1. ANNEXURE
With HEXA Oil and Gas Services L.L.C., Abu Dhabi, UAE As Section Head - Projects
Since Mar’ 14 till to date
Key Role: Managing and Monitoring Project & its Budget, Handling EPC including Testing, Commissioning, Warranty
of the Project, Coordination with Client for Engineering Documents Approval & requirements, Successful
Project completion and timely handover.
Project: Upgrade of 3.3kV switchboards at Substation 2, 3, 6 and 11kV switchboard at Substation 5 at Habshan (0)
Value: AED 19.945 million
Period: Aug 2015 till April 2017
Client: GASCO Habshan ( ADNOC Group of companies )
Role:
. Finalizing the vendors/OEM and Consultants as per Project requirements.
. Organising the Engineering, Construction and Civil teams for the project.
Project: Fire and Gas Maintenance
Value: AED 7.45 million
Period: Aug 2015 till Aug 2018
Client: GASCO Asab ( ADNOC Group of companies )
Role:
. Short listing the appropriate candidates for the client interview.
. Close Coordination with client for Takeover of the Project from its existing Contractor ( Tyco )
Project: ELV Works in Ruwais Housing Complex Expansion 4 for M/s Ghantoot Contracting Company
Value: AED 4.84 million
Period: June 2015 till April 2016
Client: M/s Ghantoot Road Division (End User – ADNOC )
Project: Electrical Works in OS11 WIP Bunduq Off shore Complex.
Value: AED 895k
Period: March 2015 till September 2015.
Client: BUNDUQ
Status: Commissioning under progress.
Project: Electrical and Control Hook ups for new Portacabin at UZSC – ADMA ( ADNOC Group of companies)
Value: AED 790k
Period: Feb 2015 till August 2015.
Client: ADMA – ADNOC Group of Company.
Status: Project under Warranty
Project: Various Electrical Works in Fertil, Ruwais, Abu Dhabi.
Value: AED 4.3 million
Period: June 2014 till November 2015.
Client: Fertil ( ADNOC Group of Companies )
Role:
. Close coordination with vendor and the client for getting the design freeze for the PA system as per the contract.
Project: AMC Contract for the Fire and Gas System for AL HOSN GAS at Shah Gas, Abu Dhabi.
Value: AED 7.45 million
Period: Dec 2014 till Dec 2017.
Client: Al Hosn Gas ( ADNOC Group of Companies )
Role:
. Planning, interview, coordination and mobilisation of team as per contract.
. Monitoring AMC every month once to understand their requirement & needs and keep the motivation level high.
. Conduct detail checks .
2. Project: Solar Lighting Project from HABSHAN 5 T junction to HABSHAN 0 roundabout.
Value: AED 7.2 million
Period: Jan’14 till Oct’14.
Client: GASCO ( ADNOC Group of Companies )
Status: Project under Warranty.
Project: HSE Training Centre at Das Island – Electrical / F&G /Telecom and HVAC works.
Value AED 2.4 million
Period: Apr’14 till Oct’14
Client: ADGAS ( ADNOC Group of Companies )
Main Contractor M/s. Granite Construction company L.L.C.
Status: Project under Warranty.
Project: TCF at Zirku Island – Electrical / F and G AND Telecom Works.
Value AED 2.7 million.
Period: May’14 till Nov 14
Client: ABB Middle East.
Main Contractor M/s. Granite Construction Company L.L.C.
Status: Project Under Warranty.
With Control and Application Emirates Middle East (CAE ME), Abu Dhabi, UAE As Manager Projects (MEP)
Since Dec’08 till Mar’ 14
Key Role: Headed operations related to the design, procurement, installation, testing & commissioning of all the MEP
services as per project requirement, Contract and design specifications, Spearheaded complete MEP
operations like designing, installation, testing, commissioning, procurement, F&G, Telecom sys, Fire fighting
sys, plumbing and drainage sys etc. towards the successful completion and hand over of this project to
client. Managed various functions, viz., project budgeting, manpower selection and building team, annual
appraisal, bonus or the promotion recommendation for the team etc.
Project: Satah Oil field development project at Zirku Island, UAE – Off shore project.
Value: AED 2.1 million
Period: 30th Nov 2012 till 30th Jan 2014.
Client: ZADCO ( ADNOC Group of companies )
Main Contractor Technip
Sub Contractor Granite Construction Co. L.L.C. UAE.
Electrical and Low Voltage System Contractor: CAE ME
Project: Main Control Building Refurbishment work at ASAB 1 – GASCO.
Value: AED 2.19 million
Period: 30th Oct 2013 till 5th May 2014.
Client: GASCO ( ADNOC Group of companies )
Main Contractor ACTCO, UAE
Sub contractor for electrical and Low voltage system – CAE ME
Project: C & C Building and OSAT Works at Zircu Island, UAE – Off shore project.
Value: AED 1.1million
Period: 30th Nov 2013 till 30th May 2014.
Client: ZADCO ( ADNOC Group of Companies )
Main Contractor AIS
Civil Contractor Granite Construction Co L.L.C.
Electrical and Fire & Gas Subcontractor – CAE ME
Project 16 Industrial Facilities Buildings, Habshan 5 Projects in Habshan, UAE
Value AED 115 million
Period Mar’11 till 28th Feb 2013
Client GASCO (Govt. Organization, UAE)
Main Contractor Al Faraa General Cont. International
MEP Contractor CAE ME
3. Project New Management and New Auditorium Bldg., Buhasa, U.A.E
Value AED 17 Million
Period Mar’11 till 9th Dec 2012
Client GASCO (Govt. Organization, UAE)
Main Contractor Al Faraa General Cont. International
MEP Contractor CAE ME
. Collaborated with existing Substation for the power supply to a newly constructed Auxiliary Building and Rerouting
works of existing underground services in addition to MEP operations.
Project Accommodation Facilities – ASAB Phase 2, Asab, U.A.E
Value AED 29 million
Period Mar’10 till 27th Nov 2011
Client Granite Construction Company, UAE
Contractor CAE ME
Role:
. Handled design, procurement, installation, testing and commissioning of all the accommodation Blocks (Junior / senior /
VIP Block) with the total accommodation for nearly 250 persons) and other facilities buildings such as the Recreation
Centre and Masjid (Mosque)
. Remodelling work of the existing Kitchen and recreation buildings.
. Managed electrical package operations including complete designing, procurement, installation, testing, commissioning
of Electrical, F&G, Telecom Activities & EPC of LV Electrical Package including Transformers & LV Boards
Project Non Process Buildings at GASCO Ruwais including Relocation of 33/11KV Transformers
Existing Location at the Elixir Plant to the New 11 KV SWGR, Ruwais, UAE
Value AED 27 million
Period Aug’09 till 23rd Jan 2012
Client GASCO (Govt. organization, UAE)
Main Contractor ASCON, UAE
Electrical Contractor CAE ME
Role:
. Carried out the entire gamut of design, supply, installation, testing and commissioning of LV transformers, LV Panels,
Lighting, Small Power, Earthing and Lightning protection works for the project
. Facilitated installation of 11KV panels and assistance in its commissioning activities to the Vendor
. Relocated:
o 33KV cables as per the SLD and its testing and commissioning
o 33/11KV transformers and its testing and commissioning
Project Civil Works for the Site Preparation and Product Handling Package, Ruwais, U.A.E
Borouge 2 Polyolifins Project – Ruwais
Value AED 7 Million
Period Sep’08 till 22nd
Dec 2009
Client Technimont SPA, Italy
Main Contractor Granite Construction Company, UAE
End User Borouge
Electrical Contractor CAE ME
. Managed entire design, supply, installation testing and commissioning of lighting, Small Power, Earthing and Lightning
Protection System for the Product Handling Building at Borouge 2 Polyolifins Projects, Ruwais.
Project Civil Works for the product handling and site preparation, Ruwais, UAE
Borouge 2 Project – Ruwais
Value AED 1 million
Period Aug’08 till 30th Nov 2009
Client Technimont SPA Italy
Main Contractor Granite Construction Company, UAE
End User Borouge
Electrical Contractor CAE ME
4. Project EPC Contract for Offsite and Utility buildings, Ruwais, UAE
Borouge 2 Project – Ruwais
Value AED 17 million
Period Aug’08 till 30th Jan 2010
Client Technicas Reunidas Spain
Main Contractor Granite Construction Company, UAE
End User Borouge
Electrical Contractor CAE ME
With Wajdi Electrical Contracting Est., Dubai As Project Manager
Since Oct’06 till Dec’08
Project Construction of 11KV / 33KV Sub Station, For Northern Emirates, FEWA (Fujairah Electrical
and Water Authority, U.A.E Govt.)
Period Apr’08 till Dec’08
Client Essa Engineering & Marine Services, UAE
Project Al Zawara Central Power Plant, FEWA (Fujairah Electrical and Water Authority, U.A.E Govt.)
Period Oct’06 till Apr’08
Client Essa Engineering & Marine Services, UAE.
With Toshiba Plant Systems & Services Corporation, Abu Dhabi As Senior Project Engineer
Since Nov’98 till Sep’06
Project Umm Al Nar Independent Water and Power Project , Abu Dhabi, U.A.E
Period May’04 till Sep’06
Client Arabian Power Company
Project Locally awarded contracts at Umm Al Nar West and East Power Stations, Abu Dhabi, U.A.E
Period Nov’02 till May’04
Client Umm Al Nar Power Station Company Abu Dhabi and ITM O & M Company Ltd.
Project PDPM-2 Contract at Umm Al Nar West and East Power Stations, Abu Dhabi, U.A.E
Period Nov’00 till Nov’02
Client Abu Dhabi Water and Electricity Authority (ADWEA, UAE Govt.)
Project PDPM-1 Contract at Umm Al Nar West Power Stations at Abu Dhabi, U.A.E
Period Nov’98 till Nov’00
Client Abu Dhabi Water and Electricity Authority (ADWEA, UAE Govt.)
Project in Kuwait As Project Engineer
Since Sep’96 till Nov’98
Project Az-zour South Distillation Plant with Recarbonation System, Stage 11-4 x 6 MIGPD for Ministry
of Electricity and Water, Az-Zour, Kuwait.
Period Sep’96 till Nov’98
Client MHI, Japan
Projects in India As Project Engineer
Since Jul’94 till Sep’96
Project 3 x 25 MW Captive Power Plants at Panipat Refinery, Panipat, Haryana State
Period Sep’95 till Sep’96
Client National Thermal Power Corporation, NTPC, India
Project 210 MW and 500 MW Thermal Power Stations at Anpara, U.P. State.
Period Jul’94 till Sep’95
Client U.P. State Electricity Board, UPSEB, India