3. 1956-1991
Industrial Policy Resolution (1956)
Generation and Distribution of
Power under State ownership
Power losses, subsidies,
infrastructure bottlenecks and
resource constrains
4. 1991-2003
Legislative and Policy Initiative (1991)
Private sector participation in Generation
Fast-track clearing mechanism of private
investment proposal
Electricity Regulatory Commissions Act 1998
5. 2003 onwards
Electricity Act 2003
National Electricity Policy 2005
National Tariff Policy 2006
National Tariff Policy 2016
6. 1910
The Electricity Act 1910 was
enacted by the British for the
growth of electricity industry in
India through private licensees who
could supply electricity in a
specified area.
7. As per the Constitution of India
• Electricity is a concurrent subject. Both
parliament and the state legislation have the
power to legislate over this subject. Central
Legislation shall prevail over State Legislation.
• There is only one exception to the
aforementioned rule, i.e., when state enacts
legislation with Presidential Assent, then state
legislation will prevail.
8. 1948
After the independence, the
Electricity (Supply) Act, 1948
was enacted for creation of
State Electricity Boards for
arranging the supply of
Electricity in the State.
9. 1976
Electricity (Supply) Act, 1948 was amended:
1. Govt. Generating Companies recognized
2. Price, terms and conditions of sale of
energy by generating companies
determined by the appropriate
Government.
10. 1991
Electricity (Supply) Act was further amended:
Private players, including foreign investors was
allowed to come in as independent power
producers (IPP) and enter into long-term
supply contracts (PPA) with utilities.
11. 1992
• Government of India adopted a two-part tariff
formula for NTPC stations based on the
recommendations of the K P Rao Committee.
• Even after 1992, overdrawals by some SEBs
during peak-load hours and under-drawals
during off-peak hours continued unabated,
causing serious frequency excursions and
perpetual operational/commercial disputes.
12. 1993
Government had engaged M/s ECC of USA an
international consultants to comprehensively
study the Indian power system and
recommend a suitable tariff structure. Their
report (ECC Report) was submitted in 1994.
13. 2002: Availability Based Tariff
Central Govt> ECC Inc, USA : 1993
ECC Report> Central Govt.: 1994
Central Govt.>National Task Force 1995
(NTF)>Central Govt>CERC 1999> ABT
Regulations 2000, T&C of ABT 2001
WR>July’2002; NR>Dec’2002; SR> Jan’2003;
ER> April’2003; NER> Nov’2003
14. Evaluation of Transmission Charges
Before 1992, cost of transmission was
clubbed with Generation Tariff.
From 1992 to 2002, transmission charges
were apportioned on the basis of energy
drawn.
From 2002 to 2011, transmission charges
were apportioned on the basis of MW
entitlements.
15. 2011: PoC Transmission Charges
From 2011 onwards, PoC transmission
charges were introduced. It is the recovery of
the cost of transmission infrastructure from
an entity in proportion to the extend of usage
of inter-State network.
16. 1998
In the year 1998, the Electricity
Regulatory Commission Act was
enacted for distancing govt.
from determination of tariffs.
17. 1998
Indian Electricity Act 1910 and Electricity
(Supply Act) 1948 was further amended:
1. Transmission recognized as independent
and licensed activity.
2. Private participation in transmission was
allowed.
18. Preamble of the Electricity Act 2003
An Act to consolidate the laws relating to generation,
transmission, distribution, trading and use of
electricity and generally for taking measures conducive
to development of electricity industry, promoting
competition therein, protecting interest of consumers
and supply of electricity to all areas, rationalization of
electricity tariff, ensuring transparent policies
regarding subsidies, promotion of efficient and
environmentally benign policies, constitution of
Central Electricity Authority, Regulatory Commissions
and establishment of Appellate Tribunal and for
matters connected therewith or incidental thereto.
19. Main Features of the E Act 2003
1. No license for generation.
2. But hydro project>25MW need
clearance from CEA.
3. Provision for private transmission &
distribution.
4. Open access.
5. Trading of power.
20. Main Features of the E Act 2003
6. Regulatory Commission.
7. Tariff based competitive bidding.
8. Appellate Tribunal.
9. CEA.
10. Cognizance of the offence.
11. Rules and Regulations.
12. Penalties.
21. Chapters of the E Act 2003
1. Preliminary: Definitions
2. National Electricity Policy & Plan
3. Generation of Electricity
4. Licensing
5. Transmission of Electricity
6. Distribution of Electricity
7. Tariff
22. 18 chapters of the E Act 2003
8. Works
9. CEA (Central Electricity Authority)
10. Regulatory Commissions
11. APTEL (Appellate Tribunal for Electricity)
12. Investigation and Enforcement
13. Reorganization of Board
14. Offences and Penalties
23. 18 chapters of the E Act 2003
15. Special Courts
16. Dispute Resolution
17. Other Provisions
18. Miscellaneous
The Schedule-Enactments
24. Act, Rules, Regulations
The Constitution of India
The Electricity Act 2003
(1) Rules by Governments
(2) Regulations by Commissions according to
Electricity Act 2003 and Rules
25. Amendments of E Act 2003
Electricity Act 2003 was amended in 2003
and 2007:
1. Captive Plant was allowed to sell power.
2. Rural Electrification was accepted as joint
Endeavour of State and Central.
3. Elimination of cross subsidy and surcharge
in open access was kept as mandatory.
26. Proposed Electricity(Amendment)Act 2018
Separation of Carriage & Content in the
Distribution sector
Determination of retail-tariff based on market
principles
To keep carriage (distribution network) as a
regulated activity.
27. Proposed Amendment of E Act (Pending)
Provision for a separate National Renewable
Energy Policy
Provisions of ‘Tariff Policy’ are proposed to be
made mandatory
Directions for use of Smart Meters
The Chairman, WBSETCL writes in the beginning of any annual report of WBSETCL “It gives me immense pleasure to share with you the performance of your company” . Who is the owner of WBSETCL?
The period before 1956 may be stated as Introductory Stage.
1956 to 1991 may be named as Nationalization Stage. From the mid-1980s, under an economy wide approach for state-owned enterprises in general, the central government had attempted to improve the efficiency of SEBs by giving them greater managerial autonomy and
increasing their access to capital, with the hope that they would become more entrepreneurial.
191 to 2003 may be stated as Liberalization Era. The central government adopted a new approach in 1991 because of India’s financial crisis, under which it sought immediate remedies. Since many years would be needed to rectify the SEB’s inefficiencies, the new
approach focused on the immediate problem of meeting the shortfall in generating capacity that had been
perpetuated by the SEB’s poor finances. The government hoped that private investors would provide large
amounts of efficient and inexpensive power capacity, even though there was little track record in developing
countries to provide credibility for this approach. A focus on private investors was also consistent with the
reformist agenda of attracting foreign direct investment. There was a broad consensus supporting this approach to
reform because of the lack of viable alternatives.
The central government created the legal conditions needed to attract private investors in electricity generation,
and it set tariff rules that would be particularly attractive to investors, with a guaranteed 16 percent return on
equity (after tax) and full repatriation of profits in dollars. To jump-start the process, the government awarded
“fast track” status to eight projects (many with foreign participation), promising rapid clearances and central
government repayment guarantees to assuage investors’ concerns about selling their output to insolvent SEBs.
Most of these projects included a cost-plus PPA between the operator and an SEB. Only three of the fast track
projects, however, have produced power more than a decade after the fast track initiative.
2003 onwards may be stated as Growth Era.
Sate Electricity Boards through 5 yr plans undertook rapid growth expansion by utilizing plan funds. Regional planning in Power Sector was introduced. DVC ACT 1948 was enacted. CEA was formed. Atomic Energy Act 1962. In 1964, the Regional Electricity Boards were established. In 1975, NTPC & NHPC were created. In 1989, Power grid was created. In 1990, HVDC regional link was thought of. In 1992 NER & ER were synchronized. Availability Based Tariff (ABT), with a unique Unscheduled Interchange
(UI) component, was recommended for Central Sector generation and
private generation by M/s ECC, USA after a nation-wide, World
Bank/ADB-sponsored study in 1993-94. In 1994, RLDCs came under PGCIL. In 1995 Mega Power Policy was declared by Central Govt. Power sector restructuring by Odisha in 1996 followed by a few States like Haryana, Andhra, Uttar Pradesh, Karnataka, Rajasthan, Delhi, MP and Gujrat. In 1999 transmission system planning reoriented towards all India system. ABT has been implemented during 2002-2003.
Economic reform in 1991 for fiscal deficit, IPP policy in 1992 to attract private and foreign investment which gave 16% RoE at 68.5% PLF when NTPC was given 12% RoE, unbundling of SEBs was thought of World Bank and Asian Development Bank. Unbundling was seen as a necessary prior condition for privatisation. Orissa pursued unbundling (1995 Act) followed it up with privatisation of the distribution companies with the transmission company being still in state hands (Ref. Ajay Pandey & Sebastian Morris, IIMA), Haryana, Andhra, UP, Karnataka, Delhi, MP and Gujrat followed by State reform Acts. Due to participation of private players need for regulating the business was felt. Hence came Regulatory Commission Act 1998.
Obliging electricity enterprises to operate according to commercial principles. These principles require that enterprises pay taxes and market-based interest rates, earn commercially competitive returns on equity capital, and have the autonomy to manage their own budgets, borrowing, procurement, and labor employment.