Project Charter Document
Project Name: To float an IPO for Facebook
Department:Underwriting
Focus Area:New securities
Product/Process: IPO



Prepared By
 Document Owner(s)                               Project/Organization Role
 Usha Joshi                                      Lead Underwriter

 VivekRathod                                     Underwriter

 SydVyawahare                                    Underwriter



Project Charter Version Control
 Version      Date         Author                Change Description
 1.0.0        Nov 12th     Usha Joshi            Document created
              2011




Confidential
projectmanagementplan-floatinganipo-120109235032-phpapp02.docx
Last printed on 1/9/2012 9:50:00 PM
Project Charter




TABLE OF CONTENTS
1     PROJECT CHARTER PURPOSE ........................................................................................... 3

2     PROJECT EXECUTIVE SUMMARY ....................................................................................... 3

3     PROJECT OVERVIEW ............................................................................................................ 3

4     PROJECT SCOPE................................................................................................................... 3

      4.1         Goals and Objectives .................................................................................................. 3

      4.2         Departmental Statements of Work (SOW) .................................................................. 4

      4.3         Organizational Impacts ............................................................................................... 4

      4.4         Project Deliverables .................................................................................................... 4

      4.5         Deliverables Out of Scope .......................................................................................... 4

      4.6         Project Estimated Costs & Duration............................................................................ 5

5     PROJECT CONDITIONS ........................................................................................................ 5

      5.1         Project Assumptions ................................................................................................... 5

      5.2         Project Issues.............................................................................................................. 5

      5.3         Project Risks ............................................................................................................... 5

      5.4         Project Constraints ...................................................................................................... 6

6     PROJECT STRUCTURE APPROACH ................................................................................... 6

7     PROJECT TEAM ORGANIZATION PLANS ........................................................................... 6

8     PROJECT REFERENCES ...................................................................................................... 6

9     APPROVALS ........................................................................................................................... 7

10 APPENDICES .......................................................................................................................... 8

      10.1        Document Guidelines .................................................................................................. 8

      10.2        Project Charter Document Sections Omitted .............................................................. 8




Confidential                                                       Page 2                                                            1/9/2012
Project Charter




1      PROJECT CHARTER PURPOSE
       [The scope of the project is limited to carrying out all the necessary activities for
       registering Facebook with the Securities and Exchange Commission. The company
       will enable Facebook to make its first sale of stock to the public. The price of the
       stock will be pre-determined in consultation with the Facebook management. The
       project is aimed to be completed from the date of the contract, the details of which
       will be included in the Time Management subsidiary plan.]

       The project charter defines the scope, objectives, and overall approach for the work to be
       completed. It is a critical element for initiating, planning, executing, controlling, and
       assessing the project. It should be the single point of reference on the project for project
       goals and objectives, scope, organization, estimates, work plan, and budget. In addition, it
       serves as a contract between the Project Team and the Project Sponsors, stating what will
       be delivered according to the budget, time constraints, risks, resources, and standards
       agreed upon for the project.




2      PROJECT EXECUTIVE SUMMARY
       [Replace this text with a high-level view of:
           project goals
           objectives
           scope
           assumptions
           risks
           costs
           timeline
           approach
           organization]




3      PROJECT OVERVIEW
       [Replace this text with the rationale and business justification for undertaking this project.]




4      PROJECT SCOPE

4.1    Goals and Objectives

         Goals                        Objectives
         [Replace this text with      [Replace this text with Objectives for each Goal. For


Confidential                                    Page 3                                         1/9/2012
Project Charter


         Project Goals. For           example:
         example: The project will    1. Develop a system by June that tracks an end-to-end
         provide an improved             process for 100% of product returns.
         system for managing
         product returns.]            2. Integrate new system with Sales in order to improve
                                         customer satisfaction 40% by year end.]



4.2    Departmental Statements of Work (SOW)

         Departmental SOW              Owner/Prime                      Due Date/Sequence




4.3    Organizational Impacts

                                                          Impact to and Participation of
         Organization                                     Organization




4.4    Project Deliverables

         Milestone                      Deliverable
         1. [Milestone Description]        [Deliverable 1—description]
                                           [Deliverable 2—description]
                                           [Deliverable n—description]
         2. [Milestone Description]        [Deliverable 1—description]
                                           [Deliverable 2—description]
                                           [Deliverable n—description]
         3.



4.5    Deliverables Out of Scope

       [Replace this text with a description of key logical areas not considered part of the
       boundaries of this project. Examples of theseOut-of-Scope Deliverables may include data,
       processes, applications, or business management.]




Confidential                                     Page 4                                     1/9/2012
Project Charter


4.6    Project Estimated Costs & Duration

         Project              Date
         Milestone            Estimate         Deliverable(s) Included          Confidence Level
         [Milestone 1]        [mm/dd/yy]       [Deliverable 1]                  [High/Medium/Low]
                                               [Deliverable 2]

         [Milestone 2]        [mm/dd/yy]       [Deliverable 1]                  [High/Medium/Low]
                                               [Deliverable 2]




5      PROJECT CONDITIONS

5.1    Project Assumptions

             [Assumption 1]
             [Assumption 2]
             [Assumption 3]


5.2    Project Issues
       Priority Criteria
       1−High-priority/critical-path issue; requires immediate follow-up and resolution.
       2 −Medium-priority issue; requires follow-up before completion of next project milestone.
       3 −Low-priority issue; to be resolved prior to project completion.
       4−Closed issue.

         #     Date           Priority     Owner       Description        Status & Resolution
         1     [mm/dd/yy]                              [Issue 1           [Replace this text with
                                                       description]       Status and Proposed or
                                                                          Actual Resolution.]
         2     [mm/dd/yy]                              [Issue 2           [Replace this text with
                                                       description]       Status and Proposed or
                                                                          Actual Resolution.]



5.3    Project Risks

         #     Risk Area      Likelihood       RiskOwner         Project Impact-Mitigation Plan
         1     [Project       [High/Medium                       [Replace this text with a description
               Risk]          /Low]                              of the Mitigation Plan.]
         2     [Project       [High/Medium                       [Replace this text with a description


Confidential                                       Page 5                                      1/9/2012
Project Charter



         #     Risk Area      Likelihood        RiskOwner         Project Impact-Mitigation Plan
               Risk]          /Low]                               of the Mitigation Plan.]



5.4    Project Constraints

             [Replace this text with a description of a Constraint.]
             [Constraint 2]
             [Constraint 3]




6      Project Structure Approach
       [Replace this text with a description of how the project will be structured and what
       approach will be used to manage the project.
             What are the dependencies of the project?
             How will you Plan and Manage the project?]




7      Project Team Organization Plans

         Project Team Role               Project Team Member(s)          Responsibilities
         [Role Title]                    [Name(s)]                       [Replace this text with a
                                                                         description of the Role
                                                                         Responsibilities.]




8      PROJECT REFERENCES

         Milestone                          Deliverable
         [Name of                           [Description with available hyperlinks]
         Document/Reference]




Confidential                                      Page 6                                        1/9/2012
Project Charter


9      APPROVALS
Prepared by    __________________________________
               Project Manager

Approved by    __________________________________
               Project Sponsor

               __________________________________
               Executive Sponsor

               __________________________________
               Client Sponsor




Confidential                          Page 7         1/9/2012
Project Charter


10     APPENDICES

10.1 Document Guidelines




10.2 Project Charter Document Sections Omitted




Confidential                     Page 8          1/9/2012

More Related Content

What's hot

13.1 Identify Stakeholders
13.1 Identify Stakeholders13.1 Identify Stakeholders
13.1 Identify StakeholdersDavidMcLachlan1
 
12.1 Plan Procurement Management
12.1 Plan Procurement Management12.1 Plan Procurement Management
12.1 Plan Procurement ManagementDavidMcLachlan1
 
Project Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern SampleProject Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern SampleAndrew Schwartz
 
009. project communication management
009. project communication management009. project communication management
009. project communication managementBoobalan G
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementMohamed Loey
 
Having a PMO with agile flavor
Having a PMO with agile flavorHaving a PMO with agile flavor
Having a PMO with agile flavorImad Alsadeq
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overviewAnand Bobade
 
Ms project 2016 overview
Ms project 2016 overviewMs project 2016 overview
Ms project 2016 overviewMaher Almohamad
 
PMI Project Management Framework
PMI Project Management FrameworkPMI Project Management Framework
PMI Project Management FrameworkAarti Dahiya PMP
 
Ms project training ppt
Ms project training pptMs project training ppt
Ms project training pptglobalp7
 
Effective GOVERNANCE in Project Portfolio Management
Effective GOVERNANCE in Project Portfolio ManagementEffective GOVERNANCE in Project Portfolio Management
Effective GOVERNANCE in Project Portfolio ManagementMichal Augustini
 
An Introduction to Project Management
An Introduction to Project Management An Introduction to Project Management
An Introduction to Project Management Krishna Kant
 
PMP chap 1 - PMP Introduction (PMBOK 6)
PMP chap 1 - PMP  Introduction (PMBOK 6)PMP chap 1 - PMP  Introduction (PMBOK 6)
PMP chap 1 - PMP Introduction (PMBOK 6)Anand Bobade
 
Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control ProcurementAnand Bobade
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Jeremy Jay Lim
 
The Project Management Process - Week 6 Leadership
The Project Management Process - Week 6   LeadershipThe Project Management Process - Week 6   Leadership
The Project Management Process - Week 6 LeadershipCraig Brown
 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify RisksAnand Bobade
 

What's hot (20)

13.1 Identify Stakeholders
13.1 Identify Stakeholders13.1 Identify Stakeholders
13.1 Identify Stakeholders
 
12.1 Plan Procurement Management
12.1 Plan Procurement Management12.1 Plan Procurement Management
12.1 Plan Procurement Management
 
Project Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern SampleProject Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern Sample
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
009. project communication management
009. project communication management009. project communication management
009. project communication management
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project Management
 
Having a PMO with agile flavor
Having a PMO with agile flavorHaving a PMO with agile flavor
Having a PMO with agile flavor
 
Pmo Why?
Pmo Why?Pmo Why?
Pmo Why?
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overview
 
Ms project 2016 overview
Ms project 2016 overviewMs project 2016 overview
Ms project 2016 overview
 
PMI Project Management Framework
PMI Project Management FrameworkPMI Project Management Framework
PMI Project Management Framework
 
Ms project training ppt
Ms project training pptMs project training ppt
Ms project training ppt
 
Effective GOVERNANCE in Project Portfolio Management
Effective GOVERNANCE in Project Portfolio ManagementEffective GOVERNANCE in Project Portfolio Management
Effective GOVERNANCE in Project Portfolio Management
 
An Introduction to Project Management
An Introduction to Project Management An Introduction to Project Management
An Introduction to Project Management
 
PMP chap 1 - PMP Introduction (PMBOK 6)
PMP chap 1 - PMP  Introduction (PMBOK 6)PMP chap 1 - PMP  Introduction (PMBOK 6)
PMP chap 1 - PMP Introduction (PMBOK 6)
 
Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control Procurement
 
Program Management Deployment Concept Consulting
Program Management Deployment Concept ConsultingProgram Management Deployment Concept Consulting
Program Management Deployment Concept Consulting
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)
 
The Project Management Process - Week 6 Leadership
The Project Management Process - Week 6   LeadershipThe Project Management Process - Week 6   Leadership
The Project Management Process - Week 6 Leadership
 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify Risks
 

Similar to Project management plan floating an ipo

Agenda for Project Status Meeting
Agenda for Project Status MeetingAgenda for Project Status Meeting
Agenda for Project Status Meetingdmdk12
 
Project scope statement template v2.3
Project scope statement template v2.3Project scope statement template v2.3
Project scope statement template v2.3Aditya Pandey
 
TopGear Corporation Project CharterProject NameProject De.docx
TopGear Corporation Project CharterProject NameProject De.docxTopGear Corporation Project CharterProject NameProject De.docx
TopGear Corporation Project CharterProject NameProject De.docxedwardmarivel
 
Put your logo herePut your organization name hereProject Sco.docx
Put your logo herePut your organization name hereProject Sco.docxPut your logo herePut your organization name hereProject Sco.docx
Put your logo herePut your organization name hereProject Sco.docxamrit47
 
Project CharterProject Charter DocumentProject Name.docx
Project CharterProject Charter DocumentProject Name.docxProject CharterProject Charter DocumentProject Name.docx
Project CharterProject Charter DocumentProject Name.docxbriancrawford30935
 
Project manager project-plan-template-cm
Project manager project-plan-template-cmProject manager project-plan-template-cm
Project manager project-plan-template-cmPrasad Reddy
 
Basics of Project Planning
Basics of Project PlanningBasics of Project Planning
Basics of Project PlanningZilicus
 
Project management plan_template
Project management plan_templateProject management plan_template
Project management plan_templateRaquel Shirazi
 
Version #Implemented byRevision DateApproved byApproval Da.docx
Version #Implemented byRevision DateApproved byApproval Da.docxVersion #Implemented byRevision DateApproved byApproval Da.docx
Version #Implemented byRevision DateApproved byApproval Da.docxjessiehampson
 
Software development plan template
Software development plan templateSoftware development plan template
Software development plan templateRina Wijaya
 
Softwaredevelopmentplantemplate 170323125907
Softwaredevelopmentplantemplate 170323125907Softwaredevelopmentplantemplate 170323125907
Softwaredevelopmentplantemplate 170323125907ahmady
 
Project charter
Project charterProject charter
Project charterArudhra N
 
Adeptus Health InternationalProject Name Project Management .docx
Adeptus Health InternationalProject Name Project Management .docxAdeptus Health InternationalProject Name Project Management .docx
Adeptus Health InternationalProject Name Project Management .docxgalerussel59292
 
Adeptus Health InternationalProject Name Project Management .docx
Adeptus Health InternationalProject Name Project Management .docxAdeptus Health InternationalProject Name Project Management .docx
Adeptus Health InternationalProject Name Project Management .docxbobbywlane695641
 
Project closure template v3.0
Project closure template v3.0Project closure template v3.0
Project closure template v3.0Aditya Pandey
 
Cdc up business_impact_analysis_template
Cdc up business_impact_analysis_templateCdc up business_impact_analysis_template
Cdc up business_impact_analysis_templatedimakarmi
 
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docxRUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docxtoltonkendal
 
EXECUTION PLAN REVISION HISTORYVersion #Implemented byRe
EXECUTION PLAN REVISION HISTORYVersion #Implemented byReEXECUTION PLAN REVISION HISTORYVersion #Implemented byRe
EXECUTION PLAN REVISION HISTORYVersion #Implemented byReBetseyCalderon89
 

Similar to Project management plan floating an ipo (20)

Agenda for Project Status Meeting
Agenda for Project Status MeetingAgenda for Project Status Meeting
Agenda for Project Status Meeting
 
Project scope statement template v2.3
Project scope statement template v2.3Project scope statement template v2.3
Project scope statement template v2.3
 
TopGear Corporation Project CharterProject NameProject De.docx
TopGear Corporation Project CharterProject NameProject De.docxTopGear Corporation Project CharterProject NameProject De.docx
TopGear Corporation Project CharterProject NameProject De.docx
 
Put your logo herePut your organization name hereProject Sco.docx
Put your logo herePut your organization name hereProject Sco.docxPut your logo herePut your organization name hereProject Sco.docx
Put your logo herePut your organization name hereProject Sco.docx
 
Project CharterProject Charter DocumentProject Name.docx
Project CharterProject Charter DocumentProject Name.docxProject CharterProject Charter DocumentProject Name.docx
Project CharterProject Charter DocumentProject Name.docx
 
Project manager project-plan-template-cm
Project manager project-plan-template-cmProject manager project-plan-template-cm
Project manager project-plan-template-cm
 
Basics of Project Planning
Basics of Project PlanningBasics of Project Planning
Basics of Project Planning
 
Project management plan_template
Project management plan_templateProject management plan_template
Project management plan_template
 
Version #Implemented byRevision DateApproved byApproval Da.docx
Version #Implemented byRevision DateApproved byApproval Da.docxVersion #Implemented byRevision DateApproved byApproval Da.docx
Version #Implemented byRevision DateApproved byApproval Da.docx
 
Software development plan template
Software development plan templateSoftware development plan template
Software development plan template
 
Softwaredevelopmentplantemplate 170323125907
Softwaredevelopmentplantemplate 170323125907Softwaredevelopmentplantemplate 170323125907
Softwaredevelopmentplantemplate 170323125907
 
Project charter
Project charterProject charter
Project charter
 
Adeptus Health InternationalProject Name Project Management .docx
Adeptus Health InternationalProject Name Project Management .docxAdeptus Health InternationalProject Name Project Management .docx
Adeptus Health InternationalProject Name Project Management .docx
 
Adeptus Health InternationalProject Name Project Management .docx
Adeptus Health InternationalProject Name Project Management .docxAdeptus Health InternationalProject Name Project Management .docx
Adeptus Health InternationalProject Name Project Management .docx
 
Project closure template v3.0
Project closure template v3.0Project closure template v3.0
Project closure template v3.0
 
Cdc up business_impact_analysis_template
Cdc up business_impact_analysis_templateCdc up business_impact_analysis_template
Cdc up business_impact_analysis_template
 
Charter template 17.01.15
Charter template 17.01.15Charter template 17.01.15
Charter template 17.01.15
 
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docxRUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
 
CDC Risk Mgmt Template
CDC Risk Mgmt TemplateCDC Risk Mgmt Template
CDC Risk Mgmt Template
 
EXECUTION PLAN REVISION HISTORYVersion #Implemented byRe
EXECUTION PLAN REVISION HISTORYVersion #Implemented byReEXECUTION PLAN REVISION HISTORYVersion #Implemented byRe
EXECUTION PLAN REVISION HISTORYVersion #Implemented byRe
 

Recently uploaded

Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetDenis Gagné
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdftbatkhuu1
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 

Recently uploaded (20)

Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdf
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 

Project management plan floating an ipo

  • 1. Project Charter Document Project Name: To float an IPO for Facebook Department:Underwriting Focus Area:New securities Product/Process: IPO Prepared By Document Owner(s) Project/Organization Role Usha Joshi Lead Underwriter VivekRathod Underwriter SydVyawahare Underwriter Project Charter Version Control Version Date Author Change Description 1.0.0 Nov 12th Usha Joshi Document created 2011 Confidential projectmanagementplan-floatinganipo-120109235032-phpapp02.docx Last printed on 1/9/2012 9:50:00 PM
  • 2. Project Charter TABLE OF CONTENTS 1 PROJECT CHARTER PURPOSE ........................................................................................... 3 2 PROJECT EXECUTIVE SUMMARY ....................................................................................... 3 3 PROJECT OVERVIEW ............................................................................................................ 3 4 PROJECT SCOPE................................................................................................................... 3 4.1 Goals and Objectives .................................................................................................. 3 4.2 Departmental Statements of Work (SOW) .................................................................. 4 4.3 Organizational Impacts ............................................................................................... 4 4.4 Project Deliverables .................................................................................................... 4 4.5 Deliverables Out of Scope .......................................................................................... 4 4.6 Project Estimated Costs & Duration............................................................................ 5 5 PROJECT CONDITIONS ........................................................................................................ 5 5.1 Project Assumptions ................................................................................................... 5 5.2 Project Issues.............................................................................................................. 5 5.3 Project Risks ............................................................................................................... 5 5.4 Project Constraints ...................................................................................................... 6 6 PROJECT STRUCTURE APPROACH ................................................................................... 6 7 PROJECT TEAM ORGANIZATION PLANS ........................................................................... 6 8 PROJECT REFERENCES ...................................................................................................... 6 9 APPROVALS ........................................................................................................................... 7 10 APPENDICES .......................................................................................................................... 8 10.1 Document Guidelines .................................................................................................. 8 10.2 Project Charter Document Sections Omitted .............................................................. 8 Confidential Page 2 1/9/2012
  • 3. Project Charter 1 PROJECT CHARTER PURPOSE [The scope of the project is limited to carrying out all the necessary activities for registering Facebook with the Securities and Exchange Commission. The company will enable Facebook to make its first sale of stock to the public. The price of the stock will be pre-determined in consultation with the Facebook management. The project is aimed to be completed from the date of the contract, the details of which will be included in the Time Management subsidiary plan.] The project charter defines the scope, objectives, and overall approach for the work to be completed. It is a critical element for initiating, planning, executing, controlling, and assessing the project. It should be the single point of reference on the project for project goals and objectives, scope, organization, estimates, work plan, and budget. In addition, it serves as a contract between the Project Team and the Project Sponsors, stating what will be delivered according to the budget, time constraints, risks, resources, and standards agreed upon for the project. 2 PROJECT EXECUTIVE SUMMARY [Replace this text with a high-level view of: project goals objectives scope assumptions risks costs timeline approach organization] 3 PROJECT OVERVIEW [Replace this text with the rationale and business justification for undertaking this project.] 4 PROJECT SCOPE 4.1 Goals and Objectives Goals Objectives [Replace this text with [Replace this text with Objectives for each Goal. For Confidential Page 3 1/9/2012
  • 4. Project Charter Project Goals. For example: example: The project will 1. Develop a system by June that tracks an end-to-end provide an improved process for 100% of product returns. system for managing product returns.] 2. Integrate new system with Sales in order to improve customer satisfaction 40% by year end.] 4.2 Departmental Statements of Work (SOW) Departmental SOW Owner/Prime Due Date/Sequence 4.3 Organizational Impacts Impact to and Participation of Organization Organization 4.4 Project Deliverables Milestone Deliverable 1. [Milestone Description] [Deliverable 1—description] [Deliverable 2—description] [Deliverable n—description] 2. [Milestone Description] [Deliverable 1—description] [Deliverable 2—description] [Deliverable n—description] 3. 4.5 Deliverables Out of Scope [Replace this text with a description of key logical areas not considered part of the boundaries of this project. Examples of theseOut-of-Scope Deliverables may include data, processes, applications, or business management.] Confidential Page 4 1/9/2012
  • 5. Project Charter 4.6 Project Estimated Costs & Duration Project Date Milestone Estimate Deliverable(s) Included Confidence Level [Milestone 1] [mm/dd/yy] [Deliverable 1] [High/Medium/Low] [Deliverable 2] [Milestone 2] [mm/dd/yy] [Deliverable 1] [High/Medium/Low] [Deliverable 2] 5 PROJECT CONDITIONS 5.1 Project Assumptions [Assumption 1] [Assumption 2] [Assumption 3] 5.2 Project Issues Priority Criteria 1−High-priority/critical-path issue; requires immediate follow-up and resolution. 2 −Medium-priority issue; requires follow-up before completion of next project milestone. 3 −Low-priority issue; to be resolved prior to project completion. 4−Closed issue. # Date Priority Owner Description Status & Resolution 1 [mm/dd/yy] [Issue 1 [Replace this text with description] Status and Proposed or Actual Resolution.] 2 [mm/dd/yy] [Issue 2 [Replace this text with description] Status and Proposed or Actual Resolution.] 5.3 Project Risks # Risk Area Likelihood RiskOwner Project Impact-Mitigation Plan 1 [Project [High/Medium [Replace this text with a description Risk] /Low] of the Mitigation Plan.] 2 [Project [High/Medium [Replace this text with a description Confidential Page 5 1/9/2012
  • 6. Project Charter # Risk Area Likelihood RiskOwner Project Impact-Mitigation Plan Risk] /Low] of the Mitigation Plan.] 5.4 Project Constraints [Replace this text with a description of a Constraint.] [Constraint 2] [Constraint 3] 6 Project Structure Approach [Replace this text with a description of how the project will be structured and what approach will be used to manage the project. What are the dependencies of the project? How will you Plan and Manage the project?] 7 Project Team Organization Plans Project Team Role Project Team Member(s) Responsibilities [Role Title] [Name(s)] [Replace this text with a description of the Role Responsibilities.] 8 PROJECT REFERENCES Milestone Deliverable [Name of [Description with available hyperlinks] Document/Reference] Confidential Page 6 1/9/2012
  • 7. Project Charter 9 APPROVALS Prepared by __________________________________ Project Manager Approved by __________________________________ Project Sponsor __________________________________ Executive Sponsor __________________________________ Client Sponsor Confidential Page 7 1/9/2012
  • 8. Project Charter 10 APPENDICES 10.1 Document Guidelines 10.2 Project Charter Document Sections Omitted Confidential Page 8 1/9/2012