This document provides status updates for two projects being managed by Kamaruddin. The DWP Thickener project is tracking to be completed by December 31st within budget despite a cost increase from the original approval. Work continues on sandblasting and painting the thickener tank and pulling cable. The Portsite VPA #2 building project has faced delays and is now forecast to finish in early August due to a batchplant breakdown, with resources redirected to the DWP Thickener project for the week.