EXCELLENCE IN
EXCAVATOR PLANNING
AT DRAYTON MINE
FROM THE DESIGN TO THE IMPLEMENTATION IN THE FIELD
Erik Heiland
Anglo American Metallurgical Coal
Australia
COAL
2
CONTENTS
• Locality and Background Information
• The Excavator Planning Process
• Conclusion
COAL
3
LOCALITY AND BACKGROUND
INFORMATION
COAL
4
LOCALITY
• Hunter Valley/ New South Wales
• One of AAMC’s most challenging
operations
• Operation began in 1983
• Scheduled production in 2010:
5Mt of thermal coal
– 4Mt for export market
– 1Mt for domestic market (Liddell
and Bayswater power stations)
Map of Region
COAL
5
MINING EQUIPMENT
• Major Mining Equipment
– One BE1370 dragline
– Two Hitachi EX5500 excavators
– One Hitachi EX3500 excavator
– Two front end loaders
(Le Tourneau L1100 and L1400)
– 24 Caterpillar 789B and C trucks
• 67% of Drayton’s prime overburden
is planned to be moved by Hitachi
EX5500 excavators
• Aim: Uncover coal in the safest and
most efficient way in accordance
with the business plan schedule
BE1370 Dragline
Excavator 305
COAL
6
COMPLEX GEOLOGY
• Deposit consists of five major seam
groups with up to 40 splits
• Major geological features are:
– 45 to 60 degree steep dipping coal
seams
– Up to 40m faults
– 100m thrust plane
– Dykes
– Intrusions
• Geology creates tough working
environment for the machinery
Drayton Mine Seam Split Diagram
COAL
7
COMPLEX GEOLOGY CONT.
• Thrusting and Faulting create a major challenge for the mining operation
• Drayton has a 100m thrust plane running through the deposit
Diagrammatic Representation of Normal Faulting and Thrust Faulting
Balmorals
COAL
• An Example: South Pit East
• Thrust plane, 10 faults, seam splitting, fill, spon com…
8
COMPLEX GEOLOGY CONT.
Diagrammatic Representation of Normal Faulting and Thrust Faulting
Representative Cross-Section Through South Pit East, October 2010
Thrust plane
SectionAB
A B
Faults
shown
in black
Faults
These are the same Grasstrees seams
COAL
9
BENCHMARK PERFORMANCE
• Drayton’s excavator fleet delivers benchmark performance within AAMC
• EXC306 and 307 are ranked No. 1 and 2 in its category
• Major Key Performance Indicator: Operational Equipment Efficiency
AAMC Operational Efficiency Ranking, Above 500t Excavator Category, August 2010
COAL
10
THE EXCAVATOR PLANNING
PROCESS
COAL
11
THE EXCAVATOR PLANNING PROCESS
• Process includes eight process steps
• Bullet point 2
• Bullet point 3
• Bullet point 4
• Bullet point 5
COAL
12
MINE ACTIVITY DESIGN (MAD)
• Compliance with
AAMC Operations
Management System
• Focus on the long
term, medium term
and short term
planning, actual
production and
reconciliation
• MAD document
focuses on the
18-month planning
process The AAMC Mine Planning Process
COAL
13
16 WEEK SCHEDULE
• Visual representation of equipment path for the Dragline and two
EX5500 Excavators
• Purpose of schedule
– Identification equipment interactions
– Input data for the 16 week drill and blast schedule
– Determination of coal uncovered dates for the coal and partings schedule
– Identification of short term truck shortages or excess
The 306 Excavator Path in the 16 Week Schedule
COAL
14
MONTHLY OPERATING PLAN (MOP) DESIGN REVIEW
• Review of excavator designs for
the following month
• Determination of average
monthly dig rate per excavator
for input in schedule
• Optimisation of dig plans
• Presentation of plans by the
excavator engineer
One of Tony’s pics
Visualisation of the EN03 Broughams dig area
COAL
15
MOP DELIVERY PLAN MEETING
• Identification of critical issues
• Ensure the monthly Key Performance Indicators are achieved
• Assign actions and agree on due dates
Key Performance Indicator: Prime, Monthly Delivery Plan, September 2010
COAL
16
EXCAVATOR PLAN SIGN OFF PROCESS
• E = Q x A [Effectiveness = Quality x Acceptance]
• Ensure that final design
plans contain the most up to
date information
• Import of actual drilling data
to deliver most accurate coal
surface
• Sign off to be completed one
week before an excavator
enters the work area
Sign off for SPW09-10P and SPW08G dig
COAL
17
WEEKLY PLAN PROCESS AND PACK
• Weekly Plan Process includes a pre-planning meeting and a planning
meeting
• Agree on the weekly equipment path, blast and mining sequence,
equipment interaction
• Weekly plan pack is a comprehensive package which is sent via E-mail
to all relevant mine personnel
Weekly Plan Excavator Path, Plan commencing 7 October 2010
COAL
18
DAILY PIT COMMUNICATION
• Pit inspections are
conducted a minimum of
three times a week
• Communication of the plan
to front line personnel
• Inspection of current and
future dig and dump areas
during the tour
• Supervisor’s light vehicle
and four bull dozers are
equipped with a GPS
• Video GPS in Supervisors light vehicle – SPW09P12 dig area
COAL
19
DAILY PIT COMMUNICATION
• Minimum three times a week
• Communication of the plan
to front line personnel
• Inspection of Current and
future dig and dump areas
are inspected during the
tour
• Supervisor’s light vehicle
and four bull dozers are
equipped with a GPS
• Video
NN10 East - Excavator
N
Shot to be fired Fired
on 26/06
Vol remaining: 735kBCM
Trucks: 7
Target seam: RL
Dig Sequence
1) Continue 4.5m BSL pass from East to West to form Ramp on Northern side
2) Come off the Ramp and BSL 4.5m passes uncover unshot material from West to East
USE MATERIAL TO COVER FIRES IN SS WHEN TRUCKING AVAILABLE
BLOCKY MATERIAL IN THE SOUTH OF THE DIG AREA
GPS FILE: NN10-190
Dump
Level 7-RL295, GPS-File: LV7REH
1
2
Unshot material to
be uncovered
70Deg PS wall
45Deg Softwall
Haul route
to
East
Ramp
Application of 3D Dig Software in the NN Pit
COAL
20
DIG AREA REVIEWS
• Dig reviews are carried out within one month after completion of the dig
• Reconciliation of planned vs. actual performance
• Key learning outcomes are identified and actions assigned
• Learning outcomes are included into the next MAD document
Excavator Dig Reconciliation
COAL
21
CONCLUSION
COAL
22
CONCLUSION
Excavator Planning at Drayton is very
comprehensive process
Key reasons for success:
– Customer focus and having good
working relationships
– Input from experienced Production
personnel in the planning process
– Use of direct communication
– Accurate tracking of Key Performance
Indicators
– Compliance with Operations
Management System
COAL
23QUESTIONS?
“THE WAVE” IN THE NN PIT BW NE Steep dip

More Related Content

What's hot

Managing Massive Updates - Using GIS to Fuel Gas Compliance
Managing Massive Updates - Using GIS to Fuel Gas ComplianceManaging Massive Updates - Using GIS to Fuel Gas Compliance
Managing Massive Updates - Using GIS to Fuel Gas ComplianceSSP Innovations
 
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Crosstown TO
 
DynaRoad in the field - Case Roan wind farm (Norway)
DynaRoad in the field - Case Roan wind farm (Norway)DynaRoad in the field - Case Roan wind farm (Norway)
DynaRoad in the field - Case Roan wind farm (Norway)Viasys VDC
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018Crosstown TO
 
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017Crosstown TO
 
Jan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily ReportJan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily ReportHonolulu Civil Beat
 
Huntington Levee Community Meeting
Huntington Levee Community Meeting Huntington Levee Community Meeting
Huntington Levee Community Meeting Fairfax County
 
Leaside - Laird Construction Liaison Committee - July 2018
Leaside - Laird Construction Liaison Committee - July 2018Leaside - Laird Construction Liaison Committee - July 2018
Leaside - Laird Construction Liaison Committee - July 2018Crosstown TO
 
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017Crosstown TO
 
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...Shanmukha S. Potti
 
Spry Scheduling and Haulage model - Tutorial
Spry Scheduling and Haulage model - TutorialSpry Scheduling and Haulage model - Tutorial
Spry Scheduling and Haulage model - TutorialVR M
 
cpwss to piler and 8other habitations
cpwss to piler and 8other habitationscpwss to piler and 8other habitations
cpwss to piler and 8other habitationsPrasadreddy Nemmali
 
October 2018 Updates on Construction Work
October 2018 Updates on Construction WorkOctober 2018 Updates on Construction Work
October 2018 Updates on Construction WorkRRFHPRusumo
 
List of Completed Projects September 2015
List of Completed Projects September  2015List of Completed Projects September  2015
List of Completed Projects September 2015Haroon Pasha Dar
 

What's hot (20)

Managing Massive Updates - Using GIS to Fuel Gas Compliance
Managing Massive Updates - Using GIS to Fuel Gas ComplianceManaging Massive Updates - Using GIS to Fuel Gas Compliance
Managing Massive Updates - Using GIS to Fuel Gas Compliance
 
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
 
DynaRoad in the field - Case Roan wind farm (Norway)
DynaRoad in the field - Case Roan wind farm (Norway)DynaRoad in the field - Case Roan wind farm (Norway)
DynaRoad in the field - Case Roan wind farm (Norway)
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
 
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
 
Jan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily ReportJan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily Report
 
Huntington Levee Community Meeting
Huntington Levee Community Meeting Huntington Levee Community Meeting
Huntington Levee Community Meeting
 
Leaside - Laird Construction Liaison Committee - July 2018
Leaside - Laird Construction Liaison Committee - July 2018Leaside - Laird Construction Liaison Committee - July 2018
Leaside - Laird Construction Liaison Committee - July 2018
 
[Belle] Resume
[Belle] Resume[Belle] Resume
[Belle] Resume
 
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
 
SMHB
SMHBSMHB
SMHB
 
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...
 
Spry Scheduling and Haulage model - Tutorial
Spry Scheduling and Haulage model - TutorialSpry Scheduling and Haulage model - Tutorial
Spry Scheduling and Haulage model - Tutorial
 
Project Analysis - PPT
Project Analysis - PPTProject Analysis - PPT
Project Analysis - PPT
 
SVR Presentation
SVR PresentationSVR Presentation
SVR Presentation
 
cpwss to piler and 8other habitations
cpwss to piler and 8other habitationscpwss to piler and 8other habitations
cpwss to piler and 8other habitations
 
October 2018 Updates on Construction Work
October 2018 Updates on Construction WorkOctober 2018 Updates on Construction Work
October 2018 Updates on Construction Work
 
CVPLAING
CVPLAINGCVPLAING
CVPLAING
 
List of Completed Projects September 2015
List of Completed Projects September  2015List of Completed Projects September  2015
List of Completed Projects September 2015
 

Viewers also liked

【機械学習プロフェッショナルシリーズ】グラフィカルモデル2章
【機械学習プロフェッショナルシリーズ】グラフィカルモデル2章 【機械学習プロフェッショナルシリーズ】グラフィカルモデル2章
【機械学習プロフェッショナルシリーズ】グラフィカルモデル2章 Hakky St
 
Resumen analitico-corregido
Resumen analitico-corregidoResumen analitico-corregido
Resumen analitico-corregidoDiego Solano
 
Preguntas 1-encu-lina-escitura
Preguntas 1-encu-lina-escituraPreguntas 1-encu-lina-escitura
Preguntas 1-encu-lina-escituraDiego Solano
 
first order chemical reaction and hall effect on mhd flow past an infinite ve...
first order chemical reaction and hall effect on mhd flow past an infinite ve...first order chemical reaction and hall effect on mhd flow past an infinite ve...
first order chemical reaction and hall effect on mhd flow past an infinite ve...INFOGAIN PUBLICATION
 
2016 đhqg ks hòa kỹ thuật ghi đo
2016 đhqg ks hòa  kỹ thuật ghi đo2016 đhqg ks hòa  kỹ thuật ghi đo
2016 đhqg ks hòa kỹ thuật ghi đoSoM
 
Comunicacion social y periodismo
Comunicacion social y periodismoComunicacion social y periodismo
Comunicacion social y periodismoSombras Prieto
 
Trabajo de fisica liceo alejo zuloaga
Trabajo de fisica liceo alejo zuloagaTrabajo de fisica liceo alejo zuloaga
Trabajo de fisica liceo alejo zuloagaYVON JANETH PEREZ
 
Fotos propuesta pedagogica tia clementina
Fotos propuesta pedagogica tia clementinaFotos propuesta pedagogica tia clementina
Fotos propuesta pedagogica tia clementinaDiego Solano
 
Entrpreneur as career
Entrpreneur as careerEntrpreneur as career
Entrpreneur as careerAnam Joy
 
21010100904 preparar los pedidos aplicando los diferentes metodos de extracci...
21010100904 preparar los pedidos aplicando los diferentes metodos de extracci...21010100904 preparar los pedidos aplicando los diferentes metodos de extracci...
21010100904 preparar los pedidos aplicando los diferentes metodos de extracci...1vivianalozano
 

Viewers also liked (19)

Resume_Dany_Habka
Resume_Dany_HabkaResume_Dany_Habka
Resume_Dany_Habka
 
El principito
El principitoEl principito
El principito
 
【機械学習プロフェッショナルシリーズ】グラフィカルモデル2章
【機械学習プロフェッショナルシリーズ】グラフィカルモデル2章 【機械学習プロフェッショナルシリーズ】グラフィカルモデル2章
【機械学習プロフェッショナルシリーズ】グラフィカルモデル2章
 
Resumen analitico-corregido
Resumen analitico-corregidoResumen analitico-corregido
Resumen analitico-corregido
 
aphorisms
aphorismsaphorisms
aphorisms
 
Preguntas 1-encu-lina-escitura
Preguntas 1-encu-lina-escituraPreguntas 1-encu-lina-escitura
Preguntas 1-encu-lina-escitura
 
first order chemical reaction and hall effect on mhd flow past an infinite ve...
first order chemical reaction and hall effect on mhd flow past an infinite ve...first order chemical reaction and hall effect on mhd flow past an infinite ve...
first order chemical reaction and hall effect on mhd flow past an infinite ve...
 
P fosiles 123
P fosiles 123P fosiles 123
P fosiles 123
 
Inovaciniai tinklai
Inovaciniai tinklaiInovaciniai tinklai
Inovaciniai tinklai
 
Power @@la+antá..
Power @@la+antá..Power @@la+antá..
Power @@la+antá..
 
2016 đhqg ks hòa kỹ thuật ghi đo
2016 đhqg ks hòa  kỹ thuật ghi đo2016 đhqg ks hòa  kỹ thuật ghi đo
2016 đhqg ks hòa kỹ thuật ghi đo
 
Comunicacion social y periodismo
Comunicacion social y periodismoComunicacion social y periodismo
Comunicacion social y periodismo
 
Trabajo de fisica liceo alejo zuloaga
Trabajo de fisica liceo alejo zuloagaTrabajo de fisica liceo alejo zuloaga
Trabajo de fisica liceo alejo zuloaga
 
Libro Jun Ts
Libro Jun TsLibro Jun Ts
Libro Jun Ts
 
CALENDARIO MUNICIPAL QUESADA 2.017
CALENDARIO MUNICIPAL QUESADA 2.017CALENDARIO MUNICIPAL QUESADA 2.017
CALENDARIO MUNICIPAL QUESADA 2.017
 
Fotos propuesta pedagogica tia clementina
Fotos propuesta pedagogica tia clementinaFotos propuesta pedagogica tia clementina
Fotos propuesta pedagogica tia clementina
 
Entrpreneur as career
Entrpreneur as careerEntrpreneur as career
Entrpreneur as career
 
scrapbook
scrapbookscrapbook
scrapbook
 
21010100904 preparar los pedidos aplicando los diferentes metodos de extracci...
21010100904 preparar los pedidos aplicando los diferentes metodos de extracci...21010100904 preparar los pedidos aplicando los diferentes metodos de extracci...
21010100904 preparar los pedidos aplicando los diferentes metodos de extracci...
 

Similar to 101025 Excellence in Exc Planning Presentation E Heiland

Project Leaders presentation
Project Leaders  presentationProject Leaders  presentation
Project Leaders presentationZiad el-Balbisi
 
SELA Region Q4-2013 Thru-tubing Recompletion and Thru-tubing Workover
SELA Region Q4-2013 Thru-tubing Recompletion  and Thru-tubing WorkoverSELA Region Q4-2013 Thru-tubing Recompletion  and Thru-tubing Workover
SELA Region Q4-2013 Thru-tubing Recompletion and Thru-tubing WorkoverKevin Kelley
 
JAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE NavyJAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE NavyMike Bisland
 
Blasting inprovement techniques
Blasting inprovement techniquesBlasting inprovement techniques
Blasting inprovement techniquesKrishna Deo Prasad
 
Benjamin Asante, Snr. Procurement Officer at GNPC - The jubilee field a world...
Benjamin Asante, Snr. Procurement Officer at GNPC - The jubilee field a world...Benjamin Asante, Snr. Procurement Officer at GNPC - The jubilee field a world...
Benjamin Asante, Snr. Procurement Officer at GNPC - The jubilee field a world...Global Business Events
 
blastinginprovementtechniques-131019092354-phpapp01 (1).pdf
blastinginprovementtechniques-131019092354-phpapp01 (1).pdfblastinginprovementtechniques-131019092354-phpapp01 (1).pdf
blastinginprovementtechniques-131019092354-phpapp01 (1).pdf20JE0369GAURAVKUMAR
 
Where Glencore Coal Assets Australia stands - Mark Winchester
Where Glencore Coal Assets Australia stands - Mark WinchesterWhere Glencore Coal Assets Australia stands - Mark Winchester
Where Glencore Coal Assets Australia stands - Mark WinchesterNSW Environment and Planning
 
Project Milestones quotes from Project Director
Project Milestones quotes from Project DirectorProject Milestones quotes from Project Director
Project Milestones quotes from Project DirectorFabien Deschamps
 
FINAL The Owens Lake Turnout Facility End Cap Budget and Schedule
FINAL The Owens Lake Turnout Facility End Cap Budget and ScheduleFINAL The Owens Lake Turnout Facility End Cap Budget and Schedule
FINAL The Owens Lake Turnout Facility End Cap Budget and ScheduleKook Dean
 
Meeting of the brossard good neighbourly relations committee september 21 2016
Meeting of the brossard good neighbourly relations committee   september 21 2016Meeting of the brossard good neighbourly relations committee   september 21 2016
Meeting of the brossard good neighbourly relations committee september 21 2016Pont Samuel-De Champlain Bridge
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCrosstown TO
 
Stormwater Monitoring - Newington Solid Waste Facility
Stormwater Monitoring - Newington Solid Waste FacilityStormwater Monitoring - Newington Solid Waste Facility
Stormwater Monitoring - Newington Solid Waste FacilityFairfax County
 
Constructionmethodologyandprojectmanagementreport
ConstructionmethodologyandprojectmanagementreportConstructionmethodologyandprojectmanagementreport
ConstructionmethodologyandprojectmanagementreportDivyesh Mungara
 
Premier Oil - Decommissioning Oil Projects In The North Sea Case Study
Premier Oil - Decommissioning Oil Projects In The North Sea Case StudyPremier Oil - Decommissioning Oil Projects In The North Sea Case Study
Premier Oil - Decommissioning Oil Projects In The North Sea Case StudyThorne & Derrick International
 
Graduation Project Book 2020
Graduation Project Book 2020Graduation Project Book 2020
Graduation Project Book 2020Mahmoud Morsy
 
Res15-Brad Young_151221
Res15-Brad Young_151221Res15-Brad Young_151221
Res15-Brad Young_151221Brad Young
 

Similar to 101025 Excellence in Exc Planning Presentation E Heiland (20)

Project Leaders presentation
Project Leaders  presentationProject Leaders  presentation
Project Leaders presentation
 
SELA Region Q4-2013 Thru-tubing Recompletion and Thru-tubing Workover
SELA Region Q4-2013 Thru-tubing Recompletion  and Thru-tubing WorkoverSELA Region Q4-2013 Thru-tubing Recompletion  and Thru-tubing Workover
SELA Region Q4-2013 Thru-tubing Recompletion and Thru-tubing Workover
 
JAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE NavyJAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE Navy
 
Blasting inprovement techniques
Blasting inprovement techniquesBlasting inprovement techniques
Blasting inprovement techniques
 
Benjamin Asante, Snr. Procurement Officer at GNPC - The jubilee field a world...
Benjamin Asante, Snr. Procurement Officer at GNPC - The jubilee field a world...Benjamin Asante, Snr. Procurement Officer at GNPC - The jubilee field a world...
Benjamin Asante, Snr. Procurement Officer at GNPC - The jubilee field a world...
 
blastinginprovementtechniques-131019092354-phpapp01 (1).pdf
blastinginprovementtechniques-131019092354-phpapp01 (1).pdfblastinginprovementtechniques-131019092354-phpapp01 (1).pdf
blastinginprovementtechniques-131019092354-phpapp01 (1).pdf
 
Where Glencore Coal Assets Australia stands - Mark Winchester
Where Glencore Coal Assets Australia stands - Mark WinchesterWhere Glencore Coal Assets Australia stands - Mark Winchester
Where Glencore Coal Assets Australia stands - Mark Winchester
 
AH15019
AH15019AH15019
AH15019
 
Project Milestones quotes from Project Director
Project Milestones quotes from Project DirectorProject Milestones quotes from Project Director
Project Milestones quotes from Project Director
 
FINAL The Owens Lake Turnout Facility End Cap Budget and Schedule
FINAL The Owens Lake Turnout Facility End Cap Budget and ScheduleFINAL The Owens Lake Turnout Facility End Cap Budget and Schedule
FINAL The Owens Lake Turnout Facility End Cap Budget and Schedule
 
Meeting of the brossard good neighbourly relations committee september 21 2016
Meeting of the brossard good neighbourly relations committee   september 21 2016Meeting of the brossard good neighbourly relations committee   september 21 2016
Meeting of the brossard good neighbourly relations committee september 21 2016
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
 
Allwyn Leo CV
Allwyn Leo CVAllwyn Leo CV
Allwyn Leo CV
 
Allwyn-PE-CV
Allwyn-PE-CVAllwyn-PE-CV
Allwyn-PE-CV
 
Katleho P LETELE CV with picture
Katleho P LETELE CV with pictureKatleho P LETELE CV with picture
Katleho P LETELE CV with picture
 
Stormwater Monitoring - Newington Solid Waste Facility
Stormwater Monitoring - Newington Solid Waste FacilityStormwater Monitoring - Newington Solid Waste Facility
Stormwater Monitoring - Newington Solid Waste Facility
 
Constructionmethodologyandprojectmanagementreport
ConstructionmethodologyandprojectmanagementreportConstructionmethodologyandprojectmanagementreport
Constructionmethodologyandprojectmanagementreport
 
Premier Oil - Decommissioning Oil Projects In The North Sea Case Study
Premier Oil - Decommissioning Oil Projects In The North Sea Case StudyPremier Oil - Decommissioning Oil Projects In The North Sea Case Study
Premier Oil - Decommissioning Oil Projects In The North Sea Case Study
 
Graduation Project Book 2020
Graduation Project Book 2020Graduation Project Book 2020
Graduation Project Book 2020
 
Res15-Brad Young_151221
Res15-Brad Young_151221Res15-Brad Young_151221
Res15-Brad Young_151221
 

101025 Excellence in Exc Planning Presentation E Heiland

  • 1. 1 EXCELLENCE IN EXCAVATOR PLANNING AT DRAYTON MINE FROM THE DESIGN TO THE IMPLEMENTATION IN THE FIELD Erik Heiland Anglo American Metallurgical Coal Australia
  • 2. COAL 2 CONTENTS • Locality and Background Information • The Excavator Planning Process • Conclusion
  • 4. COAL 4 LOCALITY • Hunter Valley/ New South Wales • One of AAMC’s most challenging operations • Operation began in 1983 • Scheduled production in 2010: 5Mt of thermal coal – 4Mt for export market – 1Mt for domestic market (Liddell and Bayswater power stations) Map of Region
  • 5. COAL 5 MINING EQUIPMENT • Major Mining Equipment – One BE1370 dragline – Two Hitachi EX5500 excavators – One Hitachi EX3500 excavator – Two front end loaders (Le Tourneau L1100 and L1400) – 24 Caterpillar 789B and C trucks • 67% of Drayton’s prime overburden is planned to be moved by Hitachi EX5500 excavators • Aim: Uncover coal in the safest and most efficient way in accordance with the business plan schedule BE1370 Dragline Excavator 305
  • 6. COAL 6 COMPLEX GEOLOGY • Deposit consists of five major seam groups with up to 40 splits • Major geological features are: – 45 to 60 degree steep dipping coal seams – Up to 40m faults – 100m thrust plane – Dykes – Intrusions • Geology creates tough working environment for the machinery Drayton Mine Seam Split Diagram
  • 7. COAL 7 COMPLEX GEOLOGY CONT. • Thrusting and Faulting create a major challenge for the mining operation • Drayton has a 100m thrust plane running through the deposit Diagrammatic Representation of Normal Faulting and Thrust Faulting Balmorals
  • 8. COAL • An Example: South Pit East • Thrust plane, 10 faults, seam splitting, fill, spon com… 8 COMPLEX GEOLOGY CONT. Diagrammatic Representation of Normal Faulting and Thrust Faulting Representative Cross-Section Through South Pit East, October 2010 Thrust plane SectionAB A B Faults shown in black Faults These are the same Grasstrees seams
  • 9. COAL 9 BENCHMARK PERFORMANCE • Drayton’s excavator fleet delivers benchmark performance within AAMC • EXC306 and 307 are ranked No. 1 and 2 in its category • Major Key Performance Indicator: Operational Equipment Efficiency AAMC Operational Efficiency Ranking, Above 500t Excavator Category, August 2010
  • 11. COAL 11 THE EXCAVATOR PLANNING PROCESS • Process includes eight process steps • Bullet point 2 • Bullet point 3 • Bullet point 4 • Bullet point 5
  • 12. COAL 12 MINE ACTIVITY DESIGN (MAD) • Compliance with AAMC Operations Management System • Focus on the long term, medium term and short term planning, actual production and reconciliation • MAD document focuses on the 18-month planning process The AAMC Mine Planning Process
  • 13. COAL 13 16 WEEK SCHEDULE • Visual representation of equipment path for the Dragline and two EX5500 Excavators • Purpose of schedule – Identification equipment interactions – Input data for the 16 week drill and blast schedule – Determination of coal uncovered dates for the coal and partings schedule – Identification of short term truck shortages or excess The 306 Excavator Path in the 16 Week Schedule
  • 14. COAL 14 MONTHLY OPERATING PLAN (MOP) DESIGN REVIEW • Review of excavator designs for the following month • Determination of average monthly dig rate per excavator for input in schedule • Optimisation of dig plans • Presentation of plans by the excavator engineer One of Tony’s pics Visualisation of the EN03 Broughams dig area
  • 15. COAL 15 MOP DELIVERY PLAN MEETING • Identification of critical issues • Ensure the monthly Key Performance Indicators are achieved • Assign actions and agree on due dates Key Performance Indicator: Prime, Monthly Delivery Plan, September 2010
  • 16. COAL 16 EXCAVATOR PLAN SIGN OFF PROCESS • E = Q x A [Effectiveness = Quality x Acceptance] • Ensure that final design plans contain the most up to date information • Import of actual drilling data to deliver most accurate coal surface • Sign off to be completed one week before an excavator enters the work area Sign off for SPW09-10P and SPW08G dig
  • 17. COAL 17 WEEKLY PLAN PROCESS AND PACK • Weekly Plan Process includes a pre-planning meeting and a planning meeting • Agree on the weekly equipment path, blast and mining sequence, equipment interaction • Weekly plan pack is a comprehensive package which is sent via E-mail to all relevant mine personnel Weekly Plan Excavator Path, Plan commencing 7 October 2010
  • 18. COAL 18 DAILY PIT COMMUNICATION • Pit inspections are conducted a minimum of three times a week • Communication of the plan to front line personnel • Inspection of current and future dig and dump areas during the tour • Supervisor’s light vehicle and four bull dozers are equipped with a GPS • Video GPS in Supervisors light vehicle – SPW09P12 dig area
  • 19. COAL 19 DAILY PIT COMMUNICATION • Minimum three times a week • Communication of the plan to front line personnel • Inspection of Current and future dig and dump areas are inspected during the tour • Supervisor’s light vehicle and four bull dozers are equipped with a GPS • Video NN10 East - Excavator N Shot to be fired Fired on 26/06 Vol remaining: 735kBCM Trucks: 7 Target seam: RL Dig Sequence 1) Continue 4.5m BSL pass from East to West to form Ramp on Northern side 2) Come off the Ramp and BSL 4.5m passes uncover unshot material from West to East USE MATERIAL TO COVER FIRES IN SS WHEN TRUCKING AVAILABLE BLOCKY MATERIAL IN THE SOUTH OF THE DIG AREA GPS FILE: NN10-190 Dump Level 7-RL295, GPS-File: LV7REH 1 2 Unshot material to be uncovered 70Deg PS wall 45Deg Softwall Haul route to East Ramp Application of 3D Dig Software in the NN Pit
  • 20. COAL 20 DIG AREA REVIEWS • Dig reviews are carried out within one month after completion of the dig • Reconciliation of planned vs. actual performance • Key learning outcomes are identified and actions assigned • Learning outcomes are included into the next MAD document Excavator Dig Reconciliation
  • 22. COAL 22 CONCLUSION Excavator Planning at Drayton is very comprehensive process Key reasons for success: – Customer focus and having good working relationships – Input from experienced Production personnel in the planning process – Use of direct communication – Accurate tracking of Key Performance Indicators – Compliance with Operations Management System
  • 23. COAL 23QUESTIONS? “THE WAVE” IN THE NN PIT BW NE Steep dip