The document discusses an interlocal agreement between the city and Wellborn SUD regarding the Greens Prairie Trail Phase 1 Widening Project. The project involves widening Greens Prairie Trail from 2 lanes to 4 lanes of concrete pavement between Royder Road and the city limit, with construction starting this fall over 9-12 months. The total budget is $4.2 million. The agreement specifies that Wellborn SUD will relocate their water lines as needed for $129,470, which the city will include in the overall construction costs since the project requires the utility relocations.