each pump should have independent power source.
  • 25. 7. Pressure Test Frequency Pressure test on well control equipment should be at least: 1. Prior to spud or upon installation. 2. After disconnection or repair of any component 3. Not to exceed 21 days. 6. Closing time RAM Annular Smaller than 18 ¾” 30 sec max. 30 sec max. 18 ¾” and larger 30 sec max. 45 sec max.
  • 26. 8. Shell or Body Test at manufacturer Shop 1 ½ times BOP rating I.e. 150% of pressure rating. 9. Closing Ratio Ratio of well head pressure to pressure required to close the BOP.
  • 27. 10. Choke Lines 1. Minimum recommended size for choke line is 2 inches for 3K and 5K arrangements and 3 inch for 10K and 15K. 2. Minimum recommended inside diameter for lines downstream of choke should be equal to or greater than the connecting lines of the choke (choke line). 3. The bleed line should be at least equal in diameter to the choke line this line allows: a) Circulation of well with preventors closed while maintaining a minimum back pressure. b) Permits high volume bleed off of well fluids to relieve casing pressure with the preventers close.
  • 28.
  • 30.
  • 31. Remote control panel When the BOP ram in the close position close line has 1500 psi. When the BOP ram in the open position open line has 1500 psi. When the 4 way valve shifts the micro switch will activate the light to illuminate. When light illuminates, it tells us that oil on its way to the BOP function. Rig air 120 psi 4 Way valve and micro switch Oil
  • 32. Indicator Lights on BOP Remote Panel A micro switch is located at the main unit, it will send a signal to the indicator lights to change color only when the 4-way valve shifts. Indicator lights, don’t tell us that the BOP’s function has completed, but they tell us that the 4-way valve is already shifted and the oil is flowing under pressure to move the functions piston to complete the close or open operations.
  • 33. indicator lights Problem while shutting in a well from remote panel 2.If indicator light does not illuminate and pressure gauges don’t drop, it means that no oil has been used and BOP piston does not move, the cause could be a)4-way valve failed to shift. b)Master control valve is not depressed with the control valve of the function. c)No air pressure is going to the remote panel. 1.If indicator light does not illuminate, but gauges drop and later rise back up which means that oil has been used to move the piston of the BOP and the function is completed so the cause is (BULB has blown).
  • 34. indicator lights Problem 4.If indicator light illuminates and pressure dropped but not rise back up it means that oil has been used, function completed but there is LEAK in hydraulic system. 5.If indicator light illuminates and pressure dropped then the manifold pressure raised back up to 1500 psi but accumulates pressure did not raise back up to 3000 psi. 3.If indicator light illuminates but pressure gauges do not drop it means that the 4-way valves has shifted but hydraulic line between the 4-way valve and the BOP is plugged.