W
hen the West Palm Beach Water
Treatment Plant (WTP) was built by
industrialist Henry Flagler in 1894,
the facility used an average of four cords of
wood per day to pump 1.5 mil gal of water per
day (mgd) to Palm Beach and surrounding
areas. Although the steam-driven pumps are
long gone and the capacity of the facility has
grown to 47 mgd, the founder of the Florida
East Coast Railroad and Palm Beach would be
proud to see his water WTP modernized with
21st-century technology.
The City of West Palm Beach’s Public Util-
ities Department has ongoing major capital im-
provement projects at its WTP that will
improve the reliability,safety,and security of its
public water supply. The source of the surface
water for the facility is a 20-sq-mi wetland
catchment area known as the Grassy Waters
Preserve, making the City one of the few utili-
ties in the state of Florida to not use groundwa-
ter. This surface water is conveyed by a canal
and two shallow lakes before ultimately reach-
ing the WTP intakes in East Clear Lake.As with
all surface water treatment facilities, rainfall,
stormwater management,and other factors can
provide fluctuations in raw water quality and
quantity that have provided challenges to the
water treatment process.
TheWest Palm BeachWTP is located in the
downtown corridor of a major metropolitan
area,surrounded by residential homes,high-rise
buildings, and businesses. In 2007, a series of
bacteriological hits in the distribution system led
to two boil-water notifications.Investigations by
public utilities department staff,regulators,con-
tract utility operators, and consulting engineers
led to the discovery of an improperly sealed in-
terconnect not shown on the as-built drawings,
City of West Palm Beach Makes Priority
Improvements to Aging Water Treatment Plant
Gerardus Schers, Becky Hachenburg, Heath Wintz, Brian LaMay,
Don Lythberg, Sam Heady, and Poonam Kalkat
Gerardus Schers is national water practice
lead, Becky Hachenburg is senior client
service lead, Heath Wintz is senior
engineer, and Don Lythberg is construction
manager with MWH in West Palm Beach.
Brian LaMay is supervising engineer with
MWH in Sunrise. Sam Heady is assistant
utility director and Poonam Kalkat is water
treatment plant manager with City of West
Palm Beach.
F W R J
Figure 1.West High Service Pump Station,
Constructed 1926. Photo of Current
Building Overlaid With Original Design. Continued on page 8
6 December 2013 • Florida Water Resources Journal
which allowed filtered, chlorinated water to by-
pass the storage tanks without providing the
contact time necessary for bacteriological and
virus kill prior to distribution. Triage for the
100-year-oldWTP involved the separation of fil-
ter backwash and side thickener supernatant re-
turn flows from the main treatment process,
isolation of the interconnect to restore disinfec-
tion contact time, and replacement of inopera-
ble valves and mechanical systems.
The City selected MWH,a global wet infra-
structure engineering,consulting,and construc-
tion firm, to perform condition assessments,
evaluations of alternative processes, bench- and
pilot-scale process investigations,and design ac-
tivities for theWTP improvements. In 2009,the
City initiated several priority projects,identified,
in part, by the condition assessment, that have
been completed or are still under construction:
Disinfection with liquid chemicals
Safe access driveway to maneuver onto and
off the WTP property
Reliable electrical/generator building
Dosing, mixing, and metering of finished
water chemicals
Automation of the treatment process
High-service pumps rehabilitation
`These projects are spread across the WTP
site,as illustrated in the graphic,requiring close
coordination with the City’s operations staff.
The combined construction value of all prior-
ity projects, which includes the projects high-
lighted in this article, is around $54 million.
As part of the priority projects,MWH pro-
vided hands-on training to the City’s operations
staff, with the goal to improve the understand-
ing of the treatment process. Training sessions
included concentration x contact time (CT)
calculations for disinfection, jar testing for co-
agulation, and turbidity trending and reporting
for media filtration. The training sessions re-
sulted in a step change of the WTP operations,
and this in itself provided a significant im-
provement to the water treatment process.
Disinfection With Liquid
Chemicals Improves Safety By
Eliminating Hazardous Gasses
Prior to 2009,all disinfection chemical feed
systems at the facility were operated manually.
Gaseous chlorine and ammonia dosing were
controlled by adjusting rotameters manually any
time the process flow was changed. Conversion
of gaseous chlorine to liquid sodium hypochlo-
rite eliminated the need to store nearly 40 1-ton
cylinders and 15 120-lb cylinders.Likewise,con-
version of anhydrous ammonia to aqueous am-
monia for chloramine disinfection eliminated
the risk of a poisonous gas leak within the city.
Installation of variable fre-
quency drives (VFD) con-
trolled metering pumps for
the liquid chlorine and am-
monia systems, and remote
monitoring of residual-free
and combined chlorine al-
lowed for remote operation
and control of the dosing
pumps as the supervisory
control and data acquisition
(SCADA) system developed.
During the design of the
sodium hypochlorite system,
the need for close coordination among proj-
ect teams became apparent. In an effort to pro-
vide operational flexibility, an existing
underground ammonia pipeline and injection
point was modified to add an additional chlo-
rine injector. A leak from an incorrectly in-
stalled chlorine pipe allowed a stream of
chlorine solution to spray and attack the stain-
less steel ammonia pipeline. The chemical and
material incompatibility led to a gaseous am-
monia leak in a confined space under the
WTP’s primary entrance/exit driveway, result-
ing in an evacuation from that area and a tem-
porary blockage of traffic using the driveway.
This situation not only brought to light the
need for an intrinsically safe chemical injec-
tion point and centralized residual monitor-
ing, but also the need to reduce vehicular
traffic near critical WTP assets.
New Access Driveway Provides
Safe Maneuvering Onto
and Off the WTP Property
The vulnerability assessment confirmed
the primary entrance to the West Palm Beach
WTP as a risk for the City, given its proximity
to critical assets.All vehicular traffic for the fa-
cility was required to navigate through the old-
est part of the facility, which contained
transfer and high-service pumping, finished
water chemical dosing, emergency power gen-
eration, and electrical switchgear. Addition-
ally, access from Banyan Boulevard was unsafe
without the presence of proper turn lanes for
maneuvering on and off the WTP property.
To reduce the risk presented by this en-
trance, a new plant-access driveway was con-
structed along the north side of the property
fromAustralianAvenue—a larger thoroughfare.
This new access driveway included a dedicated
turn lane,security guard checkpoint,video sur-
veillance, and card-swipe-access control for the
City staff. Chemical deliveries,sludge transport,
Figure 2. West Palm Beach WTP Site Plan with Priority
Projects Highlighted. Figure 3. Safe Access Driveway from Australian Avenue.
Continued on page 10
Continued from page 6
8 December 2013 • Florida Water Resources Journal
10 December 2013 • Florida Water Resources Journal
and traffic from ongoing construction are now
safely separated from the critical assets.
Water Treatment Plant Reliability
Improved With New
Electrical/Generator Building
Following Hurricanes Frances and Jeanne
in 2004, the standby generators of the West
Palm Beach WTP failed. A natural sense of ur-
gency prompted the City to purchase two 2,000
kW remanufactured generators to provide gen-
erator power to the WTP. The new generators
proved too large for the building, prompting
the removal of the roof and façade and creating
other challenges, such as a fan-driven rainwa-
ter short in the NEMA1 electrical equipment,
failure of the automatic transfer switch, failure
of a generator stator,and noise complaints from
nearby residential neighbors.
Additionally, the switchgear for the WTP
was constructed in 1985 as part of a new build-
ing that also housed the transfer and high-ser-
vice pumps. During a loss of utility power, and
subsequently a failure of the generators, the
transfer pump clearwell overflowed within just
15 min and flooded the building,threatening the
adjacent electrical switchgear on the first floor.
To address these issues, MWH designed a
new electrical/generator building and a dedi-
cated “express” electrical feed from the Evernia
Street substation located on the WTP site. The
new generator building includes three 2,500 kW
generators, an air intake rain knockdown
plenum,sound damping exhaust plenum,and a
new Florida Power and Light transformer vault,
as well as 4160V primary and generator
switchgear. The express electrical feed, aug-
mentedwithtwoadditionalutilityfeedsfromthe
Evernia and West Palm Beach substations, pro-
vides power to the double-ended switchboards
and subsequently to all equipment, with an op-
tion to seamlessly transfer between utility and
on-site generated power. This transfer feature is
of critical importance during the wet season, al-
lowing seamless transitioning between preferred
power sources. Proactive management between
sourceshelpstonavigatethroughbrownoutsand
blackouts and avoids interruptions to the treat-
ment process and
high-service pump-
ing. This project also
eliminates or re-
placesmany obsolete
loop switches,motor
control centers, and
electrical distribu-
tion panel boards.
Historically, con-
stant speed motors
have shut down at
the WTP upon util-
ity power failure. As
part of the improvements to the facility,a num-
ber of VFDs have been added and programmed
for power loss “ride-through” by using the ca-
pacitors in the direct current bus of the drives.
The primary function of these capacitors is to
filter the voltage and provide a stable direct cur-
rent source for the inverter section of the drive.
However,throughVFD programming,these ca-
pacitors can discharge over a three-second
switchover to standby power,avoiding a process
interruption or a pressure loss in the distribu-
tion system during brownouts and short black-
outs. These VFDs provide the added benefit of
reducing current in-rush to the motors in order
to“peak-shave”electrical demands of the facil-
ity, reducing electricty costs.
Construction of the generator building at
the heart of an aged facility has not been with-
out challenges.During construction,unreliable
record drawings of underground utilities and
inoperable isolation valves complicated the re-
location of a 42-in.finished water line.To facil-
itate the relocation, 42-in. and 24-in. line stops
were installed to bypass this section of the
pipeline, which was nearly 15 ft deep and lo-
cated only 25 ft away from a railway. The proj-
ect team members, including MWH, ensured
that adequate shoring and thrust restraint was
provided for this hot tap. The work was done
successfully and this section of pipe was by-
passed, while protecting the arterial line sup-
plying potable water to the downtown area.
Dosing, Mixing, and Metering
of Finished Water Chemicals
Stabilizes Finished Water Quality
Initial investigations in 2008 revealed that
the mixing of disinfection chemicals was insuf-
Figure 5.42-in. Line Stop to Bypass In-Service Water Main
Supplying.
Figure 4B. View on Double-Ended Main and Generator
Switchgear.
Figure 4A. New Electrical/Generator Building Increases
Reliability of WTP Service.
Continued from page 8
Florida Water Resources Journal • December 2013 11
ficient. Chlorine and ammonia were being in-
jected into a 60-in. gravity, prestressed cylindri-
cal concrete pipe (PCCP) immediately upstream
of the transfer pump clearwell.Although trans-
fer pump impellers provided the mixing energy
downstream, quiescent plug flow through the
125,000-gal clearwell did not provide the favor-
able conditions necessary for immediate and
complete monochloramine formation.
During the construction of the sodium
hypochlorite system, a chemical piping trench
was added to accommodate all finished water
chemical pipelines from the dosing pumps to a
new central dosing point. Prior to the construc-
tion of this piping trench,finished water chemi-
calfeedlineswerespreadovermultiplecorridors
to multiple injection points across the property.
These finished water chemicals included sodium
hypochlorite, ammonium hydroxide, sodium
hydroxide, ortho/polyphosphate blend, and hy-
drofluosilicic acid.
The existing chemical injection points re-
lied on turbulence from fittings and pipe
bends, which provided incomplete mixing and
reaction. Furthermore, finished water chemi-
cals were dosed based on an aggregate flow
from 26 individual filter effluent flow meters.
With an inaccuracy of +/- 0.5 percent each, the
total inaccuracy of the finished water flow sig-
nal could be as high as +/- 13 percent. To alle-
viate these issues, the City constructed an
above-grade 48-in. in-line static mixer and a
centralized venturi flow meter between the
transfer pump station and the ground storage
tanks. Since the system only has enough stor-
age to be off line for 8 hours, the design in-
cluded a 20 mgd temporary bypass system
from the transfer pump clearwell to the
ground storage tanks to enable the WTP to re-
main in service during the construction tie-
ins.
The centralized flow meter provides a sig-
nal by which all finished water chemicals are
flow-paced with greater accuracy and reliabil-
ity. A major improvement to the process and to
finished water quality has been the addition of
the mixing and metering header, and the au-
tomation of the finished water chemical dosing
and controls.
Automated and Remotely
Monitored Treatment Process
in Real Time
The WTP was operated manually from
1894 until the early 1990s, when a slow transi-
tion was made from manual to automatic oper-
ation. The improvements that were made
included analog instrumentation and local con-
trolpanels.Processmonitoringoveranalogcom-
munications was transcribed by circular chart
recorders for operations and compliance report-
ing. In 1996, a complete plant upgrade was un-
dertaken, including the addition of Siemens S5
programmablelogiccontrollers(PLCs). Newin-
struments and sensors were provided, while au-
tomatic control was achieved through actuation
of valves throughout theWTP.Critical functions
andcontrolswerenetworkedviafiberopticcable
to the control room.In 2007,the filters were up-
graded with new Siemens S7 PLCs and the com-
municationnetworkof theRotork actuatorswas
replaced to Profibus. In 2008, a radio telemetry
networkwasinstalledtomonitorandcontrolthe
remote booster pump stations and PLC hard-
ware consisting of Allen Bradley CompactLogix
and ControLogix.
The development of the control system
over this 20-year period spanned generations
of SCADA technology evolution. Process
monitoring and control systems of the WTP
were stitched together as a patchwork quilt to
meet the immediate needs of various projects
without a unified framework. Operators in-
terfaced process equipment through the
Human Machine Interface (HMI) software,
which differed greatly among the systems con-
trolled. These inconsistencies in the software
Figure 6. Mixing and Metering Header.
Figure 7. Triple-Ringed Fiber Optic Control Network Architecture.
Continued on page 12
12 December 2013 • Florida Water Resources Journal
and interface increased the potential risk of
operator error.
To address these inconsistency issues, the
control system was redesigned from the ground
up. Efforts were made to standardize operation
of devices via universally accepted communica-
tion protocols; these included Modbus, De-
viceNet, Profibus and TCP/IP. Implementation
of the new system was achieved with a phased
approach: 1) fiber optic network construction,
2) PLC and remote rack installation, and 3)
process software refinement.Following the con-
struction of a triple-ringed fiber optic control
network around the facility in 2009,the SCADA
network was developed using twin 48-strand,
62.5 micron multimode fiber. Three PLCs op-
erate separate control rings, which in turn op-
erate a total of 22 local interface units (LIU) for
a distributive control system, as illustrated in
the network architecture graphic. These LIUs
include fiber-to-ethernet converters to com-
municate to the remote PLC racks. The remote
PLC racks communicate via hard wiring to the
remote devices (i.e., pressure transmitters, flow
switches,residual monitors,and turbidimeters).
Five remotely located Thin Client touchscreens
provide consistent and coherent graphic oper-
ator interfaces using Wonderware software for
monitoring and control.
The City continues to make improvements
to the control network. In 2013, MWH helped
the City with equipment updates and adjust-
ments to Profibus communications of the
media filters.
The City faced serious challenges in the
transitioning from existing to new SCADA,and
could only allow for very limited facility shut-
downs to facilitate system changeovers.The key
was to avoid blind spots in the system and run
parallel programming simultaneously in the old
and new systems to satisfy the health depart-
ment’s requirement of continuous monitoring.
Each input/output (I/O) had to be moved one-
by-one and verified before proceeding to the
next. Naturally, the hardest part of the
switchover comes when it’s time to decommis-
sion and remove the fiber to the old remote ter-
minal units (RTU). Therefore, old RTU
obsolescence was verified by powering down
the cabinets and confirming that no signals
were lost and no unknown or undocumented
junctions were overlooked.
As a result of the methodical improve-
ments to the controls, the manual operation
of flow control valves and chemical dosing
pumps is now history, and the delayed process
performance monitoring and control by peri-
odic sampling and laboratory analysis is min-
imized. The process is now remotely
monitored and controlled in real time with
minimal manual intervention.
High-Service Pump Rehabilitation
The seven existing high-service pumps
range in age from 17 to 60 years. The pumps
were evaluated to identify opportunities to in-
crease capacity and reduce power consumption,
either through operational improvements or
equipment modifications. A condition assess-
ment was conducted by MWH to document
physical deficiencies of the existing pumps.
The condition assessment indicated the
pumps were, generally, in good to fair condi-
tion, with a need for typical rehabilitation of
pumps this age, including replacement of seals,
wear rings, couplings, O-rings, nuts and bolts,
coatings and exterior paint.Additionally,MWH
compared the current performance of the
pumps with the manufacturer pump curves to
identify areas for improvement.This evaluation
identified the potential to increase the capacity
of three high-service pumps with minor mod-
ifications to the existing impellers as follows:
High-Service Pump 3 – The current impeller
only draws 235 horsepower (hp) from the
existing 300 hp motor. Additionally, the
pump curve is “flat” and the operating head
is much lower than the other pumps.This re-
sults in reduced output when the other
pumps are in operation, making the pump
least useful when it is most likely needed.In-
stalling a larger-diameter impeller to take ad-
vantage of the existing 300 hp motor
increases the operating head, thereby in-
creasing the capacity of the pump.
High-Service Pumps 6 and 7 – The pumps
operate near the shutoff head and draw less
than their rated capacity when the distribu-
tion system pressure is high.Installing larger-
diameter impellers takes advantage of the
existing motors to increase capacity with
minimal capital cost.
Through detailed assessment and evalua-
tion, the City was able to achieve cost savings
by rehabilitating existing pumps, rather than
purchasing new pumps, and increasing pump
capacity by modifying,with minimal capital in-
vestment, the existing pumps to take advantage
of existing motors and electrical supply.
The Result: Finished
Water Quality Improvements
In time, the improvement of the facility
operations and finished water quality was bro-
ken down into four phases: operational im-
provements via staff augmentation and
training (completed in mid-2008), filter im-
provements (completed in mid-2009), new
mixing and metering header (completed in
November 2011), and a new SCADA system
(completed in February 2012).
Whereas previously, total chlorine, pH,
color,and turbidity would fluctuate quite dras-
tically, the finished water quality has become
Figure 9. High-Service Pump No. 7.
Above: Figure 8A. Old Remote Terminal
Unit (RTU). At right: Figure 8B. New Local
Interface Unit (LIU).
Continued from page 11
Florida Water Resources Journal • December 2013 13
more stable,evident in the trends and variances
of the daily data obtained from monthly oper-
ating reports and the SCADA system. The
graphs for total chlorine and pH, particularly,
show the narrower band in which total chlorine
and pH are controlled in the finished water. For
instance, the variance of the finished water pH
dropped from 0.10 to 0.04 when operations
were augmented by contract staff trained in
mid-2008, with a further reduction to 0.01
when the mixing and metering header and
SCADA system were completed in early 2012.
The graph for finished water turbidity shows a
consistent downward trend since the first im-
provements were made in mid-2008. Opera-
tions augmentation and training helped reduce
average turbidity levels from 0.21 to 0.11 neph-
elometric turbidity unit (NTU), but another
step-change improvement to a turbidity of 0.10
NTU was made with the completion of the
SCADA system in early 2012.The graph for fin-
ished water color, on the other hand, shows the
step-change improvement in mid-2008 when
operations instigated the more frequent sam-
pling regime (every 4 hours) on the settled
water to ensure the ferric sulfate and lime dos-
ing and pH conditions were always kept opti-
mum for maximum organics and color removal
in the sedimentation basins. The average color
levels dropped from 7.6 to 3.3 PCU when this
operational change was made.
Summary
Through new controls hardware and soft-
ware, the West Palm Beach WTP is more reli-
able and produces more consistent finished
water quality with minimal manual interven-
tion. Hazardous, gaseous chlorine and ammo-
nia have been replaced with liquids, and a new
safe access driveway provides safer ingress and
egress.Obsolete chemical systems have been au-
tomated and replaced with state-of-the-art
equipment.A new electrical/generator building
with an express power feed is under construc-
tion with double-ended switchgear and standby
generators providing reliably power to all
equipment, with an option to seamlessly trans-
fer between utility and generator power.
With the right infrastructure and im-
proved operator attention,significant improve-
ments have been made to the water treatment
process evidenced by improved finished water
quality and operational reliability.
Acknowledgements
Thanks from MWH go to the City of West
Palm Beach for its support and to acknowledge
thefollowingteammemberswhocontributedto
the improvements at theWTP:Jacobs Engineer-
ing and subconsultants GlobalTech,Song+Asso-
ciates, and Integration Systems Incorporated.
Figure 10A. Total Chlorine (Free + Combined) Figure 10B. Finished Water pH
Figure 10C. Finished Water Turbidity Figure 10D. Finished Water Color
Data sets were cleaned up for outliers, anomalies, and readings below detectable limit (BDL).
Turbidity data recorded as < 0.1 is depicted as 0.1. Color data recorded as < 3 is depicted as 3.0.

More Related Content

What's hot

15.PROJECT REPORT - UWSSRP1 - MASVINGO final draft
15.PROJECT REPORT - UWSSRP1 - MASVINGO final draft15.PROJECT REPORT - UWSSRP1 - MASVINGO final draft
15.PROJECT REPORT - UWSSRP1 - MASVINGO final draftLloyd Farai Fende
 
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...Toronto Public Consultation Unit
 
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...Ekonnect
 
Storm Water manual
Storm Water manualStorm Water manual
Storm Water manualgscplanning
 
Master Plan Project Report on Remodeling of Storm Water Drains_BBMP
Master Plan Project Report on Remodeling of Storm Water Drains_BBMP Master Plan Project Report on Remodeling of Storm Water Drains_BBMP
Master Plan Project Report on Remodeling of Storm Water Drains_BBMP Ekonnect
 
Cameron Run Tributary At La Vista Drive: Stream Restoration
Cameron Run Tributary At La Vista Drive: Stream RestorationCameron Run Tributary At La Vista Drive: Stream Restoration
Cameron Run Tributary At La Vista Drive: Stream RestorationFairfax County
 
1.principle of o&amp;m
1.principle of o&amp;m1.principle of o&amp;m
1.principle of o&amp;mMadhabKoirala
 
Rehabilitation of Three Equalization Basins and Ancillary Facilities
Rehabilitation of Three Equalization Basins and Ancillary Facilities Rehabilitation of Three Equalization Basins and Ancillary Facilities
Rehabilitation of Three Equalization Basins and Ancillary Facilities Fairfax County
 
Integrated Sewer Metering Project 1
Integrated Sewer Metering Project 1Integrated Sewer Metering Project 1
Integrated Sewer Metering Project 1Fairfax County
 
Preliminary_Design_Report_Upper_Fintry_Valley_of_the_Sun___TRUE_2010.pdf
Preliminary_Design_Report_Upper_Fintry_Valley_of_the_Sun___TRUE_2010.pdfPreliminary_Design_Report_Upper_Fintry_Valley_of_the_Sun___TRUE_2010.pdf
Preliminary_Design_Report_Upper_Fintry_Valley_of_the_Sun___TRUE_2010.pdfBappy114
 

What's hot (20)

15.PROJECT REPORT - UWSSRP1 - MASVINGO final draft
15.PROJECT REPORT - UWSSRP1 - MASVINGO final draft15.PROJECT REPORT - UWSSRP1 - MASVINGO final draft
15.PROJECT REPORT - UWSSRP1 - MASVINGO final draft
 
BF Area 35 PIC 1 Boards_final
BF Area 35 PIC 1 Boards_finalBF Area 35 PIC 1 Boards_final
BF Area 35 PIC 1 Boards_final
 
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
Basement Flooding Remediation and Water Quality Improvement Master Plan Class...
 
City of Toronto Basement Flooding Area 37 Display Boards
City of Toronto Basement Flooding Area 37 Display Boards City of Toronto Basement Flooding Area 37 Display Boards
City of Toronto Basement Flooding Area 37 Display Boards
 
Area 38 pic 1 final presentation
Area 38 pic 1   final presentationArea 38 pic 1   final presentation
Area 38 pic 1 final presentation
 
ASCE OC - EWRI: OCWD Mid-Basin Injection: Centennial Park Project
ASCE OC - EWRI: OCWD Mid-Basin Injection: Centennial Park ProjectASCE OC - EWRI: OCWD Mid-Basin Injection: Centennial Park Project
ASCE OC - EWRI: OCWD Mid-Basin Injection: Centennial Park Project
 
Area36 final pic1 boards
Area36 final pic1 boardsArea36 final pic1 boards
Area36 final pic1 boards
 
Planning of irrigation system
Planning of irrigation systemPlanning of irrigation system
Planning of irrigation system
 
Checkdam
CheckdamCheckdam
Checkdam
 
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
 
Area 21 & 23 Pic1 display panels
Area 21 & 23 Pic1 display panelsArea 21 & 23 Pic1 display panels
Area 21 & 23 Pic1 display panels
 
Storm Water manual
Storm Water manualStorm Water manual
Storm Water manual
 
Master Plan Project Report on Remodeling of Storm Water Drains_BBMP
Master Plan Project Report on Remodeling of Storm Water Drains_BBMP Master Plan Project Report on Remodeling of Storm Water Drains_BBMP
Master Plan Project Report on Remodeling of Storm Water Drains_BBMP
 
Areas2123 pic2boards
Areas2123 pic2boardsAreas2123 pic2boards
Areas2123 pic2boards
 
Mining Operations Optimize Dewatering Processes
Mining Operations Optimize Dewatering ProcessesMining Operations Optimize Dewatering Processes
Mining Operations Optimize Dewatering Processes
 
Cameron Run Tributary At La Vista Drive: Stream Restoration
Cameron Run Tributary At La Vista Drive: Stream RestorationCameron Run Tributary At La Vista Drive: Stream Restoration
Cameron Run Tributary At La Vista Drive: Stream Restoration
 
1.principle of o&amp;m
1.principle of o&amp;m1.principle of o&amp;m
1.principle of o&amp;m
 
Rehabilitation of Three Equalization Basins and Ancillary Facilities
Rehabilitation of Three Equalization Basins and Ancillary Facilities Rehabilitation of Three Equalization Basins and Ancillary Facilities
Rehabilitation of Three Equalization Basins and Ancillary Facilities
 
Integrated Sewer Metering Project 1
Integrated Sewer Metering Project 1Integrated Sewer Metering Project 1
Integrated Sewer Metering Project 1
 
Preliminary_Design_Report_Upper_Fintry_Valley_of_the_Sun___TRUE_2010.pdf
Preliminary_Design_Report_Upper_Fintry_Valley_of_the_Sun___TRUE_2010.pdfPreliminary_Design_Report_Upper_Fintry_Valley_of_the_Sun___TRUE_2010.pdf
Preliminary_Design_Report_Upper_Fintry_Valley_of_the_Sun___TRUE_2010.pdf
 

Similar to 2013 FWRJ December WPB

NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012Mike Vernon
 
Climax Nomination for 2014 Hardrock Mining Reclamation Awards
Climax Nomination for 2014 Hardrock Mining Reclamation AwardsClimax Nomination for 2014 Hardrock Mining Reclamation Awards
Climax Nomination for 2014 Hardrock Mining Reclamation AwardsKathy Remias
 
Cowlitz falls paper naes power contractors lewis county pud-final
Cowlitz falls paper   naes power contractors lewis county pud-finalCowlitz falls paper   naes power contractors lewis county pud-final
Cowlitz falls paper naes power contractors lewis county pud-finalNAES Corporation
 
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014Joseph Merzlak
 
PIA Magazine May - June 2014 (lift-out)
PIA Magazine May - June 2014 (lift-out)PIA Magazine May - June 2014 (lift-out)
PIA Magazine May - June 2014 (lift-out)Matt Kirkbride
 
Construction Dewatering PowerPoint
Construction Dewatering PowerPointConstruction Dewatering PowerPoint
Construction Dewatering PowerPointTerry Aylward
 
Island Water Treatment Plant Capacity Expansion - Project File Report
Island Water Treatment Plant Capacity Expansion - Project File ReportIsland Water Treatment Plant Capacity Expansion - Project File Report
Island Water Treatment Plant Capacity Expansion - Project File ReportToronto Public Consultation Unit
 
1 How to Overcome Public Perception Issues on Potable R.docx
1  How to Overcome Public Perception Issues on Potable R.docx1  How to Overcome Public Perception Issues on Potable R.docx
1 How to Overcome Public Perception Issues on Potable R.docxpoulterbarbara
 
1 How to Overcome Public Perception Issues on Potable R.docx
1  How to Overcome Public Perception Issues on Potable R.docx1  How to Overcome Public Perception Issues on Potable R.docx
1 How to Overcome Public Perception Issues on Potable R.docxjeremylockett77
 
Stormwater Management Information Sharing with Shandong Province, China
Stormwater Management Information Sharing with Shandong Province, ChinaStormwater Management Information Sharing with Shandong Province, China
Stormwater Management Information Sharing with Shandong Province, ChinaFairfax County
 
WET Feature 4 - Building bigger and better - Jan_16
WET Feature 4 - Building bigger and better - Jan_16WET Feature 4 - Building bigger and better - Jan_16
WET Feature 4 - Building bigger and better - Jan_16Tim Bail
 
FSAWWA Paper and Presentation Integrated master planning WPB 12012015
FSAWWA Paper and Presentation Integrated master planning WPB 12012015FSAWWA Paper and Presentation Integrated master planning WPB 12012015
FSAWWA Paper and Presentation Integrated master planning WPB 12012015GJ Schers
 
Woodrock retrofit 11-13-14
Woodrock retrofit 11-13-14Woodrock retrofit 11-13-14
Woodrock retrofit 11-13-14MCDEP
 
Feb 11 2014 public meeting show
Feb 11 2014 public meeting showFeb 11 2014 public meeting show
Feb 11 2014 public meeting showMCDEP
 
Nottoway Park Stormwater and Water Quality Improvements Phases 1, 2, & 3
Nottoway Park Stormwater and Water Quality Improvements Phases 1, 2, & 3Nottoway Park Stormwater and Water Quality Improvements Phases 1, 2, & 3
Nottoway Park Stormwater and Water Quality Improvements Phases 1, 2, & 3Fairfax County
 

Similar to 2013 FWRJ December WPB (20)

NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012
 
Climax Nomination for 2014 Hardrock Mining Reclamation Awards
Climax Nomination for 2014 Hardrock Mining Reclamation AwardsClimax Nomination for 2014 Hardrock Mining Reclamation Awards
Climax Nomination for 2014 Hardrock Mining Reclamation Awards
 
Donnie Belloit_Reume
Donnie Belloit_ReumeDonnie Belloit_Reume
Donnie Belloit_Reume
 
Wetlands and Stormwater Management
Wetlands and Stormwater ManagementWetlands and Stormwater Management
Wetlands and Stormwater Management
 
Cowlitz falls paper naes power contractors lewis county pud-final
Cowlitz falls paper   naes power contractors lewis county pud-finalCowlitz falls paper   naes power contractors lewis county pud-final
Cowlitz falls paper naes power contractors lewis county pud-final
 
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014
Presentation-Orange-County-Great-Park-Storm-Water-Reuse-Pond-System-June-2014
 
PIA Magazine May - June 2014 (lift-out)
PIA Magazine May - June 2014 (lift-out)PIA Magazine May - June 2014 (lift-out)
PIA Magazine May - June 2014 (lift-out)
 
Construction Dewatering PowerPoint
Construction Dewatering PowerPointConstruction Dewatering PowerPoint
Construction Dewatering PowerPoint
 
Island Water Treatment Plant Capacity Expansion - Project File Report
Island Water Treatment Plant Capacity Expansion - Project File ReportIsland Water Treatment Plant Capacity Expansion - Project File Report
Island Water Treatment Plant Capacity Expansion - Project File Report
 
1 How to Overcome Public Perception Issues on Potable R.docx
1  How to Overcome Public Perception Issues on Potable R.docx1  How to Overcome Public Perception Issues on Potable R.docx
1 How to Overcome Public Perception Issues on Potable R.docx
 
1 How to Overcome Public Perception Issues on Potable R.docx
1  How to Overcome Public Perception Issues on Potable R.docx1  How to Overcome Public Perception Issues on Potable R.docx
1 How to Overcome Public Perception Issues on Potable R.docx
 
today
todaytoday
today
 
Stormwater Management Information Sharing with Shandong Province, China
Stormwater Management Information Sharing with Shandong Province, ChinaStormwater Management Information Sharing with Shandong Province, China
Stormwater Management Information Sharing with Shandong Province, China
 
WET Feature 4 - Building bigger and better - Jan_16
WET Feature 4 - Building bigger and better - Jan_16WET Feature 4 - Building bigger and better - Jan_16
WET Feature 4 - Building bigger and better - Jan_16
 
Jack Oler 1
Jack Oler 1Jack Oler 1
Jack Oler 1
 
Hydropower
HydropowerHydropower
Hydropower
 
FSAWWA Paper and Presentation Integrated master planning WPB 12012015
FSAWWA Paper and Presentation Integrated master planning WPB 12012015FSAWWA Paper and Presentation Integrated master planning WPB 12012015
FSAWWA Paper and Presentation Integrated master planning WPB 12012015
 
Woodrock retrofit 11-13-14
Woodrock retrofit 11-13-14Woodrock retrofit 11-13-14
Woodrock retrofit 11-13-14
 
Feb 11 2014 public meeting show
Feb 11 2014 public meeting showFeb 11 2014 public meeting show
Feb 11 2014 public meeting show
 
Nottoway Park Stormwater and Water Quality Improvements Phases 1, 2, & 3
Nottoway Park Stormwater and Water Quality Improvements Phases 1, 2, & 3Nottoway Park Stormwater and Water Quality Improvements Phases 1, 2, & 3
Nottoway Park Stormwater and Water Quality Improvements Phases 1, 2, & 3
 

2013 FWRJ December WPB

  • 1. W hen the West Palm Beach Water Treatment Plant (WTP) was built by industrialist Henry Flagler in 1894, the facility used an average of four cords of wood per day to pump 1.5 mil gal of water per day (mgd) to Palm Beach and surrounding areas. Although the steam-driven pumps are long gone and the capacity of the facility has grown to 47 mgd, the founder of the Florida East Coast Railroad and Palm Beach would be proud to see his water WTP modernized with 21st-century technology. The City of West Palm Beach’s Public Util- ities Department has ongoing major capital im- provement projects at its WTP that will improve the reliability,safety,and security of its public water supply. The source of the surface water for the facility is a 20-sq-mi wetland catchment area known as the Grassy Waters Preserve, making the City one of the few utili- ties in the state of Florida to not use groundwa- ter. This surface water is conveyed by a canal and two shallow lakes before ultimately reach- ing the WTP intakes in East Clear Lake.As with all surface water treatment facilities, rainfall, stormwater management,and other factors can provide fluctuations in raw water quality and quantity that have provided challenges to the water treatment process. TheWest Palm BeachWTP is located in the downtown corridor of a major metropolitan area,surrounded by residential homes,high-rise buildings, and businesses. In 2007, a series of bacteriological hits in the distribution system led to two boil-water notifications.Investigations by public utilities department staff,regulators,con- tract utility operators, and consulting engineers led to the discovery of an improperly sealed in- terconnect not shown on the as-built drawings, City of West Palm Beach Makes Priority Improvements to Aging Water Treatment Plant Gerardus Schers, Becky Hachenburg, Heath Wintz, Brian LaMay, Don Lythberg, Sam Heady, and Poonam Kalkat Gerardus Schers is national water practice lead, Becky Hachenburg is senior client service lead, Heath Wintz is senior engineer, and Don Lythberg is construction manager with MWH in West Palm Beach. Brian LaMay is supervising engineer with MWH in Sunrise. Sam Heady is assistant utility director and Poonam Kalkat is water treatment plant manager with City of West Palm Beach. F W R J Figure 1.West High Service Pump Station, Constructed 1926. Photo of Current Building Overlaid With Original Design. Continued on page 8 6 December 2013 • Florida Water Resources Journal
  • 2. which allowed filtered, chlorinated water to by- pass the storage tanks without providing the contact time necessary for bacteriological and virus kill prior to distribution. Triage for the 100-year-oldWTP involved the separation of fil- ter backwash and side thickener supernatant re- turn flows from the main treatment process, isolation of the interconnect to restore disinfec- tion contact time, and replacement of inopera- ble valves and mechanical systems. The City selected MWH,a global wet infra- structure engineering,consulting,and construc- tion firm, to perform condition assessments, evaluations of alternative processes, bench- and pilot-scale process investigations,and design ac- tivities for theWTP improvements. In 2009,the City initiated several priority projects,identified, in part, by the condition assessment, that have been completed or are still under construction: Disinfection with liquid chemicals Safe access driveway to maneuver onto and off the WTP property Reliable electrical/generator building Dosing, mixing, and metering of finished water chemicals Automation of the treatment process High-service pumps rehabilitation `These projects are spread across the WTP site,as illustrated in the graphic,requiring close coordination with the City’s operations staff. The combined construction value of all prior- ity projects, which includes the projects high- lighted in this article, is around $54 million. As part of the priority projects,MWH pro- vided hands-on training to the City’s operations staff, with the goal to improve the understand- ing of the treatment process. Training sessions included concentration x contact time (CT) calculations for disinfection, jar testing for co- agulation, and turbidity trending and reporting for media filtration. The training sessions re- sulted in a step change of the WTP operations, and this in itself provided a significant im- provement to the water treatment process. Disinfection With Liquid Chemicals Improves Safety By Eliminating Hazardous Gasses Prior to 2009,all disinfection chemical feed systems at the facility were operated manually. Gaseous chlorine and ammonia dosing were controlled by adjusting rotameters manually any time the process flow was changed. Conversion of gaseous chlorine to liquid sodium hypochlo- rite eliminated the need to store nearly 40 1-ton cylinders and 15 120-lb cylinders.Likewise,con- version of anhydrous ammonia to aqueous am- monia for chloramine disinfection eliminated the risk of a poisonous gas leak within the city. Installation of variable fre- quency drives (VFD) con- trolled metering pumps for the liquid chlorine and am- monia systems, and remote monitoring of residual-free and combined chlorine al- lowed for remote operation and control of the dosing pumps as the supervisory control and data acquisition (SCADA) system developed. During the design of the sodium hypochlorite system, the need for close coordination among proj- ect teams became apparent. In an effort to pro- vide operational flexibility, an existing underground ammonia pipeline and injection point was modified to add an additional chlo- rine injector. A leak from an incorrectly in- stalled chlorine pipe allowed a stream of chlorine solution to spray and attack the stain- less steel ammonia pipeline. The chemical and material incompatibility led to a gaseous am- monia leak in a confined space under the WTP’s primary entrance/exit driveway, result- ing in an evacuation from that area and a tem- porary blockage of traffic using the driveway. This situation not only brought to light the need for an intrinsically safe chemical injec- tion point and centralized residual monitor- ing, but also the need to reduce vehicular traffic near critical WTP assets. New Access Driveway Provides Safe Maneuvering Onto and Off the WTP Property The vulnerability assessment confirmed the primary entrance to the West Palm Beach WTP as a risk for the City, given its proximity to critical assets.All vehicular traffic for the fa- cility was required to navigate through the old- est part of the facility, which contained transfer and high-service pumping, finished water chemical dosing, emergency power gen- eration, and electrical switchgear. Addition- ally, access from Banyan Boulevard was unsafe without the presence of proper turn lanes for maneuvering on and off the WTP property. To reduce the risk presented by this en- trance, a new plant-access driveway was con- structed along the north side of the property fromAustralianAvenue—a larger thoroughfare. This new access driveway included a dedicated turn lane,security guard checkpoint,video sur- veillance, and card-swipe-access control for the City staff. Chemical deliveries,sludge transport, Figure 2. West Palm Beach WTP Site Plan with Priority Projects Highlighted. Figure 3. Safe Access Driveway from Australian Avenue. Continued on page 10 Continued from page 6 8 December 2013 • Florida Water Resources Journal
  • 3. 10 December 2013 • Florida Water Resources Journal and traffic from ongoing construction are now safely separated from the critical assets. Water Treatment Plant Reliability Improved With New Electrical/Generator Building Following Hurricanes Frances and Jeanne in 2004, the standby generators of the West Palm Beach WTP failed. A natural sense of ur- gency prompted the City to purchase two 2,000 kW remanufactured generators to provide gen- erator power to the WTP. The new generators proved too large for the building, prompting the removal of the roof and façade and creating other challenges, such as a fan-driven rainwa- ter short in the NEMA1 electrical equipment, failure of the automatic transfer switch, failure of a generator stator,and noise complaints from nearby residential neighbors. Additionally, the switchgear for the WTP was constructed in 1985 as part of a new build- ing that also housed the transfer and high-ser- vice pumps. During a loss of utility power, and subsequently a failure of the generators, the transfer pump clearwell overflowed within just 15 min and flooded the building,threatening the adjacent electrical switchgear on the first floor. To address these issues, MWH designed a new electrical/generator building and a dedi- cated “express” electrical feed from the Evernia Street substation located on the WTP site. The new generator building includes three 2,500 kW generators, an air intake rain knockdown plenum,sound damping exhaust plenum,and a new Florida Power and Light transformer vault, as well as 4160V primary and generator switchgear. The express electrical feed, aug- mentedwithtwoadditionalutilityfeedsfromthe Evernia and West Palm Beach substations, pro- vides power to the double-ended switchboards and subsequently to all equipment, with an op- tion to seamlessly transfer between utility and on-site generated power. This transfer feature is of critical importance during the wet season, al- lowing seamless transitioning between preferred power sources. Proactive management between sourceshelpstonavigatethroughbrownoutsand blackouts and avoids interruptions to the treat- ment process and high-service pump- ing. This project also eliminates or re- placesmany obsolete loop switches,motor control centers, and electrical distribu- tion panel boards. Historically, con- stant speed motors have shut down at the WTP upon util- ity power failure. As part of the improvements to the facility,a num- ber of VFDs have been added and programmed for power loss “ride-through” by using the ca- pacitors in the direct current bus of the drives. The primary function of these capacitors is to filter the voltage and provide a stable direct cur- rent source for the inverter section of the drive. However,throughVFD programming,these ca- pacitors can discharge over a three-second switchover to standby power,avoiding a process interruption or a pressure loss in the distribu- tion system during brownouts and short black- outs. These VFDs provide the added benefit of reducing current in-rush to the motors in order to“peak-shave”electrical demands of the facil- ity, reducing electricty costs. Construction of the generator building at the heart of an aged facility has not been with- out challenges.During construction,unreliable record drawings of underground utilities and inoperable isolation valves complicated the re- location of a 42-in.finished water line.To facil- itate the relocation, 42-in. and 24-in. line stops were installed to bypass this section of the pipeline, which was nearly 15 ft deep and lo- cated only 25 ft away from a railway. The proj- ect team members, including MWH, ensured that adequate shoring and thrust restraint was provided for this hot tap. The work was done successfully and this section of pipe was by- passed, while protecting the arterial line sup- plying potable water to the downtown area. Dosing, Mixing, and Metering of Finished Water Chemicals Stabilizes Finished Water Quality Initial investigations in 2008 revealed that the mixing of disinfection chemicals was insuf- Figure 5.42-in. Line Stop to Bypass In-Service Water Main Supplying. Figure 4B. View on Double-Ended Main and Generator Switchgear. Figure 4A. New Electrical/Generator Building Increases Reliability of WTP Service. Continued from page 8
  • 4. Florida Water Resources Journal • December 2013 11 ficient. Chlorine and ammonia were being in- jected into a 60-in. gravity, prestressed cylindri- cal concrete pipe (PCCP) immediately upstream of the transfer pump clearwell.Although trans- fer pump impellers provided the mixing energy downstream, quiescent plug flow through the 125,000-gal clearwell did not provide the favor- able conditions necessary for immediate and complete monochloramine formation. During the construction of the sodium hypochlorite system, a chemical piping trench was added to accommodate all finished water chemical pipelines from the dosing pumps to a new central dosing point. Prior to the construc- tion of this piping trench,finished water chemi- calfeedlineswerespreadovermultiplecorridors to multiple injection points across the property. These finished water chemicals included sodium hypochlorite, ammonium hydroxide, sodium hydroxide, ortho/polyphosphate blend, and hy- drofluosilicic acid. The existing chemical injection points re- lied on turbulence from fittings and pipe bends, which provided incomplete mixing and reaction. Furthermore, finished water chemi- cals were dosed based on an aggregate flow from 26 individual filter effluent flow meters. With an inaccuracy of +/- 0.5 percent each, the total inaccuracy of the finished water flow sig- nal could be as high as +/- 13 percent. To alle- viate these issues, the City constructed an above-grade 48-in. in-line static mixer and a centralized venturi flow meter between the transfer pump station and the ground storage tanks. Since the system only has enough stor- age to be off line for 8 hours, the design in- cluded a 20 mgd temporary bypass system from the transfer pump clearwell to the ground storage tanks to enable the WTP to re- main in service during the construction tie- ins. The centralized flow meter provides a sig- nal by which all finished water chemicals are flow-paced with greater accuracy and reliabil- ity. A major improvement to the process and to finished water quality has been the addition of the mixing and metering header, and the au- tomation of the finished water chemical dosing and controls. Automated and Remotely Monitored Treatment Process in Real Time The WTP was operated manually from 1894 until the early 1990s, when a slow transi- tion was made from manual to automatic oper- ation. The improvements that were made included analog instrumentation and local con- trolpanels.Processmonitoringoveranalogcom- munications was transcribed by circular chart recorders for operations and compliance report- ing. In 1996, a complete plant upgrade was un- dertaken, including the addition of Siemens S5 programmablelogiccontrollers(PLCs). Newin- struments and sensors were provided, while au- tomatic control was achieved through actuation of valves throughout theWTP.Critical functions andcontrolswerenetworkedviafiberopticcable to the control room.In 2007,the filters were up- graded with new Siemens S7 PLCs and the com- municationnetworkof theRotork actuatorswas replaced to Profibus. In 2008, a radio telemetry networkwasinstalledtomonitorandcontrolthe remote booster pump stations and PLC hard- ware consisting of Allen Bradley CompactLogix and ControLogix. The development of the control system over this 20-year period spanned generations of SCADA technology evolution. Process monitoring and control systems of the WTP were stitched together as a patchwork quilt to meet the immediate needs of various projects without a unified framework. Operators in- terfaced process equipment through the Human Machine Interface (HMI) software, which differed greatly among the systems con- trolled. These inconsistencies in the software Figure 6. Mixing and Metering Header. Figure 7. Triple-Ringed Fiber Optic Control Network Architecture. Continued on page 12
  • 5. 12 December 2013 • Florida Water Resources Journal and interface increased the potential risk of operator error. To address these inconsistency issues, the control system was redesigned from the ground up. Efforts were made to standardize operation of devices via universally accepted communica- tion protocols; these included Modbus, De- viceNet, Profibus and TCP/IP. Implementation of the new system was achieved with a phased approach: 1) fiber optic network construction, 2) PLC and remote rack installation, and 3) process software refinement.Following the con- struction of a triple-ringed fiber optic control network around the facility in 2009,the SCADA network was developed using twin 48-strand, 62.5 micron multimode fiber. Three PLCs op- erate separate control rings, which in turn op- erate a total of 22 local interface units (LIU) for a distributive control system, as illustrated in the network architecture graphic. These LIUs include fiber-to-ethernet converters to com- municate to the remote PLC racks. The remote PLC racks communicate via hard wiring to the remote devices (i.e., pressure transmitters, flow switches,residual monitors,and turbidimeters). Five remotely located Thin Client touchscreens provide consistent and coherent graphic oper- ator interfaces using Wonderware software for monitoring and control. The City continues to make improvements to the control network. In 2013, MWH helped the City with equipment updates and adjust- ments to Profibus communications of the media filters. The City faced serious challenges in the transitioning from existing to new SCADA,and could only allow for very limited facility shut- downs to facilitate system changeovers.The key was to avoid blind spots in the system and run parallel programming simultaneously in the old and new systems to satisfy the health depart- ment’s requirement of continuous monitoring. Each input/output (I/O) had to be moved one- by-one and verified before proceeding to the next. Naturally, the hardest part of the switchover comes when it’s time to decommis- sion and remove the fiber to the old remote ter- minal units (RTU). Therefore, old RTU obsolescence was verified by powering down the cabinets and confirming that no signals were lost and no unknown or undocumented junctions were overlooked. As a result of the methodical improve- ments to the controls, the manual operation of flow control valves and chemical dosing pumps is now history, and the delayed process performance monitoring and control by peri- odic sampling and laboratory analysis is min- imized. The process is now remotely monitored and controlled in real time with minimal manual intervention. High-Service Pump Rehabilitation The seven existing high-service pumps range in age from 17 to 60 years. The pumps were evaluated to identify opportunities to in- crease capacity and reduce power consumption, either through operational improvements or equipment modifications. A condition assess- ment was conducted by MWH to document physical deficiencies of the existing pumps. The condition assessment indicated the pumps were, generally, in good to fair condi- tion, with a need for typical rehabilitation of pumps this age, including replacement of seals, wear rings, couplings, O-rings, nuts and bolts, coatings and exterior paint.Additionally,MWH compared the current performance of the pumps with the manufacturer pump curves to identify areas for improvement.This evaluation identified the potential to increase the capacity of three high-service pumps with minor mod- ifications to the existing impellers as follows: High-Service Pump 3 – The current impeller only draws 235 horsepower (hp) from the existing 300 hp motor. Additionally, the pump curve is “flat” and the operating head is much lower than the other pumps.This re- sults in reduced output when the other pumps are in operation, making the pump least useful when it is most likely needed.In- stalling a larger-diameter impeller to take ad- vantage of the existing 300 hp motor increases the operating head, thereby in- creasing the capacity of the pump. High-Service Pumps 6 and 7 – The pumps operate near the shutoff head and draw less than their rated capacity when the distribu- tion system pressure is high.Installing larger- diameter impellers takes advantage of the existing motors to increase capacity with minimal capital cost. Through detailed assessment and evalua- tion, the City was able to achieve cost savings by rehabilitating existing pumps, rather than purchasing new pumps, and increasing pump capacity by modifying,with minimal capital in- vestment, the existing pumps to take advantage of existing motors and electrical supply. The Result: Finished Water Quality Improvements In time, the improvement of the facility operations and finished water quality was bro- ken down into four phases: operational im- provements via staff augmentation and training (completed in mid-2008), filter im- provements (completed in mid-2009), new mixing and metering header (completed in November 2011), and a new SCADA system (completed in February 2012). Whereas previously, total chlorine, pH, color,and turbidity would fluctuate quite dras- tically, the finished water quality has become Figure 9. High-Service Pump No. 7. Above: Figure 8A. Old Remote Terminal Unit (RTU). At right: Figure 8B. New Local Interface Unit (LIU). Continued from page 11
  • 6. Florida Water Resources Journal • December 2013 13 more stable,evident in the trends and variances of the daily data obtained from monthly oper- ating reports and the SCADA system. The graphs for total chlorine and pH, particularly, show the narrower band in which total chlorine and pH are controlled in the finished water. For instance, the variance of the finished water pH dropped from 0.10 to 0.04 when operations were augmented by contract staff trained in mid-2008, with a further reduction to 0.01 when the mixing and metering header and SCADA system were completed in early 2012. The graph for finished water turbidity shows a consistent downward trend since the first im- provements were made in mid-2008. Opera- tions augmentation and training helped reduce average turbidity levels from 0.21 to 0.11 neph- elometric turbidity unit (NTU), but another step-change improvement to a turbidity of 0.10 NTU was made with the completion of the SCADA system in early 2012.The graph for fin- ished water color, on the other hand, shows the step-change improvement in mid-2008 when operations instigated the more frequent sam- pling regime (every 4 hours) on the settled water to ensure the ferric sulfate and lime dos- ing and pH conditions were always kept opti- mum for maximum organics and color removal in the sedimentation basins. The average color levels dropped from 7.6 to 3.3 PCU when this operational change was made. Summary Through new controls hardware and soft- ware, the West Palm Beach WTP is more reli- able and produces more consistent finished water quality with minimal manual interven- tion. Hazardous, gaseous chlorine and ammo- nia have been replaced with liquids, and a new safe access driveway provides safer ingress and egress.Obsolete chemical systems have been au- tomated and replaced with state-of-the-art equipment.A new electrical/generator building with an express power feed is under construc- tion with double-ended switchgear and standby generators providing reliably power to all equipment, with an option to seamlessly trans- fer between utility and generator power. With the right infrastructure and im- proved operator attention,significant improve- ments have been made to the water treatment process evidenced by improved finished water quality and operational reliability. Acknowledgements Thanks from MWH go to the City of West Palm Beach for its support and to acknowledge thefollowingteammemberswhocontributedto the improvements at theWTP:Jacobs Engineer- ing and subconsultants GlobalTech,Song+Asso- ciates, and Integration Systems Incorporated. Figure 10A. Total Chlorine (Free + Combined) Figure 10B. Finished Water pH Figure 10C. Finished Water Turbidity Figure 10D. Finished Water Color Data sets were cleaned up for outliers, anomalies, and readings below detectable limit (BDL). Turbidity data recorded as < 0.1 is depicted as 0.1. Color data recorded as < 3 is depicted as 3.0.