This document summarizes the procedures, time, and costs to obtain construction permits for building a warehouse in Kuala Lumpur, Malaysia. There are 15 procedures that must be completed, including obtaining development approval, submitting pre-construction notifications, requesting final inspections, and obtaining clearance letters from various regulatory agencies. On average, the process takes 61 days and costs MYR 2,900 in fees. Utilities connections with water and telecom authorities are additional steps.