SlideShare a Scribd company logo
Proj : 1460-403-11-111
PM : Kamaruddin
DWP Thickener
1
OVERALL PROJECT STATUS
MINIMUM REQUIREMENT SCOPE
Completion Date Cost
Current Approval 31-Dec-14 (IFR) $ 9,811,000
Current Forecast 31-Dec-14 $ 23,403,095
This Week To Date
Planned 2.23% 90.55% (IFR)
Earned 2.61% 88.91%
Continue progress at DWP Thickener
Project
Continue sandblast and painting inside
Thickener tank
Continue pulling cable above pipe rack
Proj : 80108031
PM : Kamaruddin
Portsite VPA #2 (Building)
2
OVERALL PROJECT STATUS
Completion Date Cost
Current Approval 31-Jul-2015 $ 32,926,000
Current Forecast 7-Aug-2015 $ 32,434,052
This Week To Date
Planned 1.22% 42.71%
Earned 0.00% 39.90%
VPA Building 2nd floor VPA Building E-house preparation before energize
Note: No progress within this week due to batchplant at Portsite breakdown since
18 November 2014 and resources allocation except civil crew are dedicated to
DWP Thickener project.

More Related Content

What's hot

المعايير الزمنية لعقود الفيديك
المعايير الزمنية لعقود الفيديكالمعايير الزمنية لعقود الفيديك
المعايير الزمنية لعقود الفيديك
Hani Saad
 
Faisalaiah project (english) 3 REV.03
Faisalaiah project (english) 3 REV.03Faisalaiah project (english) 3 REV.03
Faisalaiah project (english) 3 REV.03
Wael Nafad
 
Glovapp Presentation140709
Glovapp Presentation140709Glovapp Presentation140709
Glovapp Presentation140709
ehiosa
 
Halil Özkan 125680 Civil Engineering
Halil Özkan 125680 Civil EngineeringHalil Özkan 125680 Civil Engineering
Halil Özkan 125680 Civil Engineering
Halil Özkan
 
Sdd engineering solutions
Sdd engineering solutionsSdd engineering solutions
Sdd engineering solutions
structuraldesign
 
Fire extinguisher monthly checklist report
Fire extinguisher monthly checklist reportFire extinguisher monthly checklist report
Fire extinguisher monthly checklist report
Azmeel Contracting Company
 
Oil refinery tank project
Oil refinery tank projectOil refinery tank project
Oil refinery tank project
ASIF AHMED SAJAL
 
Monthly smoke derector inspection report
Monthly smoke derector inspection reportMonthly smoke derector inspection report
Monthly smoke derector inspection report
Azmeel Contracting Company
 
BIM-Pier5
BIM-Pier5BIM-Pier5
Estimated value delivery
Estimated value deliveryEstimated value delivery
Estimated value delivery
Stephan Blom
 

What's hot (10)

المعايير الزمنية لعقود الفيديك
المعايير الزمنية لعقود الفيديكالمعايير الزمنية لعقود الفيديك
المعايير الزمنية لعقود الفيديك
 
Faisalaiah project (english) 3 REV.03
Faisalaiah project (english) 3 REV.03Faisalaiah project (english) 3 REV.03
Faisalaiah project (english) 3 REV.03
 
Glovapp Presentation140709
Glovapp Presentation140709Glovapp Presentation140709
Glovapp Presentation140709
 
Halil Özkan 125680 Civil Engineering
Halil Özkan 125680 Civil EngineeringHalil Özkan 125680 Civil Engineering
Halil Özkan 125680 Civil Engineering
 
Sdd engineering solutions
Sdd engineering solutionsSdd engineering solutions
Sdd engineering solutions
 
Fire extinguisher monthly checklist report
Fire extinguisher monthly checklist reportFire extinguisher monthly checklist report
Fire extinguisher monthly checklist report
 
Oil refinery tank project
Oil refinery tank projectOil refinery tank project
Oil refinery tank project
 
Monthly smoke derector inspection report
Monthly smoke derector inspection reportMonthly smoke derector inspection report
Monthly smoke derector inspection report
 
BIM-Pier5
BIM-Pier5BIM-Pier5
BIM-Pier5
 
Estimated value delivery
Estimated value deliveryEstimated value delivery
Estimated value delivery
 

Viewers also liked

Mapping Civil Society and Social Economy
Mapping Civil Society and Social EconomyMapping Civil Society and Social Economy
Mapping Civil Society and Social Economy
Wojtek Sokolowski
 
Map Tools in AutoCAD Civil 3D
Map Tools in AutoCAD Civil 3DMap Tools in AutoCAD Civil 3D
Map Tools in AutoCAD Civil 3D
Richard Chappell, GISP
 
Understanding ASL Grammatical Features and Discourse Mapping
Understanding ASL Grammatical Features and Discourse MappingUnderstanding ASL Grammatical Features and Discourse Mapping
Understanding ASL Grammatical Features and Discourse Mapping
Doug Stringham
 
Map Reading
Map ReadingMap Reading
Map Reading
Sam Olayvar
 
Effluent Treatment Plant(ETP)
Effluent Treatment Plant(ETP)Effluent Treatment Plant(ETP)
Effluent Treatment Plant(ETP)
Nishith Tripathi
 
Water treatment plant of environmental engineering
Water treatment plant of environmental engineeringWater treatment plant of environmental engineering
Water treatment plant of environmental engineering
Sehrish Mehmood
 
Water Treatment Plant Design project
Water Treatment Plant Design projectWater Treatment Plant Design project
Water Treatment Plant Design project
chris30277
 
water treatment slides
water treatment slideswater treatment slides
water treatment slides
Anand Keshri
 
28737268 waste-water-treatment-ppt
28737268 waste-water-treatment-ppt28737268 waste-water-treatment-ppt
28737268 waste-water-treatment-ppt
abhiiii4558
 
HOW TO MAP CONTENT TO THE BUYER'S JOURNEY & THE MARKETER'S FUNNEL [INBOUND 2014]
HOW TO MAP CONTENT TO THE BUYER'S JOURNEY & THE MARKETER'S FUNNEL [INBOUND 2014]HOW TO MAP CONTENT TO THE BUYER'S JOURNEY & THE MARKETER'S FUNNEL [INBOUND 2014]
HOW TO MAP CONTENT TO THE BUYER'S JOURNEY & THE MARKETER'S FUNNEL [INBOUND 2014]
HubSpot
 
Water Treatment Plant
Water Treatment PlantWater Treatment Plant
Water Treatment Plant
GAURAV. H .TANDON
 

Viewers also liked (11)

Mapping Civil Society and Social Economy
Mapping Civil Society and Social EconomyMapping Civil Society and Social Economy
Mapping Civil Society and Social Economy
 
Map Tools in AutoCAD Civil 3D
Map Tools in AutoCAD Civil 3DMap Tools in AutoCAD Civil 3D
Map Tools in AutoCAD Civil 3D
 
Understanding ASL Grammatical Features and Discourse Mapping
Understanding ASL Grammatical Features and Discourse MappingUnderstanding ASL Grammatical Features and Discourse Mapping
Understanding ASL Grammatical Features and Discourse Mapping
 
Map Reading
Map ReadingMap Reading
Map Reading
 
Effluent Treatment Plant(ETP)
Effluent Treatment Plant(ETP)Effluent Treatment Plant(ETP)
Effluent Treatment Plant(ETP)
 
Water treatment plant of environmental engineering
Water treatment plant of environmental engineeringWater treatment plant of environmental engineering
Water treatment plant of environmental engineering
 
Water Treatment Plant Design project
Water Treatment Plant Design projectWater Treatment Plant Design project
Water Treatment Plant Design project
 
water treatment slides
water treatment slideswater treatment slides
water treatment slides
 
28737268 waste-water-treatment-ppt
28737268 waste-water-treatment-ppt28737268 waste-water-treatment-ppt
28737268 waste-water-treatment-ppt
 
HOW TO MAP CONTENT TO THE BUYER'S JOURNEY & THE MARKETER'S FUNNEL [INBOUND 2014]
HOW TO MAP CONTENT TO THE BUYER'S JOURNEY & THE MARKETER'S FUNNEL [INBOUND 2014]HOW TO MAP CONTENT TO THE BUYER'S JOURNEY & THE MARKETER'S FUNNEL [INBOUND 2014]
HOW TO MAP CONTENT TO THE BUYER'S JOURNEY & THE MARKETER'S FUNNEL [INBOUND 2014]
 
Water Treatment Plant
Water Treatment PlantWater Treatment Plant
Water Treatment Plant
 

Similar to Dec 22 2014 CSLL

T0352 - Al Wajba presentation for the Construction Sequence
T0352 - Al Wajba presentation for the Construction SequenceT0352 - Al Wajba presentation for the Construction Sequence
T0352 - Al Wajba presentation for the Construction Sequence
chethanshivram
 
ARENA: Large-scale solar photovoltaics – competitive round
ARENA: Large-scale solar photovoltaics – competitive roundARENA: Large-scale solar photovoltaics – competitive round
ARENA: Large-scale solar photovoltaics – competitive round
NSW Environment and Planning
 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptx
TalebAlfihan
 
Sample DPR for Hydro Project (10 MW) (2012)
Sample DPR for Hydro Project (10 MW) (2012)Sample DPR for Hydro Project (10 MW) (2012)
Sample DPR for Hydro Project (10 MW) (2012)
Nikhil Jaipurkar
 
Project assign 2
Project assign 2Project assign 2
Project assign 2
Moses Seriki
 
AIWSP presentation SCM 3 11.09.2018 (1).ppt
AIWSP presentation SCM 3  11.09.2018 (1).pptAIWSP presentation SCM 3  11.09.2018 (1).ppt
AIWSP presentation SCM 3 11.09.2018 (1).ppt
Rajabdeen Amjath
 
Water-Wastewater Impact Fees
Water-Wastewater Impact FeesWater-Wastewater Impact Fees
Water-Wastewater Impact Fees
City of College Station
 
Water-Wastewater Impact Fees
Water-Wastewater Impact FeesWater-Wastewater Impact Fees
Water-Wastewater Impact Fees
City of College Station
 
Cu-Boil Pot Upgrade - Closeout Presentation Rev2a
Cu-Boil Pot Upgrade - Closeout Presentation Rev2aCu-Boil Pot Upgrade - Closeout Presentation Rev2a
Cu-Boil Pot Upgrade - Closeout Presentation Rev2a
Brandon Smith
 
Al Qasr Mall presentation
Al Qasr Mall presentationAl Qasr Mall presentation
Al Qasr Mall presentation
Mamdouh Attia
 
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2Ahmed Al Balawi-Sea Water Cooling System For Jubail 2
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2
syed abdul wahab
 
Final Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptxFinal Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptx
IESGATEWiz
 
PPT_Final_18-02-15
PPT_Final_18-02-15PPT_Final_18-02-15
PPT_Final_18-02-15
Eklavya Misra
 
New Persentation
New PersentationNew Persentation
New Persentation
Tarek Fagal
 
Project Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.pptProject Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.ppt
AkdDeshmukh
 
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 2014112961T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
James Zhang (Chi, Zhang)
 
Pre bid meeting presentation
Pre bid meeting presentationPre bid meeting presentation
Pre bid meeting presentation
Riaz Zalil
 
Ervin Guinit Buagas CV & Resume
Ervin Guinit Buagas CV & ResumeErvin Guinit Buagas CV & Resume
Ervin Guinit Buagas CV & Resume
Ervin Buagas
 
Annexure - Projects
Annexure - ProjectsAnnexure - Projects
Annexure - Projects
Mohit Verma
 
PG Thesis Presentation
PG Thesis PresentationPG Thesis Presentation
PG Thesis Presentation
Kannan Paramasivan
 

Similar to Dec 22 2014 CSLL (20)

T0352 - Al Wajba presentation for the Construction Sequence
T0352 - Al Wajba presentation for the Construction SequenceT0352 - Al Wajba presentation for the Construction Sequence
T0352 - Al Wajba presentation for the Construction Sequence
 
ARENA: Large-scale solar photovoltaics – competitive round
ARENA: Large-scale solar photovoltaics – competitive roundARENA: Large-scale solar photovoltaics – competitive round
ARENA: Large-scale solar photovoltaics – competitive round
 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptx
 
Sample DPR for Hydro Project (10 MW) (2012)
Sample DPR for Hydro Project (10 MW) (2012)Sample DPR for Hydro Project (10 MW) (2012)
Sample DPR for Hydro Project (10 MW) (2012)
 
Project assign 2
Project assign 2Project assign 2
Project assign 2
 
AIWSP presentation SCM 3 11.09.2018 (1).ppt
AIWSP presentation SCM 3  11.09.2018 (1).pptAIWSP presentation SCM 3  11.09.2018 (1).ppt
AIWSP presentation SCM 3 11.09.2018 (1).ppt
 
Water-Wastewater Impact Fees
Water-Wastewater Impact FeesWater-Wastewater Impact Fees
Water-Wastewater Impact Fees
 
Water-Wastewater Impact Fees
Water-Wastewater Impact FeesWater-Wastewater Impact Fees
Water-Wastewater Impact Fees
 
Cu-Boil Pot Upgrade - Closeout Presentation Rev2a
Cu-Boil Pot Upgrade - Closeout Presentation Rev2aCu-Boil Pot Upgrade - Closeout Presentation Rev2a
Cu-Boil Pot Upgrade - Closeout Presentation Rev2a
 
Al Qasr Mall presentation
Al Qasr Mall presentationAl Qasr Mall presentation
Al Qasr Mall presentation
 
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2Ahmed Al Balawi-Sea Water Cooling System For Jubail 2
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2
 
Final Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptxFinal Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptx
 
PPT_Final_18-02-15
PPT_Final_18-02-15PPT_Final_18-02-15
PPT_Final_18-02-15
 
New Persentation
New PersentationNew Persentation
New Persentation
 
Project Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.pptProject Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.ppt
 
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 2014112961T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
 
Pre bid meeting presentation
Pre bid meeting presentationPre bid meeting presentation
Pre bid meeting presentation
 
Ervin Guinit Buagas CV & Resume
Ervin Guinit Buagas CV & ResumeErvin Guinit Buagas CV & Resume
Ervin Guinit Buagas CV & Resume
 
Annexure - Projects
Annexure - ProjectsAnnexure - Projects
Annexure - Projects
 
PG Thesis Presentation
PG Thesis PresentationPG Thesis Presentation
PG Thesis Presentation
 

Dec 22 2014 CSLL

  • 1. Proj : 1460-403-11-111 PM : Kamaruddin DWP Thickener 1 OVERALL PROJECT STATUS MINIMUM REQUIREMENT SCOPE Completion Date Cost Current Approval 31-Dec-14 (IFR) $ 9,811,000 Current Forecast 31-Dec-14 $ 23,403,095 This Week To Date Planned 2.23% 90.55% (IFR) Earned 2.61% 88.91% Continue progress at DWP Thickener Project Continue sandblast and painting inside Thickener tank Continue pulling cable above pipe rack
  • 2. Proj : 80108031 PM : Kamaruddin Portsite VPA #2 (Building) 2 OVERALL PROJECT STATUS Completion Date Cost Current Approval 31-Jul-2015 $ 32,926,000 Current Forecast 7-Aug-2015 $ 32,434,052 This Week To Date Planned 1.22% 42.71% Earned 0.00% 39.90% VPA Building 2nd floor VPA Building E-house preparation before energize Note: No progress within this week due to batchplant at Portsite breakdown since 18 November 2014 and resources allocation except civil crew are dedicated to DWP Thickener project.