The document provides a timeline and overview of the Enron Dabhol Power Company (DPC) project in India from 1991-2001. It details how the project was initially invited and approved by the Indian government but then faced increasing political and social opposition. It eventually collapsed in 2001 due to the high cost of power from DPC and Enron's bankruptcy. The power plant is now operational again under new ownership and management.