Al Qasr Mall Project
20th Feb. 2012
Al-Qasr Plan
Al Qasr Shopping Centre
Lead Architect: Albert Speer & Partners
Lead Consultant: Saudi Diyar
Main Contractor: Saudi Constructioneers
67,500 m² Land Area
215,000 m² of BUA
76,489.6 m² of Leasable Area
368 Shop/Store
1756 Parking Capacity
Construction Start: May 2008
Expected completion: 31st
Jan 2012
Current Status of Packages
Pkg 6A: SAUDICO- Structural Works
Work In Place 100%
Forecast Completion Date 17-Dec-09
Pkg 6B: SAUDICO- Finishes & MEP Works
Work In Place 98.8%
Forecast Completion Date 15-Feb-12
Pkg 6C: Al Ojaimi- Substation & Cable Works
Work In Place 100%
Forecast Completion Date 30-Oct-11
Project Total of completion all packages: 99.6%
Critical Milestones to Achieve
Completion Date
All Construction Works Completed on or before- 15 Feb 2012
Energize Transformer Rooms- 30 Oct 2011 ( Done)
Telephone Cables and Cabinet- all material delivered & partially installed.
Way finding mock up approval : 04.01.12, 45days for installation after
releasing LOI.
Balance of the interior design packages in Process
Electrical Panel Boards Delivery- 100 % delivered.
Execution of the STC Contract Agreement- awaiting Signature
Finalizing Al Shaya requirements
Finalizing the A/C requirements for the Stores
Finalizing The Food Court Requirement (GAS)
Epoxy Paint- Ground Floor painting
PROJECT: AL QASR MALL
LIST OF POTENTIAL ADDITIONAL WORKS
SN Description Rough Estimated Cost Duration Remarks
1 Fun Zone (Part A) - Waterproofing Awaiting SCE Cost
2 Drop Off area
Awaiting SCE Cost from conceptual drawing
provided by SDC
3 Additional Parking Areas (at North East) Awaiting SCE Cost
4 LPG Central Tank & Services 649,982.00 2 months
SR 649,982 - cost from Supplier/contractor
(AL ROWAFED Est), Excluding Civil works
which still awaiting from SCE
5 Additional HVAC works for Tenant (AL SHAYAH) 6,000,000.00 9 months As proposed by SCE
6 Water and Drainage for 17 shops 590,150.00 10 weeks (2.5 month) As proposed by SCE
7 Additional 4 nos. Panoramic Elevator 12 Months
* includes 1month design period of SDC
* SDC awaiting DAAR's instruction to provide
the design.
Floor
Total
(1)
In Process of
Handing Over
(2)
Total HO To
DAAR-PM (or
skipped)
(3)
Handed Over to
DAAR-PM with
No
Tenant Action
(4)
Handed
Over to
Tenant with
No Further
Action
(5)
Tenant Submitted
Fit Out Design
Drawings
for DAAR Approval
but Did Not Start Fit-
Out Works
(6)
Fit-Out
Works
Started
(7)
Ground Floor 54 2 52 44 2 1 5
First Floor 79 2 77 22 8 0 47
Second Floor 91 1 90 66 4 0 20
Third Floor 140 84 56 38 8 1 9
TOTAL 364 89 275 170 22 2 81
Area of Fit out on board
M2
Total Leasable Area M2 Percentage achieved
33793 76489.6 44.18%
THE KEY PRE-OPENING TASKS NEEDED TO BE
COMPLETED PRIOR TO THE MALL OPENING
Saudi Diyar consultant
Al Qasr Mall Project
Thank You

More Related Content

Similar to Al Qasr Mall presentation

Presentation Sample KAAU
Presentation Sample KAAUPresentation Sample KAAU
Presentation Sample KAAUAbdullah Bakhsh
 
HKIS windows analysis delay-------------
HKIS windows analysis delay-------------HKIS windows analysis delay-------------
HKIS windows analysis delay-------------engmts19861
 
AGTL Project Status and Progress_20-01-2021.pptx
AGTL Project Status and Progress_20-01-2021.pptxAGTL Project Status and Progress_20-01-2021.pptx
AGTL Project Status and Progress_20-01-2021.pptxMdAbuNaser13
 
RCREEE-enerMENA_pgesco profile-rcree
RCREEE-enerMENA_pgesco profile-rcreeRCREEE-enerMENA_pgesco profile-rcree
RCREEE-enerMENA_pgesco profile-rcreeRCREEE
 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptxTalebAlfihan
 
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016Mujahid Ali Akhtar
 
MOHMED EZZ 2014CV
MOHMED EZZ 2014CVMOHMED EZZ 2014CV
MOHMED EZZ 2014CVmohamed ezz
 
QC Engineer Oil Gas
QC Engineer  Oil GasQC Engineer  Oil Gas
QC Engineer Oil GasKader Meeran
 
updated Presentation for NCC-FFP Meeting -Keyal HPP.pptx
updated Presentation  for NCC-FFP Meeting -Keyal HPP.pptxupdated Presentation  for NCC-FFP Meeting -Keyal HPP.pptx
updated Presentation for NCC-FFP Meeting -Keyal HPP.pptxhurain5
 
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptx
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptxFinal Presentation for 1st GMs-PDs Conference 03.02.2023.pptx
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptxhurain5
 
Attachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution PlanAttachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution PlanJames Zhang (Chi, Zhang)
 
Review of PH-16 With CRB.pptx
Review of PH-16 With CRB.pptxReview of PH-16 With CRB.pptx
Review of PH-16 With CRB.pptxMayankGandhi51
 
GSC meeting PM - Final
GSC meeting  PM - FinalGSC meeting  PM - Final
GSC meeting PM - FinalDavid Nderimo
 

Similar to Al Qasr Mall presentation (20)

Presentation Sample KAAU
Presentation Sample KAAUPresentation Sample KAAU
Presentation Sample KAAU
 
Mitigtion Plan Presentation
Mitigtion Plan PresentationMitigtion Plan Presentation
Mitigtion Plan Presentation
 
HKIS windows analysis delay-------------
HKIS windows analysis delay-------------HKIS windows analysis delay-------------
HKIS windows analysis delay-------------
 
Window Analysis @ 30-June-2012
Window Analysis @ 30-June-2012Window Analysis @ 30-June-2012
Window Analysis @ 30-June-2012
 
Monthly Progress Report - September 2014
Monthly Progress Report - September 2014Monthly Progress Report - September 2014
Monthly Progress Report - September 2014
 
AGTL Project Status and Progress_20-01-2021.pptx
AGTL Project Status and Progress_20-01-2021.pptxAGTL Project Status and Progress_20-01-2021.pptx
AGTL Project Status and Progress_20-01-2021.pptx
 
RCREEE-enerMENA_pgesco profile-rcree
RCREEE-enerMENA_pgesco profile-rcreeRCREEE-enerMENA_pgesco profile-rcree
RCREEE-enerMENA_pgesco profile-rcree
 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptx
 
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
 
MOHMED EZZ 2014CV
MOHMED EZZ 2014CVMOHMED EZZ 2014CV
MOHMED EZZ 2014CV
 
SISCO - Presentation SABIC
SISCO - Presentation SABICSISCO - Presentation SABIC
SISCO - Presentation SABIC
 
QC Engineer Oil Gas
QC Engineer  Oil GasQC Engineer  Oil Gas
QC Engineer Oil Gas
 
updated Presentation for NCC-FFP Meeting -Keyal HPP.pptx
updated Presentation  for NCC-FFP Meeting -Keyal HPP.pptxupdated Presentation  for NCC-FFP Meeting -Keyal HPP.pptx
updated Presentation for NCC-FFP Meeting -Keyal HPP.pptx
 
SABER CV
SABER CVSABER CV
SABER CV
 
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptx
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptxFinal Presentation for 1st GMs-PDs Conference 03.02.2023.pptx
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptx
 
Work Experience
Work ExperienceWork Experience
Work Experience
 
Attachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution PlanAttachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution Plan
 
CV
CVCV
CV
 
Review of PH-16 With CRB.pptx
Review of PH-16 With CRB.pptxReview of PH-16 With CRB.pptx
Review of PH-16 With CRB.pptx
 
GSC meeting PM - Final
GSC meeting  PM - FinalGSC meeting  PM - Final
GSC meeting PM - Final
 

Al Qasr Mall presentation

  • 1. Saudi Diyar consultant Al Qasr Mall Project 20th Feb. 2012
  • 3. Al Qasr Shopping Centre Lead Architect: Albert Speer & Partners Lead Consultant: Saudi Diyar Main Contractor: Saudi Constructioneers 67,500 m² Land Area 215,000 m² of BUA 76,489.6 m² of Leasable Area 368 Shop/Store 1756 Parking Capacity Construction Start: May 2008 Expected completion: 31st Jan 2012
  • 4. Current Status of Packages Pkg 6A: SAUDICO- Structural Works Work In Place 100% Forecast Completion Date 17-Dec-09 Pkg 6B: SAUDICO- Finishes & MEP Works Work In Place 98.8% Forecast Completion Date 15-Feb-12 Pkg 6C: Al Ojaimi- Substation & Cable Works Work In Place 100% Forecast Completion Date 30-Oct-11 Project Total of completion all packages: 99.6%
  • 5. Critical Milestones to Achieve Completion Date All Construction Works Completed on or before- 15 Feb 2012 Energize Transformer Rooms- 30 Oct 2011 ( Done) Telephone Cables and Cabinet- all material delivered & partially installed. Way finding mock up approval : 04.01.12, 45days for installation after releasing LOI. Balance of the interior design packages in Process Electrical Panel Boards Delivery- 100 % delivered. Execution of the STC Contract Agreement- awaiting Signature Finalizing Al Shaya requirements Finalizing the A/C requirements for the Stores Finalizing The Food Court Requirement (GAS) Epoxy Paint- Ground Floor painting
  • 6.
  • 7.
  • 8.
  • 9.
  • 10.
  • 11.
  • 12.
  • 13.
  • 14.
  • 15.
  • 16.
  • 17. PROJECT: AL QASR MALL LIST OF POTENTIAL ADDITIONAL WORKS SN Description Rough Estimated Cost Duration Remarks 1 Fun Zone (Part A) - Waterproofing Awaiting SCE Cost 2 Drop Off area Awaiting SCE Cost from conceptual drawing provided by SDC 3 Additional Parking Areas (at North East) Awaiting SCE Cost 4 LPG Central Tank & Services 649,982.00 2 months SR 649,982 - cost from Supplier/contractor (AL ROWAFED Est), Excluding Civil works which still awaiting from SCE 5 Additional HVAC works for Tenant (AL SHAYAH) 6,000,000.00 9 months As proposed by SCE 6 Water and Drainage for 17 shops 590,150.00 10 weeks (2.5 month) As proposed by SCE 7 Additional 4 nos. Panoramic Elevator 12 Months * includes 1month design period of SDC * SDC awaiting DAAR's instruction to provide the design.
  • 18.
  • 19.
  • 20.
  • 21.
  • 22.
  • 23.
  • 24.
  • 25.
  • 26.
  • 27.
  • 28.
  • 29.
  • 30.
  • 31.
  • 32.
  • 33.
  • 34.
  • 35.
  • 36.
  • 37.
  • 38.
  • 39.
  • 40.
  • 41.
  • 42.
  • 43.
  • 44.
  • 45.
  • 46.
  • 47.
  • 48.
  • 49.
  • 50.
  • 51.
  • 52.
  • 53.
  • 54. Floor Total (1) In Process of Handing Over (2) Total HO To DAAR-PM (or skipped) (3) Handed Over to DAAR-PM with No Tenant Action (4) Handed Over to Tenant with No Further Action (5) Tenant Submitted Fit Out Design Drawings for DAAR Approval but Did Not Start Fit- Out Works (6) Fit-Out Works Started (7) Ground Floor 54 2 52 44 2 1 5 First Floor 79 2 77 22 8 0 47 Second Floor 91 1 90 66 4 0 20 Third Floor 140 84 56 38 8 1 9 TOTAL 364 89 275 170 22 2 81 Area of Fit out on board M2 Total Leasable Area M2 Percentage achieved 33793 76489.6 44.18%
  • 55. THE KEY PRE-OPENING TASKS NEEDED TO BE COMPLETED PRIOR TO THE MALL OPENING