SlideShare a Scribd company logo
Managing Massive Updates
Esri User Conference 2015
Using GIS to Fuel Gas Compliance
Managing Massive Updates – Using GIS to Fuel Gas Compliance
• Introductions
• Business Drivers
– Project Background
• Business Challenges
• Solution Overview
– Process
– Workflow & QAQC
– Additional Challenges
• Business Benefits
Agenda
Managing Massive Updates – Using GIS to Fuel Gas Compliance
Jill Gehrig | NIPSCO
– Leader of Maps & Records
– PM for the Data Mining Gas Asset Integrity & Pipeline Safety Project
– 39 Years of experience in gas and electric utility industry
– Involved with NIPSCO mapping from Linens to Esri ArcGIS / ArcFM
Skye Perry | SSP Innovations
– Founder & Principal Consultant
– Esri & Schneider Electric Technical Architect
– Began work with NIPSCO in 2004
– NIPSCO was SSP’s Founding Customer
Introductions
Managing Massive Updates – Using GIS to Fuel Gas Compliance
Business Drivers
Project Objectives
– Reduce excavation damage driven from incomplete records information
– Achieve continual and sustainable improvement in the quality and
content of gas system condition and performance data used for integrity
decision making
Project Approach
– Establish a data collection, storage and retrieval framework that defines
GIS and Maximo as the primary “Sources of Truth”
– Define the key data element required to fulfill the project objectives
– Migrate existing paper records and disparate data sources to the
GIS/MAXIMO framework
Project Background
The following steps were completed in 2014:
• GIS Transmission Main Centerline Rectification
• GIS Sessions Cleanup
• Selection of RAMTeCH to Digitize Data from Linens into GIS for entire
service territory
• Initial Planning and Scoping Effort
• Source Data Matrix
• Conversion Specification
• Data Model Changes in Test Environment (GIS)
Managing Massive Updates – Using GIS to Fuel Gas Compliance
Business Challenges
RAMTeCH will apply edits to the following GIS record types:
– Gas Main Locations
– Abandoned Gas Main Locations
– Controllable Fittings
– Non Controllable Fittings
– Drips
– Gas Valves
– Pipe Changes (based on WO/Material/etc.)
– Regulator Stations
– Vertical Pipe (aka Risers)
Managing Massive Updates – Using GIS to Fuel Gas Compliance
– Dimensions
– Foreign Utility Lines
– Gas Main
– Gas Pipe Casings
– Service Lines
– Crossings
– CP Circuits
– Excess Flow Valves
– Various Relationships between features
Business Challenges
RAMTeCH will create up to 20 versions per Month
– Working in a copy of the NIPSCO geodatabase
– Up to 40 RAMTeCH editors in India
– Desire to work without ArcFM
– Expected Duration of ~30 months
– Deliveries back to NIPSCO each month
Managing Massive Updates – Using GIS to Fuel Gas Compliance
Business Challenges
High Volume of External RAMTeCH Edits + High Volume of Ongoing Internal Edits
– Production Updates Cannot Stop
– Need a Process to Merge RAMTeCH Edits into Production GDB
– Need ArcFM AutoUpdaters and QAQC Validation to Fire
– Need to pass all pertinent updates back to Maximo Asset Management via existing interface
– Need to do it all while minimizing any production downtime
Managing Massive Updates – Using GIS to Fuel Gas Compliance
A True Challenge of Massive Data Updates and Moving Parts…
Engaged SSP Innovations to assist
Solution Overview
SSP Proposed to Use Existing “SSP All Edits State 0 Technology”
– Used with other utilities to extract all versions in a geodatabase
– Allows for compress to state 0 for any activities requiring state 0 including dropping the network
– Automatically recreates all geodatabase versions from scratch
– Re-synchronizes all ArcFM Sessions and Designer Designs
– System comes back online as if versions were intact the whole time
Managing Massive Updates – Using GIS to Fuel Gas Compliance
New Process Created as the “SSP All Edits Replay”
– Versioned Edits extracted from RAMTeCH’s copy of the geodatabase each month
– Automatically replayed into ArcFM Sessions over a weekend each month
– Replayed with ArcFM AutoUpdaters On
– Sessions reviewed and posted per normal QAQC
– Maximo Interface Enabled for all Assets
Solution Overview - Process
Managing Massive Updates – Using GIS to Fuel Gas Compliance
NIPSCO
GeoDB
RAMTeCH
GeoDB
1. Take a Copy of GDB
2. RAMTeCH Creates up to 20 Versions
3. RAMTeCH Edits Version for ~1mo+
SSP All
Edits
4. SSP Extracts Edits into SSP All Edits Format
*For each version
5. Create NIPSCO ArcFM Sessions/Versions
6. SSP Replays Edits into ArcFM Sessions
Solution Overview – Workflow & QAQC
Managing Massive Updates – Using GIS to Fuel Gas Compliance
Solution Overview – Additional Challenges
The following Issues Arose During The Project:
– Maximo interface was too slow to handle the volume of edits over a weekend
• Expected time was 24-30 hours of processing
• The interface was refactored resulting in an improvement of 5000%
– Additional QAQC Reports Desired to Drive Faster Review
• Reports being developed on “before” and “after” data elements
• Validates NULL attribute values now populated and number of features created by RAMTeCH
Managing Massive Updates – Using GIS to Fuel Gas Compliance
Business Benefits
The following Technical Benefits Have Been Achieved:
– Pulling a Version When Needed (Just In Time) Reduces Performance Impact on Production]
– Allows NIPSCO to Review the Edits Prior to Posting
– Allows Maximo to be Updated Per Each RAMTeCH Edit
– Allows Edits to be Applied as if an Editor Applied the Edit in Real Time
– Edits Are Applied en masse to Production Allowing for the Process to be Closely Monitored
– Allows RAMTeCH To Edit without Any ArcFM Technology in Place
Managing Massive Updates – Using GIS to Fuel Gas Compliance
Business Benefits
The following are Benefits of the Overall Data Mining Project:
– Elimination of widely dispersed and disparate sources of asset condition and performance
information
– Reduction in excavation damage due to inadequate data
– Improved efficiencies in collecting data to support risk assessments…and subsequent
increased awareness of all threats and risks to pipeline safety
– Enables linkage between Asset Health and Condition, Risk and Capital Investment / O&M
Spending Portfolio optimization
– Efficient integration of enabling IT Platforms (e.g.; GIS and MAXIMO)
– Streamlined asset data retrieval, dissemination and storage practices for Field personnel
Clearly understood and communicated “single source of truth”
Managing Massive Updates – Using GIS to Fuel Gas Compliance
Wrap Up
Managing Massive Updates – Using GIS to Fuel Gas Compliance
Skye Perry
Principal Consultant
SSP Innovations
skye.perry@sspinnovations.com
Jill Gehrig
PM Data Mining Gas Asset Integrity
NIPSCO
jagehrig@nisource.com
Questions?
Managing Massive Updates
Esri User Conference 2015
Using GIS to Fuel Gas Compliance

More Related Content

What's hot

RESUME _2016 Rev (A1)
RESUME  _2016 Rev (A1)RESUME  _2016 Rev (A1)
RESUME _2016 Rev (A1)Ken Gates
 
Intergrated Rice Plant Progress 2013
Intergrated Rice Plant Progress 2013 Intergrated Rice Plant Progress 2013
Intergrated Rice Plant Progress 2013 M Abid Latif
 
Cheryl Massie Presentation New York City Green Plan
Cheryl Massie Presentation New York City Green  PlanCheryl Massie Presentation New York City Green  Plan
Cheryl Massie Presentation New York City Green PlanRyan Slack
 
04.15.15 energy design assistance program tracker 2
04.15.15 energy design assistance program tracker 204.15.15 energy design assistance program tracker 2
04.15.15 energy design assistance program tracker 2melanie_bissonnette
 
3.17.15 commercial solar_design_training
3.17.15 commercial solar_design_training3.17.15 commercial solar_design_training
3.17.15 commercial solar_design_trainingmelanie_bissonnette
 
DynaRoad in the field - Case Roan wind farm (Norway)
DynaRoad in the field - Case Roan wind farm (Norway)DynaRoad in the field - Case Roan wind farm (Norway)
DynaRoad in the field - Case Roan wind farm (Norway)Viasys VDC
 
Steve gough western power innovation community energy grid connection 300715
Steve gough western power innovation community energy grid connection 300715Steve gough western power innovation community energy grid connection 300715
Steve gough western power innovation community energy grid connection 300715The Future Economy Network
 
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...Shanmukha S. Potti
 
Energy Savings for Occupancy-Based Control of Variable-Air-Volume Systems
Energy Savings for Occupancy-Based Control of Variable-Air-Volume SystemsEnergy Savings for Occupancy-Based Control of Variable-Air-Volume Systems
Energy Savings for Occupancy-Based Control of Variable-Air-Volume Systemsmelanie_bissonnette
 
Western Power Distribution Presentation Distributed Community Energy Low Carb...
Western Power Distribution Presentation Distributed Community Energy Low Carb...Western Power Distribution Presentation Distributed Community Energy Low Carb...
Western Power Distribution Presentation Distributed Community Energy Low Carb...The Future Economy Network
 
101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E Heiland101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E HeilandErik Heiland
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationFairfax County
 
Combined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NWCombined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NWmelanie_bissonnette
 
CooperMS Resume 05272016
CooperMS Resume 05272016CooperMS Resume 05272016
CooperMS Resume 05272016Maryann Cooper
 
150312 updating history_deep_retrofits
150312 updating history_deep_retrofits150312 updating history_deep_retrofits
150312 updating history_deep_retrofitsmelanie_bissonnette
 

What's hot (20)

RESUME _2016 Rev (A1)
RESUME  _2016 Rev (A1)RESUME  _2016 Rev (A1)
RESUME _2016 Rev (A1)
 
Intergrated Rice Plant Progress 2013
Intergrated Rice Plant Progress 2013 Intergrated Rice Plant Progress 2013
Intergrated Rice Plant Progress 2013
 
Cheryl Massie Presentation New York City Green Plan
Cheryl Massie Presentation New York City Green  PlanCheryl Massie Presentation New York City Green  Plan
Cheryl Massie Presentation New York City Green Plan
 
04.15.15 energy design assistance program tracker 2
04.15.15 energy design assistance program tracker 204.15.15 energy design assistance program tracker 2
04.15.15 energy design assistance program tracker 2
 
3.17.15 commercial solar_design_training
3.17.15 commercial solar_design_training3.17.15 commercial solar_design_training
3.17.15 commercial solar_design_training
 
Besf building renewal_021815
Besf building renewal_021815Besf building renewal_021815
Besf building renewal_021815
 
[Belle] Resume
[Belle] Resume[Belle] Resume
[Belle] Resume
 
DynaRoad in the field - Case Roan wind farm (Norway)
DynaRoad in the field - Case Roan wind farm (Norway)DynaRoad in the field - Case Roan wind farm (Norway)
DynaRoad in the field - Case Roan wind farm (Norway)
 
Steve gough western power innovation community energy grid connection 300715
Steve gough western power innovation community energy grid connection 300715Steve gough western power innovation community energy grid connection 300715
Steve gough western power innovation community energy grid connection 300715
 
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...
 
Energy Savings for Occupancy-Based Control of Variable-Air-Volume Systems
Energy Savings for Occupancy-Based Control of Variable-Air-Volume SystemsEnergy Savings for Occupancy-Based Control of Variable-Air-Volume Systems
Energy Savings for Occupancy-Based Control of Variable-Air-Volume Systems
 
Western Power Distribution Presentation Distributed Community Energy Low Carb...
Western Power Distribution Presentation Distributed Community Energy Low Carb...Western Power Distribution Presentation Distributed Community Energy Low Carb...
Western Power Distribution Presentation Distributed Community Energy Low Carb...
 
101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E Heiland101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E Heiland
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
 
Sustaining energy performance
Sustaining energy performanceSustaining energy performance
Sustaining energy performance
 
Combined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NWCombined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NW
 
Edward J Key
Edward J KeyEdward J Key
Edward J Key
 
Edward J
Edward JEdward J
Edward J
 
CooperMS Resume 05272016
CooperMS Resume 05272016CooperMS Resume 05272016
CooperMS Resume 05272016
 
150312 updating history_deep_retrofits
150312 updating history_deep_retrofits150312 updating history_deep_retrofits
150312 updating history_deep_retrofits
 

Viewers also liked

Enterprise Audit Tracking at CenterPoint Energy, Show Me the Edits!
Enterprise Audit Tracking at CenterPoint Energy, Show Me the Edits!Enterprise Audit Tracking at CenterPoint Energy, Show Me the Edits!
Enterprise Audit Tracking at CenterPoint Energy, Show Me the Edits!SSP Innovations
 
Transformer Management . Full Lifecycle Support Using GIS and a Web Applicat...
Transformer Management.  Full Lifecycle Support Using GIS and a Web Applicat...Transformer Management.  Full Lifecycle Support Using GIS and a Web Applicat...
Transformer Management . Full Lifecycle Support Using GIS and a Web Applicat...SSP Innovations
 
Opening the Outage Door: Integrating OMS into CIS
Opening the Outage Door: Integrating OMS into CISOpening the Outage Door: Integrating OMS into CIS
Opening the Outage Door: Integrating OMS into CISSSP Innovations
 
State Zero: Middle Tennessee Electric Membership Corporation
State Zero: Middle Tennessee Electric Membership CorporationState Zero: Middle Tennessee Electric Membership Corporation
State Zero: Middle Tennessee Electric Membership CorporationSSP Innovations
 
Utilizing Esri Out of the Box Tools for Field Data Verification
Utilizing Esri Out of the Box Tools for Field Data VerificationUtilizing Esri Out of the Box Tools for Field Data Verification
Utilizing Esri Out of the Box Tools for Field Data VerificationSSP Innovations
 
How to Become a Superstar for Your Utility in 2 Weeks
How to Become a Superstar for Your Utility in 2 WeeksHow to Become a Superstar for Your Utility in 2 Weeks
How to Become a Superstar for Your Utility in 2 WeeksSSP Innovations
 
From Field to Office: Streamlining the Management of Streetlight & Cover-ups ...
From Field to Office: Streamlining the Management of Streetlight & Cover-ups ...From Field to Office: Streamlining the Management of Streetlight & Cover-ups ...
From Field to Office: Streamlining the Management of Streetlight & Cover-ups ...SSP Innovations
 
Integrating the Mobile Workforce with OMS
Integrating the Mobile Workforce with OMSIntegrating the Mobile Workforce with OMS
Integrating the Mobile Workforce with OMSSSP Innovations
 
Learning Lessons the Hard Way: A Large Utility’s Experience Upgrading from Ar...
Learning Lessons the Hard Way: A Large Utility’s Experience Upgrading from Ar...Learning Lessons the Hard Way: A Large Utility’s Experience Upgrading from Ar...
Learning Lessons the Hard Way: A Large Utility’s Experience Upgrading from Ar...SSP Innovations
 
Transformer Loading, Driving Enterprise Decisions with ArcGIS Online
Transformer Loading, Driving Enterprise Decisions with ArcGIS OnlineTransformer Loading, Driving Enterprise Decisions with ArcGIS Online
Transformer Loading, Driving Enterprise Decisions with ArcGIS OnlineSSP Innovations
 
Provisioning Bandwidth & Logical Circuits Using Telecom-Based GIS .
Provisioning Bandwidth & Logical Circuits Using Telecom-Based GIS.Provisioning Bandwidth & Logical Circuits Using Telecom-Based GIS.
Provisioning Bandwidth & Logical Circuits Using Telecom-Based GIS .SSP Innovations
 
Maximizing ROI on Utility Work Management Systems
Maximizing ROI on Utility Work Management SystemsMaximizing ROI on Utility Work Management Systems
Maximizing ROI on Utility Work Management SystemsSSP Innovations
 
Portal vs. ArcGIS Online
Portal vs. ArcGIS OnlinePortal vs. ArcGIS Online
Portal vs. ArcGIS OnlineSSP Innovations
 
Creating New Channels for Outage Reporting
Creating New Channels for Outage ReportingCreating New Channels for Outage Reporting
Creating New Channels for Outage ReportingSSP Innovations
 
Pre-Posting and Partial Energization
Pre-Posting and Partial EnergizationPre-Posting and Partial Energization
Pre-Posting and Partial EnergizationSSP Innovations
 
Connecting through the OMS
Connecting through the OMSConnecting through the OMS
Connecting through the OMSSSP Innovations
 
MTEMC’s State 0 Changes with 1700+ Versions Intact
MTEMC’s State 0 Changes with 1700+ Versions IntactMTEMC’s State 0 Changes with 1700+ Versions Intact
MTEMC’s State 0 Changes with 1700+ Versions IntactSSP Innovations
 
Rule-Driven, Fully-Configurable Asset Tracking with GIS
Rule-Driven, Fully-Configurable Asset Tracking with GISRule-Driven, Fully-Configurable Asset Tracking with GIS
Rule-Driven, Fully-Configurable Asset Tracking with GISSSP Innovations
 

Viewers also liked (19)

Enterprise Audit Tracking at CenterPoint Energy, Show Me the Edits!
Enterprise Audit Tracking at CenterPoint Energy, Show Me the Edits!Enterprise Audit Tracking at CenterPoint Energy, Show Me the Edits!
Enterprise Audit Tracking at CenterPoint Energy, Show Me the Edits!
 
Transformer Management . Full Lifecycle Support Using GIS and a Web Applicat...
Transformer Management.  Full Lifecycle Support Using GIS and a Web Applicat...Transformer Management.  Full Lifecycle Support Using GIS and a Web Applicat...
Transformer Management . Full Lifecycle Support Using GIS and a Web Applicat...
 
Opening the Outage Door: Integrating OMS into CIS
Opening the Outage Door: Integrating OMS into CISOpening the Outage Door: Integrating OMS into CIS
Opening the Outage Door: Integrating OMS into CIS
 
State Zero: Middle Tennessee Electric Membership Corporation
State Zero: Middle Tennessee Electric Membership CorporationState Zero: Middle Tennessee Electric Membership Corporation
State Zero: Middle Tennessee Electric Membership Corporation
 
Utilizing Esri Out of the Box Tools for Field Data Verification
Utilizing Esri Out of the Box Tools for Field Data VerificationUtilizing Esri Out of the Box Tools for Field Data Verification
Utilizing Esri Out of the Box Tools for Field Data Verification
 
How to Become a Superstar for Your Utility in 2 Weeks
How to Become a Superstar for Your Utility in 2 WeeksHow to Become a Superstar for Your Utility in 2 Weeks
How to Become a Superstar for Your Utility in 2 Weeks
 
From Field to Office: Streamlining the Management of Streetlight & Cover-ups ...
From Field to Office: Streamlining the Management of Streetlight & Cover-ups ...From Field to Office: Streamlining the Management of Streetlight & Cover-ups ...
From Field to Office: Streamlining the Management of Streetlight & Cover-ups ...
 
Integrating the Mobile Workforce with OMS
Integrating the Mobile Workforce with OMSIntegrating the Mobile Workforce with OMS
Integrating the Mobile Workforce with OMS
 
Learning Lessons the Hard Way: A Large Utility’s Experience Upgrading from Ar...
Learning Lessons the Hard Way: A Large Utility’s Experience Upgrading from Ar...Learning Lessons the Hard Way: A Large Utility’s Experience Upgrading from Ar...
Learning Lessons the Hard Way: A Large Utility’s Experience Upgrading from Ar...
 
Transformer Loading, Driving Enterprise Decisions with ArcGIS Online
Transformer Loading, Driving Enterprise Decisions with ArcGIS OnlineTransformer Loading, Driving Enterprise Decisions with ArcGIS Online
Transformer Loading, Driving Enterprise Decisions with ArcGIS Online
 
Portal for ArcGIS
Portal for ArcGISPortal for ArcGIS
Portal for ArcGIS
 
Provisioning Bandwidth & Logical Circuits Using Telecom-Based GIS .
Provisioning Bandwidth & Logical Circuits Using Telecom-Based GIS.Provisioning Bandwidth & Logical Circuits Using Telecom-Based GIS.
Provisioning Bandwidth & Logical Circuits Using Telecom-Based GIS .
 
Maximizing ROI on Utility Work Management Systems
Maximizing ROI on Utility Work Management SystemsMaximizing ROI on Utility Work Management Systems
Maximizing ROI on Utility Work Management Systems
 
Portal vs. ArcGIS Online
Portal vs. ArcGIS OnlinePortal vs. ArcGIS Online
Portal vs. ArcGIS Online
 
Creating New Channels for Outage Reporting
Creating New Channels for Outage ReportingCreating New Channels for Outage Reporting
Creating New Channels for Outage Reporting
 
Pre-Posting and Partial Energization
Pre-Posting and Partial EnergizationPre-Posting and Partial Energization
Pre-Posting and Partial Energization
 
Connecting through the OMS
Connecting through the OMSConnecting through the OMS
Connecting through the OMS
 
MTEMC’s State 0 Changes with 1700+ Versions Intact
MTEMC’s State 0 Changes with 1700+ Versions IntactMTEMC’s State 0 Changes with 1700+ Versions Intact
MTEMC’s State 0 Changes with 1700+ Versions Intact
 
Rule-Driven, Fully-Configurable Asset Tracking with GIS
Rule-Driven, Fully-Configurable Asset Tracking with GISRule-Driven, Fully-Configurable Asset Tracking with GIS
Rule-Driven, Fully-Configurable Asset Tracking with GIS
 

Similar to Managing Massive Updates - Using GIS to Fuel Gas Compliance

Using Aspen HYSYS Upstream for Sizing and Scheduling of Gathering Systems
Using Aspen HYSYS Upstream for Sizing and Scheduling of Gathering SystemsUsing Aspen HYSYS Upstream for Sizing and Scheduling of Gathering Systems
Using Aspen HYSYS Upstream for Sizing and Scheduling of Gathering SystemsProcess Ecology Inc
 
Integrated Asset Modeling for Market Driven Gas Planning - GasAssure
Integrated Asset Modeling for Market Driven Gas Planning - GasAssureIntegrated Asset Modeling for Market Driven Gas Planning - GasAssure
Integrated Asset Modeling for Market Driven Gas Planning - GasAssureStochastic Simulation
 
CV of Instrumentation Consultant_Rashesh Shah_32 years plus exp
CV of Instrumentation Consultant_Rashesh Shah_32 years plus expCV of Instrumentation Consultant_Rashesh Shah_32 years plus exp
CV of Instrumentation Consultant_Rashesh Shah_32 years plus expRashesh Shah
 
Moving To New AVEVA Technology
Moving To New AVEVA TechnologyMoving To New AVEVA Technology
Moving To New AVEVA TechnologyAVEVA Group plc
 
UPDM & APR Implementation for Gas Transmission
UPDM & APR Implementation for Gas TransmissionUPDM & APR Implementation for Gas Transmission
UPDM & APR Implementation for Gas TransmissionSSP Innovations
 
ArcGIS Pipeline Referencing - Lessons Learned
ArcGIS Pipeline Referencing - Lessons LearnedArcGIS Pipeline Referencing - Lessons Learned
ArcGIS Pipeline Referencing - Lessons LearnedSSP Innovations
 
Gas Liquid Engineering - Presentation Brazil
Gas Liquid Engineering - Presentation BrazilGas Liquid Engineering - Presentation Brazil
Gas Liquid Engineering - Presentation BrazilSistema FIEB
 
FEWS Data Analysis with ARR2016
FEWS Data Analysis with ARR2016 FEWS Data Analysis with ARR2016
FEWS Data Analysis with ARR2016 Lindsay Millard
 
Robert Hensel resume v111416 Lnkedin
Robert Hensel resume v111416 LnkedinRobert Hensel resume v111416 Lnkedin
Robert Hensel resume v111416 LnkedinBob Hensel
 
Leveraging Collector & UtiliSync to Manage Utilities
Leveraging Collector & UtiliSync to Manage UtilitiesLeveraging Collector & UtiliSync to Manage Utilities
Leveraging Collector & UtiliSync to Manage UtilitiesMatthew Stayner
 
Pre-Con Ed: Upgrading to CA Service Management
Pre-Con Ed: Upgrading to CA Service ManagementPre-Con Ed: Upgrading to CA Service Management
Pre-Con Ed: Upgrading to CA Service ManagementCA Technologies
 
NRG INTERN POWER DOWN END OF SUMMER PRESENTATION
NRG INTERN POWER DOWN END OF SUMMER PRESENTATIONNRG INTERN POWER DOWN END OF SUMMER PRESENTATION
NRG INTERN POWER DOWN END OF SUMMER PRESENTATIONElliott Molnar
 
Row #9: An architecture overview of APNIC's RDAP deployment to the cloud
Row #9: An architecture overview of APNIC's RDAP deployment to the cloudRow #9: An architecture overview of APNIC's RDAP deployment to the cloud
Row #9: An architecture overview of APNIC's RDAP deployment to the cloudAPNIC
 
FME Around the World
FME Around the WorldFME Around the World
FME Around the WorldSafe Software
 
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...Energy Construction Forum
 

Similar to Managing Massive Updates - Using GIS to Fuel Gas Compliance (20)

An introduction to energy management
An introduction to energy managementAn introduction to energy management
An introduction to energy management
 
Using Aspen HYSYS Upstream for Sizing and Scheduling of Gathering Systems
Using Aspen HYSYS Upstream for Sizing and Scheduling of Gathering SystemsUsing Aspen HYSYS Upstream for Sizing and Scheduling of Gathering Systems
Using Aspen HYSYS Upstream for Sizing and Scheduling of Gathering Systems
 
Integrated Asset Modeling for Market Driven Gas Planning - GasAssure
Integrated Asset Modeling for Market Driven Gas Planning - GasAssureIntegrated Asset Modeling for Market Driven Gas Planning - GasAssure
Integrated Asset Modeling for Market Driven Gas Planning - GasAssure
 
Gi oss offering top cell_partnership (1)
Gi oss offering top cell_partnership (1)Gi oss offering top cell_partnership (1)
Gi oss offering top cell_partnership (1)
 
CV of Instrumentation Consultant_Rashesh Shah_32 years plus exp
CV of Instrumentation Consultant_Rashesh Shah_32 years plus expCV of Instrumentation Consultant_Rashesh Shah_32 years plus exp
CV of Instrumentation Consultant_Rashesh Shah_32 years plus exp
 
Moving To New AVEVA Technology
Moving To New AVEVA TechnologyMoving To New AVEVA Technology
Moving To New AVEVA Technology
 
UPDM & APR Implementation for Gas Transmission
UPDM & APR Implementation for Gas TransmissionUPDM & APR Implementation for Gas Transmission
UPDM & APR Implementation for Gas Transmission
 
Resume-Vispute_Prashant
Resume-Vispute_PrashantResume-Vispute_Prashant
Resume-Vispute_Prashant
 
ArcGIS Pipeline Referencing - Lessons Learned
ArcGIS Pipeline Referencing - Lessons LearnedArcGIS Pipeline Referencing - Lessons Learned
ArcGIS Pipeline Referencing - Lessons Learned
 
Gas Liquid Engineering - Presentation Brazil
Gas Liquid Engineering - Presentation BrazilGas Liquid Engineering - Presentation Brazil
Gas Liquid Engineering - Presentation Brazil
 
FEWS Data Analysis with ARR2016
FEWS Data Analysis with ARR2016 FEWS Data Analysis with ARR2016
FEWS Data Analysis with ARR2016
 
Robert Hensel resume v111416 Lnkedin
Robert Hensel resume v111416 LnkedinRobert Hensel resume v111416 Lnkedin
Robert Hensel resume v111416 Lnkedin
 
GeoForum EDINA report 2017
GeoForum EDINA report 2017GeoForum EDINA report 2017
GeoForum EDINA report 2017
 
sdasdsacszc
sdasdsacszcsdasdsacszc
sdasdsacszc
 
Leveraging Collector & UtiliSync to Manage Utilities
Leveraging Collector & UtiliSync to Manage UtilitiesLeveraging Collector & UtiliSync to Manage Utilities
Leveraging Collector & UtiliSync to Manage Utilities
 
Pre-Con Ed: Upgrading to CA Service Management
Pre-Con Ed: Upgrading to CA Service ManagementPre-Con Ed: Upgrading to CA Service Management
Pre-Con Ed: Upgrading to CA Service Management
 
NRG INTERN POWER DOWN END OF SUMMER PRESENTATION
NRG INTERN POWER DOWN END OF SUMMER PRESENTATIONNRG INTERN POWER DOWN END OF SUMMER PRESENTATION
NRG INTERN POWER DOWN END OF SUMMER PRESENTATION
 
Row #9: An architecture overview of APNIC's RDAP deployment to the cloud
Row #9: An architecture overview of APNIC's RDAP deployment to the cloudRow #9: An architecture overview of APNIC's RDAP deployment to the cloud
Row #9: An architecture overview of APNIC's RDAP deployment to the cloud
 
FME Around the World
FME Around the WorldFME Around the World
FME Around the World
 
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
 

More from SSP Innovations

Utility Focused Asset and Work Management
Utility Focused Asset and Work ManagementUtility Focused Asset and Work Management
Utility Focused Asset and Work ManagementSSP Innovations
 
How will the Utility Network Affect You?
How will the Utility Network Affect You? How will the Utility Network Affect You?
How will the Utility Network Affect You? SSP Innovations
 
Outside of the Box Integrations
Outside of the Box Integrations Outside of the Box Integrations
Outside of the Box Integrations SSP Innovations
 
What's it like to use the Utility Network
What's it like to use the Utility NetworkWhat's it like to use the Utility Network
What's it like to use the Utility NetworkSSP Innovations
 
Memphis Light Gas & WATER Upgrade Case Study
Memphis Light Gas & WATER Upgrade Case StudyMemphis Light Gas & WATER Upgrade Case Study
Memphis Light Gas & WATER Upgrade Case StudySSP Innovations
 
Management of Fiber Optics for Utilities
Management of Fiber Optics for UtilitiesManagement of Fiber Optics for Utilities
Management of Fiber Optics for UtilitiesSSP Innovations
 
Link2015 Tri-State Provisioning Bandwidth & Logical Circuits with Fiber Manager
Link2015 Tri-State Provisioning Bandwidth & Logical Circuits with Fiber ManagerLink2015 Tri-State Provisioning Bandwidth & Logical Circuits with Fiber Manager
Link2015 Tri-State Provisioning Bandwidth & Logical Circuits with Fiber ManagerSSP Innovations
 
Transformer Loading. Driving Enterprise Decisions with ArcGIS Online.
Transformer Loading.  Driving Enterprise Decisions with ArcGIS Online.Transformer Loading.  Driving Enterprise Decisions with ArcGIS Online.
Transformer Loading. Driving Enterprise Decisions with ArcGIS Online.SSP Innovations
 
Using ArcGIS Online for Meter Replacement Project
Using ArcGIS Online for Meter Replacement ProjectUsing ArcGIS Online for Meter Replacement Project
Using ArcGIS Online for Meter Replacement ProjectSSP Innovations
 

More from SSP Innovations (10)

Utility Focused Asset and Work Management
Utility Focused Asset and Work ManagementUtility Focused Asset and Work Management
Utility Focused Asset and Work Management
 
How will the Utility Network Affect You?
How will the Utility Network Affect You? How will the Utility Network Affect You?
How will the Utility Network Affect You?
 
Outside of the Box Integrations
Outside of the Box Integrations Outside of the Box Integrations
Outside of the Box Integrations
 
What's it like to use the Utility Network
What's it like to use the Utility NetworkWhat's it like to use the Utility Network
What's it like to use the Utility Network
 
Memphis Light Gas & WATER Upgrade Case Study
Memphis Light Gas & WATER Upgrade Case StudyMemphis Light Gas & WATER Upgrade Case Study
Memphis Light Gas & WATER Upgrade Case Study
 
Management of Fiber Optics for Utilities
Management of Fiber Optics for UtilitiesManagement of Fiber Optics for Utilities
Management of Fiber Optics for Utilities
 
Link2015 Tri-State Provisioning Bandwidth & Logical Circuits with Fiber Manager
Link2015 Tri-State Provisioning Bandwidth & Logical Circuits with Fiber ManagerLink2015 Tri-State Provisioning Bandwidth & Logical Circuits with Fiber Manager
Link2015 Tri-State Provisioning Bandwidth & Logical Circuits with Fiber Manager
 
Transformer Loading. Driving Enterprise Decisions with ArcGIS Online.
Transformer Loading.  Driving Enterprise Decisions with ArcGIS Online.Transformer Loading.  Driving Enterprise Decisions with ArcGIS Online.
Transformer Loading. Driving Enterprise Decisions with ArcGIS Online.
 
Using ArcGIS Online for Meter Replacement Project
Using ArcGIS Online for Meter Replacement ProjectUsing ArcGIS Online for Meter Replacement Project
Using ArcGIS Online for Meter Replacement Project
 
Collector for ArcGIS
Collector for ArcGISCollector for ArcGIS
Collector for ArcGIS
 

Recently uploaded

AI for workflow automation Use cases applications benefits and development.pdf
AI for workflow automation Use cases applications benefits and development.pdfAI for workflow automation Use cases applications benefits and development.pdf
AI for workflow automation Use cases applications benefits and development.pdfmahaffeycheryld
 
School management system project report.pdf
School management system project report.pdfSchool management system project report.pdf
School management system project report.pdfKamal Acharya
 
Top 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering ScientistTop 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering Scientistgettygaming1
 
Electrostatic field in a coaxial transmission line
Electrostatic field in a coaxial transmission lineElectrostatic field in a coaxial transmission line
Electrostatic field in a coaxial transmission lineJulioCesarSalazarHer1
 
Fruit shop management system project report.pdf
Fruit shop management system project report.pdfFruit shop management system project report.pdf
Fruit shop management system project report.pdfKamal Acharya
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdfKamal Acharya
 
A case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfA case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfKamal Acharya
 
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfA CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfKamal Acharya
 
Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfAbrahamGadissa
 
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfRESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfKamal Acharya
 
shape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptxshape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptxVishalDeshpande27
 
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical SolutionsRS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical SolutionsAtif Razi
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdfKamal Acharya
 
Natalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in KrakówNatalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in Krakówbim.edu.pl
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdfKamal Acharya
 
Online resume builder management system project report.pdf
Online resume builder management system project report.pdfOnline resume builder management system project report.pdf
Online resume builder management system project report.pdfKamal Acharya
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdfKamal Acharya
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.PrashantGoswami42
 
retail automation billing system ppt.pptx
retail automation billing system ppt.pptxretail automation billing system ppt.pptx
retail automation billing system ppt.pptxfaamieahmd
 

Recently uploaded (20)

AI for workflow automation Use cases applications benefits and development.pdf
AI for workflow automation Use cases applications benefits and development.pdfAI for workflow automation Use cases applications benefits and development.pdf
AI for workflow automation Use cases applications benefits and development.pdf
 
School management system project report.pdf
School management system project report.pdfSchool management system project report.pdf
School management system project report.pdf
 
Top 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering ScientistTop 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering Scientist
 
Electrostatic field in a coaxial transmission line
Electrostatic field in a coaxial transmission lineElectrostatic field in a coaxial transmission line
Electrostatic field in a coaxial transmission line
 
Fruit shop management system project report.pdf
Fruit shop management system project report.pdfFruit shop management system project report.pdf
Fruit shop management system project report.pdf
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdf
 
A case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfA case study of cinema management system project report..pdf
A case study of cinema management system project report..pdf
 
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfA CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
 
Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdf
 
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfRESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
 
shape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptxshape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptx
 
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical SolutionsRS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Natalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in KrakówNatalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in Kraków
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
Online resume builder management system project report.pdf
Online resume builder management system project report.pdfOnline resume builder management system project report.pdf
Online resume builder management system project report.pdf
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdf
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
retail automation billing system ppt.pptx
retail automation billing system ppt.pptxretail automation billing system ppt.pptx
retail automation billing system ppt.pptx
 

Managing Massive Updates - Using GIS to Fuel Gas Compliance

  • 1. Managing Massive Updates Esri User Conference 2015 Using GIS to Fuel Gas Compliance
  • 2. Managing Massive Updates – Using GIS to Fuel Gas Compliance • Introductions • Business Drivers – Project Background • Business Challenges • Solution Overview – Process – Workflow & QAQC – Additional Challenges • Business Benefits Agenda
  • 3. Managing Massive Updates – Using GIS to Fuel Gas Compliance Jill Gehrig | NIPSCO – Leader of Maps & Records – PM for the Data Mining Gas Asset Integrity & Pipeline Safety Project – 39 Years of experience in gas and electric utility industry – Involved with NIPSCO mapping from Linens to Esri ArcGIS / ArcFM Skye Perry | SSP Innovations – Founder & Principal Consultant – Esri & Schneider Electric Technical Architect – Began work with NIPSCO in 2004 – NIPSCO was SSP’s Founding Customer Introductions
  • 4. Managing Massive Updates – Using GIS to Fuel Gas Compliance Business Drivers Project Objectives – Reduce excavation damage driven from incomplete records information – Achieve continual and sustainable improvement in the quality and content of gas system condition and performance data used for integrity decision making Project Approach – Establish a data collection, storage and retrieval framework that defines GIS and Maximo as the primary “Sources of Truth” – Define the key data element required to fulfill the project objectives – Migrate existing paper records and disparate data sources to the GIS/MAXIMO framework
  • 5. Project Background The following steps were completed in 2014: • GIS Transmission Main Centerline Rectification • GIS Sessions Cleanup • Selection of RAMTeCH to Digitize Data from Linens into GIS for entire service territory • Initial Planning and Scoping Effort • Source Data Matrix • Conversion Specification • Data Model Changes in Test Environment (GIS) Managing Massive Updates – Using GIS to Fuel Gas Compliance
  • 6. Business Challenges RAMTeCH will apply edits to the following GIS record types: – Gas Main Locations – Abandoned Gas Main Locations – Controllable Fittings – Non Controllable Fittings – Drips – Gas Valves – Pipe Changes (based on WO/Material/etc.) – Regulator Stations – Vertical Pipe (aka Risers) Managing Massive Updates – Using GIS to Fuel Gas Compliance – Dimensions – Foreign Utility Lines – Gas Main – Gas Pipe Casings – Service Lines – Crossings – CP Circuits – Excess Flow Valves – Various Relationships between features
  • 7. Business Challenges RAMTeCH will create up to 20 versions per Month – Working in a copy of the NIPSCO geodatabase – Up to 40 RAMTeCH editors in India – Desire to work without ArcFM – Expected Duration of ~30 months – Deliveries back to NIPSCO each month Managing Massive Updates – Using GIS to Fuel Gas Compliance
  • 8. Business Challenges High Volume of External RAMTeCH Edits + High Volume of Ongoing Internal Edits – Production Updates Cannot Stop – Need a Process to Merge RAMTeCH Edits into Production GDB – Need ArcFM AutoUpdaters and QAQC Validation to Fire – Need to pass all pertinent updates back to Maximo Asset Management via existing interface – Need to do it all while minimizing any production downtime Managing Massive Updates – Using GIS to Fuel Gas Compliance A True Challenge of Massive Data Updates and Moving Parts… Engaged SSP Innovations to assist
  • 9. Solution Overview SSP Proposed to Use Existing “SSP All Edits State 0 Technology” – Used with other utilities to extract all versions in a geodatabase – Allows for compress to state 0 for any activities requiring state 0 including dropping the network – Automatically recreates all geodatabase versions from scratch – Re-synchronizes all ArcFM Sessions and Designer Designs – System comes back online as if versions were intact the whole time Managing Massive Updates – Using GIS to Fuel Gas Compliance New Process Created as the “SSP All Edits Replay” – Versioned Edits extracted from RAMTeCH’s copy of the geodatabase each month – Automatically replayed into ArcFM Sessions over a weekend each month – Replayed with ArcFM AutoUpdaters On – Sessions reviewed and posted per normal QAQC – Maximo Interface Enabled for all Assets
  • 10. Solution Overview - Process Managing Massive Updates – Using GIS to Fuel Gas Compliance NIPSCO GeoDB RAMTeCH GeoDB 1. Take a Copy of GDB 2. RAMTeCH Creates up to 20 Versions 3. RAMTeCH Edits Version for ~1mo+ SSP All Edits 4. SSP Extracts Edits into SSP All Edits Format *For each version 5. Create NIPSCO ArcFM Sessions/Versions 6. SSP Replays Edits into ArcFM Sessions
  • 11. Solution Overview – Workflow & QAQC Managing Massive Updates – Using GIS to Fuel Gas Compliance
  • 12. Solution Overview – Additional Challenges The following Issues Arose During The Project: – Maximo interface was too slow to handle the volume of edits over a weekend • Expected time was 24-30 hours of processing • The interface was refactored resulting in an improvement of 5000% – Additional QAQC Reports Desired to Drive Faster Review • Reports being developed on “before” and “after” data elements • Validates NULL attribute values now populated and number of features created by RAMTeCH Managing Massive Updates – Using GIS to Fuel Gas Compliance
  • 13. Business Benefits The following Technical Benefits Have Been Achieved: – Pulling a Version When Needed (Just In Time) Reduces Performance Impact on Production] – Allows NIPSCO to Review the Edits Prior to Posting – Allows Maximo to be Updated Per Each RAMTeCH Edit – Allows Edits to be Applied as if an Editor Applied the Edit in Real Time – Edits Are Applied en masse to Production Allowing for the Process to be Closely Monitored – Allows RAMTeCH To Edit without Any ArcFM Technology in Place Managing Massive Updates – Using GIS to Fuel Gas Compliance
  • 14. Business Benefits The following are Benefits of the Overall Data Mining Project: – Elimination of widely dispersed and disparate sources of asset condition and performance information – Reduction in excavation damage due to inadequate data – Improved efficiencies in collecting data to support risk assessments…and subsequent increased awareness of all threats and risks to pipeline safety – Enables linkage between Asset Health and Condition, Risk and Capital Investment / O&M Spending Portfolio optimization – Efficient integration of enabling IT Platforms (e.g.; GIS and MAXIMO) – Streamlined asset data retrieval, dissemination and storage practices for Field personnel Clearly understood and communicated “single source of truth” Managing Massive Updates – Using GIS to Fuel Gas Compliance
  • 15. Wrap Up Managing Massive Updates – Using GIS to Fuel Gas Compliance Skye Perry Principal Consultant SSP Innovations skye.perry@sspinnovations.com Jill Gehrig PM Data Mining Gas Asset Integrity NIPSCO jagehrig@nisource.com Questions?
  • 16. Managing Massive Updates Esri User Conference 2015 Using GIS to Fuel Gas Compliance

Editor's Notes

  1. Abstract (500 characters): NIPSCO was required to undergo massive data updates to their GIS to meet new gas regulation. A series of projects allowed for the rectification of all gas transmission assets and the manual update of system-wide records to accommodate the requirements. SSP technology was implemented to allow for outsourced updates to be replayed into the versioned production GIS while maintaining fulltime day-to-day editing. This provided maximum flexibility while minimizing downtime and any performance impact.
  2. Jill to give a brief overview of the agenda
  3. Jill send Skye introduce themselves
  4. Jill to review the business drivers behind the project.
  5. Jill, include the work that was done leading up to the replay…
  6. Jill talk to the types of edits RAMTeCH will be collecting emphasizing that there is a lot of data being collected.
  7. Jill talk to the huger scope of this overall project – building up to it being a massive undertaking with significant challenges.
  8. Jill talk about needing to keep RAMTeCH going while keeping production editing going at the same time over the coming years. Skye can jump in on any of the bullets as needed. The end game was Jill calling Skye as a trusted advisor for help with how to make this all together. Skye will take over here.
  9. Skye to review the past technology that provided the basis for the project
  10. Skye review the process we are using.
  11. Skye touch briefly on the workflow and qaqc.
  12. Skye talk to additional issues encountered and how they were remedied
  13. Skye to talk to technical benefits of the project…
  14. Jill to talk to the overall benefits of the data mining project and getting the linen updates into GIS.
  15. Q&A
  16. Abstract (500 characters): NIPSCO was required to undergo massive data updates to their GIS to meet new gas regulation. A series of projects allowed for the rectification of all gas transmission assets and the manual update of system-wide records to accommodate the requirements. SSP technology was implemented to allow for outsourced updates to be replayed into the versioned production GIS while maintaining fulltime day-to-day editing. This provided maximum flexibility while minimizing downtime and any performance impact.