SlideShare a Scribd company logo
1 of 2
Download to read offline
Background
In 2007 Atkins was appointed by the 2012
Olympic Development Agency (ODA) and
their Delivery Partner (CLM) to design the
new potable water network serving the 2012
Games and the ongoing legacy development
of the Olympic Park.
The Olympic Park site was a large Brownfield
site in Stratford, east London (right), previ-
ously used for light engineering and commer-
cial use and with a history of industrial use
dating back to the 1600’s.
The site was compulsorily purchased in 2007,
existing businesses relocated and all local
services removed- overhead HV cables were
routed underground and the site underwent
an extensive programme of remediation and
enabling works to allow a completely new
multi-utility network to be created.
The new potable water network was crucial
to the overall utility construction programme
as the water mains were generally the deep-
est of the services in the new multi-utility
service corridors that were created across the
park.
Design Brief
The basic design brief was unusual in that the
client wanted a design that could be operated
by a third party under an Inset Agreement, a
provision of the 1991 Water Act which allows
third parties to own and operate networks
within the geographical area of the host util-
ity, in this case Thames Water.
This in turn has major implications for the
design, since resilience is more critical. A
feature of this type of network is that it is
linked to the host network by relatively few
connections, to simplify the supply and billing
of water from the host utility.
Network Model
The design was based on a network model
which enabled us to test a variety of ring
main configurations and pipe diameters.
The main
venues had
specific de-
mand re-
quirements
and it was
necessary to
demonstrate
that fire de-
mands could
be met under various emergency scenarios.
The basic network design was based on a ring
main around the Park with connections to the
Athlete’s Village and Westfield developments
and with two metered connections to the
Thames Water host network.
Water Demand
An unusual feature of the design was that
predicted water demand was the reverse of
the normal case: peak demand would be for a
Case Study
2012 Olympic Park Development
New Potable Water Network Design
short period during the 2012 Games but
would then drop to a very low level, increas-
ing gradually to the long term predicted value
as legacy development moved forward.
The Adoptable Standard
A basic requirement of the design was
that it should comply with the ‘adoptable
standard’, ie it should comply with all
Thames Water standards, and to this end
regular design review meetings were
organised and managed by Atkins.
These meetings created a formal envi-
ronment in which design issues could be
highlighted well in advance and solutions
agreed such that the main development
programme did not get delayed.
Pipe Material & Jointing
The Olympic Park site had a long history
of industrial use and the site was classi-
fied by Thames Water as ‘contaminated’;
for this reason PE pipe could not be used
under the current WRAS guidelines. A
number of pipe materials were evaluated
and ductile iron was selected for the
main network, though PE was used for
bridge crossings. The network used an-
chor gaskets throughout primarily to
avoid concrete thrust blocks in the multi-
utility service corridors, where space was
at a premium.
Delivery Flow and Pressure
The network model used basic data on
the likely operating pressures that would
be experienced at the two proposed
points of connection, provided by
Thames Water under worst case condi-
tions.
Resilience
System resilience was a key issue in the
network design– the network had to be
supported under all conditions from one
of two main metered connections to the
Thames Water network. Specific fire de-
mand conditions at the venues were
required and separate design approval
was obtained from the London Fire Bri-
gade. All key conditions were built in to
the hydraulic model and a number of key
main break scenarios tested—the basic
ring-main concept allowed dual supply to
all parts of the network in such an event.
Bridge Designs
A major feature of the Olympic Park was
the number of bridges crossing the vari-
ous waterways which gave the Park its
unique appearance. The bridges also
presented challenging design problems
in housing a wide variety of utilities,
which included insulated steel heating
and cooling pipework, electrical cables,
comms cables and the 600mm potable
water ring main housed in a steel sleeve.
(see below)
Bridge F06 was the showpiece bridge on
the Park, and featured twin spans set at
an angle (above), presenting major de-
sign challenges in accommodating multi-
ple utilities in a confined space, yet pro-
viding adequate access for maintenance
and repair.
Design Approval
The Atkins design received formal ap-
proval as conforming to the Adoptable
Standard in November 2007; similar for-
mal approval was also obtained from the
London Fire Brigade in 2008.
Tender Evaluation
The approved design was offered for
tender and Atkins evaluated the tender
documents received. The D&B contract
was awarded to the multi-utility contrac-
tor McNicholas and Atkins worked
closely with their designer (Hyder) and
Thames Water to finalise construction
design and develop a detailed Commis-
sioning Plan to meet Thames’ require-
ments
Own and Operate
Evaluation
A number of Own and Operate compa-
nies expressed an interest in operating
the potable and foul networks under an
inset agreement– the bids were evalu-
ated and Atkins advised the ODA on the
way ahead.
The design was reviewed by the O&O
bidders and since it had been approved
by Thames Water as compliant with the
Adoptable Standard, this review was
confirmed quickly.
The ODA decided that the best long-
term solution would be for Thames Wa-
ter to adopt the network.
Atkins role in this high-profile project
included design, consultancy and sup-
port to the ODA in creating a fully func-
tional approved and commissioned po-
table water network for the 2012
Games.
A key role was in enabling, facilitating
and resolving issues with Thames Water
such that a very complex process was
carried out with minimal delay and dis-
ruption to the overall Park development
programme. Atkins provided that key
expertise to ensure a highly successful
outcome.

More Related Content

What's hot

G_Clifford_resume_Feb 15
G_Clifford_resume_Feb 15G_Clifford_resume_Feb 15
G_Clifford_resume_Feb 15
Greg Clifford
 
New generation of copper alloy conductors for overhead electricity lines
New generation of copper alloy conductors for overhead electricity linesNew generation of copper alloy conductors for overhead electricity lines
New generation of copper alloy conductors for overhead electricity lines
Leonardo ENERGY
 
Res Sher Chauhan general est Nov 2016
Res  Sher Chauhan general est Nov 2016Res  Sher Chauhan general est Nov 2016
Res Sher Chauhan general est Nov 2016
Sher Chuhan
 
Copper alloy conductors for overhead lines - CIGRÉ Regional South-East Europe...
Copper alloy conductors for overhead lines - CIGRÉ Regional South-East Europe...Copper alloy conductors for overhead lines - CIGRÉ Regional South-East Europe...
Copper alloy conductors for overhead lines - CIGRÉ Regional South-East Europe...
Leonardo ENERGY
 
Slideshare September 2010
Slideshare September 2010Slideshare September 2010
Slideshare September 2010
Joel Johnson
 
Marange Resources Water Supply System Design-Odzi to Concession Pipeline
Marange Resources Water Supply System Design-Odzi to Concession PipelineMarange Resources Water Supply System Design-Odzi to Concession Pipeline
Marange Resources Water Supply System Design-Odzi to Concession Pipeline
Augustine Marume
 
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LININGSEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
DEEPAK MALLICK
 
GZA Upper Roberts Meadow Dam Public Forum Presentation 10-27-10
GZA Upper Roberts Meadow Dam Public Forum Presentation 10-27-10GZA Upper Roberts Meadow Dam Public Forum Presentation 10-27-10
GZA Upper Roberts Meadow Dam Public Forum Presentation 10-27-10
Adam Cohen
 

What's hot (20)

Tidal Lagoon Power - Presentation to CCC
Tidal Lagoon Power - Presentation to CCCTidal Lagoon Power - Presentation to CCC
Tidal Lagoon Power - Presentation to CCC
 
G_Clifford_resume_Feb 15
G_Clifford_resume_Feb 15G_Clifford_resume_Feb 15
G_Clifford_resume_Feb 15
 
The Severn Estuary - A sustainable low carbon energy resource - Peter Kydd
The Severn Estuary - A sustainable low carbon energy resource - Peter KyddThe Severn Estuary - A sustainable low carbon energy resource - Peter Kydd
The Severn Estuary - A sustainable low carbon energy resource - Peter Kydd
 
Geotechnical characterizaton of soft clays of the godavari delta
Geotechnical characterizaton of soft clays of the godavari deltaGeotechnical characterizaton of soft clays of the godavari delta
Geotechnical characterizaton of soft clays of the godavari delta
 
New generation of copper alloy conductors for overhead electricity lines
New generation of copper alloy conductors for overhead electricity linesNew generation of copper alloy conductors for overhead electricity lines
New generation of copper alloy conductors for overhead electricity lines
 
Scoping meeting presentation 4 29-13
Scoping meeting presentation 4 29-13Scoping meeting presentation 4 29-13
Scoping meeting presentation 4 29-13
 
Res Sher Chauhan general est Nov 2016
Res  Sher Chauhan general est Nov 2016Res  Sher Chauhan general est Nov 2016
Res Sher Chauhan general est Nov 2016
 
Micro-alloyed copper overhead line conductors - Wire & Cable Technology Inter...
Micro-alloyed copper overhead line conductors - Wire & Cable Technology Inter...Micro-alloyed copper overhead line conductors - Wire & Cable Technology Inter...
Micro-alloyed copper overhead line conductors - Wire & Cable Technology Inter...
 
Micro-alloyed copper overhead line conductors - PowerGrid International Augus...
Micro-alloyed copper overhead line conductors - PowerGrid International Augus...Micro-alloyed copper overhead line conductors - PowerGrid International Augus...
Micro-alloyed copper overhead line conductors - PowerGrid International Augus...
 
CV Krishna Dhanya
CV Krishna DhanyaCV Krishna Dhanya
CV Krishna Dhanya
 
Copper alloy conductors for overhead lines - CIGRÉ Regional South-East Europe...
Copper alloy conductors for overhead lines - CIGRÉ Regional South-East Europe...Copper alloy conductors for overhead lines - CIGRÉ Regional South-East Europe...
Copper alloy conductors for overhead lines - CIGRÉ Regional South-East Europe...
 
Disinfection System
Disinfection SystemDisinfection System
Disinfection System
 
Slideshare September 2010
Slideshare September 2010Slideshare September 2010
Slideshare September 2010
 
Marange Resources Water Supply System Design-Odzi to Concession Pipeline
Marange Resources Water Supply System Design-Odzi to Concession PipelineMarange Resources Water Supply System Design-Odzi to Concession Pipeline
Marange Resources Water Supply System Design-Odzi to Concession Pipeline
 
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LININGSEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
 
GZA Upper Roberts Meadow Dam Public Forum Presentation 10-27-10
GZA Upper Roberts Meadow Dam Public Forum Presentation 10-27-10GZA Upper Roberts Meadow Dam Public Forum Presentation 10-27-10
GZA Upper Roberts Meadow Dam Public Forum Presentation 10-27-10
 
RESUME
RESUMERESUME
RESUME
 
Resolving Project Boundary Challenges to Streamline FERC Hydropower Dam Relic...
Resolving Project Boundary Challenges to Streamline FERC Hydropower Dam Relic...Resolving Project Boundary Challenges to Streamline FERC Hydropower Dam Relic...
Resolving Project Boundary Challenges to Streamline FERC Hydropower Dam Relic...
 
2014 mike by dhi uk symposium user group meeting - presentations and papers...
2014 mike by dhi uk symposium   user group meeting - presentations and papers...2014 mike by dhi uk symposium   user group meeting - presentations and papers...
2014 mike by dhi uk symposium user group meeting - presentations and papers...
 
Adnoc and masdar project may 2013
Adnoc and masdar project   may 2013Adnoc and masdar project   may 2013
Adnoc and masdar project may 2013
 

Viewers also liked

Back Window Advertisement
Back Window AdvertisementBack Window Advertisement
Back Window Advertisement
Jessica Morgan
 
CT-We Cant Fix Your Boss
CT-We Cant Fix Your BossCT-We Cant Fix Your Boss
CT-We Cant Fix Your Boss
Pamela Jordan
 

Viewers also liked (17)

mapa conceptual de maquinas hidráulica
mapa conceptual de maquinas hidráulica  mapa conceptual de maquinas hidráulica
mapa conceptual de maquinas hidráulica
 
Cover 2
Cover 2Cover 2
Cover 2
 
Tema01: Conociendo SqLite Studio
Tema01: Conociendo SqLite StudioTema01: Conociendo SqLite Studio
Tema01: Conociendo SqLite Studio
 
E-Learning Begoña Gros
E-Learning Begoña GrosE-Learning Begoña Gros
E-Learning Begoña Gros
 
Princess Diana 1
Princess Diana 1Princess Diana 1
Princess Diana 1
 
Livros
LivrosLivros
Livros
 
Proyecto de vida
Proyecto de vidaProyecto de vida
Proyecto de vida
 
Lo7
Lo7Lo7
Lo7
 
Media Relations
Media Relations  Media Relations
Media Relations
 
Presentacion taller telar 2015 FABLAB Madrid
Presentacion taller telar 2015 FABLAB MadridPresentacion taller telar 2015 FABLAB Madrid
Presentacion taller telar 2015 FABLAB Madrid
 
Comenius nTrilateral Meeting in Garbsen - March 2015
Comenius nTrilateral Meeting in Garbsen - March 2015Comenius nTrilateral Meeting in Garbsen - March 2015
Comenius nTrilateral Meeting in Garbsen - March 2015
 
Grade 5 final full
Grade 5 final fullGrade 5 final full
Grade 5 final full
 
LA VISPA TERESA (ovvero il ministro Galletti e il SISTRI)
LA VISPA TERESA  (ovvero il ministro Galletti e il SISTRI)LA VISPA TERESA  (ovvero il ministro Galletti e il SISTRI)
LA VISPA TERESA (ovvero il ministro Galletti e il SISTRI)
 
Back Window Advertisement
Back Window AdvertisementBack Window Advertisement
Back Window Advertisement
 
CT-We Cant Fix Your Boss
CT-We Cant Fix Your BossCT-We Cant Fix Your Boss
CT-We Cant Fix Your Boss
 
Eric mircsov
Eric mircsovEric mircsov
Eric mircsov
 
EvictionRecords.com Resident Screening Plans to Educate through NAPBS
EvictionRecords.com Resident Screening Plans to Educate through NAPBSEvictionRecords.com Resident Screening Plans to Educate through NAPBS
EvictionRecords.com Resident Screening Plans to Educate through NAPBS
 

Similar to 2012 Network design

Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011
Mike Bisland
 
MES Case Study - Carlton Park Substation
MES Case Study - Carlton Park SubstationMES Case Study - Carlton Park Substation
MES Case Study - Carlton Park Substation
Steve Sadler
 
060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar
060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar
060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar
Javad Akhtar
 
Pic booklet screen view 2
Pic booklet   screen view 2Pic booklet   screen view 2
Pic booklet screen view 2
Amin Hadjaran
 
Craig MacIntyre CV_EA Engineering
Craig MacIntyre CV_EA EngineeringCraig MacIntyre CV_EA Engineering
Craig MacIntyre CV_EA Engineering
Craig MacIntyre
 
- Nabil Resume - Civil - Construction-1 (3)( 2)
- Nabil Resume - Civil - Construction-1 (3)( 2)- Nabil Resume - Civil - Construction-1 (3)( 2)
- Nabil Resume - Civil - Construction-1 (3)( 2)
NABIL NASSAR
 
Baraa Mohd Al Sotari CV
Baraa  Mohd Al Sotari CVBaraa  Mohd Al Sotari CV
Baraa Mohd Al Sotari CV
baraa Mohammad
 
Ayman El Messlamy CV, RE-Updated 4-10-15
Ayman El Messlamy CV, RE-Updated 4-10-15Ayman El Messlamy CV, RE-Updated 4-10-15
Ayman El Messlamy CV, RE-Updated 4-10-15
Ayman El Messlamy
 
RPS CV of Simon Hua
RPS CV of Simon HuaRPS CV of Simon Hua
RPS CV of Simon Hua
Simon Hua
 

Similar to 2012 Network design (20)

Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011
 
MES Case Study - Carlton Park Substation
MES Case Study - Carlton Park SubstationMES Case Study - Carlton Park Substation
MES Case Study - Carlton Park Substation
 
Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...
Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...
Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...
 
EDIST 2018 SAE+Alectra Grounding Presentation
EDIST 2018 SAE+Alectra Grounding PresentationEDIST 2018 SAE+Alectra Grounding Presentation
EDIST 2018 SAE+Alectra Grounding Presentation
 
Abergeldie Brochure
Abergeldie BrochureAbergeldie Brochure
Abergeldie Brochure
 
Firas Abbawy CV - Atkins
Firas Abbawy CV - AtkinsFiras Abbawy CV - Atkins
Firas Abbawy CV - Atkins
 
060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar
060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar
060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar
 
Project charter presentation
Project charter presentationProject charter presentation
Project charter presentation
 
Pic booklet screen view 2
Pic booklet   screen view 2Pic booklet   screen view 2
Pic booklet screen view 2
 
Craig MacIntyre CV_EA Engineering
Craig MacIntyre CV_EA EngineeringCraig MacIntyre CV_EA Engineering
Craig MacIntyre CV_EA Engineering
 
- Nabil Resume - Civil - Construction-1 (3)( 2)
- Nabil Resume - Civil - Construction-1 (3)( 2)- Nabil Resume - Civil - Construction-1 (3)( 2)
- Nabil Resume - Civil - Construction-1 (3)( 2)
 
Baraa Mohd Al Sotari CV
Baraa  Mohd Al Sotari CVBaraa  Mohd Al Sotari CV
Baraa Mohd Al Sotari CV
 
Ayman El Messlamy CV, RE-Updated 4-10-15
Ayman El Messlamy CV, RE-Updated 4-10-15Ayman El Messlamy CV, RE-Updated 4-10-15
Ayman El Messlamy CV, RE-Updated 4-10-15
 
Aac booklet
Aac bookletAac booklet
Aac booklet
 
projects
projectsprojects
projects
 
Paul Crooks - Abu Dhabi Carbon Capture, Usage and Storage Project
Paul Crooks - Abu Dhabi Carbon Capture, Usage and Storage ProjectPaul Crooks - Abu Dhabi Carbon Capture, Usage and Storage Project
Paul Crooks - Abu Dhabi Carbon Capture, Usage and Storage Project
 
Whitescape Civil Engineering Case Study
Whitescape Civil Engineering Case StudyWhitescape Civil Engineering Case Study
Whitescape Civil Engineering Case Study
 
Prime consulting group brochure
Prime consulting group brochurePrime consulting group brochure
Prime consulting group brochure
 
John_Buckley_CV_Dec 2016
John_Buckley_CV_Dec 2016John_Buckley_CV_Dec 2016
John_Buckley_CV_Dec 2016
 
RPS CV of Simon Hua
RPS CV of Simon HuaRPS CV of Simon Hua
RPS CV of Simon Hua
 

2012 Network design

  • 1. Background In 2007 Atkins was appointed by the 2012 Olympic Development Agency (ODA) and their Delivery Partner (CLM) to design the new potable water network serving the 2012 Games and the ongoing legacy development of the Olympic Park. The Olympic Park site was a large Brownfield site in Stratford, east London (right), previ- ously used for light engineering and commer- cial use and with a history of industrial use dating back to the 1600’s. The site was compulsorily purchased in 2007, existing businesses relocated and all local services removed- overhead HV cables were routed underground and the site underwent an extensive programme of remediation and enabling works to allow a completely new multi-utility network to be created. The new potable water network was crucial to the overall utility construction programme as the water mains were generally the deep- est of the services in the new multi-utility service corridors that were created across the park. Design Brief The basic design brief was unusual in that the client wanted a design that could be operated by a third party under an Inset Agreement, a provision of the 1991 Water Act which allows third parties to own and operate networks within the geographical area of the host util- ity, in this case Thames Water. This in turn has major implications for the design, since resilience is more critical. A feature of this type of network is that it is linked to the host network by relatively few connections, to simplify the supply and billing of water from the host utility. Network Model The design was based on a network model which enabled us to test a variety of ring main configurations and pipe diameters. The main venues had specific de- mand re- quirements and it was necessary to demonstrate that fire de- mands could be met under various emergency scenarios. The basic network design was based on a ring main around the Park with connections to the Athlete’s Village and Westfield developments and with two metered connections to the Thames Water host network. Water Demand An unusual feature of the design was that predicted water demand was the reverse of the normal case: peak demand would be for a Case Study 2012 Olympic Park Development New Potable Water Network Design
  • 2. short period during the 2012 Games but would then drop to a very low level, increas- ing gradually to the long term predicted value as legacy development moved forward. The Adoptable Standard A basic requirement of the design was that it should comply with the ‘adoptable standard’, ie it should comply with all Thames Water standards, and to this end regular design review meetings were organised and managed by Atkins. These meetings created a formal envi- ronment in which design issues could be highlighted well in advance and solutions agreed such that the main development programme did not get delayed. Pipe Material & Jointing The Olympic Park site had a long history of industrial use and the site was classi- fied by Thames Water as ‘contaminated’; for this reason PE pipe could not be used under the current WRAS guidelines. A number of pipe materials were evaluated and ductile iron was selected for the main network, though PE was used for bridge crossings. The network used an- chor gaskets throughout primarily to avoid concrete thrust blocks in the multi- utility service corridors, where space was at a premium. Delivery Flow and Pressure The network model used basic data on the likely operating pressures that would be experienced at the two proposed points of connection, provided by Thames Water under worst case condi- tions. Resilience System resilience was a key issue in the network design– the network had to be supported under all conditions from one of two main metered connections to the Thames Water network. Specific fire de- mand conditions at the venues were required and separate design approval was obtained from the London Fire Bri- gade. All key conditions were built in to the hydraulic model and a number of key main break scenarios tested—the basic ring-main concept allowed dual supply to all parts of the network in such an event. Bridge Designs A major feature of the Olympic Park was the number of bridges crossing the vari- ous waterways which gave the Park its unique appearance. The bridges also presented challenging design problems in housing a wide variety of utilities, which included insulated steel heating and cooling pipework, electrical cables, comms cables and the 600mm potable water ring main housed in a steel sleeve. (see below) Bridge F06 was the showpiece bridge on the Park, and featured twin spans set at an angle (above), presenting major de- sign challenges in accommodating multi- ple utilities in a confined space, yet pro- viding adequate access for maintenance and repair. Design Approval The Atkins design received formal ap- proval as conforming to the Adoptable Standard in November 2007; similar for- mal approval was also obtained from the London Fire Brigade in 2008. Tender Evaluation The approved design was offered for tender and Atkins evaluated the tender documents received. The D&B contract was awarded to the multi-utility contrac- tor McNicholas and Atkins worked closely with their designer (Hyder) and Thames Water to finalise construction design and develop a detailed Commis- sioning Plan to meet Thames’ require- ments Own and Operate Evaluation A number of Own and Operate compa- nies expressed an interest in operating the potable and foul networks under an inset agreement– the bids were evalu- ated and Atkins advised the ODA on the way ahead. The design was reviewed by the O&O bidders and since it had been approved by Thames Water as compliant with the Adoptable Standard, this review was confirmed quickly. The ODA decided that the best long- term solution would be for Thames Wa- ter to adopt the network. Atkins role in this high-profile project included design, consultancy and sup- port to the ODA in creating a fully func- tional approved and commissioned po- table water network for the 2012 Games. A key role was in enabling, facilitating and resolving issues with Thames Water such that a very complex process was carried out with minimal delay and dis- ruption to the overall Park development programme. Atkins provided that key expertise to ensure a highly successful outcome.