WELCOME TO
OUR PRESENTATION
OIL REFINERY
TANK PROJECT
PRESENTED BY:
RUMAN MAHMUD #ID: 192138
MD. ASHRAFUL ISLAM #ID: 192129
ASIF AHMED SAJAL #ID: 192119
ABU RAYHAN MIAH #ID: 192118
WE WILL DESCRIBE ABOUT THE
INSTALLATION PROCEDURES OF A
RESERVE TANK OF A OIL REFINERY
FACTORY AND IT’S ACTIVITY THAT
HAVE TO BE COMPLETED WITH
THE TIME SCALED DIAGRAM AND
THE PRECEDENCE DIAGRAM.
TIME SCALED DIAGRAM
Description Activity Predecessor Duration
Design Tank
Project
A _ 5
Select Tank
supplier
B A(FS1) 4
Construct Tank
foundation
C A(SS2) 9
Manufacture Tank
Components
D B 5
Preparing
Installation
Drawing
E B(FF1) 2
Deliver Tank
Components
F D(SS2) 2
Assemble Tank G C(FS-1),E,F 7
Test for
Commission Tank
H G 2
“
”
CRITICAL PATH : A → B → D → F → G → H
PRECEDENCE DIAGRAM
THANK YOU

Oil refinery tank project

  • 1.
  • 2.
    OIL REFINERY TANK PROJECT PRESENTEDBY: RUMAN MAHMUD #ID: 192138 MD. ASHRAFUL ISLAM #ID: 192129 ASIF AHMED SAJAL #ID: 192119 ABU RAYHAN MIAH #ID: 192118
  • 3.
    WE WILL DESCRIBEABOUT THE INSTALLATION PROCEDURES OF A RESERVE TANK OF A OIL REFINERY FACTORY AND IT’S ACTIVITY THAT HAVE TO BE COMPLETED WITH THE TIME SCALED DIAGRAM AND THE PRECEDENCE DIAGRAM.
  • 4.
    TIME SCALED DIAGRAM DescriptionActivity Predecessor Duration Design Tank Project A _ 5 Select Tank supplier B A(FS1) 4 Construct Tank foundation C A(SS2) 9 Manufacture Tank Components D B 5 Preparing Installation Drawing E B(FF1) 2 Deliver Tank Components F D(SS2) 2 Assemble Tank G C(FS-1),E,F 7 Test for Commission Tank H G 2
  • 5.
    “ ” CRITICAL PATH :A → B → D → F → G → H PRECEDENCE DIAGRAM
  • 6.