SlideShare a Scribd company logo
1 of 7
Download to read offline
TELKOMNIKA, Vol.15, No.4, December 2017, pp. 1540~1546
ISSN: 1693-6930, accredited A by DIKTI, Decree No: 58/DIKTI/Kep/2013
DOI: 10.12928/TELKOMNIKA.v15i4.7232  1540
Received September 2, 2017; Revised November 10, 2017; Accepted November 25, 2017
Design and Evaluation of Submersible 11/0.415kV
Distribution Substation for Flood Prone Areas
M. D. M. Amir*, S. Ishak, A. Raj Gopal
TNB Research Sdn Bhd, Kawasan Institusi Penyelidikan, 43000 Kajang, Selangor,
Malaysia +60389225000
*Corresponding author, e-mail: dzaki.amir@tnb.com.my
Abstract
Flood levels exceeding 2 metres above ground level has been observed causing electrical
equipment in the 11/0.415kV substation to be fully submerged. This caused widespread supply disruption
as the equipment need to be switched off due to safety reasons and prevention of further equipment
damage. The use of submersible equipment and accessories has been identified as one of the mitigation
methods to ensure continuous electrical supply during flood events. A research project was undertaken to
develop the design criteria of the selection of submersible equipment and accessories as well as to
develop the test method and evaluate the selected submersible equipment and accessories in a substation
configuration. All the equipment could continuously operate in ON condition during the wet test. However,
design improvements are suggested for the submersible switchgear and feeder pillar for better
performance during and after flood events.
Keywords: high voltage testing, submersible substation, submersible electrical equipment, flood mitigation
Copyright © 2017 Universitas Ahmad Dahlan. All rights reserved.
1. Introduction
During the last major Malaysian flood events in 2014; the water level in several areas
exceeded 2 metres above ground level. This caused electrical equipment in the 11/0.415kV
distribution substation to be fully submerged. As the equipment is not rated for submersible
operations, the equipment in the flood affected substation need to be switched off due to safety
reasons and to prevent further damage to the equipment.
This does not only cause supply disruption to the local area served by the flood affected
substation but also any substation downstream to the affected substation. This is especially
critical in spur feeder configuration, normally used in rural areas, which is the most prone to
flood events. This may cause a larger than necessary number of customers to be affected by
the flood as the downstream substations might not be affected by the flood (as illustrated in
Figure 1).
Figure 1. All the substations downstream of the affected substation will suffer from supply
disruption even though they are not flooded themselves
TELKOMNIKA ISSN: 1693-6930 
Design and Evaluation of Submersible 11/0.415kV Distribution Substation .... (M. D. M. Amir)
1541
During the flood events, Tenaga Nasional Berhad (TNB), which is the Malaysian
national power utility company, will incur a large cost to replace and/or repair any equipment
damaged by the flood as well the cost of providing temporary supply by using mobile gen-sets
to areas downstream of the flood-affected substation. As the flood events can last up to one
week, TNB suffered losses due to unserved energy during this period. Finally, TNB also
suffered from intangible losses such as reputation loss in the eyes of the public and investors
due to taking longer time in restoring the supply.
1.1. Current Utility Practice in Mitigating Flood Events
There are several major approaches used by utilities worldwide to mitigate flood events.
Bogees proposes the elevation of the substation as a mitigation for flooding. Distribution
voltages are more convenient to elevate due to the availability of many substation designs that
can be placed on stilts, platforms or slabs [1]. However, it is more tedious to elevate a
transmission substation due to the large space needed for increased electrical clearances at
high voltages. This will lead to increase in material cost for concrete and steel. This is practiced
by TNB for flood-prone areas but its limitations are that this mitigation method caters only for
low flood level. Figure 2(a) and 2(b) show example of raised substation for flood level above and
below 3 metres respectively.
Succeeding suggestion of Joseph Baker is to elevate the substation that he defined as
raising the substation utilizing existing structures [2]. The suggestion to elevate to existing
structures makes the solution economical. The solution has an acceptable schedule criterion.
However, the risk of service disruption time is relatively high with moderate increase in
operation and maintenance risk.
Another option is to elevate to a new site to reduce service interruption time as
discussed in [3]. This may prove to be costly and has a long lead time. Additional land is
required to allow construction to allow continuation of supply. The recommended height raise
is 1.2 m.
(a) (b)
Figure 2. (a) Raised substation for flood level above 3 metres
(b) Raised substation for flood level below 3 metres
Another major approach is by using floodwalls. Floodwalls are defined as constructed
barriers that provide more than 4 feet flood protection to buildings. Joseph Baker suggests in his
paper that the floodwall around the substation will protect the substation and additions of pumps
will remove entrapped water [2]. This method is economically viable and has minimum
construction duration with minimal service disruption. However, the drawbacks may be
additional monitoring of pump is needed and if the floodwall breaches complete operational
failure may cause a devastating impact.
Mark Dunk in “Substation Flood Protection (2016)” agrees with flood protection for
substations as a main highlight. This is due to the flooding events recorded across England and
Wales. According to him the factors of flood are coastal (tidal), fluvial (river) or pluvial (surface
water) [4].
His mitigation suggestions are using reinforced concrete retaining/flood walls around
entire substation sites including using flood gates, raising equipment above level of flood,
ensuring all ducts are sealed from water ingress using approved duct systems, sealing low level
 ISSN: 1693-6930
TELKOMNIKA Vol. 15, No. 4, December 2017 : 1540 – 1546
1542
air brick vents, installing non return valves on flood drainage systems, using temporary flood
barriers and installating of pump system and pumping to external storage. Figure 3 below shows
an example of a substation fitted with floodwall protection using concrete walls and removable
panels.
Figure 3. Floodwall protection using concrete walls and removable panels [4]
The final approach to allow continuous operation of the electrical equipment in flood
conditions is by using electrical equipment which has been rated for submersible operations.
The standard IEEE C57.12.24-2016 defined submerged operation for transformers below
3750kVA as being capable of continuous unattended operation under 3m of water over the top
of the tank [5]. IEC 62271-111:2012 similarly has a water head limit of not more than 3m over
the base of the enclosure [6]. As part of their flood mitigation methods, Con Edison, which is the
power utility in New York, has installed 52% of the underground transformers and switches in
flood plains with submersible-capable equipment. Con Edison is planning to replace the
remaining underground electrical equipment with submersible type in the 100-year
floodplain [7].
1.2. Research Objectives
In Malaysia, submersible equipment has not yet been used in the distribution network
among the three mitigation methods presented in the previous section. Hence, this method has
been identified as one of the potential flood mitigation methods for further evaluation. The test
methods in both IEEE and IEC standards only refer to individual testing of the electrical
equipment. There is no method yet to test the equipment connected in a substation
configuration. Hence, a research project was undertaken with the following objectives:
 Development of design criteria for the selection of submersible equipment and accessories
to be used in a submersible substation
 Developing the testing method for the submersible equipment connected in a substation
configuration as per actual flood condition.
 Evaluation of the performance of the submersible equipment using the method developed
above.
2. Proposed Design Criteria
A typical 11/0.415kV distribution substation contains 11kV switchgears or ring main
units, 11/0.415kV transformer and 415V feeder pillar as well as other substation accessories
(DC supply, remote terminal units, remote control box etc.). For the purpose of laboratory
testing and to ensure the substation are fully submersible, accessories are installed which are
submersible 11kV and 415V cable termination as well as seals for the cable entry. Table 1
shows the design criteria of the submersible equipment and accessories. The design criteria are
based on the standard operating procedure used by TNB during flood events.
Based on the design criteria, market survey was performed to determine suitable
equipment which can withstand the flood conditions. There are many switchgear brands/models
which can meet the design criteria. These switchgears can be grouped into two main
technologies which are underground SF6 gas insulated switchgears and solid insulated
switchgears (SIS). SIS was chosen as the technology because of the lower price and to support
TELKOMNIKA ISSN: 1693-6930 
Design and Evaluation of Submersible 11/0.415kV Distribution Substation .... (M. D. M. Amir)
1543
the nation’s commitment in reducing greenhouse gas emission of which includes SF6 gas.
While there are several submersible transformers available in the market, it was decided to
partner with a local manufacturer to develop the submersible transformer to support the local
transformer industry.
Table 1. The Design Criteria for the Submersible Equipment and Accessories During
and After Flooding
Equipment /
Accessories
During Flooding After Flooding
11kV switchgear 1. No water ingress into the live parts of the
switchgear (busbar, vacuum interrupters)
2. Switchgear can continue to be in ON condition.
3. Switchgear protection system should be able
to continue function.
4. Switchgear status can be partially be
monitored.
5. Trip operation is possible once.
1. Switchgear can continue to be in ON
condition.
2. Trip operation is possible once prior
to retesting & inspection
3. Normal operation can only be allowed
after retesting & inspection.
11/0.415kV
transformer
1. No water ingress into the internal parts of the
transformer
2. Transformer can continue to be in ON
condition.
1. Transformer can continue to be in ON
condition.
2. Normal operation can only be allowed
after retesting & inspection.
415V feeder pillar 1. No water ingress into the live parts of the
feeder pillar (busbar)
2. Feeder pillar can continue to be in ON
condition.
3. Transformer can continue to be in ON
condition.
4. Normal operation can only be allowed
after retesting & inspection.
11kV and 415V
cable termination
1. No water ingress into the live elements of the
connection.
2. No damage to the cable termination insulation
material.
1. Cable termination can be reused after
flooding.
Seals for cable
entry
1. No water ingress into the cable compartments.
2. No physical damage to the seals.
1. Seals can be reused after flooding.
There is currently, no commercially available submersible feeder pillar. This is most
probably due to the technical difficulty in balancing ventilation needs as well as preventing water
ingress during the flooding. Another likely cause is the lack of demand for submersible feeder
pillars compared to submersible switchgears and transformers. A local manufacturer was
contracted to design and develop the submersible feeder pillar. The selected equipment is as
detailed in Table 2 below.
Table 2. The Description of Submersible Equipment Evaluated in the Submersible Test
Equipment Description
11kV switchgear 1. Solid insulated switchgear technology
2. Live parts encapsulated in solid resin insulation with IP67 protection
3. Other switchgear parts (e.g. motor, LV components, trip coils) are housed in a IP4X
rated panel
11/0.415kV
transformer
1. Almost identical to a normal 11/0.415kV transformer design.
2. The main difference with non-submersible transformer is in the use of bushing which
is specifically made for submersible conditions.
3. This bushing is rated IP67.
415V feeder pillar 1. Equipped with valve to allow air flow (ventilation) during normal conditions
2. Valves are opened during normal conditions
3. Sensors are installed to detect water level
4. During flood, the valves will be closed automatically if the pre-determined water level
are exceeded to prevent water ingress
5. After flood receded, the valves are opened again automatically
3. Research Method
Each of the submersible equipment and accessory are placed in a specially designed
water tank for the purpose of testing. The cables from the high voltage sources are inserted into
the tank through designated cable entry holes which are then closed off by using the cable entry
seal as shown in Figure 4. The test-setup for the submersible equipment and accessories
 ISSN: 1693-6930
TELKOMNIKA Vol. 15, No. 4, December 2017 : 1540 – 1546
1544
during the test is shown in Figure 5. Table 3 shows each phase for the submersible substation
testing with the tests performed during each phase. Figure 6(a) and 6(b) show the condition of
the submersible equipment and accessories during and after the wet test.
Figure 4. Use of seal for the cable entry hole
Figure 5. Test set-up for the submersible equipment and accessories in a substation
configuration
Table 3. The phases during the testing method for the submersible equipment connected in a
substation configuration as per actual flood condition.
Phase Tests Performed
Pre-testing for submersible equipment 1. Functional test for switchgear
2. Dielectric withstand test for switchgear
3. Insulation resistance (IR) test for transformer and switchgear
4. Test on secondary circuits
5. Contact resistance (CR) for switchgear
Dry test (240V supply – single phase) 6. Check relay output
7. Check supply output from feeder pillar
Dry test (6.5kV supply – single phase) 8. Check outgoing voltage at feeder pillar
9. Remote tripping test
Wet test (Circuit not energized) 10. Fill the tank with water at various levels (0.5m, 1m, 1.5m, 2m)
11. IR test at various levels
12. Current leakage tests throughout the wet test
Wet test (Circuit energized at 6.5kV
supply single phase for 48 hours)
13. Current leakage tests throughout the wet test
14. Switchgear remote tripping test after 48 hours
Post-testing for submersible equipment 15. Visual inspection of all equipment and accessories
16. Functional test for switchgear
17. Dielectric withstand test for switchgear
18. Insulation resistance (IR) test for transformer and switchgear
19. Contact resistance (CR) for switchgear
TELKOMNIKA ISSN: 1693-6930 
Design and Evaluation of Submersible 11/0.415kV Distribution Substation .... (M. D. M. Amir)
1545
(a) (b)
Figure 6. (a) Submersible test at 2 metre water level (b) Conditions of the submersible
substation after water level receded. Note that the both sets of 11kV and 415V cable termination
installed on the transformer are still in good condition
4. Results and Analysis
Table 4 summarises the results of the performance of the submersible equipment and
accessories during the submersible test. The main pass criterion is that each of the equipment
is able to continuously operate in ON condition while the circuit is energized at 6.5kV for 48
hours without tripping the main circuit.
Table 4. Results of the Performance of the Submersible Equipment using the Testing Method
for the Submersible Equipment Connected in a Substation Configuration as per Actual Flood
Condition
Equipment / Accessories Pass Criteria Results
11kV solid insulated
switchgear
Pass the wet test at 6.5kV for 48 hours
Able to trip during the flood
Pass IR test before & after the wet test.
Passed
11/0.415kV custom-made
transformer
Pass the wet test at 6.5kV for 48 hours.
Pass IR test before & after the wet test.
Passed
415V custom-made
feeder pillar
Pass the wet test at 6.5kV for 48 hours.
Pass IR test before & after the wet test.
Partially Passed
(Water droplets were observed inside the
feeder pillar after the wet test)
11kV submersible cable
termination
Pass the wet test at 6.5kV for 48 hours.
Pass IR test before & after the wet test.
Passed
415V submersible cable
termination
Pass the wet test at 6.5kV for 48 hours. Passed
Seals for cable entry No leaks during the wet test. Passed
All the equipment could continuously operate in ON condition during the wet test. The
submersible transformer, cable termination and seals for cable entry performed as per design
criteria and can be reused immediately after flood with only requiring minor external cleaning. It
proved to be robust enough to withstand the flood while resuming operation as usual
afterwards.
For the submersible feeder pillar, a little amount of water droplets was observed in the
feeder pillar after the submersible testing. Investigations determined that the root cause is due
to water seeping through the valve. This was caused by the weakness in the ball valve design.
Despite that, the main circuit was not tripped throughout the wet test indicating that the feeder
pillar was still able to continuously operate in ON condition.
 ISSN: 1693-6930
TELKOMNIKA Vol. 15, No. 4, December 2017 : 1540 – 1546
1546
Even though the submersible switchgear could pass the test, several components need
to be replaced after the wet test. These components, which include the motor, trip and close coil
as well as the operation counter, are not situated inside the IP67 solid insulated tank, but rather
within the IP4X panel. This means that after flooding, maintenance will need to be performed
prior to restoring the switchgear to full service. This has the implication of extra expenditure for
the utility due to maintenance works and component replacement costs.
5. Conclusion
The design criteria for the selection of submersible equipment and accessories to be
used in a submersible substation have been developed based on the prevailing TNB standard
operating procedure during flood conditions. The equipment and accessories were then
selected partly based on commercially available products in the market and partly developed in
collaboration with local manufacturers.
The test method for the submersible equipment connected in a substation configuration
as per flood condition has been developed. The test method is separated into 6 different phases
designed to test the performance of the submersible equipment in different conditions. The
facilities for the submersible substation test were constructed and can be used for testing of
other types of electrical equipment under submerged conditions.
All the equipment could continuously operate in ON condition during the wet test. The
submersible transformer, cable termination and seals for cable entry performed as per design
criteria and can be reused immediately after flood with only requiring minor external cleaning.
The submersible switchgear requires maintenance works and component replacement after
flood events. It is recommended for the manufacturer to improve the design and durability of the
components to minimize the replacement works.
Water droplets were found in the feeder pillar caused by the weakness in the ball valve
design. The corrective measure will be to redesign and retest the feeder pillar. A potential
improvement is by replacing the ball valve using a latching solenoid valve. By doing so, the
solenoid valve will be useful to prevent water seeping through due to its better mechanical
design capability.
In summary, the use of submersible equipment and accessories is technically feasible
as a mitigation method for flood conditions. However, several design improvements need to be
made in the evaluated submersible switchgear and feeder pillar before being implemented in
the field.
References
[1] Boggess JM, Becker GW, Mitchell MK. Storm & flood hardening of electrical substations. IEEE PES
T&D Conference and Exposition. Chicago. 2014: 1 - 5.
[2] Baker JW. Eliminating hurricane-induced storm surge damage to electric utilities via in-place
elevation of substation structures and equipment. IEEE PES T&D Conference and Exposition.
Chicago. 2014: 1 - 5.
[3] Matos SM, Joao PC. Flood Adaptation Measures Applicable in the Design of Urban Public Spaces:
Proposal for a Conceptual Framework. Water. 2016; 8(7): 284.
[4] Dunk M. Substation Flood Protection: Engineering Design Standard. UK Power Networks. EDS 07-
0106. 2016.
[5] IEEE Standards Association. C57.12.24-2016, IEEE Standard for Submersible, Three-Phase
Transformers, 3750kVA and Smaller: High Voltage, 34 500 GRDY/19 920 Volts and Below; Low
Voltage, 600 Volts and Below. IEEE Press. 2016.
[6] International Electrotechnical Commission. 62271-111:2012, High Voltage Switchgear and
Controlgear – Part 111: Automatic Circuit Reclosers and Fault Interrupters for Alternating Current
Systems up to 38kV. IEC. 2012.
[7] A Stronger, More Resilient New York. New York: City of New York. 2013: 107 – 129.

More Related Content

What's hot

A Study of the Root Causes of High Failure Rate of Distribution Transformer -...
A Study of the Root Causes of High Failure Rate of Distribution Transformer -...A Study of the Root Causes of High Failure Rate of Distribution Transformer -...
A Study of the Root Causes of High Failure Rate of Distribution Transformer -...theijes
 
Statoil innovate subsea_technology_v5
Statoil innovate subsea_technology_v5Statoil innovate subsea_technology_v5
Statoil innovate subsea_technology_v5Statoil
 
Energy efficiant megaship in the Caribbean
Energy efficiant megaship in the CaribbeanEnergy efficiant megaship in the Caribbean
Energy efficiant megaship in the CaribbeanVacon Plc
 
2012 Network design
2012 Network design2012 Network design
2012 Network designJohn Snoxell
 
Global Perspective on the Future of Subsea Technology
Global Perspective on the Future of Subsea TechnologyGlobal Perspective on the Future of Subsea Technology
Global Perspective on the Future of Subsea TechnologyConference_Presentations
 
SIMULATION OF PRESSURE VARIATIONS WITHIN KIMILILI WATER SUPPLY SYSTEM USING E...
SIMULATION OF PRESSURE VARIATIONS WITHIN KIMILILI WATER SUPPLY SYSTEM USING E...SIMULATION OF PRESSURE VARIATIONS WITHIN KIMILILI WATER SUPPLY SYSTEM USING E...
SIMULATION OF PRESSURE VARIATIONS WITHIN KIMILILI WATER SUPPLY SYSTEM USING E...IAEME Publication
 
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...Stephen Flood
 
2013 FWRJ December WPB
2013 FWRJ December WPB2013 FWRJ December WPB
2013 FWRJ December WPBGJ Schers
 
Ice midlands region warwick, 2010
Ice midlands region warwick, 2010Ice midlands region warwick, 2010
Ice midlands region warwick, 2010Warwick Knowledge
 
48. ss-esmmp-for-foundationerection-and-stringing-work-may-2015
48. ss-esmmp-for-foundationerection-and-stringing-work-may-201548. ss-esmmp-for-foundationerection-and-stringing-work-may-2015
48. ss-esmmp-for-foundationerection-and-stringing-work-may-2015Sandeep Bhowmick
 
Assessment of Swan and Canning River Tidal and Storm Surge Water Levels - Ala...
Assessment of Swan and Canning River Tidal and Storm Surge Water Levels - Ala...Assessment of Swan and Canning River Tidal and Storm Surge Water Levels - Ala...
Assessment of Swan and Canning River Tidal and Storm Surge Water Levels - Ala...Stephen Flood
 
Risk management during start up and commissioning of super critical once thro...
Risk management during start up and commissioning of super critical once thro...Risk management during start up and commissioning of super critical once thro...
Risk management during start up and commissioning of super critical once thro...HIMADRI BANERJI
 
Thiet ke duong_ong_tren_bo
Thiet ke duong_ong_tren_boThiet ke duong_ong_tren_bo
Thiet ke duong_ong_tren_boRobinking Boley
 
Recent Advancements in Piping industry and Piping materials.
Recent Advancements in Piping industry and Piping materials.Recent Advancements in Piping industry and Piping materials.
Recent Advancements in Piping industry and Piping materials.Asheesh Padiyar
 
50-Marco Casirati-Nord Stream Pre-Commissioning
50-Marco Casirati-Nord Stream Pre-Commissioning50-Marco Casirati-Nord Stream Pre-Commissioning
50-Marco Casirati-Nord Stream Pre-CommissioningJohn Grover
 
Analysis of the drinking water supply system of dire dawa town & proposal...
Analysis of the drinking water supply system of dire dawa town & proposal...Analysis of the drinking water supply system of dire dawa town & proposal...
Analysis of the drinking water supply system of dire dawa town & proposal...Endale Belete
 

What's hot (20)

A Study of the Root Causes of High Failure Rate of Distribution Transformer -...
A Study of the Root Causes of High Failure Rate of Distribution Transformer -...A Study of the Root Causes of High Failure Rate of Distribution Transformer -...
A Study of the Root Causes of High Failure Rate of Distribution Transformer -...
 
Submarine outfalls & intakes ppt
Submarine outfalls & intakes pptSubmarine outfalls & intakes ppt
Submarine outfalls & intakes ppt
 
Statoil innovate subsea_technology_v5
Statoil innovate subsea_technology_v5Statoil innovate subsea_technology_v5
Statoil innovate subsea_technology_v5
 
Energy efficiant megaship in the Caribbean
Energy efficiant megaship in the CaribbeanEnergy efficiant megaship in the Caribbean
Energy efficiant megaship in the Caribbean
 
2012 Network design
2012 Network design2012 Network design
2012 Network design
 
Global Perspective on the Future of Subsea Technology
Global Perspective on the Future of Subsea TechnologyGlobal Perspective on the Future of Subsea Technology
Global Perspective on the Future of Subsea Technology
 
Contech DuroMaxx Steel Reinforced Polyethylene
Contech DuroMaxx Steel Reinforced PolyethyleneContech DuroMaxx Steel Reinforced Polyethylene
Contech DuroMaxx Steel Reinforced Polyethylene
 
SIMULATION OF PRESSURE VARIATIONS WITHIN KIMILILI WATER SUPPLY SYSTEM USING E...
SIMULATION OF PRESSURE VARIATIONS WITHIN KIMILILI WATER SUPPLY SYSTEM USING E...SIMULATION OF PRESSURE VARIATIONS WITHIN KIMILILI WATER SUPPLY SYSTEM USING E...
SIMULATION OF PRESSURE VARIATIONS WITHIN KIMILILI WATER SUPPLY SYSTEM USING E...
 
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...
 
2013 FWRJ December WPB
2013 FWRJ December WPB2013 FWRJ December WPB
2013 FWRJ December WPB
 
Ice midlands region warwick, 2010
Ice midlands region warwick, 2010Ice midlands region warwick, 2010
Ice midlands region warwick, 2010
 
48. ss-esmmp-for-foundationerection-and-stringing-work-may-2015
48. ss-esmmp-for-foundationerection-and-stringing-work-may-201548. ss-esmmp-for-foundationerection-and-stringing-work-may-2015
48. ss-esmmp-for-foundationerection-and-stringing-work-may-2015
 
Assessment of Swan and Canning River Tidal and Storm Surge Water Levels - Ala...
Assessment of Swan and Canning River Tidal and Storm Surge Water Levels - Ala...Assessment of Swan and Canning River Tidal and Storm Surge Water Levels - Ala...
Assessment of Swan and Canning River Tidal and Storm Surge Water Levels - Ala...
 
Risk management during start up and commissioning of super critical once thro...
Risk management during start up and commissioning of super critical once thro...Risk management during start up and commissioning of super critical once thro...
Risk management during start up and commissioning of super critical once thro...
 
Thiet ke duong_ong_tren_bo
Thiet ke duong_ong_tren_boThiet ke duong_ong_tren_bo
Thiet ke duong_ong_tren_bo
 
Recent Advancements in Piping industry and Piping materials.
Recent Advancements in Piping industry and Piping materials.Recent Advancements in Piping industry and Piping materials.
Recent Advancements in Piping industry and Piping materials.
 
Trenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe InstallationsTrenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe Installations
 
50-Marco Casirati-Nord Stream Pre-Commissioning
50-Marco Casirati-Nord Stream Pre-Commissioning50-Marco Casirati-Nord Stream Pre-Commissioning
50-Marco Casirati-Nord Stream Pre-Commissioning
 
Analysis of the drinking water supply system of dire dawa town & proposal...
Analysis of the drinking water supply system of dire dawa town & proposal...Analysis of the drinking water supply system of dire dawa town & proposal...
Analysis of the drinking water supply system of dire dawa town & proposal...
 
E&I Farukh
E&I FarukhE&I Farukh
E&I Farukh
 

Similar to Design and Test Submersible 11kV Distribution Substation

Building Services Project 02
Building Services Project 02Building Services Project 02
Building Services Project 02Bolin Loong
 
26-grover-john-draft
26-grover-john-draft26-grover-john-draft
26-grover-john-draftJohn Grover
 
132 k v-substation-training-for-students
132 k v-substation-training-for-students132 k v-substation-training-for-students
132 k v-substation-training-for-studentsSanjay Kumar Sharma
 
Training at 132 kv substation
Training at 132 kv substation Training at 132 kv substation
Training at 132 kv substation Tejveer Choudhary
 
IRJET- Transmission of Ac Power from Offshore to Onshore by using Low Frequen...
IRJET- Transmission of Ac Power from Offshore to Onshore by using Low Frequen...IRJET- Transmission of Ac Power from Offshore to Onshore by using Low Frequen...
IRJET- Transmission of Ac Power from Offshore to Onshore by using Low Frequen...IRJET Journal
 
B service project 2
B service project 2B service project 2
B service project 2- -
 
A Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv SubstationA Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv SubstationSubhrajit Ghosh
 
Engineering Final Year Project Report on "Electrical Safety and Protection of...
Engineering Final Year Project Report on "Electrical Safety and Protection of...Engineering Final Year Project Report on "Electrical Safety and Protection of...
Engineering Final Year Project Report on "Electrical Safety and Protection of...Pratap Bhunia
 
23-2009 Pre-piling for wind farms.pdf
23-2009 Pre-piling for wind farms.pdf23-2009 Pre-piling for wind farms.pdf
23-2009 Pre-piling for wind farms.pdframadhitaerdina1
 
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...Ivan Rojas Soliz
 
“HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”
“HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”“HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”
“HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”IRJET Journal
 
Subsea completion and control system
Subsea completion and control systemSubsea completion and control system
Subsea completion and control systemAmit Nitharwal
 
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...nak maneth
 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentationRajashekar Gurrala
 
Wind Power Plant Planning And Commisioning
Wind Power Plant  Planning  And CommisioningWind Power Plant  Planning  And Commisioning
Wind Power Plant Planning And CommisioningSuraj Naik
 
Performance evaluation of PV penetration at different locations in a LV distr...
Performance evaluation of PV penetration at different locations in a LV distr...Performance evaluation of PV penetration at different locations in a LV distr...
Performance evaluation of PV penetration at different locations in a LV distr...nooriasukmaningtyas
 

Similar to Design and Test Submersible 11kV Distribution Substation (20)

Building Services Project 02
Building Services Project 02Building Services Project 02
Building Services Project 02
 
26-grover-john-draft
26-grover-john-draft26-grover-john-draft
26-grover-john-draft
 
132 k v-substation-training-for-students
132 k v-substation-training-for-students132 k v-substation-training-for-students
132 k v-substation-training-for-students
 
Training at 132 kv substation
Training at 132 kv substation Training at 132 kv substation
Training at 132 kv substation
 
IRJET- Transmission of Ac Power from Offshore to Onshore by using Low Frequen...
IRJET- Transmission of Ac Power from Offshore to Onshore by using Low Frequen...IRJET- Transmission of Ac Power from Offshore to Onshore by using Low Frequen...
IRJET- Transmission of Ac Power from Offshore to Onshore by using Low Frequen...
 
A modified bridge-type nonsuperconducting fault current limiter for distribut...
A modified bridge-type nonsuperconducting fault current limiter for distribut...A modified bridge-type nonsuperconducting fault current limiter for distribut...
A modified bridge-type nonsuperconducting fault current limiter for distribut...
 
B service project 2
B service project 2B service project 2
B service project 2
 
2012 offshore wind cables
2012 offshore wind cables2012 offshore wind cables
2012 offshore wind cables
 
Oil pipiline stress monitoring
Oil pipiline  stress monitoringOil pipiline  stress monitoring
Oil pipiline stress monitoring
 
A Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv SubstationA Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv Substation
 
Engineering Final Year Project Report on "Electrical Safety and Protection of...
Engineering Final Year Project Report on "Electrical Safety and Protection of...Engineering Final Year Project Report on "Electrical Safety and Protection of...
Engineering Final Year Project Report on "Electrical Safety and Protection of...
 
23-2009 Pre-piling for wind farms.pdf
23-2009 Pre-piling for wind farms.pdf23-2009 Pre-piling for wind farms.pdf
23-2009 Pre-piling for wind farms.pdf
 
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
 
“HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”
“HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”“HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”
“HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”
 
Subsea completion and control system
Subsea completion and control systemSubsea completion and control system
Subsea completion and control system
 
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentation
 
Wind Power Plant Planning And Commisioning
Wind Power Plant  Planning  And CommisioningWind Power Plant  Planning  And Commisioning
Wind Power Plant Planning And Commisioning
 
Shipboard High Voltage- Safeties & Applications
Shipboard High Voltage- Safeties & ApplicationsShipboard High Voltage- Safeties & Applications
Shipboard High Voltage- Safeties & Applications
 
Performance evaluation of PV penetration at different locations in a LV distr...
Performance evaluation of PV penetration at different locations in a LV distr...Performance evaluation of PV penetration at different locations in a LV distr...
Performance evaluation of PV penetration at different locations in a LV distr...
 

More from TELKOMNIKA JOURNAL

Amazon products reviews classification based on machine learning, deep learni...
Amazon products reviews classification based on machine learning, deep learni...Amazon products reviews classification based on machine learning, deep learni...
Amazon products reviews classification based on machine learning, deep learni...TELKOMNIKA JOURNAL
 
Design, simulation, and analysis of microstrip patch antenna for wireless app...
Design, simulation, and analysis of microstrip patch antenna for wireless app...Design, simulation, and analysis of microstrip patch antenna for wireless app...
Design, simulation, and analysis of microstrip patch antenna for wireless app...TELKOMNIKA JOURNAL
 
Design and simulation an optimal enhanced PI controller for congestion avoida...
Design and simulation an optimal enhanced PI controller for congestion avoida...Design and simulation an optimal enhanced PI controller for congestion avoida...
Design and simulation an optimal enhanced PI controller for congestion avoida...TELKOMNIKA JOURNAL
 
Improving the detection of intrusion in vehicular ad-hoc networks with modifi...
Improving the detection of intrusion in vehicular ad-hoc networks with modifi...Improving the detection of intrusion in vehicular ad-hoc networks with modifi...
Improving the detection of intrusion in vehicular ad-hoc networks with modifi...TELKOMNIKA JOURNAL
 
Conceptual model of internet banking adoption with perceived risk and trust f...
Conceptual model of internet banking adoption with perceived risk and trust f...Conceptual model of internet banking adoption with perceived risk and trust f...
Conceptual model of internet banking adoption with perceived risk and trust f...TELKOMNIKA JOURNAL
 
Efficient combined fuzzy logic and LMS algorithm for smart antenna
Efficient combined fuzzy logic and LMS algorithm for smart antennaEfficient combined fuzzy logic and LMS algorithm for smart antenna
Efficient combined fuzzy logic and LMS algorithm for smart antennaTELKOMNIKA JOURNAL
 
Design and implementation of a LoRa-based system for warning of forest fire
Design and implementation of a LoRa-based system for warning of forest fireDesign and implementation of a LoRa-based system for warning of forest fire
Design and implementation of a LoRa-based system for warning of forest fireTELKOMNIKA JOURNAL
 
Wavelet-based sensing technique in cognitive radio network
Wavelet-based sensing technique in cognitive radio networkWavelet-based sensing technique in cognitive radio network
Wavelet-based sensing technique in cognitive radio networkTELKOMNIKA JOURNAL
 
A novel compact dual-band bandstop filter with enhanced rejection bands
A novel compact dual-band bandstop filter with enhanced rejection bandsA novel compact dual-band bandstop filter with enhanced rejection bands
A novel compact dual-band bandstop filter with enhanced rejection bandsTELKOMNIKA JOURNAL
 
Deep learning approach to DDoS attack with imbalanced data at the application...
Deep learning approach to DDoS attack with imbalanced data at the application...Deep learning approach to DDoS attack with imbalanced data at the application...
Deep learning approach to DDoS attack with imbalanced data at the application...TELKOMNIKA JOURNAL
 
Brief note on match and miss-match uncertainties
Brief note on match and miss-match uncertaintiesBrief note on match and miss-match uncertainties
Brief note on match and miss-match uncertaintiesTELKOMNIKA JOURNAL
 
Implementation of FinFET technology based low power 4×4 Wallace tree multipli...
Implementation of FinFET technology based low power 4×4 Wallace tree multipli...Implementation of FinFET technology based low power 4×4 Wallace tree multipli...
Implementation of FinFET technology based low power 4×4 Wallace tree multipli...TELKOMNIKA JOURNAL
 
Evaluation of the weighted-overlap add model with massive MIMO in a 5G system
Evaluation of the weighted-overlap add model with massive MIMO in a 5G systemEvaluation of the weighted-overlap add model with massive MIMO in a 5G system
Evaluation of the weighted-overlap add model with massive MIMO in a 5G systemTELKOMNIKA JOURNAL
 
Reflector antenna design in different frequencies using frequency selective s...
Reflector antenna design in different frequencies using frequency selective s...Reflector antenna design in different frequencies using frequency selective s...
Reflector antenna design in different frequencies using frequency selective s...TELKOMNIKA JOURNAL
 
Reagentless iron detection in water based on unclad fiber optical sensor
Reagentless iron detection in water based on unclad fiber optical sensorReagentless iron detection in water based on unclad fiber optical sensor
Reagentless iron detection in water based on unclad fiber optical sensorTELKOMNIKA JOURNAL
 
Impact of CuS counter electrode calcination temperature on quantum dot sensit...
Impact of CuS counter electrode calcination temperature on quantum dot sensit...Impact of CuS counter electrode calcination temperature on quantum dot sensit...
Impact of CuS counter electrode calcination temperature on quantum dot sensit...TELKOMNIKA JOURNAL
 
A progressive learning for structural tolerance online sequential extreme lea...
A progressive learning for structural tolerance online sequential extreme lea...A progressive learning for structural tolerance online sequential extreme lea...
A progressive learning for structural tolerance online sequential extreme lea...TELKOMNIKA JOURNAL
 
Electroencephalography-based brain-computer interface using neural networks
Electroencephalography-based brain-computer interface using neural networksElectroencephalography-based brain-computer interface using neural networks
Electroencephalography-based brain-computer interface using neural networksTELKOMNIKA JOURNAL
 
Adaptive segmentation algorithm based on level set model in medical imaging
Adaptive segmentation algorithm based on level set model in medical imagingAdaptive segmentation algorithm based on level set model in medical imaging
Adaptive segmentation algorithm based on level set model in medical imagingTELKOMNIKA JOURNAL
 
Automatic channel selection using shuffled frog leaping algorithm for EEG bas...
Automatic channel selection using shuffled frog leaping algorithm for EEG bas...Automatic channel selection using shuffled frog leaping algorithm for EEG bas...
Automatic channel selection using shuffled frog leaping algorithm for EEG bas...TELKOMNIKA JOURNAL
 

More from TELKOMNIKA JOURNAL (20)

Amazon products reviews classification based on machine learning, deep learni...
Amazon products reviews classification based on machine learning, deep learni...Amazon products reviews classification based on machine learning, deep learni...
Amazon products reviews classification based on machine learning, deep learni...
 
Design, simulation, and analysis of microstrip patch antenna for wireless app...
Design, simulation, and analysis of microstrip patch antenna for wireless app...Design, simulation, and analysis of microstrip patch antenna for wireless app...
Design, simulation, and analysis of microstrip patch antenna for wireless app...
 
Design and simulation an optimal enhanced PI controller for congestion avoida...
Design and simulation an optimal enhanced PI controller for congestion avoida...Design and simulation an optimal enhanced PI controller for congestion avoida...
Design and simulation an optimal enhanced PI controller for congestion avoida...
 
Improving the detection of intrusion in vehicular ad-hoc networks with modifi...
Improving the detection of intrusion in vehicular ad-hoc networks with modifi...Improving the detection of intrusion in vehicular ad-hoc networks with modifi...
Improving the detection of intrusion in vehicular ad-hoc networks with modifi...
 
Conceptual model of internet banking adoption with perceived risk and trust f...
Conceptual model of internet banking adoption with perceived risk and trust f...Conceptual model of internet banking adoption with perceived risk and trust f...
Conceptual model of internet banking adoption with perceived risk and trust f...
 
Efficient combined fuzzy logic and LMS algorithm for smart antenna
Efficient combined fuzzy logic and LMS algorithm for smart antennaEfficient combined fuzzy logic and LMS algorithm for smart antenna
Efficient combined fuzzy logic and LMS algorithm for smart antenna
 
Design and implementation of a LoRa-based system for warning of forest fire
Design and implementation of a LoRa-based system for warning of forest fireDesign and implementation of a LoRa-based system for warning of forest fire
Design and implementation of a LoRa-based system for warning of forest fire
 
Wavelet-based sensing technique in cognitive radio network
Wavelet-based sensing technique in cognitive radio networkWavelet-based sensing technique in cognitive radio network
Wavelet-based sensing technique in cognitive radio network
 
A novel compact dual-band bandstop filter with enhanced rejection bands
A novel compact dual-band bandstop filter with enhanced rejection bandsA novel compact dual-band bandstop filter with enhanced rejection bands
A novel compact dual-band bandstop filter with enhanced rejection bands
 
Deep learning approach to DDoS attack with imbalanced data at the application...
Deep learning approach to DDoS attack with imbalanced data at the application...Deep learning approach to DDoS attack with imbalanced data at the application...
Deep learning approach to DDoS attack with imbalanced data at the application...
 
Brief note on match and miss-match uncertainties
Brief note on match and miss-match uncertaintiesBrief note on match and miss-match uncertainties
Brief note on match and miss-match uncertainties
 
Implementation of FinFET technology based low power 4×4 Wallace tree multipli...
Implementation of FinFET technology based low power 4×4 Wallace tree multipli...Implementation of FinFET technology based low power 4×4 Wallace tree multipli...
Implementation of FinFET technology based low power 4×4 Wallace tree multipli...
 
Evaluation of the weighted-overlap add model with massive MIMO in a 5G system
Evaluation of the weighted-overlap add model with massive MIMO in a 5G systemEvaluation of the weighted-overlap add model with massive MIMO in a 5G system
Evaluation of the weighted-overlap add model with massive MIMO in a 5G system
 
Reflector antenna design in different frequencies using frequency selective s...
Reflector antenna design in different frequencies using frequency selective s...Reflector antenna design in different frequencies using frequency selective s...
Reflector antenna design in different frequencies using frequency selective s...
 
Reagentless iron detection in water based on unclad fiber optical sensor
Reagentless iron detection in water based on unclad fiber optical sensorReagentless iron detection in water based on unclad fiber optical sensor
Reagentless iron detection in water based on unclad fiber optical sensor
 
Impact of CuS counter electrode calcination temperature on quantum dot sensit...
Impact of CuS counter electrode calcination temperature on quantum dot sensit...Impact of CuS counter electrode calcination temperature on quantum dot sensit...
Impact of CuS counter electrode calcination temperature on quantum dot sensit...
 
A progressive learning for structural tolerance online sequential extreme lea...
A progressive learning for structural tolerance online sequential extreme lea...A progressive learning for structural tolerance online sequential extreme lea...
A progressive learning for structural tolerance online sequential extreme lea...
 
Electroencephalography-based brain-computer interface using neural networks
Electroencephalography-based brain-computer interface using neural networksElectroencephalography-based brain-computer interface using neural networks
Electroencephalography-based brain-computer interface using neural networks
 
Adaptive segmentation algorithm based on level set model in medical imaging
Adaptive segmentation algorithm based on level set model in medical imagingAdaptive segmentation algorithm based on level set model in medical imaging
Adaptive segmentation algorithm based on level set model in medical imaging
 
Automatic channel selection using shuffled frog leaping algorithm for EEG bas...
Automatic channel selection using shuffled frog leaping algorithm for EEG bas...Automatic channel selection using shuffled frog leaping algorithm for EEG bas...
Automatic channel selection using shuffled frog leaping algorithm for EEG bas...
 

Recently uploaded

OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 

Recently uploaded (20)

OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 

Design and Test Submersible 11kV Distribution Substation

  • 1. TELKOMNIKA, Vol.15, No.4, December 2017, pp. 1540~1546 ISSN: 1693-6930, accredited A by DIKTI, Decree No: 58/DIKTI/Kep/2013 DOI: 10.12928/TELKOMNIKA.v15i4.7232  1540 Received September 2, 2017; Revised November 10, 2017; Accepted November 25, 2017 Design and Evaluation of Submersible 11/0.415kV Distribution Substation for Flood Prone Areas M. D. M. Amir*, S. Ishak, A. Raj Gopal TNB Research Sdn Bhd, Kawasan Institusi Penyelidikan, 43000 Kajang, Selangor, Malaysia +60389225000 *Corresponding author, e-mail: dzaki.amir@tnb.com.my Abstract Flood levels exceeding 2 metres above ground level has been observed causing electrical equipment in the 11/0.415kV substation to be fully submerged. This caused widespread supply disruption as the equipment need to be switched off due to safety reasons and prevention of further equipment damage. The use of submersible equipment and accessories has been identified as one of the mitigation methods to ensure continuous electrical supply during flood events. A research project was undertaken to develop the design criteria of the selection of submersible equipment and accessories as well as to develop the test method and evaluate the selected submersible equipment and accessories in a substation configuration. All the equipment could continuously operate in ON condition during the wet test. However, design improvements are suggested for the submersible switchgear and feeder pillar for better performance during and after flood events. Keywords: high voltage testing, submersible substation, submersible electrical equipment, flood mitigation Copyright © 2017 Universitas Ahmad Dahlan. All rights reserved. 1. Introduction During the last major Malaysian flood events in 2014; the water level in several areas exceeded 2 metres above ground level. This caused electrical equipment in the 11/0.415kV distribution substation to be fully submerged. As the equipment is not rated for submersible operations, the equipment in the flood affected substation need to be switched off due to safety reasons and to prevent further damage to the equipment. This does not only cause supply disruption to the local area served by the flood affected substation but also any substation downstream to the affected substation. This is especially critical in spur feeder configuration, normally used in rural areas, which is the most prone to flood events. This may cause a larger than necessary number of customers to be affected by the flood as the downstream substations might not be affected by the flood (as illustrated in Figure 1). Figure 1. All the substations downstream of the affected substation will suffer from supply disruption even though they are not flooded themselves
  • 2. TELKOMNIKA ISSN: 1693-6930  Design and Evaluation of Submersible 11/0.415kV Distribution Substation .... (M. D. M. Amir) 1541 During the flood events, Tenaga Nasional Berhad (TNB), which is the Malaysian national power utility company, will incur a large cost to replace and/or repair any equipment damaged by the flood as well the cost of providing temporary supply by using mobile gen-sets to areas downstream of the flood-affected substation. As the flood events can last up to one week, TNB suffered losses due to unserved energy during this period. Finally, TNB also suffered from intangible losses such as reputation loss in the eyes of the public and investors due to taking longer time in restoring the supply. 1.1. Current Utility Practice in Mitigating Flood Events There are several major approaches used by utilities worldwide to mitigate flood events. Bogees proposes the elevation of the substation as a mitigation for flooding. Distribution voltages are more convenient to elevate due to the availability of many substation designs that can be placed on stilts, platforms or slabs [1]. However, it is more tedious to elevate a transmission substation due to the large space needed for increased electrical clearances at high voltages. This will lead to increase in material cost for concrete and steel. This is practiced by TNB for flood-prone areas but its limitations are that this mitigation method caters only for low flood level. Figure 2(a) and 2(b) show example of raised substation for flood level above and below 3 metres respectively. Succeeding suggestion of Joseph Baker is to elevate the substation that he defined as raising the substation utilizing existing structures [2]. The suggestion to elevate to existing structures makes the solution economical. The solution has an acceptable schedule criterion. However, the risk of service disruption time is relatively high with moderate increase in operation and maintenance risk. Another option is to elevate to a new site to reduce service interruption time as discussed in [3]. This may prove to be costly and has a long lead time. Additional land is required to allow construction to allow continuation of supply. The recommended height raise is 1.2 m. (a) (b) Figure 2. (a) Raised substation for flood level above 3 metres (b) Raised substation for flood level below 3 metres Another major approach is by using floodwalls. Floodwalls are defined as constructed barriers that provide more than 4 feet flood protection to buildings. Joseph Baker suggests in his paper that the floodwall around the substation will protect the substation and additions of pumps will remove entrapped water [2]. This method is economically viable and has minimum construction duration with minimal service disruption. However, the drawbacks may be additional monitoring of pump is needed and if the floodwall breaches complete operational failure may cause a devastating impact. Mark Dunk in “Substation Flood Protection (2016)” agrees with flood protection for substations as a main highlight. This is due to the flooding events recorded across England and Wales. According to him the factors of flood are coastal (tidal), fluvial (river) or pluvial (surface water) [4]. His mitigation suggestions are using reinforced concrete retaining/flood walls around entire substation sites including using flood gates, raising equipment above level of flood, ensuring all ducts are sealed from water ingress using approved duct systems, sealing low level
  • 3.  ISSN: 1693-6930 TELKOMNIKA Vol. 15, No. 4, December 2017 : 1540 – 1546 1542 air brick vents, installing non return valves on flood drainage systems, using temporary flood barriers and installating of pump system and pumping to external storage. Figure 3 below shows an example of a substation fitted with floodwall protection using concrete walls and removable panels. Figure 3. Floodwall protection using concrete walls and removable panels [4] The final approach to allow continuous operation of the electrical equipment in flood conditions is by using electrical equipment which has been rated for submersible operations. The standard IEEE C57.12.24-2016 defined submerged operation for transformers below 3750kVA as being capable of continuous unattended operation under 3m of water over the top of the tank [5]. IEC 62271-111:2012 similarly has a water head limit of not more than 3m over the base of the enclosure [6]. As part of their flood mitigation methods, Con Edison, which is the power utility in New York, has installed 52% of the underground transformers and switches in flood plains with submersible-capable equipment. Con Edison is planning to replace the remaining underground electrical equipment with submersible type in the 100-year floodplain [7]. 1.2. Research Objectives In Malaysia, submersible equipment has not yet been used in the distribution network among the three mitigation methods presented in the previous section. Hence, this method has been identified as one of the potential flood mitigation methods for further evaluation. The test methods in both IEEE and IEC standards only refer to individual testing of the electrical equipment. There is no method yet to test the equipment connected in a substation configuration. Hence, a research project was undertaken with the following objectives:  Development of design criteria for the selection of submersible equipment and accessories to be used in a submersible substation  Developing the testing method for the submersible equipment connected in a substation configuration as per actual flood condition.  Evaluation of the performance of the submersible equipment using the method developed above. 2. Proposed Design Criteria A typical 11/0.415kV distribution substation contains 11kV switchgears or ring main units, 11/0.415kV transformer and 415V feeder pillar as well as other substation accessories (DC supply, remote terminal units, remote control box etc.). For the purpose of laboratory testing and to ensure the substation are fully submersible, accessories are installed which are submersible 11kV and 415V cable termination as well as seals for the cable entry. Table 1 shows the design criteria of the submersible equipment and accessories. The design criteria are based on the standard operating procedure used by TNB during flood events. Based on the design criteria, market survey was performed to determine suitable equipment which can withstand the flood conditions. There are many switchgear brands/models which can meet the design criteria. These switchgears can be grouped into two main technologies which are underground SF6 gas insulated switchgears and solid insulated switchgears (SIS). SIS was chosen as the technology because of the lower price and to support
  • 4. TELKOMNIKA ISSN: 1693-6930  Design and Evaluation of Submersible 11/0.415kV Distribution Substation .... (M. D. M. Amir) 1543 the nation’s commitment in reducing greenhouse gas emission of which includes SF6 gas. While there are several submersible transformers available in the market, it was decided to partner with a local manufacturer to develop the submersible transformer to support the local transformer industry. Table 1. The Design Criteria for the Submersible Equipment and Accessories During and After Flooding Equipment / Accessories During Flooding After Flooding 11kV switchgear 1. No water ingress into the live parts of the switchgear (busbar, vacuum interrupters) 2. Switchgear can continue to be in ON condition. 3. Switchgear protection system should be able to continue function. 4. Switchgear status can be partially be monitored. 5. Trip operation is possible once. 1. Switchgear can continue to be in ON condition. 2. Trip operation is possible once prior to retesting & inspection 3. Normal operation can only be allowed after retesting & inspection. 11/0.415kV transformer 1. No water ingress into the internal parts of the transformer 2. Transformer can continue to be in ON condition. 1. Transformer can continue to be in ON condition. 2. Normal operation can only be allowed after retesting & inspection. 415V feeder pillar 1. No water ingress into the live parts of the feeder pillar (busbar) 2. Feeder pillar can continue to be in ON condition. 3. Transformer can continue to be in ON condition. 4. Normal operation can only be allowed after retesting & inspection. 11kV and 415V cable termination 1. No water ingress into the live elements of the connection. 2. No damage to the cable termination insulation material. 1. Cable termination can be reused after flooding. Seals for cable entry 1. No water ingress into the cable compartments. 2. No physical damage to the seals. 1. Seals can be reused after flooding. There is currently, no commercially available submersible feeder pillar. This is most probably due to the technical difficulty in balancing ventilation needs as well as preventing water ingress during the flooding. Another likely cause is the lack of demand for submersible feeder pillars compared to submersible switchgears and transformers. A local manufacturer was contracted to design and develop the submersible feeder pillar. The selected equipment is as detailed in Table 2 below. Table 2. The Description of Submersible Equipment Evaluated in the Submersible Test Equipment Description 11kV switchgear 1. Solid insulated switchgear technology 2. Live parts encapsulated in solid resin insulation with IP67 protection 3. Other switchgear parts (e.g. motor, LV components, trip coils) are housed in a IP4X rated panel 11/0.415kV transformer 1. Almost identical to a normal 11/0.415kV transformer design. 2. The main difference with non-submersible transformer is in the use of bushing which is specifically made for submersible conditions. 3. This bushing is rated IP67. 415V feeder pillar 1. Equipped with valve to allow air flow (ventilation) during normal conditions 2. Valves are opened during normal conditions 3. Sensors are installed to detect water level 4. During flood, the valves will be closed automatically if the pre-determined water level are exceeded to prevent water ingress 5. After flood receded, the valves are opened again automatically 3. Research Method Each of the submersible equipment and accessory are placed in a specially designed water tank for the purpose of testing. The cables from the high voltage sources are inserted into the tank through designated cable entry holes which are then closed off by using the cable entry seal as shown in Figure 4. The test-setup for the submersible equipment and accessories
  • 5.  ISSN: 1693-6930 TELKOMNIKA Vol. 15, No. 4, December 2017 : 1540 – 1546 1544 during the test is shown in Figure 5. Table 3 shows each phase for the submersible substation testing with the tests performed during each phase. Figure 6(a) and 6(b) show the condition of the submersible equipment and accessories during and after the wet test. Figure 4. Use of seal for the cable entry hole Figure 5. Test set-up for the submersible equipment and accessories in a substation configuration Table 3. The phases during the testing method for the submersible equipment connected in a substation configuration as per actual flood condition. Phase Tests Performed Pre-testing for submersible equipment 1. Functional test for switchgear 2. Dielectric withstand test for switchgear 3. Insulation resistance (IR) test for transformer and switchgear 4. Test on secondary circuits 5. Contact resistance (CR) for switchgear Dry test (240V supply – single phase) 6. Check relay output 7. Check supply output from feeder pillar Dry test (6.5kV supply – single phase) 8. Check outgoing voltage at feeder pillar 9. Remote tripping test Wet test (Circuit not energized) 10. Fill the tank with water at various levels (0.5m, 1m, 1.5m, 2m) 11. IR test at various levels 12. Current leakage tests throughout the wet test Wet test (Circuit energized at 6.5kV supply single phase for 48 hours) 13. Current leakage tests throughout the wet test 14. Switchgear remote tripping test after 48 hours Post-testing for submersible equipment 15. Visual inspection of all equipment and accessories 16. Functional test for switchgear 17. Dielectric withstand test for switchgear 18. Insulation resistance (IR) test for transformer and switchgear 19. Contact resistance (CR) for switchgear
  • 6. TELKOMNIKA ISSN: 1693-6930  Design and Evaluation of Submersible 11/0.415kV Distribution Substation .... (M. D. M. Amir) 1545 (a) (b) Figure 6. (a) Submersible test at 2 metre water level (b) Conditions of the submersible substation after water level receded. Note that the both sets of 11kV and 415V cable termination installed on the transformer are still in good condition 4. Results and Analysis Table 4 summarises the results of the performance of the submersible equipment and accessories during the submersible test. The main pass criterion is that each of the equipment is able to continuously operate in ON condition while the circuit is energized at 6.5kV for 48 hours without tripping the main circuit. Table 4. Results of the Performance of the Submersible Equipment using the Testing Method for the Submersible Equipment Connected in a Substation Configuration as per Actual Flood Condition Equipment / Accessories Pass Criteria Results 11kV solid insulated switchgear Pass the wet test at 6.5kV for 48 hours Able to trip during the flood Pass IR test before & after the wet test. Passed 11/0.415kV custom-made transformer Pass the wet test at 6.5kV for 48 hours. Pass IR test before & after the wet test. Passed 415V custom-made feeder pillar Pass the wet test at 6.5kV for 48 hours. Pass IR test before & after the wet test. Partially Passed (Water droplets were observed inside the feeder pillar after the wet test) 11kV submersible cable termination Pass the wet test at 6.5kV for 48 hours. Pass IR test before & after the wet test. Passed 415V submersible cable termination Pass the wet test at 6.5kV for 48 hours. Passed Seals for cable entry No leaks during the wet test. Passed All the equipment could continuously operate in ON condition during the wet test. The submersible transformer, cable termination and seals for cable entry performed as per design criteria and can be reused immediately after flood with only requiring minor external cleaning. It proved to be robust enough to withstand the flood while resuming operation as usual afterwards. For the submersible feeder pillar, a little amount of water droplets was observed in the feeder pillar after the submersible testing. Investigations determined that the root cause is due to water seeping through the valve. This was caused by the weakness in the ball valve design. Despite that, the main circuit was not tripped throughout the wet test indicating that the feeder pillar was still able to continuously operate in ON condition.
  • 7.  ISSN: 1693-6930 TELKOMNIKA Vol. 15, No. 4, December 2017 : 1540 – 1546 1546 Even though the submersible switchgear could pass the test, several components need to be replaced after the wet test. These components, which include the motor, trip and close coil as well as the operation counter, are not situated inside the IP67 solid insulated tank, but rather within the IP4X panel. This means that after flooding, maintenance will need to be performed prior to restoring the switchgear to full service. This has the implication of extra expenditure for the utility due to maintenance works and component replacement costs. 5. Conclusion The design criteria for the selection of submersible equipment and accessories to be used in a submersible substation have been developed based on the prevailing TNB standard operating procedure during flood conditions. The equipment and accessories were then selected partly based on commercially available products in the market and partly developed in collaboration with local manufacturers. The test method for the submersible equipment connected in a substation configuration as per flood condition has been developed. The test method is separated into 6 different phases designed to test the performance of the submersible equipment in different conditions. The facilities for the submersible substation test were constructed and can be used for testing of other types of electrical equipment under submerged conditions. All the equipment could continuously operate in ON condition during the wet test. The submersible transformer, cable termination and seals for cable entry performed as per design criteria and can be reused immediately after flood with only requiring minor external cleaning. The submersible switchgear requires maintenance works and component replacement after flood events. It is recommended for the manufacturer to improve the design and durability of the components to minimize the replacement works. Water droplets were found in the feeder pillar caused by the weakness in the ball valve design. The corrective measure will be to redesign and retest the feeder pillar. A potential improvement is by replacing the ball valve using a latching solenoid valve. By doing so, the solenoid valve will be useful to prevent water seeping through due to its better mechanical design capability. In summary, the use of submersible equipment and accessories is technically feasible as a mitigation method for flood conditions. However, several design improvements need to be made in the evaluated submersible switchgear and feeder pillar before being implemented in the field. References [1] Boggess JM, Becker GW, Mitchell MK. Storm & flood hardening of electrical substations. IEEE PES T&D Conference and Exposition. Chicago. 2014: 1 - 5. [2] Baker JW. Eliminating hurricane-induced storm surge damage to electric utilities via in-place elevation of substation structures and equipment. IEEE PES T&D Conference and Exposition. Chicago. 2014: 1 - 5. [3] Matos SM, Joao PC. Flood Adaptation Measures Applicable in the Design of Urban Public Spaces: Proposal for a Conceptual Framework. Water. 2016; 8(7): 284. [4] Dunk M. Substation Flood Protection: Engineering Design Standard. UK Power Networks. EDS 07- 0106. 2016. [5] IEEE Standards Association. C57.12.24-2016, IEEE Standard for Submersible, Three-Phase Transformers, 3750kVA and Smaller: High Voltage, 34 500 GRDY/19 920 Volts and Below; Low Voltage, 600 Volts and Below. IEEE Press. 2016. [6] International Electrotechnical Commission. 62271-111:2012, High Voltage Switchgear and Controlgear – Part 111: Automatic Circuit Reclosers and Fault Interrupters for Alternating Current Systems up to 38kV. IEC. 2012. [7] A Stronger, More Resilient New York. New York: City of New York. 2013: 107 – 129.