2. 1. Point precinct
2. Maydon Wharf precinct
3. Durban Container Terminal precinct
4. Operation Phakisa projects
CONTENTS
3. POINT PRECINCT
POINT PRECINCT
PROJECT: PERMANENT SAND BYPASS
Progress to date:
Construction Phase
• Started in July 2012
• Main Civil Works 100% Complete.
• Pipes and pumps installed.
• Electrical connection complete.
Commissioning
• Started in September 2016
• Water commissioning 70%. Resume 18 April 2017
• Slurry commissioning 20%. Resume 4 May 2017
• Performance Testing 0%. Commence 9 May 2017
Handover:
• Target date is May 2017
Notes:
• Direct Discharge Line is operational and 600 000 cubes of sand have been supplied to the beaches.
4. MAYDON WHARF PROJECT : Rehabilitation of Maydon Wharf berths
Scope of Works Replacement of old steel sheet pile at Berths 1-4, 12 ,13 and 14 with new deep water berths.
Progress to date:
• As per weekly update on following slides.
MAYDON WHARF PRECINCT
5.
6.
7. RECONSTRUCTION & DEEPENING OF MAYDON
WHARF BERTHS 1 & 2
The image below is evidence of the above statements.
8. RECONSTRUCTION & DEEPENING OF MAYDON WHARF BERTHS 3 & 4
The image below is evidence of the above statements.
9. RECONSTRUCTION & DEEPENING OF MAYDON WHARF BERTHS 1 -4, 13
& 14The image below is evidence of the above statements.
10. DURBAN CONTAINER TERMINAL
BERTH DEEPENING: BERTH 203 , 204 , 205
Progress to date:
• Detailed design 100% complete
• FEL 03 stage 100% complete
• Ministerial approval (DPE & DEA) 100% complete
Procurement:
• Tendering phase 30% complete
• Anticipated contract Award Aug 2018
• Targeted execution date Jan 2019
SALISBURY ISLAND INFILL
Progress to date:
• FEL 3 60% complete
Targeted submission to Gate Review Nov
2019
• EIA progress TNPA is preparing an
Environmental Impact Report and conducting
Specialist environmental studies.
• Anticipated contract Award July 2021
• Awaiting Signing of the Lease Agreement by
DPW.
• Negotiations on going.
• Anticipated contract completion July 2026
11. Progress to date
BAYHEAD PARK – Operation Phakisa
Durban Projects FEL Percentage Completed
Rehabilitation of the inner caisson FEL 2
FEL 2 - 100% complete. In a request for funding
process.
Overhead Cranes for Workshop 24 &
Pump House
FEL 3
75% complete, project at design stage. Completion
19 April 2017.
Equipment Upgrade for Workshop 24 FEL 4
55% complete, tender to be awarded by 31 March
2017. Contract starts on 03 April 2017.
Pump House Upgrade FEL 3
55% complete, tender was awarded. Design in
progress. Completion 31 May 2017.
Fire System Upgrade FEL 3
55% complete, tender was awarded. Design in
progress. Completion 15 June 2017.
Dry Dock Capstans FEL 2
FEL 2 - 100% complete. In a request for funding
process.
Replacement of South Side Crane Rail at
Dry Dock
FEL 3
29% complete, project is at feasibility stage. This will
be executed concurrently to the Jib Cranes
Upgrade of the Floating Dock FEL 2
FEL 2 - 100% complete. Pursuing alternative funding
through the “Section 56” process is in progress.
Jib Cranes FEL 3
13% complete, project will be executed in
collaboration with Transnet Engineering
• Outer Caisson Rehabilitation
• Dry Dock Concrete Repairs
• Procurement of 6ton Forklift
• Procurement of Welding Equipment
Completed Project.