NKW Cu-Boil Pots
Upgrade
Brandon Smith
Senior Project Engineer – NKW Projects
28th February 2012
Overview
NKW Projects – FY12 – NKW Cu-Boil Pots Upgrade Page 2
Project Brief
• Replace the existing vessels during November 2011 Cu-
Boil shutdown:
– D2C-17 (#1 Pot);
– D2C-18 (#2 Pot);
– Existing vessels 40+ years old – asset at end of
serviceable life.
• Basic Scope:
– Improve Material (Duplex SS Grade SAF2205);
– Improve design;
– Improve sparger/ring main fabrication;
– Improve access to area (Confined space
access/Platforms/Stairs).
• Risk Reduction project. (CURA = 90)
• Complex replacement methodology – Brownfield
installation
NKW Projects – FY12 – NKW Cu-Boil Pots Upgrade Page 3
Project Team
Page 4NKW Projects – FY12 – NKW Cu-Boil Pots Upgrade
Project Manager
Brandon Smith
Project Team
Snr Mechnical Project
Engineer
Frederik Mollentze
Electrical Project
Engineer
Katie Singh
Planner/Scheduler
Joe Kopilovic
Mechanical Project
Officer
Allen Terry
Electrical Project
Officer
Tom McClements
Drafting Coordinator
Dean Alexander
EPCM
PROTEUS
Snr Mech Engineer
Tony Balloch
Access Petrotec
Vinod Gupta
GHD
Peeyush Mathur
Fabrication
Specialised Welding
Services
Phil Bell
QA/QC - Welding
Inspector
Jason Buchanan
Mixtec Australia
Parag Dharkar
Crisp Engineering
Alan Crisp
Installation
Installation
Management
GRS
Installation Contractor
(Mech)
Downer
Installation Contractor
(Structural)
Cape
Installation Contractor
(Elec)
Downer
Scaffolding
ATIVO
Freo Cranes
Michael Viachi
Project Sponsor
Jacques du Toit
Stakeholders
Manager -
Maintenance NKW
Johan Snyman
Reliability
Superintendent
Brent Johndahl
Plant Integrity
Marcus Bredenhann
Snr Asset
Improvement
Engineer
Stefan Depre
Snr Integrity Engineer
Leon Mascini
Permit Coordinator -
North
Andrew Garforth
Permits
Lance O'Connor
Production
Coordinator - North
Dragan Supljelav
Zero Harm
TOTAL MAN-HOURS (DIRECT): >18,300hrs (~18 people for 3.5 mths)
• Fabrication Man-hours: >7,000hrs
• Pre-Outage Man-hours: >5,600hrs
• Installation Man-hours: >4,700hrs
• Post-Outage Man-hours: >1,000hrs
First Aid Cases (FAC): 3
• Nickel Rash – repeat FAC from other work
• Scalp Rash – poor hygiene
• Bruised Knee – inexperienced personnel
Incidents: 2
• DMS# 1039441 – Dropped object from height (~4m) within controlled area
• DMS# 1039429 – Contractors Sprayed with process liquor while removing valve
NKW Projects – FY12 – NKW Cu-Boil Pots Upgrade Page 5
Schedule
Definition: ~6 mths
• Approved – 28 Feb 2011
• Target Completion – 29 July 2011
• Actual Completion - 15 July 2011
Execution: ~3.5 mths
• Approved –15 July 2011
• Fabrication: 3 mths (Included material
procurement, fabrication, NDT, lagging, delivery)
• Installation Window: 10 days (31st Oct 2011- 9th
Nov 2011)
• Target Practical Completion – 30 Nov 2011
• Actual Practical Completion - 28 Nov 2011
NKW Projects – FY12 – NKW Cu-Boil Pots Upgrade Page 6
Cost
D2C-17 – No.1 Cu-boil Pot
Actual Total Cost (AUD$ YTD) = 1,835,375
D2C-18 – No.2 Cu-boil Pot
Actual Total Cost (AUD$ YTD) = 1,859,305
NKW Projects – FY12 – NKW Cu-Boil Pots Upgrade Page 7
Phase USD Ex Rate Stretch Target Threshold
Definition 97.19 211,500 235,000 258,200
Execution 103.6 1,534,096 1,704,551 1,875,006
TOTAL
(AUD$)
103.6 1,663,119 1,925,011 2,032,701
Phase USD Ex Rate Stretch Target Threshold
Definition 97.19 211,500 235,000 258,200
Execution 103.6 1,534,096 1,704,551 1,875,006
TOTAL
(AUD$)
103.6 1,663,119 1,925,011 2,032,701
Lessons Learnt - Δ’s
• Aggressive target dates
• Supply/HR issues – verification of contract
information not correct
• Welding (onsite) – workload underestimated / poor
quality of workforce
• Materials – problems with correct identification
and delivery of all materials required (i.e. 7 TPI vs
8 TPI studs)
• Poor workforce interaction –
Maintenance/Operations/Projects
• Scope creep - interaction with surrounding pipe
work & pipe stresses
NKW Projects – FY12 – NKW Cu-Boil Pots Upgrade Page 8
Lessons Learnt - +ve’s
• Zero Harm
• Maximised offsite Fabrication (Modular
approach)
• Dedicated planner/scheduler
• QA/QC – Excellent utilisation of third
party expert
• ITP – Fabrication/Installation
• Identification of quality manufacturer
• Precision Engineering and Installation
NKW Projects – FY12 – NKW Cu-Boil Pots Upgrade Page 9
Outcomes
• Replacement of vessels within aggressive
target dates
• Improved plant reliability
• Increased plant integrity
• Reduced risk: 90 to 3 (No longer a
material risk to NKW)
• Reduced MFL (Maximum Foreseeable
Loss) = $22M to $1M
• Improved maintenance & operational
access to area
NKW Projects – FY12 – NKW Cu-Boil Pots Upgrade Page 10
Overall Outcomes
NKW Projects – FY12 – NKW Cu-Boil Pots Upgrade Page 11
Ongoing Commitment
NKW Projects – FY12 – NKW Cu-Boil Pots Upgrade Page 12

More Related Content

What's hot (20)

CVAQ5
CVAQ5CVAQ5
CVAQ5
 
ROSARIO LEO G_CV
ROSARIO LEO G_CVROSARIO LEO G_CV
ROSARIO LEO G_CV
 
Gana Khaidav -May-2015
Gana Khaidav -May-2015Gana Khaidav -May-2015
Gana Khaidav -May-2015
 
GW Amec Foster Wheeler
GW Amec Foster WheelerGW Amec Foster Wheeler
GW Amec Foster Wheeler
 
CV. Mechincal Engineer
CV. Mechincal EngineerCV. Mechincal Engineer
CV. Mechincal Engineer
 
Leslie Banks 2016
Leslie Banks 2016Leslie Banks 2016
Leslie Banks 2016
 
Resume
ResumeResume
Resume
 
cgts_services
cgts_servicescgts_services
cgts_services
 
Resume Thad Gilbert
Resume Thad GilbertResume Thad Gilbert
Resume Thad Gilbert
 
jahangir
jahangirjahangir
jahangir
 
resume-garychu
resume-garychuresume-garychu
resume-garychu
 
Work Experience
Work ExperienceWork Experience
Work Experience
 
CV_Doug_Mast
CV_Doug_MastCV_Doug_Mast
CV_Doug_Mast
 
Vause Wayne - 6829
Vause Wayne - 6829Vause Wayne - 6829
Vause Wayne - 6829
 
Resume Jaime Lopez 2016
Resume Jaime Lopez 2016Resume Jaime Lopez 2016
Resume Jaime Lopez 2016
 
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 2014112961T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
 
bio data 1
bio data 1bio data 1
bio data 1
 
CV-Balamurugan.
CV-Balamurugan.CV-Balamurugan.
CV-Balamurugan.
 
LarrySmock Resume 3_24_2015
LarrySmock Resume 3_24_2015LarrySmock Resume 3_24_2015
LarrySmock Resume 3_24_2015
 
KDK RES 2016 Sunoco
KDK RES 2016 SunocoKDK RES 2016 Sunoco
KDK RES 2016 Sunoco
 

Similar to NKW Cu-Boil Pots Upgrade Project

Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016
Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016
Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016Khoirul A'mal Mohd Hanafiah
 
Delay analysis of raw water reservoir and pumping Station
Delay analysis of raw water reservoir and pumping StationDelay analysis of raw water reservoir and pumping Station
Delay analysis of raw water reservoir and pumping Stationchetlapally balakrishna
 
Resume_Lead Mechanical Engineer - Static Equipment and Package Units
Resume_Lead Mechanical Engineer - Static Equipment and Package UnitsResume_Lead Mechanical Engineer - Static Equipment and Package Units
Resume_Lead Mechanical Engineer - Static Equipment and Package UnitsNirav Mistry
 
Resume_Lead Mechanical Engineer - Static Equipment and Package Units
Resume_Lead Mechanical Engineer - Static Equipment and Package UnitsResume_Lead Mechanical Engineer - Static Equipment and Package Units
Resume_Lead Mechanical Engineer - Static Equipment and Package UnitsNirav Mistry
 
Ian_Rowell_Resume_June_2015
Ian_Rowell_Resume_June_2015Ian_Rowell_Resume_June_2015
Ian_Rowell_Resume_June_2015Ian Rowell
 
Breiter_Kevin_BreiteK_2016 (D)
Breiter_Kevin_BreiteK_2016 (D)Breiter_Kevin_BreiteK_2016 (D)
Breiter_Kevin_BreiteK_2016 (D)kevin breiter
 
FINAL The Owens Lake Turnout Facility End Cap Budget and Schedule
FINAL The Owens Lake Turnout Facility End Cap Budget and ScheduleFINAL The Owens Lake Turnout Facility End Cap Budget and Schedule
FINAL The Owens Lake Turnout Facility End Cap Budget and ScheduleKook Dean
 
151111 Progress Update WP2 (Bram Westerweel)
151111 Progress Update WP2 (Bram Westerweel)151111 Progress Update WP2 (Bram Westerweel)
151111 Progress Update WP2 (Bram Westerweel)SINTAS
 
Structural Engineer_Duong Quoc Huan_2015
Structural Engineer_Duong Quoc Huan_2015Structural Engineer_Duong Quoc Huan_2015
Structural Engineer_Duong Quoc Huan_2015Huan Duong Quoc
 
Ron Williams CV Feb 2017
Ron Williams CV Feb 2017Ron Williams CV Feb 2017
Ron Williams CV Feb 2017Ron Williams
 
CV-SC-Shaukat Mahmood Khan(5306) January 08,2017
CV-SC-Shaukat Mahmood Khan(5306) January 08,2017CV-SC-Shaukat Mahmood Khan(5306) January 08,2017
CV-SC-Shaukat Mahmood Khan(5306) January 08,2017Shaukat Mahmood Khan
 
SELA Region Q4-2013 Thru-tubing Recompletion and Thru-tubing Workover
SELA Region Q4-2013 Thru-tubing Recompletion  and Thru-tubing WorkoverSELA Region Q4-2013 Thru-tubing Recompletion  and Thru-tubing Workover
SELA Region Q4-2013 Thru-tubing Recompletion and Thru-tubing WorkoverKevin Kelley
 

Similar to NKW Cu-Boil Pots Upgrade Project (20)

Sagar_cv
Sagar_cv Sagar_cv
Sagar_cv
 
Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016
Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016
Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016
 
Working Experience
Working ExperienceWorking Experience
Working Experience
 
Delay analysis of raw water reservoir and pumping Station
Delay analysis of raw water reservoir and pumping StationDelay analysis of raw water reservoir and pumping Station
Delay analysis of raw water reservoir and pumping Station
 
Darrell Resume2014
Darrell Resume2014Darrell Resume2014
Darrell Resume2014
 
Resume_Lead Mechanical Engineer - Static Equipment and Package Units
Resume_Lead Mechanical Engineer - Static Equipment and Package UnitsResume_Lead Mechanical Engineer - Static Equipment and Package Units
Resume_Lead Mechanical Engineer - Static Equipment and Package Units
 
CV
CVCV
CV
 
Resume_Lead Mechanical Engineer - Static Equipment and Package Units
Resume_Lead Mechanical Engineer - Static Equipment and Package UnitsResume_Lead Mechanical Engineer - Static Equipment and Package Units
Resume_Lead Mechanical Engineer - Static Equipment and Package Units
 
Ian_Rowell_Resume_June_2015
Ian_Rowell_Resume_June_2015Ian_Rowell_Resume_June_2015
Ian_Rowell_Resume_June_2015
 
CV_AKSHAY RAJPUT
CV_AKSHAY RAJPUTCV_AKSHAY RAJPUT
CV_AKSHAY RAJPUT
 
hdebelenjr-latest-CV
hdebelenjr-latest-CVhdebelenjr-latest-CV
hdebelenjr-latest-CV
 
Breiter_Kevin_BreiteK_2016 (D)
Breiter_Kevin_BreiteK_2016 (D)Breiter_Kevin_BreiteK_2016 (D)
Breiter_Kevin_BreiteK_2016 (D)
 
Factory built substation case study
Factory built substation case studyFactory built substation case study
Factory built substation case study
 
FINAL The Owens Lake Turnout Facility End Cap Budget and Schedule
FINAL The Owens Lake Turnout Facility End Cap Budget and ScheduleFINAL The Owens Lake Turnout Facility End Cap Budget and Schedule
FINAL The Owens Lake Turnout Facility End Cap Budget and Schedule
 
151111 Progress Update WP2 (Bram Westerweel)
151111 Progress Update WP2 (Bram Westerweel)151111 Progress Update WP2 (Bram Westerweel)
151111 Progress Update WP2 (Bram Westerweel)
 
Structural Engineer_Duong Quoc Huan_2015
Structural Engineer_Duong Quoc Huan_2015Structural Engineer_Duong Quoc Huan_2015
Structural Engineer_Duong Quoc Huan_2015
 
Ron Williams CV Feb 2017
Ron Williams CV Feb 2017Ron Williams CV Feb 2017
Ron Williams CV Feb 2017
 
Final TEAM SLIDE PRESENTATION (1)
Final TEAM  SLIDE PRESENTATION (1)Final TEAM  SLIDE PRESENTATION (1)
Final TEAM SLIDE PRESENTATION (1)
 
CV-SC-Shaukat Mahmood Khan(5306) January 08,2017
CV-SC-Shaukat Mahmood Khan(5306) January 08,2017CV-SC-Shaukat Mahmood Khan(5306) January 08,2017
CV-SC-Shaukat Mahmood Khan(5306) January 08,2017
 
SELA Region Q4-2013 Thru-tubing Recompletion and Thru-tubing Workover
SELA Region Q4-2013 Thru-tubing Recompletion  and Thru-tubing WorkoverSELA Region Q4-2013 Thru-tubing Recompletion  and Thru-tubing Workover
SELA Region Q4-2013 Thru-tubing Recompletion and Thru-tubing Workover
 

NKW Cu-Boil Pots Upgrade Project

  • 1. NKW Cu-Boil Pots Upgrade Brandon Smith Senior Project Engineer – NKW Projects 28th February 2012
  • 2. Overview NKW Projects – FY12 – NKW Cu-Boil Pots Upgrade Page 2
  • 3. Project Brief • Replace the existing vessels during November 2011 Cu- Boil shutdown: – D2C-17 (#1 Pot); – D2C-18 (#2 Pot); – Existing vessels 40+ years old – asset at end of serviceable life. • Basic Scope: – Improve Material (Duplex SS Grade SAF2205); – Improve design; – Improve sparger/ring main fabrication; – Improve access to area (Confined space access/Platforms/Stairs). • Risk Reduction project. (CURA = 90) • Complex replacement methodology – Brownfield installation NKW Projects – FY12 – NKW Cu-Boil Pots Upgrade Page 3
  • 4. Project Team Page 4NKW Projects – FY12 – NKW Cu-Boil Pots Upgrade Project Manager Brandon Smith Project Team Snr Mechnical Project Engineer Frederik Mollentze Electrical Project Engineer Katie Singh Planner/Scheduler Joe Kopilovic Mechanical Project Officer Allen Terry Electrical Project Officer Tom McClements Drafting Coordinator Dean Alexander EPCM PROTEUS Snr Mech Engineer Tony Balloch Access Petrotec Vinod Gupta GHD Peeyush Mathur Fabrication Specialised Welding Services Phil Bell QA/QC - Welding Inspector Jason Buchanan Mixtec Australia Parag Dharkar Crisp Engineering Alan Crisp Installation Installation Management GRS Installation Contractor (Mech) Downer Installation Contractor (Structural) Cape Installation Contractor (Elec) Downer Scaffolding ATIVO Freo Cranes Michael Viachi Project Sponsor Jacques du Toit Stakeholders Manager - Maintenance NKW Johan Snyman Reliability Superintendent Brent Johndahl Plant Integrity Marcus Bredenhann Snr Asset Improvement Engineer Stefan Depre Snr Integrity Engineer Leon Mascini Permit Coordinator - North Andrew Garforth Permits Lance O'Connor Production Coordinator - North Dragan Supljelav
  • 5. Zero Harm TOTAL MAN-HOURS (DIRECT): >18,300hrs (~18 people for 3.5 mths) • Fabrication Man-hours: >7,000hrs • Pre-Outage Man-hours: >5,600hrs • Installation Man-hours: >4,700hrs • Post-Outage Man-hours: >1,000hrs First Aid Cases (FAC): 3 • Nickel Rash – repeat FAC from other work • Scalp Rash – poor hygiene • Bruised Knee – inexperienced personnel Incidents: 2 • DMS# 1039441 – Dropped object from height (~4m) within controlled area • DMS# 1039429 – Contractors Sprayed with process liquor while removing valve NKW Projects – FY12 – NKW Cu-Boil Pots Upgrade Page 5
  • 6. Schedule Definition: ~6 mths • Approved – 28 Feb 2011 • Target Completion – 29 July 2011 • Actual Completion - 15 July 2011 Execution: ~3.5 mths • Approved –15 July 2011 • Fabrication: 3 mths (Included material procurement, fabrication, NDT, lagging, delivery) • Installation Window: 10 days (31st Oct 2011- 9th Nov 2011) • Target Practical Completion – 30 Nov 2011 • Actual Practical Completion - 28 Nov 2011 NKW Projects – FY12 – NKW Cu-Boil Pots Upgrade Page 6
  • 7. Cost D2C-17 – No.1 Cu-boil Pot Actual Total Cost (AUD$ YTD) = 1,835,375 D2C-18 – No.2 Cu-boil Pot Actual Total Cost (AUD$ YTD) = 1,859,305 NKW Projects – FY12 – NKW Cu-Boil Pots Upgrade Page 7 Phase USD Ex Rate Stretch Target Threshold Definition 97.19 211,500 235,000 258,200 Execution 103.6 1,534,096 1,704,551 1,875,006 TOTAL (AUD$) 103.6 1,663,119 1,925,011 2,032,701 Phase USD Ex Rate Stretch Target Threshold Definition 97.19 211,500 235,000 258,200 Execution 103.6 1,534,096 1,704,551 1,875,006 TOTAL (AUD$) 103.6 1,663,119 1,925,011 2,032,701
  • 8. Lessons Learnt - Δ’s • Aggressive target dates • Supply/HR issues – verification of contract information not correct • Welding (onsite) – workload underestimated / poor quality of workforce • Materials – problems with correct identification and delivery of all materials required (i.e. 7 TPI vs 8 TPI studs) • Poor workforce interaction – Maintenance/Operations/Projects • Scope creep - interaction with surrounding pipe work & pipe stresses NKW Projects – FY12 – NKW Cu-Boil Pots Upgrade Page 8
  • 9. Lessons Learnt - +ve’s • Zero Harm • Maximised offsite Fabrication (Modular approach) • Dedicated planner/scheduler • QA/QC – Excellent utilisation of third party expert • ITP – Fabrication/Installation • Identification of quality manufacturer • Precision Engineering and Installation NKW Projects – FY12 – NKW Cu-Boil Pots Upgrade Page 9
  • 10. Outcomes • Replacement of vessels within aggressive target dates • Improved plant reliability • Increased plant integrity • Reduced risk: 90 to 3 (No longer a material risk to NKW) • Reduced MFL (Maximum Foreseeable Loss) = $22M to $1M • Improved maintenance & operational access to area NKW Projects – FY12 – NKW Cu-Boil Pots Upgrade Page 10
  • 11. Overall Outcomes NKW Projects – FY12 – NKW Cu-Boil Pots Upgrade Page 11
  • 12. Ongoing Commitment NKW Projects – FY12 – NKW Cu-Boil Pots Upgrade Page 12