SlideShare a Scribd company logo
1 of 12
Download to read offline
Results Announcement 2016
DURBAN PORT COMMITTEE
Port Development Projects
20 April 2017
1. Point precinct
2. Maydon Wharf precinct
3. Durban Container Terminal precinct
4. Operation Phakisa projects
CONTENTS
POINT PRECINCT
POINT PRECINCT
PROJECT: PERMANENT SAND BYPASS
Progress to date:
Construction Phase
• Started in July 2012
• Main Civil Works 100% Complete.
• Pipes and pumps installed.
• Electrical connection complete.
Commissioning
• Started in September 2016
• Water commissioning 70%. Resume 18 April 2017
• Slurry commissioning 20%. Resume 4 May 2017
• Performance Testing 0%. Commence 9 May 2017
Handover:
• Target date is May 2017
Notes:
• Direct Discharge Line is operational and 600 000 cubes of sand have been supplied to the beaches.
MAYDON WHARF PROJECT : Rehabilitation of Maydon Wharf berths
Scope of Works Replacement of old steel sheet pile at Berths 1-4, 12 ,13 and 14 with new deep water berths.
Progress to date:
• As per weekly update on following slides.
MAYDON WHARF PRECINCT
RECONSTRUCTION & DEEPENING OF MAYDON
WHARF BERTHS 1 & 2
The image below is evidence of the above statements.
RECONSTRUCTION & DEEPENING OF MAYDON WHARF BERTHS 3 & 4
The image below is evidence of the above statements.
RECONSTRUCTION & DEEPENING OF MAYDON WHARF BERTHS 1 -4, 13
& 14The image below is evidence of the above statements.
DURBAN CONTAINER TERMINAL
BERTH DEEPENING: BERTH 203 , 204 , 205
Progress to date:
• Detailed design  100% complete
• FEL 03 stage  100% complete
• Ministerial approval (DPE & DEA) 100% complete
Procurement:
• Tendering phase  30% complete
• Anticipated contract Award  Aug 2018
• Targeted execution date  Jan 2019
SALISBURY ISLAND INFILL
Progress to date:
• FEL 3  60% complete
Targeted submission to Gate Review Nov
2019
• EIA progress  TNPA is preparing an
Environmental Impact Report and conducting
Specialist environmental studies.
• Anticipated contract Award  July 2021
• Awaiting Signing of the Lease Agreement by
DPW.
• Negotiations on going.
• Anticipated contract completion July 2026
Progress to date
BAYHEAD PARK – Operation Phakisa
Durban Projects FEL Percentage Completed
Rehabilitation of the inner caisson FEL 2
FEL 2 - 100% complete. In a request for funding
process.
Overhead Cranes for Workshop 24 &
Pump House
FEL 3
75% complete, project at design stage. Completion
19 April 2017.
Equipment Upgrade for Workshop 24 FEL 4
55% complete, tender to be awarded by 31 March
2017. Contract starts on 03 April 2017.
Pump House Upgrade FEL 3
55% complete, tender was awarded. Design in
progress. Completion 31 May 2017.
Fire System Upgrade FEL 3
55% complete, tender was awarded. Design in
progress. Completion 15 June 2017.
Dry Dock Capstans FEL 2
FEL 2 - 100% complete. In a request for funding
process.
Replacement of South Side Crane Rail at
Dry Dock
FEL 3
29% complete, project is at feasibility stage. This will
be executed concurrently to the Jib Cranes
Upgrade of the Floating Dock FEL 2
FEL 2 - 100% complete. Pursuing alternative funding
through the “Section 56” process is in progress.
Jib Cranes FEL 3
13% complete, project will be executed in
collaboration with Transnet Engineering
• Outer Caisson Rehabilitation
• Dry Dock Concrete Repairs
• Procurement of 6ton Forklift
• Procurement of Welding Equipment
Completed Project.
Thank You

More Related Content

What's hot

60% Design and Cost Estimate
60% Design and Cost Estimate60% Design and Cost Estimate
60% Design and Cost Estimatepublicinvolvement
 
101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E Heiland101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E HeilandErik Heiland
 
Little Hunting Creek Pump Station Rehabilitation
Little Hunting Creek Pump Station RehabilitationLittle Hunting Creek Pump Station Rehabilitation
Little Hunting Creek Pump Station RehabilitationFairfax County
 
Mc kenna great marsh symposium 11-12-14
Mc kenna great marsh symposium 11-12-14Mc kenna great marsh symposium 11-12-14
Mc kenna great marsh symposium 11-12-14greenbelt82
 
AtoP Pipeline fro linked in
AtoP Pipeline fro linked inAtoP Pipeline fro linked in
AtoP Pipeline fro linked inHelen Simpson
 
Project Milestones quotes from Project Director
Project Milestones quotes from Project DirectorProject Milestones quotes from Project Director
Project Milestones quotes from Project DirectorFabien Deschamps
 
Lakevale Sewer Improvements Community Meeting
Lakevale Sewer Improvements Community MeetingLakevale Sewer Improvements Community Meeting
Lakevale Sewer Improvements Community MeetingFairfax County
 
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meeting
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meetingTysons Fire Station #29 and Bus Transit Facility - 111621 community meeting
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meetingFairfax County
 
Public Facilities Manual Flexibility Project : Update to the Development Proc...
Public Facilities Manual Flexibility Project : Update to the Development Proc...Public Facilities Manual Flexibility Project : Update to the Development Proc...
Public Facilities Manual Flexibility Project : Update to the Development Proc...Fairfax County
 
High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations Project
  High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations Project  High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations Project
High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations ProjectFairfax County
 
OC harbor brook wetlands stakeholder 6 15-11 final-1
OC harbor brook wetlands stakeholder 6 15-11 final-1OC harbor brook wetlands stakeholder 6 15-11 final-1
OC harbor brook wetlands stakeholder 6 15-11 final-1Onondaga County Save the Rain
 
Lick Creek Wastewater Treatment Plant Expansion
Lick Creek Wastewater Treatment Plant Expansion Lick Creek Wastewater Treatment Plant Expansion
Lick Creek Wastewater Treatment Plant Expansion City of College Station
 
Kirby Road Emergency Gravity Sewer Repair Completed November 2020
Kirby Road Emergency Gravity Sewer Repair Completed November 2020Kirby Road Emergency Gravity Sewer Repair Completed November 2020
Kirby Road Emergency Gravity Sewer Repair Completed November 2020Fairfax County
 
Huntington Levee Community Meeting: Nov. 1, 2017
Huntington Levee Community Meeting: Nov. 1, 2017Huntington Levee Community Meeting: Nov. 1, 2017
Huntington Levee Community Meeting: Nov. 1, 2017Fairfax County
 

What's hot (20)

60% Design and Cost Estimate
60% Design and Cost Estimate60% Design and Cost Estimate
60% Design and Cost Estimate
 
101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E Heiland101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E Heiland
 
Little Hunting Creek Pump Station Rehabilitation
Little Hunting Creek Pump Station RehabilitationLittle Hunting Creek Pump Station Rehabilitation
Little Hunting Creek Pump Station Rehabilitation
 
Chp presentation 1st july 2015
Chp presentation 1st july 2015Chp presentation 1st july 2015
Chp presentation 1st july 2015
 
Mc kenna great marsh symposium 11-12-14
Mc kenna great marsh symposium 11-12-14Mc kenna great marsh symposium 11-12-14
Mc kenna great marsh symposium 11-12-14
 
Linkedin-Doc
Linkedin-DocLinkedin-Doc
Linkedin-Doc
 
AtoP Pipeline fro linked in
AtoP Pipeline fro linked inAtoP Pipeline fro linked in
AtoP Pipeline fro linked in
 
Project Milestones quotes from Project Director
Project Milestones quotes from Project DirectorProject Milestones quotes from Project Director
Project Milestones quotes from Project Director
 
Lakevale Sewer Improvements Community Meeting
Lakevale Sewer Improvements Community MeetingLakevale Sewer Improvements Community Meeting
Lakevale Sewer Improvements Community Meeting
 
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meeting
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meetingTysons Fire Station #29 and Bus Transit Facility - 111621 community meeting
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meeting
 
Interlocal Agreement with Wellborn SUD
Interlocal Agreement with Wellborn SUDInterlocal Agreement with Wellborn SUD
Interlocal Agreement with Wellborn SUD
 
Public Facilities Manual Flexibility Project : Update to the Development Proc...
Public Facilities Manual Flexibility Project : Update to the Development Proc...Public Facilities Manual Flexibility Project : Update to the Development Proc...
Public Facilities Manual Flexibility Project : Update to the Development Proc...
 
SLRD - Bralorne Sewer Upgrade: Project Update (June 28, 2018)
SLRD - Bralorne Sewer Upgrade: Project Update (June 28, 2018)SLRD - Bralorne Sewer Upgrade: Project Update (June 28, 2018)
SLRD - Bralorne Sewer Upgrade: Project Update (June 28, 2018)
 
High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations Project
  High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations Project  High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations Project
High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations Project
 
OC harbor brook wetlands stakeholder 6 15-11 final-1
OC harbor brook wetlands stakeholder 6 15-11 final-1OC harbor brook wetlands stakeholder 6 15-11 final-1
OC harbor brook wetlands stakeholder 6 15-11 final-1
 
City council june 18, 2013 hickory update
City council june 18, 2013   hickory updateCity council june 18, 2013   hickory update
City council june 18, 2013 hickory update
 
Lick Creek Wastewater Treatment Plant Expansion
Lick Creek Wastewater Treatment Plant Expansion Lick Creek Wastewater Treatment Plant Expansion
Lick Creek Wastewater Treatment Plant Expansion
 
Kirby Road Emergency Gravity Sewer Repair Completed November 2020
Kirby Road Emergency Gravity Sewer Repair Completed November 2020Kirby Road Emergency Gravity Sewer Repair Completed November 2020
Kirby Road Emergency Gravity Sewer Repair Completed November 2020
 
Kalorama Community Meeting (July 17, 2014)
Kalorama Community Meeting (July 17, 2014)Kalorama Community Meeting (July 17, 2014)
Kalorama Community Meeting (July 17, 2014)
 
Huntington Levee Community Meeting: Nov. 1, 2017
Huntington Levee Community Meeting: Nov. 1, 2017Huntington Levee Community Meeting: Nov. 1, 2017
Huntington Levee Community Meeting: Nov. 1, 2017
 

Similar to Durban Port Committee Announces 2016 Results and Development Projects

Leaside Laird CLC November 2019 Presentation
Leaside Laird CLC November 2019 PresentationLeaside Laird CLC November 2019 Presentation
Leaside Laird CLC November 2019 PresentationCrosstown TO
 
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018Fairfax County
 
C&ess presentation performance review 2016 (copy 1)
C&ess presentation  performance review 2016 (copy 1)C&ess presentation  performance review 2016 (copy 1)
C&ess presentation performance review 2016 (copy 1)Baig Ali
 
C&ess presentation performance review 2016 (copy 1)
C&ess presentation  performance review 2016 (copy 1)C&ess presentation  performance review 2016 (copy 1)
C&ess presentation performance review 2016 (copy 1)Baig Ali
 
Meeting of the brossard good neighbourly relations committee september 21 2016
Meeting of the brossard good neighbourly relations committee   september 21 2016Meeting of the brossard good neighbourly relations committee   september 21 2016
Meeting of the brossard good neighbourly relations committee september 21 2016Pont Samuel-De Champlain Bridge
 
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017Pont Samuel-De Champlain Bridge
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...Fairfax County
 
Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdfCLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdfCrosstown TO
 
Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019Crosstown TO
 
Brossard Good Neighbourly Relations Committee - May 17, 2017
Brossard Good Neighbourly Relations Committee - May 17, 2017Brossard Good Neighbourly Relations Committee - May 17, 2017
Brossard Good Neighbourly Relations Committee - May 17, 2017Pont Samuel-De Champlain Bridge
 
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Leaside - Laird Construction Liaison Committee Meeting  - July 2017Leaside - Laird Construction Liaison Committee Meeting  - July 2017
Leaside - Laird Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Addison Capital Projects Update
Addison Capital Projects UpdateAddison Capital Projects Update
Addison Capital Projects UpdateTownofAddison
 
Project charter presentation
Project charter presentationProject charter presentation
Project charter presentationKunal Gudwani
 
20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptxAmirShafiq25
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingCrosstown TO
 
Virtual Open House: Eastern Works
Virtual Open House: Eastern WorksVirtual Open House: Eastern Works
Virtual Open House: Eastern WorksCrosstown TO
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingCrosstown TO
 
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020Crosstown TO
 

Similar to Durban Port Committee Announces 2016 Results and Development Projects (20)

Leaside Laird CLC November 2019 Presentation
Leaside Laird CLC November 2019 PresentationLeaside Laird CLC November 2019 Presentation
Leaside Laird CLC November 2019 Presentation
 
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
 
C&ess presentation performance review 2016 (copy 1)
C&ess presentation  performance review 2016 (copy 1)C&ess presentation  performance review 2016 (copy 1)
C&ess presentation performance review 2016 (copy 1)
 
C&ess presentation performance review 2016 (copy 1)
C&ess presentation  performance review 2016 (copy 1)C&ess presentation  performance review 2016 (copy 1)
C&ess presentation performance review 2016 (copy 1)
 
Meeting of the brossard good neighbourly relations committee september 21 2016
Meeting of the brossard good neighbourly relations committee   september 21 2016Meeting of the brossard good neighbourly relations committee   september 21 2016
Meeting of the brossard good neighbourly relations committee september 21 2016
 
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
 
Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019
 
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdfCLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
 
Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019
 
Brossard Good Neighbourly Relations Committee - May 17, 2017
Brossard Good Neighbourly Relations Committee - May 17, 2017Brossard Good Neighbourly Relations Committee - May 17, 2017
Brossard Good Neighbourly Relations Committee - May 17, 2017
 
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Leaside - Laird Construction Liaison Committee Meeting  - July 2017Leaside - Laird Construction Liaison Committee Meeting  - July 2017
Leaside - Laird Construction Liaison Committee Meeting - July 2017
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
 
Addison Capital Projects Update
Addison Capital Projects UpdateAddison Capital Projects Update
Addison Capital Projects Update
 
Project charter presentation
Project charter presentationProject charter presentation
Project charter presentation
 
20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Virtual Open House: Eastern Works
Virtual Open House: Eastern WorksVirtual Open House: Eastern Works
Virtual Open House: Eastern Works
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC Meeting
 
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
 

More from Marketing Durban Chamber

Smme forum business optimization - 08 june 2017
Smme forum   business optimization - 08 june 2017Smme forum   business optimization - 08 june 2017
Smme forum business optimization - 08 june 2017Marketing Durban Chamber
 
Health Professionals Business Forum - 06 April 2017
Health Professionals Business Forum - 06 April 2017Health Professionals Business Forum - 06 April 2017
Health Professionals Business Forum - 06 April 2017Marketing Durban Chamber
 
Infrastructure and Northern Area Business Forum
Infrastructure and Northern Area Business ForumInfrastructure and Northern Area Business Forum
Infrastructure and Northern Area Business ForumMarketing Durban Chamber
 
Infrastructure and Northern Area Business Forum
Infrastructure and Northern Area Business Forum Infrastructure and Northern Area Business Forum
Infrastructure and Northern Area Business Forum Marketing Durban Chamber
 
Combined Durban Port Committee and Western Area Business Forum
Combined Durban Port Committee and Western Area Business ForumCombined Durban Port Committee and Western Area Business Forum
Combined Durban Port Committee and Western Area Business ForumMarketing Durban Chamber
 

More from Marketing Durban Chamber (20)

Smme forum business optimization - 08 june 2017
Smme forum   business optimization - 08 june 2017Smme forum   business optimization - 08 june 2017
Smme forum business optimization - 08 june 2017
 
Environmental Affairs Forum - 15 June
Environmental Affairs Forum - 15 June Environmental Affairs Forum - 15 June
Environmental Affairs Forum - 15 June
 
Environmental Affairs Forum - 15 June
Environmental Affairs Forum - 15 June Environmental Affairs Forum - 15 June
Environmental Affairs Forum - 15 June
 
Environmental Affairs Forum - 15 June
Environmental Affairs Forum - 15 June Environmental Affairs Forum - 15 June
Environmental Affairs Forum - 15 June
 
Trade and Investment Forum - 07 June
Trade and Investment Forum - 07 June Trade and Investment Forum - 07 June
Trade and Investment Forum - 07 June
 
Tourism Forum Business Forum - 18 April
Tourism Forum Business Forum - 18 April Tourism Forum Business Forum - 18 April
Tourism Forum Business Forum - 18 April
 
DURBAN PORT COMMITTEE - 20 April
 DURBAN PORT COMMITTEE - 20 April DURBAN PORT COMMITTEE - 20 April
DURBAN PORT COMMITTEE - 20 April
 
DURBAN PORT COMMITTEE - 20 April
DURBAN PORT COMMITTEE - 20 April DURBAN PORT COMMITTEE - 20 April
DURBAN PORT COMMITTEE - 20 April
 
EThekwini Weekly Bulletin Issue­_74
EThekwini Weekly Bulletin Issue­_74EThekwini Weekly Bulletin Issue­_74
EThekwini Weekly Bulletin Issue­_74
 
Tourism Forum Business Forum - 18 April
Tourism Forum Business Forum - 18 April Tourism Forum Business Forum - 18 April
Tourism Forum Business Forum - 18 April
 
Trade and Investment Forum - 12 April
Trade and Investment Forum - 12 AprilTrade and Investment Forum - 12 April
Trade and Investment Forum - 12 April
 
HR Forum - Update on IR climate in 2017
HR Forum - Update on IR climate in 2017HR Forum - Update on IR climate in 2017
HR Forum - Update on IR climate in 2017
 
HR Forum - Update on IR climate in 2017
HR Forum - Update on IR climate in 2017HR Forum - Update on IR climate in 2017
HR Forum - Update on IR climate in 2017
 
HR Forum - Update on IR climate in 2017
HR Forum - Update on IR climate in 2017HR Forum - Update on IR climate in 2017
HR Forum - Update on IR climate in 2017
 
HR Forum - Update on IR climate in 2017
HR Forum - Update on IR climate in 2017HR Forum - Update on IR climate in 2017
HR Forum - Update on IR climate in 2017
 
Health Professionals Business Forum - 06 April 2017
Health Professionals Business Forum - 06 April 2017Health Professionals Business Forum - 06 April 2017
Health Professionals Business Forum - 06 April 2017
 
Infrastructure and Northern Area Business Forum
Infrastructure and Northern Area Business ForumInfrastructure and Northern Area Business Forum
Infrastructure and Northern Area Business Forum
 
Infrastructure and Northern Area Business Forum
Infrastructure and Northern Area Business Forum Infrastructure and Northern Area Business Forum
Infrastructure and Northern Area Business Forum
 
Combined Durban Port Committee and Western Area Business Forum
Combined Durban Port Committee and Western Area Business ForumCombined Durban Port Committee and Western Area Business Forum
Combined Durban Port Committee and Western Area Business Forum
 
Trade and Investment Forum
Trade and Investment ForumTrade and Investment Forum
Trade and Investment Forum
 

Recently uploaded

Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetDenis Gagné
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfCatalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfOrient Homes
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 

Recently uploaded (20)

Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
 
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Best Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting PartnershipBest Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting Partnership
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfCatalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 

Durban Port Committee Announces 2016 Results and Development Projects

  • 1. Results Announcement 2016 DURBAN PORT COMMITTEE Port Development Projects 20 April 2017
  • 2. 1. Point precinct 2. Maydon Wharf precinct 3. Durban Container Terminal precinct 4. Operation Phakisa projects CONTENTS
  • 3. POINT PRECINCT POINT PRECINCT PROJECT: PERMANENT SAND BYPASS Progress to date: Construction Phase • Started in July 2012 • Main Civil Works 100% Complete. • Pipes and pumps installed. • Electrical connection complete. Commissioning • Started in September 2016 • Water commissioning 70%. Resume 18 April 2017 • Slurry commissioning 20%. Resume 4 May 2017 • Performance Testing 0%. Commence 9 May 2017 Handover: • Target date is May 2017 Notes: • Direct Discharge Line is operational and 600 000 cubes of sand have been supplied to the beaches.
  • 4. MAYDON WHARF PROJECT : Rehabilitation of Maydon Wharf berths Scope of Works Replacement of old steel sheet pile at Berths 1-4, 12 ,13 and 14 with new deep water berths. Progress to date: • As per weekly update on following slides. MAYDON WHARF PRECINCT
  • 5.
  • 6.
  • 7. RECONSTRUCTION & DEEPENING OF MAYDON WHARF BERTHS 1 & 2 The image below is evidence of the above statements.
  • 8. RECONSTRUCTION & DEEPENING OF MAYDON WHARF BERTHS 3 & 4 The image below is evidence of the above statements.
  • 9. RECONSTRUCTION & DEEPENING OF MAYDON WHARF BERTHS 1 -4, 13 & 14The image below is evidence of the above statements.
  • 10. DURBAN CONTAINER TERMINAL BERTH DEEPENING: BERTH 203 , 204 , 205 Progress to date: • Detailed design  100% complete • FEL 03 stage  100% complete • Ministerial approval (DPE & DEA) 100% complete Procurement: • Tendering phase  30% complete • Anticipated contract Award  Aug 2018 • Targeted execution date  Jan 2019 SALISBURY ISLAND INFILL Progress to date: • FEL 3  60% complete Targeted submission to Gate Review Nov 2019 • EIA progress  TNPA is preparing an Environmental Impact Report and conducting Specialist environmental studies. • Anticipated contract Award  July 2021 • Awaiting Signing of the Lease Agreement by DPW. • Negotiations on going. • Anticipated contract completion July 2026
  • 11. Progress to date BAYHEAD PARK – Operation Phakisa Durban Projects FEL Percentage Completed Rehabilitation of the inner caisson FEL 2 FEL 2 - 100% complete. In a request for funding process. Overhead Cranes for Workshop 24 & Pump House FEL 3 75% complete, project at design stage. Completion 19 April 2017. Equipment Upgrade for Workshop 24 FEL 4 55% complete, tender to be awarded by 31 March 2017. Contract starts on 03 April 2017. Pump House Upgrade FEL 3 55% complete, tender was awarded. Design in progress. Completion 31 May 2017. Fire System Upgrade FEL 3 55% complete, tender was awarded. Design in progress. Completion 15 June 2017. Dry Dock Capstans FEL 2 FEL 2 - 100% complete. In a request for funding process. Replacement of South Side Crane Rail at Dry Dock FEL 3 29% complete, project is at feasibility stage. This will be executed concurrently to the Jib Cranes Upgrade of the Floating Dock FEL 2 FEL 2 - 100% complete. Pursuing alternative funding through the “Section 56” process is in progress. Jib Cranes FEL 3 13% complete, project will be executed in collaboration with Transnet Engineering • Outer Caisson Rehabilitation • Dry Dock Concrete Repairs • Procurement of 6ton Forklift • Procurement of Welding Equipment Completed Project.