3.1 Engineering Set Up
3.2 Engineering Schedule Preparation
Monitoring and Controlling
3.3 Enggineering Documentation 3.5 Site Engineering
3.1.1 Identify and Build Resource Pool
3.1.3 Define Project Template
3.1.2 Define Design Input Process
3.2.1.Prepare Engineering Schedule
3.2.1 Measure Engineering Progress and Reports
3.4.1 Define and Identify Engineering Task and Sub
Task
3.3.2. Define Document Identification procedure
3.4.7. Define Approval Workflow as per Project
Requirement
3.5.1. Define Scope Creep Process
3.5.2. Define GFC Change Request Process
3.2.2 Prepare Catch up Plan
3.4 Engineering Activities
3.3.1. Define Document Storage and Maintainence
procedure
3.3.4 Manage Document Revision and Version3.1.4. Decision to outsource
3.4.4. Define Drawing Interdiscipline Checking and
Approval Procedure
3.4.5 Define Transmittal creation and release
procedure
3.4.3. Prepare Design & Drawing creation procedure
3.4.6 Define client Submission and Approval Process
3.3.3. Integrate plan with information
3.2.3 Prepare MOM and Action Items
3.4.2.Prepare Checklist
3.5.3 Prepare Site Visit Report
3.3.5 Compare Document Revision
3.1.1 Identify and Build Resource Pool
Receive request to
initiate Engineering
for project
Identify and Assign
Engineering co-
ordinator
Prepare Resource
Pool
Start
END
Create Project
PBCBD&E
Covered in Project
Planning
PBCBEnggCo-ordinator 3.1.2 Define Design Input Management
Receive client
document for Design
Input
Distribute to
assigned Resource
to prepare Design
and Drawing
Start
Receipt and Analyse
client design input
Engg-Designer
Clarify for any
doubts and
completeness/
readiness for the
Document
END
The document type inculde
1.Job Specification,Scope of work
2. Drawing, P&ID Diagram
3. Survey Reports and Reference
documents etc
Complile client
document and send
to Engineering C0-
ordinator
Request to PBCB for
technical document
provided by client
EnggCo-ordinator
Start
Define design and
drawing templates
as per project
Requriment
Define Transmittal
templates as per
project Requriment
Define MOM
templates
Define Document
Diistribution List
Define Life Cycle
status
Define Approval
Status Code(Interna,
MINT and Client)
Define Revision
Series,LCS
Define ageing Days
Release/Mail
to Resource
Pool
END
3.1.3 Define Engineering Template
3.1.4. Decision to outsourceEngineeringCo-ordinatorEngg-HOD
Analyse
technical
requirement
for project
Resource Avaliability
Calculate
resource and
time required
to complete
job
Define engineering
package to be
completed by internally
& sub conconsultant
Receive request for
Approval
Send to HOD
Change required
Yes
No
PBCB
Send to PBCB
Raise PI for Sub-
consultant
Input to
commercial
PBCB 3.2.1 Prepare Engineering ScheduleEngineeringCo-
ordinator
Send request
to prepare
Engineering
Schedule
Project Plan
Receive
request to
prepare
Engineering
Schedule
Start
Send request to
prepare drawing
list to respective
Department
with timeline
and Resource
Receive MDL
From
Respective
Department
Assign Flow of
work to MDL
Compile and
Submit
Engineering
Schedule
3.2.2. Define Daily Job Tracking ProcedurePBCB
EngineeringCo-
ordinator
WorkResources
Rtrive Daily
Job card from
project plan
Mail Daily Job
card from
project plan
Receive Daily
Job card
Do assigned
Job
Update
Manhour
Spent on JOB
Receive Daily
ODIF
Update into
project plan
Project Plan
3.2.3. Prepare Engineering BudgetEngg-Coordinator
Calculated
Manhours
Calculate
Manhour Cost
Calculate Sub
consultant cost
Calculate
Miscillineous
Cost
Prepare
Project
Budget
EnggHOD
Review project
budget
Change
Required
Review the
Budget
Send to PBCB
Yes
No
Change
Required
Yes
NoCompile into
Master
project
Budget
PBCB
END
3.2.4 Measure Engineering ProgressEnggCo-ordinator
Project
Plan
Identify
design and
drawing
workflow
stage
Calculate the
progress at
Leaf Level
Task
Defined weightage at
workflow stage
Roll out the
progress at
Main Task
Calculate
Actual Value
Planned Value
in term of
Budget
Planned Value
in term of
Time
Analyse data
and prepare
various
reports as
Required
END
3.2.5 Prepare Catchup PlanEnggCo-ordinatorPBCB
Start
Share progress
with PBCB
Receive the
Report
Draft Catchup
Plan
Analyse
Report
EnggHOD
Receive and
Analyse catch
up plan
Share the
Plan with
Engg HOD
Change
Required
Assign Action
Items
Yes
No
END
3.2.6 Prepare MOM and Action ItemsD&E
Start
Request for
Meeting
Note down
Action Items
The meeting
type may include Assign action
Items
Track Action
Items
Close
3.3.1. Define Document Storage and Maintainence procedureEngineeringCo-ordinator
Start
Define
Document
Categories
IT
Define
Standard
Central Folder
Structure
END
Document category
includes
BOQ
Drawings
Data Sheets
Specifications
Calculations
Lists
Reports
MTO
Vendor Documentation
Correspondence
Client Documents
Minutes Of Meeting
Provide
required
acess right to
Resources
Security
Matrix
Document
Assign
Workflow/
Revision
Series to
folders
3.3.2. Define Document Identification procedureEngineeringCo-ordinator
Start
Classify
Documents
Store
document
type with
unique ID
Develop
Numbering
Logic as per
project
requirement
END
Logic should clearly define
following
1. Project
2. Disclipline
3. Type
4. Number
The documents can be
classified as
1. Internal document
2. External Document
3. Correspondance
3.3.3 Integrate Project plan with Project informationD&E-DC
Start
Identify task
type
(Documented
/Non
documented
Task) from
project plan
Designers
Link
document to
particular task
Attach
correspondan
ce to
document
Attach
comment/
References
to document
Attach
images/or any
related
information
to document
Develop
standarised/
Integrated
plan with
information
Provide acess
right as per
project
requirement
END
3.3.4 Manage Document Revision and VersionDCResourcepool
Start
Prepare Design and
Drawing with proper
nomeclature inclding
revision
Route it for
approval
Increase revision
number if document
has to be
resubmitted to client
Increase the
version number if
document has to
resubmitted
internally
END
3.3.5 Compare Version and RevisionD&E
Start
Receive
revised
drawing
Select
previous
drawing
Define color
code for
addition and
deletion
Prepare
reports
END
3.4.1 Define and Identify Engineering Task and Sub TaskEngineeringHODDepartmentalHead
Start
Send request to
respective
department to
prepare
activities and
sub activity list
Prepare
activity and
subactivity
list
Incorporate
Approx time
to complete
activity and
Sub activity
Verify the
activity and
sub-activity
duration
Release
defined
standard
activity and
duration
matrix
END
3.4.2.Prepare ChecklistD&E
Prepare list of
task to be
completed for
all defined
document
type
Start
Provide
Nomeclature
of checklist
Link checklist
to every
document
type
Link checklist
to every
document
type
End
Checklist should
be updated
before routing to
next stage
3.4.3. Prepare Design & Drawing Creation procedureD&E
Start
Create
Drawing from
existing
template
Link to the Task
Provide proper
Nnomeclature
Select the
Workflow
Select the
workflow and
send it for
Review
Close
Update
checklist
3.4.4. Define Drawing Interdiscipline Checking and Approval ProcedureReviewer
Receive
drawing for
review
Mark up
drawing
Attach
comment File
Ensure the
design is as
per contract
line
Prepared
drawing
Ensure the
design is as
per contract
line
Change
Required
Yes
Yes
Send to
defined user
for approval
END
3.4.5 Define Transmittal creation and release procedureDocumentController
Internally
Approvad
Drawing
Receive
request to
create
transmittal
Select the drawing
to create
transmittal
Define Transmittal
nomeclature
Select transmittal
type and category
Send to client/
Consultant and
predefined
stakeholders
END
Create
Transmittal
3.4.6 Define client Submission and Approval ProcessClient
Submitted
Drawing
Receipt of
Drawing for
Review
DC
Send to JWIL
DC
Add Approval
Status code
Add
Comment/
Review
Receipt of
updated
Document
Analyse the
comment
Incorporate
Approval
status
category/
Receipt Date
End
3.4.7. Define Approval Workflow as per Project RequirementEngg-Cordinator
Start
Analyse the project
Requirement
Define the flow of Design
and Drawing
Draft the Flow
Engg-HOD
Review the FlowChange Required
Yes
Release the Flow END
No
3.5.1. Define Scope Creep ProcessClientSitePBCB
Start
Addition/
Change in
Scope of Work
Send Request
to Contractor/
JWIL
Receive
request from
Client Draft and Submit
to PBCB for
Review
Review and
Forward to
D&E
Analyse the
cost
Implication &
Submit to
Project
D&E
Incorporate
Change
required
Change
Required
Receive and
Submit to
Client
Receive and
Submit to
Client
Yes
GFC
NO
END
3.5.2. GFC Change Request ProcessSiteD&EClient
Hurdle in
construction due
to unexpected
finding,Social
resistance,Natura
l Difficulties etc
GFC
Prepare Report
Submit Request
to D&E to make
required changes
Receive the
request
Analyse and
Incorporate
change
Submit to
Client
Receipt of
request from
client
Review the
Request
Change
Required
Yes
No
Receive
Approved
Drawing
3.5.3 Prepare Site Visit ReportProjectSiteD&E
Start
Request from site to
provide technical
solution
Receive request from
site team
Technical
Issue on
project site
Prepare Plan
as per
requirement
Visit onsite
and Analyse
the Issue
Collect
data,Take
Images,obser
vation
Prepare
Reports
Close
Engineering process flow

More Related Content

What's hot

Interview questions-answers-for-planning-engineers-r.00
Interview questions-answers-for-planning-engineers-r.00Interview questions-answers-for-planning-engineers-r.00
Interview questions-answers-for-planning-engineers-r.00
Praveen Krishna
 
Project Management Proposal Template Powerpoint Presentation Slides
Project Management Proposal Template Powerpoint Presentation SlidesProject Management Proposal Template Powerpoint Presentation Slides
Project Management Proposal Template Powerpoint Presentation Slides
SlideTeam
 
TOGAF em Ação
TOGAF em AçãoTOGAF em Ação
PC 2012 PMO plan
PC 2012 PMO planPC 2012 PMO plan
PC 2012 PMO plan
drewboy07
 
Project Management Fundamentals | Project Management Simplified | PMP® Traini...
Project Management Fundamentals | Project Management Simplified | PMP® Traini...Project Management Fundamentals | Project Management Simplified | PMP® Traini...
Project Management Fundamentals | Project Management Simplified | PMP® Traini...
Edureka!
 
WSP USA Overview
WSP USA OverviewWSP USA Overview
WSP USA Overview
WSP USA
 
PMO Presentation
PMO PresentationPMO Presentation
PMO PresentationTURKI , PMP
 
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m magedDelay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Energy contracts & disputes presentation slides - 25 September 2012
Energy contracts & disputes presentation slides - 25 September 2012Energy contracts & disputes presentation slides - 25 September 2012
Energy contracts & disputes presentation slides - 25 September 2012Eversheds Sutherland
 
Case study successfully planning and executing a p6 eppm implementation roa...
Case study   successfully planning and executing a p6 eppm implementation roa...Case study   successfully planning and executing a p6 eppm implementation roa...
Case study successfully planning and executing a p6 eppm implementation roa...
p6academy
 
プロダクトマネージャとして海外で働き始めて、自分の視点をどこに持ってこようかと考えた話 #pm_roppongi
プロダクトマネージャとして海外で働き始めて、自分の視点をどこに持ってこようかと考えた話 #pm_roppongiプロダクトマネージャとして海外で働き始めて、自分の視点をどこに持ってこようかと考えた話 #pm_roppongi
プロダクトマネージャとして海外で働き始めて、自分の視点をどこに持ってこようかと考えた話 #pm_roppongi
Daisuke Matsuda
 
Proposed Project Management Office
Proposed Project Management OfficeProposed Project Management Office
Proposed Project Management Office
Josh Folgado
 
Modulo 002- Fundamentos do Gerenciamento de Projetos
Modulo 002- Fundamentos do Gerenciamento de ProjetosModulo 002- Fundamentos do Gerenciamento de Projetos
Modulo 002- Fundamentos do Gerenciamento de Projetos
Instituto de Capacitação Business School Brasil - BSB
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo
 
Modelos eap
Modelos eapModelos eap
Modelos eap
ren543210
 
Termo de abertura do projeto - beauty
Termo de abertura do projeto - beautyTermo de abertura do projeto - beauty
Termo de abertura do projeto - beautyMLGV
 
Making the Case for a PMO to Help Defense ROI
Making the Case for a PMO to Help Defense ROIMaking the Case for a PMO to Help Defense ROI
Making the Case for a PMO to Help Defense ROI
Gigi Steele McAlwee
 
Project Business Case
Project Business CaseProject Business Case
Project Business CaseNader Jarmooz
 
Project Management Plan One Pager Presentation Report Infographic Ppt Pdf Doc...
Project Management Plan One Pager Presentation Report Infographic Ppt Pdf Doc...Project Management Plan One Pager Presentation Report Infographic Ppt Pdf Doc...
Project Management Plan One Pager Presentation Report Infographic Ppt Pdf Doc...
SlideTeam
 

What's hot (20)

Interview questions-answers-for-planning-engineers-r.00
Interview questions-answers-for-planning-engineers-r.00Interview questions-answers-for-planning-engineers-r.00
Interview questions-answers-for-planning-engineers-r.00
 
Project Management Proposal Template Powerpoint Presentation Slides
Project Management Proposal Template Powerpoint Presentation SlidesProject Management Proposal Template Powerpoint Presentation Slides
Project Management Proposal Template Powerpoint Presentation Slides
 
TOGAF em Ação
TOGAF em AçãoTOGAF em Ação
TOGAF em Ação
 
PC 2012 PMO plan
PC 2012 PMO planPC 2012 PMO plan
PC 2012 PMO plan
 
Project Management Fundamentals | Project Management Simplified | PMP® Traini...
Project Management Fundamentals | Project Management Simplified | PMP® Traini...Project Management Fundamentals | Project Management Simplified | PMP® Traini...
Project Management Fundamentals | Project Management Simplified | PMP® Traini...
 
WSP USA Overview
WSP USA OverviewWSP USA Overview
WSP USA Overview
 
PMO Presentation
PMO PresentationPMO Presentation
PMO Presentation
 
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m magedDelay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
 
Energy contracts & disputes presentation slides - 25 September 2012
Energy contracts & disputes presentation slides - 25 September 2012Energy contracts & disputes presentation slides - 25 September 2012
Energy contracts & disputes presentation slides - 25 September 2012
 
Case study successfully planning and executing a p6 eppm implementation roa...
Case study   successfully planning and executing a p6 eppm implementation roa...Case study   successfully planning and executing a p6 eppm implementation roa...
Case study successfully planning and executing a p6 eppm implementation roa...
 
プロダクトマネージャとして海外で働き始めて、自分の視点をどこに持ってこようかと考えた話 #pm_roppongi
プロダクトマネージャとして海外で働き始めて、自分の視点をどこに持ってこようかと考えた話 #pm_roppongiプロダクトマネージャとして海外で働き始めて、自分の視点をどこに持ってこようかと考えた話 #pm_roppongi
プロダクトマネージャとして海外で働き始めて、自分の視点をどこに持ってこようかと考えた話 #pm_roppongi
 
Proposed Project Management Office
Proposed Project Management OfficeProposed Project Management Office
Proposed Project Management Office
 
Modulo 002- Fundamentos do Gerenciamento de Projetos
Modulo 002- Fundamentos do Gerenciamento de ProjetosModulo 002- Fundamentos do Gerenciamento de Projetos
Modulo 002- Fundamentos do Gerenciamento de Projetos
 
I2m - Strategy PMO Case Study Presentation
I2m - Strategy PMO Case Study PresentationI2m - Strategy PMO Case Study Presentation
I2m - Strategy PMO Case Study Presentation
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
 
Modelos eap
Modelos eapModelos eap
Modelos eap
 
Termo de abertura do projeto - beauty
Termo de abertura do projeto - beautyTermo de abertura do projeto - beauty
Termo de abertura do projeto - beauty
 
Making the Case for a PMO to Help Defense ROI
Making the Case for a PMO to Help Defense ROIMaking the Case for a PMO to Help Defense ROI
Making the Case for a PMO to Help Defense ROI
 
Project Business Case
Project Business CaseProject Business Case
Project Business Case
 
Project Management Plan One Pager Presentation Report Infographic Ppt Pdf Doc...
Project Management Plan One Pager Presentation Report Infographic Ppt Pdf Doc...Project Management Plan One Pager Presentation Report Infographic Ppt Pdf Doc...
Project Management Plan One Pager Presentation Report Infographic Ppt Pdf Doc...
 

Similar to Engineering process flow

CCI PM Processes (within PMP Process Groups and Knowledge Areas)
CCI PM Processes (within PMP Process Groups and Knowledge Areas)CCI PM Processes (within PMP Process Groups and Knowledge Areas)
CCI PM Processes (within PMP Process Groups and Knowledge Areas)Pamela Garrett
 
MGT-Ch07.ppt
MGT-Ch07.pptMGT-Ch07.ppt
MGT-Ch07.ppt
MarkNaguibElAbd
 
Ch4 project management process
Ch4 project management processCh4 project management process
Ch4 project management processKittitouch Suteeca
 
SDLC
SDLCSDLC
SDLC
jamzak
 
Interconnect Presentation
Interconnect PresentationInterconnect Presentation
Interconnect PresentationEric Deitrick
 
Fall 2018 Project guideline Name CWID Identifi.docx
  Fall 2018 Project guideline Name CWID Identifi.docx  Fall 2018 Project guideline Name CWID Identifi.docx
Fall 2018 Project guideline Name CWID Identifi.docx
ShiraPrater50
 
Gonzales.matthew
Gonzales.matthewGonzales.matthew
Gonzales.matthewNASAPMC
 
Project closure template v3.0
Project closure template v3.0Project closure template v3.0
Project closure template v3.0
Aditya Pandey
 
04c_Process_Map_Templates-V2.0_(pdf).pdf
04c_Process_Map_Templates-V2.0_(pdf).pdf04c_Process_Map_Templates-V2.0_(pdf).pdf
04c_Process_Map_Templates-V2.0_(pdf).pdf
hippiemx
 
Cpmgt 303 cpmgt303
Cpmgt 303 cpmgt303Cpmgt 303 cpmgt303
Cpmgt 303 cpmgt303
GOODCourseHelp
 
Summary of key project manager actions & results
Summary of key project manager actions & resultsSummary of key project manager actions & results
Summary of key project manager actions & resultsTut Andrei-Eugen
 
Pmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_aPmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_a
Forbes Chanakira
 
EO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.pptEO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.ppt
yashchotaliyael21
 
Spm project planning
Spm project planning Spm project planning
Spm project planning
Kanchana Devi
 
2.05 scope management 1
2.05 scope management 12.05 scope management 1
2.05 scope management 1reddvise
 
NCV 4 Project Management Hands-On Support Slide Show - Module 2
NCV 4 Project Management Hands-On Support Slide Show - Module 2NCV 4 Project Management Hands-On Support Slide Show - Module 2
NCV 4 Project Management Hands-On Support Slide Show - Module 2
Future Managers
 

Similar to Engineering process flow (20)

CCI PM Processes (within PMP Process Groups and Knowledge Areas)
CCI PM Processes (within PMP Process Groups and Knowledge Areas)CCI PM Processes (within PMP Process Groups and Knowledge Areas)
CCI PM Processes (within PMP Process Groups and Knowledge Areas)
 
MGT-Ch07.ppt
MGT-Ch07.pptMGT-Ch07.ppt
MGT-Ch07.ppt
 
Ch4 project management process
Ch4 project management processCh4 project management process
Ch4 project management process
 
SDLC
SDLCSDLC
SDLC
 
Interconnect Presentation
Interconnect PresentationInterconnect Presentation
Interconnect Presentation
 
CV-ANIL
CV-ANILCV-ANIL
CV-ANIL
 
Fall 2018 Project guideline Name CWID Identifi.docx
  Fall 2018 Project guideline Name CWID Identifi.docx  Fall 2018 Project guideline Name CWID Identifi.docx
Fall 2018 Project guideline Name CWID Identifi.docx
 
Gonzales.matthew
Gonzales.matthewGonzales.matthew
Gonzales.matthew
 
3.2 Years exp
3.2 Years exp3.2 Years exp
3.2 Years exp
 
Project closure template v3.0
Project closure template v3.0Project closure template v3.0
Project closure template v3.0
 
ACH 216 Lecture 06 (Pre Construction Planning)
ACH 216 Lecture 06 (Pre Construction Planning)ACH 216 Lecture 06 (Pre Construction Planning)
ACH 216 Lecture 06 (Pre Construction Planning)
 
04c_Process_Map_Templates-V2.0_(pdf).pdf
04c_Process_Map_Templates-V2.0_(pdf).pdf04c_Process_Map_Templates-V2.0_(pdf).pdf
04c_Process_Map_Templates-V2.0_(pdf).pdf
 
Cpmgt 303 cpmgt303
Cpmgt 303 cpmgt303Cpmgt 303 cpmgt303
Cpmgt 303 cpmgt303
 
Summary of key project manager actions & results
Summary of key project manager actions & resultsSummary of key project manager actions & results
Summary of key project manager actions & results
 
Pmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_aPmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_a
 
EO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.pptEO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.ppt
 
Spm project planning
Spm project planning Spm project planning
Spm project planning
 
2.05 scope management 1
2.05 scope management 12.05 scope management 1
2.05 scope management 1
 
NCV 4 Project Management Hands-On Support Slide Show - Module 2
NCV 4 Project Management Hands-On Support Slide Show - Module 2NCV 4 Project Management Hands-On Support Slide Show - Module 2
NCV 4 Project Management Hands-On Support Slide Show - Module 2
 
GISWORX_ADM_2015
GISWORX_ADM_2015GISWORX_ADM_2015
GISWORX_ADM_2015
 

Recently uploaded

Elevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object CalisthenicsElevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object Calisthenics
Dorra BARTAGUIZ
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
Product School
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
DianaGray10
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Product School
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
OnBoard
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
Product School
 
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Ramesh Iyer
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
Jemma Hussein Allen
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
Kari Kakkonen
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Jeffrey Haguewood
 
Generating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using SmithyGenerating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using Smithy
g2nightmarescribd
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance
 
Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*
Frank van Harmelen
 
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
Product School
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
RTTS
 
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdfFIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
DianaGray10
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Albert Hoitingh
 
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Thierry Lestable
 
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdfFIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance
 

Recently uploaded (20)

Elevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object CalisthenicsElevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object Calisthenics
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
 
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
 
Generating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using SmithyGenerating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using Smithy
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
 
Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*
 
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
 
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdfFIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
 
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
 
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdfFIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
 

Engineering process flow

  • 1. 3.1 Engineering Set Up 3.2 Engineering Schedule Preparation Monitoring and Controlling 3.3 Enggineering Documentation 3.5 Site Engineering 3.1.1 Identify and Build Resource Pool 3.1.3 Define Project Template 3.1.2 Define Design Input Process 3.2.1.Prepare Engineering Schedule 3.2.1 Measure Engineering Progress and Reports 3.4.1 Define and Identify Engineering Task and Sub Task 3.3.2. Define Document Identification procedure 3.4.7. Define Approval Workflow as per Project Requirement 3.5.1. Define Scope Creep Process 3.5.2. Define GFC Change Request Process 3.2.2 Prepare Catch up Plan 3.4 Engineering Activities 3.3.1. Define Document Storage and Maintainence procedure 3.3.4 Manage Document Revision and Version3.1.4. Decision to outsource 3.4.4. Define Drawing Interdiscipline Checking and Approval Procedure 3.4.5 Define Transmittal creation and release procedure 3.4.3. Prepare Design & Drawing creation procedure 3.4.6 Define client Submission and Approval Process 3.3.3. Integrate plan with information 3.2.3 Prepare MOM and Action Items 3.4.2.Prepare Checklist 3.5.3 Prepare Site Visit Report 3.3.5 Compare Document Revision
  • 2. 3.1.1 Identify and Build Resource Pool Receive request to initiate Engineering for project Identify and Assign Engineering co- ordinator Prepare Resource Pool Start END Create Project PBCBD&E Covered in Project Planning
  • 3. PBCBEnggCo-ordinator 3.1.2 Define Design Input Management Receive client document for Design Input Distribute to assigned Resource to prepare Design and Drawing Start Receipt and Analyse client design input Engg-Designer Clarify for any doubts and completeness/ readiness for the Document END The document type inculde 1.Job Specification,Scope of work 2. Drawing, P&ID Diagram 3. Survey Reports and Reference documents etc Complile client document and send to Engineering C0- ordinator Request to PBCB for technical document provided by client
  • 4. EnggCo-ordinator Start Define design and drawing templates as per project Requriment Define Transmittal templates as per project Requriment Define MOM templates Define Document Diistribution List Define Life Cycle status Define Approval Status Code(Interna, MINT and Client) Define Revision Series,LCS Define ageing Days Release/Mail to Resource Pool END 3.1.3 Define Engineering Template
  • 5. 3.1.4. Decision to outsourceEngineeringCo-ordinatorEngg-HOD Analyse technical requirement for project Resource Avaliability Calculate resource and time required to complete job Define engineering package to be completed by internally & sub conconsultant Receive request for Approval Send to HOD Change required Yes No PBCB Send to PBCB Raise PI for Sub- consultant Input to commercial
  • 6. PBCB 3.2.1 Prepare Engineering ScheduleEngineeringCo- ordinator Send request to prepare Engineering Schedule Project Plan Receive request to prepare Engineering Schedule Start Send request to prepare drawing list to respective Department with timeline and Resource Receive MDL From Respective Department Assign Flow of work to MDL Compile and Submit Engineering Schedule
  • 7. 3.2.2. Define Daily Job Tracking ProcedurePBCB EngineeringCo- ordinator WorkResources Rtrive Daily Job card from project plan Mail Daily Job card from project plan Receive Daily Job card Do assigned Job Update Manhour Spent on JOB Receive Daily ODIF Update into project plan Project Plan
  • 8. 3.2.3. Prepare Engineering BudgetEngg-Coordinator Calculated Manhours Calculate Manhour Cost Calculate Sub consultant cost Calculate Miscillineous Cost Prepare Project Budget EnggHOD Review project budget Change Required Review the Budget Send to PBCB Yes No Change Required Yes NoCompile into Master project Budget PBCB END
  • 9. 3.2.4 Measure Engineering ProgressEnggCo-ordinator Project Plan Identify design and drawing workflow stage Calculate the progress at Leaf Level Task Defined weightage at workflow stage Roll out the progress at Main Task Calculate Actual Value Planned Value in term of Budget Planned Value in term of Time Analyse data and prepare various reports as Required END
  • 10. 3.2.5 Prepare Catchup PlanEnggCo-ordinatorPBCB Start Share progress with PBCB Receive the Report Draft Catchup Plan Analyse Report EnggHOD Receive and Analyse catch up plan Share the Plan with Engg HOD Change Required Assign Action Items Yes No END
  • 11. 3.2.6 Prepare MOM and Action ItemsD&E Start Request for Meeting Note down Action Items The meeting type may include Assign action Items Track Action Items Close
  • 12. 3.3.1. Define Document Storage and Maintainence procedureEngineeringCo-ordinator Start Define Document Categories IT Define Standard Central Folder Structure END Document category includes BOQ Drawings Data Sheets Specifications Calculations Lists Reports MTO Vendor Documentation Correspondence Client Documents Minutes Of Meeting Provide required acess right to Resources Security Matrix Document Assign Workflow/ Revision Series to folders
  • 13. 3.3.2. Define Document Identification procedureEngineeringCo-ordinator Start Classify Documents Store document type with unique ID Develop Numbering Logic as per project requirement END Logic should clearly define following 1. Project 2. Disclipline 3. Type 4. Number The documents can be classified as 1. Internal document 2. External Document 3. Correspondance
  • 14. 3.3.3 Integrate Project plan with Project informationD&E-DC Start Identify task type (Documented /Non documented Task) from project plan Designers Link document to particular task Attach correspondan ce to document Attach comment/ References to document Attach images/or any related information to document Develop standarised/ Integrated plan with information Provide acess right as per project requirement END
  • 15. 3.3.4 Manage Document Revision and VersionDCResourcepool Start Prepare Design and Drawing with proper nomeclature inclding revision Route it for approval Increase revision number if document has to be resubmitted to client Increase the version number if document has to resubmitted internally END
  • 16. 3.3.5 Compare Version and RevisionD&E Start Receive revised drawing Select previous drawing Define color code for addition and deletion Prepare reports END
  • 17. 3.4.1 Define and Identify Engineering Task and Sub TaskEngineeringHODDepartmentalHead Start Send request to respective department to prepare activities and sub activity list Prepare activity and subactivity list Incorporate Approx time to complete activity and Sub activity Verify the activity and sub-activity duration Release defined standard activity and duration matrix END
  • 18. 3.4.2.Prepare ChecklistD&E Prepare list of task to be completed for all defined document type Start Provide Nomeclature of checklist Link checklist to every document type Link checklist to every document type End Checklist should be updated before routing to next stage
  • 19. 3.4.3. Prepare Design & Drawing Creation procedureD&E Start Create Drawing from existing template Link to the Task Provide proper Nnomeclature Select the Workflow Select the workflow and send it for Review Close Update checklist
  • 20. 3.4.4. Define Drawing Interdiscipline Checking and Approval ProcedureReviewer Receive drawing for review Mark up drawing Attach comment File Ensure the design is as per contract line Prepared drawing Ensure the design is as per contract line Change Required Yes Yes Send to defined user for approval END
  • 21. 3.4.5 Define Transmittal creation and release procedureDocumentController Internally Approvad Drawing Receive request to create transmittal Select the drawing to create transmittal Define Transmittal nomeclature Select transmittal type and category Send to client/ Consultant and predefined stakeholders END Create Transmittal
  • 22. 3.4.6 Define client Submission and Approval ProcessClient Submitted Drawing Receipt of Drawing for Review DC Send to JWIL DC Add Approval Status code Add Comment/ Review Receipt of updated Document Analyse the comment Incorporate Approval status category/ Receipt Date End
  • 23. 3.4.7. Define Approval Workflow as per Project RequirementEngg-Cordinator Start Analyse the project Requirement Define the flow of Design and Drawing Draft the Flow Engg-HOD Review the FlowChange Required Yes Release the Flow END No
  • 24. 3.5.1. Define Scope Creep ProcessClientSitePBCB Start Addition/ Change in Scope of Work Send Request to Contractor/ JWIL Receive request from Client Draft and Submit to PBCB for Review Review and Forward to D&E Analyse the cost Implication & Submit to Project D&E Incorporate Change required Change Required Receive and Submit to Client Receive and Submit to Client Yes GFC NO END
  • 25. 3.5.2. GFC Change Request ProcessSiteD&EClient Hurdle in construction due to unexpected finding,Social resistance,Natura l Difficulties etc GFC Prepare Report Submit Request to D&E to make required changes Receive the request Analyse and Incorporate change Submit to Client Receipt of request from client Review the Request Change Required Yes No Receive Approved Drawing
  • 26. 3.5.3 Prepare Site Visit ReportProjectSiteD&E Start Request from site to provide technical solution Receive request from site team Technical Issue on project site Prepare Plan as per requirement Visit onsite and Analyse the Issue Collect data,Take Images,obser vation Prepare Reports Close