1. CV Ngo Viet Thuc3614e5e7-79f2-4fc0-8cf2-af3244a3a626-161109030440
1/12
NGO VIET THUC
1. Current Position : Water Supply/Wastewater and Sanitation Engineer
2. Name Of Firm : CDM International Inc.
3. Name Of Staff : Ngo Viet Thuc
4. Date Of Birth : 10 February 1972 Nationality: Viet Nam
5. Education : 1996, Hanoi University of Civil Engineering
Bachelor of Engineering Science: Water Supply, Sewerage,
drainage and Environmental Engineering Faculty
6. Membership Of
Professional Associations
:
Vietnam Water Supply and Sewerage Association
7. Other Trainings : 2004, Academy of Managers for Construction and Cities - Ministry
of Construction:
Certificate, Further training on Construction Supervision Works
2006, World Bank Institute:
Certificate, Training course on Non-revenue water
2007, Center for training and management development:
Certificate, Bidding competence knowledge
8. Countries Of Work
Experience
: Viet Nam
9. Languages : Speaking Reading Writing
English
Vietnamese
Proficient
Native
Proficient
Native
Proficient
Native
10. Employment Record:
From 2011 : To present
Employer : CDM International Inc.
Position Held : Senior Engineer in the field of Water supply, Sewerage/Drainage,
Sanitation
From 2005 : To 2011
Employer : Social and Environmental Development, Joint Stock Company –
SECO
Position Held : Procurement specialist; Senior Engineer in the field of Water
supply, Sewerage/Drainage, Sanitation and Environment
From 2000 : To 2005
Employer : Consultants – Designers & Contractors Corporation (CDC), Center
of Water Technology and Environment
Position Held : Procurement specialist; Senior Engineer in the field of Water
supply, Sewerage/Drainage, Sanitation and Environment
From 1997 : To 2000
Employer : Consultants – Designers & Contractors Corporation (CDC), Center
of Water Technology and Environment
Position Held : Junior Engineer in the field of Water supply, Sewerage/Drainage,
Sanitation and Environment
From 1996 : To 1997
Employer : H.T. Electrical Engineer Pte.
Position Held : Construction Supervision Engineer
11. Detailed Tasks Assigned:
Mr. Thuc is a Water Supply, Drainage/Sewage and Sanitation Specialist. He has more than 19 years
working experiences about fields:
Hydraulic modeling for water supply and sewage/drainage networks.
Design water supply and sewage/drainage networks and water and wastewater treatment
plants.
Provide technical solutions for the water supply and sewage/drainage systems.
Prepare bidding documents; Evaluate bids and proposals
2. CV Ngo Viet Thuc3614e5e7-79f2-4fc0-8cf2-af3244a3a626-161109030440
2/12
Technical Assistance consultant for the projects as well as PMUs
Mr. Thuc has deeply understood the water supply, sewage/drainage and sanitation sector. He had
been participating in a lot of Water supply, sewage and sanitation projects in Vietnam.
12. Work undertaken that best illustrates capacity to handle the tasks assigned:
Name of assignment or project: Da Nang Sustainable City Development Project
Period 2015
Location Da Nang City
Client PMU of Da Nang City Priority Infrastructure Investment Project
Main features of Project The Project has total budget of US$272.2 million and is expected
to benefit a population of 400,000, including approximately
205,000 women.
The Project comprises 5 components: (i) Drainage and
Wastewater Improvement (Drainage improvement: rehabilitation
of retention lakes, rehabilitation and construction of box culverts
and open canals; and rehabilitation and construction of outlets to
lakes and offshore outlets. Wastewater Collection and
Treatment: construction of house connections to sewerage
networks; construction of wastewater collection and transmission
pipelines; construction of Lien Chieu wastewater treatment plant;
expansion of Hoa Xuan wastewater treatment plant; and
upgrading of existing Son Tra, Hoa Cuong, Phu Loc an Ngu Hanh
Son wastewater treatment plants); (ii) Bus Rapid Transit
Development; (iii) Urban strategic roads; (iv) Technicaal
assistance and Capacity building; and (v) Transferred Activities
of Da Nang Priority Infrastructure Investment Project.
Position held Design Manager for designing Wastewater Treatment Plants (Hoa
Xuan and Lien Chieu) and Interceptors
Activities performed Manage and assist the design team in:
Designing expansion of Hoa Xuan wastewater treatment plant
– Phase 2 with addition of capacity of 40,000m3/day;
Designing Lien Chieu wastewater treatment plant with
capacity of 20,000m3/day;
Designing the interceptors to collect and convey wastewater
from resident areas to Hoa Xuan and Lien Chieu wastewater
treatment plants.
Name of assignment or project: Central Regions Rural Water Supply and Sanitation Sector
Project – ADB
Period 2011 – Present
Location Thanh Hoa, Nghe An, Ha Tinh, Quang Binh, Quang Nam and Binh
Dinh
Client National Center for Rural Water Supply and Environmental
Sanitation
Main features of Project The Project has a total budget of US$50 million and is expected
to provide piped water and hygienic sanitation for about 33
communes in the six provinces: Thanh Hoa, Nghe An, Ha Tinh,
Quang Binh, Quang Nam and Binh Dinh.
The Project comprise 5 components: (i) Construction and
sustainable management and operation of piped water systems;
(ii) Improvement of household and public toilets; (iii)
Improvement of communities’ hygienic practice; (iv)
Strengthening sector planning and implementation capacity; and
(v) Improvement of project management capacity.
Position held Assistant to Team Leader / Senior Water Supply and Sanitation
Specialist / Assistant to Procurement Specialists / Engineering and
ProcurementGroup Leader
Activities performed Prepare guidelines and Guide/Assist and support PPMUs and
their Consultants to preparation of FS report and basic design
documents;
3. CV Ngo Viet Thuc3614e5e7-79f2-4fc0-8cf2-af3244a3a626-161109030440
3/12
Work with PPMUs and assist to manage the subprojects,
including (i) Contract management; (ii) Management of quality
and quantity of construction works; and (iii) Progress
management;
Work with costs estimators to prepare detailed cost schedules;
Assist procurement specialist and PPMUs to prepare the
bidding documents and bid evaluation reports;
Preparation of Subproject Appraisal Reports of the subprojects
Name of assignment or project: Da Nang City Priority Infrastructure Investment Project –
Preparation of CIPRs, Basic Designs, Bidding Plan & Bidding
Documents for Phase 2 of the Project & Preparation of
Hydraulic Model of the Drainage System of the City /
Prevention of Sand Deposition at the Mouth of the Phu Loc
River. (Total Project Value = 218 Million USD)
Year 2011
Location: Da Nang City
Client: PMU of Da Nang City Priority Infrastructure Investment Project
Main project features: The project includes Construction Investment Project Report, Basic
Design, Detailed Design, Biding Plan and Biding Documents for:
Component A – Urban Upgrading 9 Low Income Areas
Component B – Environment Infrastructure Improvement on
drainage, wastewater collection & treatment: provides around
8000 meters of box culvert storm water drains 1500x1500 to
2500x2000 size, dredging and lining of open channels around
1500 meters, plus outfalls to beach in Lien Chieu District, Son
Tra (North) District, Central Area-Thanh Khe/Hai Chau.;
Extension wastewater sewerage systems; 15,000 meters of
interceptor sewers from DN200-400; around 4500 meters of
pressure mains DN200-400; 104 Combined Sewer Overflows
(CSOs, 10 no. submersible pumping stations with capacities from
9 l/s to 130 l/s, together house connections in Lien Chieu (East),
Son Tra (North) and city central areas (Hai Chau/Thanh Khe
district).
Build – Operation (B-0) for 2 new wastewater treatment plants in
Hoa Xuan and Lien Chieu with initial capacity of 20,000m3/day
and ultimate capacity of 320,000 m3 /day for Hoa Xuan and
120,000 m 3/day for Lien Chieu; Upgrading 4 existing WWTPs
(Hoa Cuong, Phu Loc, Son Tra and Ngu Hanh Son);
Component B27 – Preparation of Hydraulic Model of the
Drainage System of the City
Component C – 3 major bridges and 2 highways
Component D – Capacity Building and Project Implementation
Support
Positions held: Assistantto Team Leader / Senior Wastewater Process Specialist
Activities performed: Prepare assessment Report on the existing conditions of four
existing wastewater treatment plants: Hoa Cuong, Phu Loc,
So Tra and Ngu Hanh Son.
Propose the solutions for upgrading the existing wastewater
treatment plants;
Develop basic design and detail design documents for
upgrading wastewater treatment plants, of which to increase
capacity of the Son Tra wastewater treatment plant, to
capacity of 23,000 m3/day, by converting from anaerobic
lagoon process to aerated lagoon process (activated sludge
process) and preparation for bidding documents
Name of assignment or project: Vietnam Urban Water Supply Development Project – World
bank
Year 2010
Location Thanh My and Phu Ninh towns, Quang Nam province
Client Quang Nam Water Supply Company
4. CV Ngo Viet Thuc3614e5e7-79f2-4fc0-8cf2-af3244a3a626-161109030440
4/12
Main features of Project Construction of water supply systems in Thanh My and Phu
Ninh towns, including: raw water intake structure, raw water
transmission pipeline, water treatment plant, water distribution
network.
Position held Team Leader
Activities performed Preparing detail design drawings of raw water intake structure
and water treatment plant, analysis and selection equipment
for water treatment plant;
Preparing detail design report
Supporting the PPMU on technical issues;
Assisting the PPMU to understand the World Bank’s policies
on the implementation of the project.
Name of assignment or project: Vietnam Red River Delta – Rural Water Supply and Sanitation
Programe – Hai Duong sub-project – World bank
Year 2010
Location: Cam Dong commune, Cam Giang district, Ha Duong province
Client: Hai Duong Project management unit for rural water supply and
sanitation
Main project features: Construction of water supply system in Cam Dong commune,
including: raw water intake structure, raw water transmission
pipeline, water treatment plant, water distribution network.
Positions held: Team Leader
Activities performed: Collecting all the required input data, hydraulic modelling for
water distribution network.
Preparing detail design drawings of raw water intake structure
and water treatment plant, analysis and selection equipment
for water treatment plant;
Preparing detail design report
Supporting the PPMU on technical issues;
Assisting the PPMU to understand the World Bank’s policies
on the implementation of the project.
Name of assignment or project: Project “Improvement of Sanitation and Protection of the
Environment of the Towns of Phan Ri Cua and Lien Huong in
Tuy Phong District of Binh Thuan Province” (VIE/04/026/11),
The construction of the sanitation landfill component –
Belgian Technical Cooperation (BTC)
Year 2009
Location: Tuy Phong district, Binh Thuan province
Client: Belgian Technical Cooperation (BTC)
Main project features: Improve conditions of sanitation, environment, poverty and
community development in two towns of Tuy Phong, Binh Thuan
province. The project aims to improve the water supply, drainage,
sanitation and solid waste services. The program will also enhance
community participation in planning, developing, operating and
maintaining urban services, raise environmental awareness;
increase the management capacity of District and District’s Urban
Public Works Management Unit. The solid waste component is one
of the components of the project, the general component’s aims to
ensure almost all of solid waste to be collected, dumped in the
sanitation landfill and environment protected when the landfill
closed.
Positions held: Team Leader – Sanitary Landfill Engineering Specialist
Activities performed: Reviewing the project’s documents, including: Construction
Investment Project Report, Basic Design Report, Basic Design
Drawings, and Detailed Design Documents based on the
information is the sanitation landfill in Tuy Phong District has
phased construction and operation, Phase 1 and Phase 2.
The subject of this assignment is a consultancy in order to
review the cost estimation and detailed design of the
5. CV Ngo Viet Thuc3614e5e7-79f2-4fc0-8cf2-af3244a3a626-161109030440
5/12
construction of a sanitary landfill with 2 cells. More specifically
will the consultant give an answer to the following questions:
- Which construction components have been omitted in the
cost estimation when compared to the original 4 cells
landfill design?
- Are the unit rates and calculations in the cost estimation
correct?
- Are the design documents and specifications clear enough
to allow construction of only 2 cells i.o. 4 cells as originally
planned?
- Do the modifications (decreasing from 4 to 2 cells) cause
additional constraints or problems that need attention
during the construction of the 2 cell landfill? Special
attention is needed for the roads (access to cells 1 and 2)
and the drainage of the whole area and cells 3 and 4.
- Preparing the review report.
Name of assignment or project: Vietnam Urban Water Supply Development Project – World
bank
Year 2009 - 2010
Location: Thai Nguyen, Bac Ninh, Bac Giang, Thanh Hoa, Dak Nong, Lam
Dong, Dak Lak provinces
Client: Management Board for Urban Technical Infrastructure
Development Projects – MoC
Main project features: Enhance the health and economic potential of households by
improving water and household sanitation services, which are
financially and environmentally sustainable, in district towns and
large urban centers. For the urban water sector the project will
introduce a new paradigm based on competition, performance and
cost recovering tariffs. The project comprises 4 components: (i)
Investment in new water supplies for district towns where WSC are
willing to contract out delivery of services through competitive
processes, and in household sanitation, including associated
hygiene education program (the “Competition Route”); (ii)
Investment to improve and expand services in better performing
WSCs (the “Performance Route”); (iii) Establishment of a non-
subsidized water supply and sanitation lending facility; (iv)
Investment in building capacity in the WSS sector; and (v)
Management of project implementation.
Positions held: Assistant to Team Leader / Water Supply - Lead engineering and
Procurement specialist
Activities performed: Participating preparation of Feasibility study and Basic design
documents for subprojects;
Participating preparation of basic design documents: hydraulic
modelling water distribution networks, designing the networks,
analysis and selection equipment for water treatment plant,
and design of water treatment plant
Preparing the procurement plans, bidding documents for
subprojects;
Supporting the PPMUs on the procurement procedures;
Assisting the PPMUs to understand the World Bank’s policies
on the implementation of the project.
Name of assignment or project: Feasibility Study for Hanoi Non-Revenue Water Management
Project – World bank
Year 2008 - 2009
Location: Ha Noi
Client: Ha Noi Water Business Company
Main project features: Prepare/develop the plan of Ha Noi non-revenue water
management. Enhance the performance and management
capacity of Ha Noi Water Business Company in order to reduce the
non-revenue water rate, the details are (i) Assessment and design
of NRW reduction strategy; (ii) Hydraulic analysis of the present
6. CV Ngo Viet Thuc3614e5e7-79f2-4fc0-8cf2-af3244a3a626-161109030440
6/12
system and preliminary design for improvements and expansions;
(iii) Support the Ha Noi Water Business Company and Enterprises
to manage the water supply system by digital data (i.e. by digital
map, database etc.); (iv) Design the Public Private Partnership
contract(s) for outsouring of NRW reduction.
Positions held: Water Supply Engineering Specialist
Activities performed: - Hydraulic modelling of distribution network;
- Preparing basic design documents: designing water
distribution network include transmission mains,
distribution pipelines and the areas with DMAs
- Preparing cost estimation;
- Preparing feasibility study report and other project
documents.
Name of assignment or project: Vietnam Red River Delta – Rural Water Supply and Sanitation
Programe - Technical assistance: Rural Water Supply,
Sanitation and Environment Project in Thai Binh provice –
World bank
Year 2008 – 2009
Location: Thai Binh province
Client: Thai Binh Project Management Unit for Rural Water supply and
Sanitation
Main project features:
The RWSS Program contributes are (a) to support GoV’s efforts to
extend coverage of sustainable water and sanitation facilities; and
(b) ensure effective use of these facilities to achieve enduring
economic and social benefits. These are consistent with the
Government’s National Target Program (NTP) for RWSS.
The development objectives of the overall RWSS Program
interventions are to contribute to improving the quality of life and
alleviating poverty in selected rural communities, through
investments in water supply and sanitation infrastructure, hygiene
and sanitation related behaviour, and capacity building.
The development objective of this Project is to improve water and
household level sanitation services and their effective use in
selected provinces in ways that are financially, technically, and
environmentally sustainable, thereby contributing to poverty
alleviation in participating rural communities.
Positions held: Team leader, Procurement Specialist, Technical Assistance
Consultant Specialist
Activities performed: Assisting the PPMU on:
- Management and coordination of the project;
- Water supply engineering, including design of distribution
network, analysis and selection equipment of water
treatment plant, water treatment process.
- The policies on the project implementation;
- The policies on the procurement procedures
- Evaluating bid documents
- Preparing the Request for Proposals for selecting the
preparation subproject consultant
- Managing finance.
- Ensure that all planning, coordination, and implementation
of Project activities are carried out according to plan, and
reflect the relevant policies, procedures and guidelines of
GOV and World Bank;
- Serve as liaison between the Executing Agency, the
Project Management Unit and Contractors;
- Monitor the progress of all project activities and advise the
PPMU of any potential discrepancies between planning
and implementation;
- Work with the PPMU and relevant Contractors to prepare
periodical reports which meet the requirements of GOV
and World Bank.
7. CV Ngo Viet Thuc3614e5e7-79f2-4fc0-8cf2-af3244a3a626-161109030440
7/12
Name of assignment or project: Construction of Drainage/sewerage and sanitation project in
Minh Duc district town, Hai Phong province – Water supply and
sanitation programme for small towns in Vietnam, funded by
Finland Government
Year 2008
Location: Minh Duc district town – Hai Phong province
Client: Water and Sanitation Project Management Unit in Hai Phong
Main project features: Improve the quality of life of inhabitants in Minh Duc district town
through improvement of drainage and sewerage systems and
household sanitation facilities.
Positions held: Team leader, drainage and sewerage and wastewater treatment
specialist
Activities performed: Detail design of drainage/sewerage systems, including:
- Rehabilitation of existing drainage system and construction
of some new pipelines;
- Construction of new sewerage system: facilities and
pipelines for collecting domestic wastewater from
households; domestic wastewater pumping stations;
wastewater treatment facilities;
- Hydraulic modelling drainage and sewerage systems,
detailed design of networks;
- Analysis and selection equipment of domestic wastewater
pumping stations, detailed design of domestic wastewater
pumping stations and wastewater treatment facilities.
Name of assignment or project: Reviewing the feasibility studies and basic design of “Water
supply projects in Phu Cat and Phu My (Hoc Mon Reservoir)
districts in Binh Dinh province” – Belgian Technical
Cooperation (BTC)
Year 2008
Location: Ha Noi and Binh Dinh province
Client: Belgian Technical Cooperation (BTC)
Main project features: The project objective is to improve the quality of life of inhabitants
in the rural areas by constructing a water supply system.
Positions held: Deputy Team leader - Water supply Engineering Specialist
Activities performed: Reviewing the feasibility study report and basic design
drawings of Phu Cat water supply project in terms of (i)
adequate contents of the report; (ii) technological and
structural basic design and cost estimations for the proposed
construction/installation facilities, including raw water intakes,
pumping stations, water treatment plant, distribution system;
(iii) Financial and economic analysis, including water
production cost calculation and setting up mapping for water
tariff increased for financial sustainability; (iv) proposed
environmental mitigation plan during construction and
operation of water supply system.
Making the comments for improving the feasibility study and
basic design in terms of (i) technical process; (ii) analysis and
selection equipment of distribution network, water treatment
plant and booster pumping stations; (iii) designing the facilities
and distribution network; (iv) financial and economic analysis;
and (v) environment mitigation plan.
Preparing the reviewing report.
Name of assignment or project: Vietnam Urban Water Supply Development Project – Water
Supply Project for 9 towns in Binh Dinh province (Binh Dinh
Sub-project) – World bank
Year 2007 – 2008
Location: Binh Dinh province
Client: Binh Dinh Water Supply Company
Main project features: Enhance the health and economic potential of households by
improving water and household sanitation services, which are
8. CV Ngo Viet Thuc3614e5e7-79f2-4fc0-8cf2-af3244a3a626-161109030440
8/12
financially and environmentally sustainable, in district towns and
large urban centers. For the urban water sector the project will
introduce a new paradigm based on competition, performance and
cost recovering tariffs. The project comprises 4 components: (i)
Investment in new water supplies for district towns where WSC are
willing to contract out delivery of services through competitive
processes, and in household sanitation, including associated
hygiene education program (the “Competition Route”); (ii)
Investment to improve and expand services in better performing
WSCs (the “Performance Route”); (iii) Establishment of a non-
subsidized water supply and sanitation lending facility; (iv)
Investment in building capacity in the WSS sector; and (v)
Management of project implementation
Positions held: Water Supply Engineering Specialist – Construction Supervision
Activities performed: Supervising the quality and quantity of works which were
implemented by contractors. Accompanying by Client and
Contractors checked and taken over the construction works
which were implemented by contractors, including selection of
materials and equipment used for the project, installation of
transmission mains and distribution network, installation of
equipment and technical pipelines in the water treatment
plant, raw water intake structure;
ensure that all planning, coordination, and implementation of
Project activities are carried out according to plan, and reflect
the relevant policies, procedures and guidelines of GOV and
World Bank;
Serve as liaison between the Executing Agency, the Project
Management Unit and Contractors;
Ensure all relevant GOV and World Bank guidelines for quality
control and quality assurance are applied;
Work with the Team Leader, PPMU and relevant Contractors
to prepare periodical reports which meet the requirements of
GOV and World Bank.
Ensure all project-financed construction is done strictly
according to plans, contracts and accepted engineering
construction standards and practice in Viet Nam;
Ensure full records of all assets being built are properly
maintained (e.g., daily reports of contractor activities, quality
and quantities of goods and materials used, equipment
procured and installed, work progress, important progress
milestones) and operations are smoothly carried out to the
satisfaction of the PMU;
Name of assignment or project: Formulation of programe “Capacity strengthening within
Vietnam for the assessment and management of water
resources as basic for rural water supply for poverty
reduction” – Belgian Technical Cooperation (BTC)
Year From August 2007 to October 2007
Location: Binh Dinh, Phu Yen, Ninh Thuan, Ha Nam, Ninh Binh, Nam Dinh
and Thai Binh provinces
Client: Belgian Technical Cooperation (BTC)
Main project features: Strengthen institutional arrangements and build capacity
within MoNRE and its provincial divisions and district bureaus
in order to support the strategic investigation of region water
resources for efficient development so as to reach the VDGs.
Build capacity and enhance MoNRE and provincial
effectiveness in: (i) assessment, management and protection
of region water resources; (ii) strategic planning for
sustainable development and use of surface water and ground
water for poverty reduction; (iii) identification, appraisal and
selection, particularly in terms of comparing the use, of
different water resources from an environmental, social and
9. CV Ngo Viet Thuc3614e5e7-79f2-4fc0-8cf2-af3244a3a626-161109030440
9/12
economical perspective; (iv) strengthen the cooperation with
other Ministries involved in the sector, in particular Ministry of
Agriculture and Rural Development (MaRD) and Ministry of
Construction (MoC); (v) support MoNRE in developing legal
text to further clarify their mandate and responsibilities; (vi)
awareness raising of the needs for the management and
protection of region water resources, in particular the need to
protect water resources from any domestic, agricultural and
industrial pollution through wastewater and solid waste
treatment; (vii) the development and implementation of the
processes for region water information gathering and sharing
within the Ministry, between Ministries and at provincial and
district levels; and (viii) the application of Integrated Water
Resource Management (IWRM) concepts and approaches in
a regional water context.
Positions held: Water supply and Sanitation specialist
Activities performed: Assessing current capacity of assessment and management
water resources within MonRE and DonREs at provinces.
Formulating programme of capacity strengthening for
assessment and management of water resources, including
Formulation Report and Technical and Financial File
Name of assignment or project: Service pipe study in Hanoi, Hai Phong and Ho Chi Minh city –
World Bank
Year 2006
Location: Hanoi, Hai Phong and Ho Chi Minh city
Client: World Bank
Main project features: Objective of project is clear understanding the factors impacted on
water losses which is understood physical losses, inaccuracies of
metered devices mainly on the service pipes at the point of
customer use. This includes in the public and public-private
partnership areas.
Positions held: Team leader, Water supply Specialist
Activities performed: Reviewing the current design and installation practices for
service pipes in Vietnam and internationally and their impact on
water losses. This includes current technical standards,
materials specifications and workmanship requirements,
collection information about the failed service pipes,
comparison of Vietnamese experiences to international
experiences.
Collecting information on the overall stocks of service pipes,
including the available materials in the market and being used
at the water supply companies.
Assessing the specific quality of service pipes for newly and
repaired installations in selected areas of Hanoi, Hai Phong and
Ho Chi Minh City.
Serve as liaison between the World Bank and Consultant
Team.
Ensure all relevant World Bank guidelines for quality control
and quality assurance are applied.
Name of assignment or project: Water supply project for An Lao town – Hai Phong city –
WSPST funded by Finnish Government
Year 2005/2007
Location: An Lao town - Hai Phong City
Client: Water and Sanitation Programme for Small Towns in Vietnam
(WSPST)
Main project features: Enhance the health and economic potential of households by
improving water and household sanitation services, which are
financially and environmentally sustainable, in district towns.
Develop the water supply systems in the district towns of
participated provinces.
10. CV Ngo Viet Thuc3614e5e7-79f2-4fc0-8cf2-af3244a3a626-161109030440
10/12
Positions held: Deputy Team leader - Water Supply Engineering and Procurement
Specialist
Activities performed: Participated in preparing Construction Investment Project
Report, Basic Design documents, including hydraulic
modelling and engineering design water distribution network,
water treatment process, analysis and selection of equipment
used for water treatment plant and design water treatment
plant.
Preparing bidding documents and bidding plan;
Ensure all relevant GOV and Donor guidelines for quality
control and quality assurance are applied;
Name of assignment or project: Construction supervision of Pilot Water Supply Project for Lim
town – Bac Ninh province – World Bank
Year 2006 – 2007
Location: Lim town, Bac Ninh Province
Client: Water Supply and Sanitation Project Management Unit – Bac Ninh
Water Supply and Drainage Company
Main project features: Construct water supply system, including deep well pumping
stations, raw water transmission mains, water treatment plant and
distribution network.
Positions held: Construction Supervision, Water Supply Engineering and
Procurement specialist
Activities performed: Assisting team leader in preparing procurement plan, mutual
consent with other members of consultant team and improving
bidding documents for water supply system.
Analysis and Selection of materials and equipment used for the
project, including materials and equipment used for pipelines and
water treatment plant, detailed design distribution network and
water treatment plant.
Supervising the construction works of water supply system,
including supply and installation technical pipelines and
equipment of water treatment plant, and installation of pipes of
distribution network.
Ensure that all planning, coordination, and implementation of
Project activities are carried out according to plan, and reflect the
relevant policies, procedures and guidelines of GOV and World
Bank;
Serve as liaison between the Executing Agency, the Project
Management Unit and Contractors;
Ensure all relevant GOV and World Bank guidelines for quality
control and quality assurance are applied;
Work with the Team Leader, PPMU and relevant Contractors to
prepare periodical reports which meet the requirements of GOV
and World Bank.
Ensure all project-financed construction is done strictly according
to plans, contracts and accepted engineering construction
standards and practice in Viet Nam;
Ensure full records of all assets being built are properly
maintained (e.g., daily reports of contractor activities, quality and
quantities of goods and materials used, equipment procured and
installed, work progress, important progress milestones) and
operations are smoothly carried out to the satisfaction of the
PMU;
Name of assignment or project: Phu Ly Water Supply Project – ODA Denmark
Year 2003
Location: Ha Nam province
Client: Ha Nam Water Supply Company
Main project features: Construction of water supply system, including transmission mains,
distribution network, raw water intake structure, water treatment
plant with capacity of 15,000m3/day.
11. CV Ngo Viet Thuc3614e5e7-79f2-4fc0-8cf2-af3244a3a626-161109030440
11/12
Positions held: Water Supply Engineering, Site supervision engineer of
construction works
Activities performed: Supervising the quality and quantity of works which were
implemented by contractors. Accompanying by Client and
Contractors checked and taken over the construction works
which were implemented by contractors, including analysis
and selection of materials and equipment used for the project,
installation of transmission mains and distribution network,
installation of equipment and technical pipelines in the water
treatment plant, raw water intake structure.
Ensure that all planning, coordination, and implementation of
Project activities are carried out according to plan, and reflect
the relevant policies, procedures and guidelines of GOV and
Donor;
Serve as liaison between the Executing Agency, the Project
Management Unit and Contractors;
Ensure all relevant GOV and Donor guidelines for quality
control and quality assurance are applied;
Work with the PMU and relevant Contractors to prepare
periodical reports which meet the requirements of GOV and
Donor.
Ensure all project-financed construction is done strictly
according to plans, contracts and accepted engineering
construction standards and practice in Viet Nam;
Ensure full records of all assets being built are properly
maintained (e.g., daily reports of contractor activities, quality
and quantities of goods and materials used, equipment
procured and installed, work progress, important progress
milestones) and operations are smoothly carried out to the
satisfaction of the PMU;
Name of assignment or project: Pilot Water Supply Project for Lim town – Bac Ninh province –
World Bank
Year 2003
Location: Lim town, Bac Ninh Province
Client: World Bank
Main project features: Preparing the Feasibility study reports, Basis design of the water
distribution networks and water treatment plants, preparing the DBL
bidding documents, evaluation of bid documents.
Positions held: Water supply Engineering and Procurement specialist
Activities performed: Participated in preparing Construction Investment Project
Report, Basic Design documents.
Prepared basic design documents: hydraulic modelling water
distribution networks, designing the networks, water treatment
process, analysis and selection equipment used for water
treatment plant, and design of water treatment plant.
Preparing bidding documents and bidding plan.
Ensure all relevant GOV and World Bank guidelines for quality
control and quality assurance are applied;
Name of assignment or project: Construction of infrastructure project of new urban area - Van
Quan, Ha Dong
Year 2002
Location: Ha Tay province
Client: Project management unit zone I – Housing and Urban
Development Corporation
Main project features: Prepare the Detailed design documents of water supply and
drainage/sewerage systems, detailed design documents of internal
roads, electricity supply systems of new urban area.
Positions held: Team leader, Drainage and sewerage specialist
Activities performed: Collecting all the required input data,
12. CV Ngo Viet Thuc3614e5e7-79f2-4fc0-8cf2-af3244a3a626-161109030440
12/12
Designing the drainage and sewerage system, detention
pond.
Preparing the technical design report.
Serve as liaison between the Consultant Team and the Project
Management Unit.
Name of assignment or project: Preparation of the Feasibility study report of
Modification/expansion project of Cao Dinh and Nam Du water
treatment plant
Year 2002
Location: Ha Noi
Client: Ha Noi Water Business Company
Main project features: Design the modification/expansion units of Cao Dinh water
treatment plant and Nam Du water treatment plant, Capacity:
60,000m3/day
Positions held: Water Treatment Engineering of Water treatment plant
Activities performed: Collecting all the required input data; Participating in
preparation of the feasibility study reports, designing the
engineering part of the water treatment plants, preparing the
design reports, including water treatment process, analysis
and selection of equipment used for water treatment plant,
design water treatment plant.
Detailed design of the Cao Dinh water treatment plant.
Ensure all relevant GOV guidelines for quality control and
quality assurance are applied;
Name of assignment or project: Vinh Yen Water Supply Project – ODA Denmark
Year 2001
Location: Vinh Yen town, Vinh Phuc province
Client: Vinh Yen Water Supply Company
Main project features: Design the water supply system, including: Exploitative deep well,
raw water transmission mains, water treatment plant – Capacity of
15,000m3/day, water distribution network.
Positions held: Team leader and Water Supply Engineering Specialist
Activities performed: Detailed design of the raw water transmission main, water
treatment plant, water distribution networks, including water
treatment process, analysis and selection of equipment used
for water treatment plant, analysis and selection of materials
and equipment used for raw water pipelines and distribution
network;
Preparing the design report.
Ensure all relevant GOV guidelines for quality control and
quality assurance are applied;
Serve as liaison between the Consultant Team and the Project
Management Unit
13. Certification
I, the undersigned, certify to the best of my knowledge and belief that:
(i) This CV correctly describes my qualifications and my experience;
(ii) I will undertake this assignment for the duration in terms of the inputs specified for me in the personal
schedule in the annual work plans approved by client in accordance with Vietnam labour law.
(iii) I am not part of the team who wrote the terms of reference for this consulting services assignment;
(iv) I am not sanctioned (ineligible for engagement) by Worlbank
I understand that any willful misstatement described herein may lead to my disqualification or dismissal, if
engaged.