REPUBLIC OF CAMEROON REPUBLIQUE DU CAMEROUN 
PEACE – WORK – FATHERLAND PAIX – TRAVIAL – 
PATIRE 
FOR 
MELUF WATER SUPPLY RE-INFORCEMENT / 
EXTENSION PROJECT 
KUMBO CENTRAL SUB-DIVISION 
BUI DIVISION 
LOCAL AUTHORITY 
DATE: _______________ 
Prepared by: Integrated Rural Community Center for Agriculture(IRCCA) & Meluf 
Water Committee
 Project title: Financial Assistance for the Re-enforcement/ Extension of Meluf village 
 Person/Persons responsible for the project: 
 The Proponent: IRCCA, Meluf water management committee, Meluf village 
Development Association and Tata John –senior civil engineering Technician. 
 Legal Holder of the project: the Inhabitants of Meluf Village 
 Project implementation: Meluf water management Committee. 
1.10 Name and Address of Applicant 
Meluf village Community 
Kumbo Bui Division 
North-West Region, Cameroon 
C/O 
CM Meluf 
P.O. Box 15 Kumbo 
Phone ;(237) 678677269/243 757564 
An application for financial assistance for the re-enforcement and extension of Meluf 
village water project 
We are through this project proposal appealing for financial assistance to enable us re-enforce 
and extend the Meluf village water to the whole community. 
TECHNICAL SPECIFICATION OF PROJECT 
Meluf Water re-enforcement and extension in Kumbo Central Sub-Division – Bui Division, 
North West Region – CAMEROON. 
 Type of Water Supply System: Gravitational 
 Present Population: 6.000 Inhabitants/ Future population 12000 
 Dry season output of the two spring sources: 0.5 Lt. /sec. 
 Network System: Existing Scheme (Water Supply Re-enforcements/Extension 
i 
water project. 
Meluf water management committee 
1.20 Contact Person 
Ngong Edwin Nkainin 
C/O P.O. Box 15 Kumbo 
Phone ;(237) 678677269/ 243 757564 
E-mail: nkainin@yahoo.com 
Dear Friend(s) and collaborators, 
Project). 
Technical Report of Feasibility Studies for MELUF Water Supply Re-enforcement/Extension Project –Kumbo Central Council.
WORK REQUIRED 
 Construction of 02 Spring Catchments 
 Construction of 01 Storage Tank 20m3/inspection Chamber attached. 
 Construction of 08 Public Stand pipes 
 Construction of 01 Common Collection Chamber 
 Supply and Laying of PVC NP. 10 Pressure pipes (4.300m = 4.3km). 
 Construction of 43 indication pillars along the pipeline 
 Supply and equip 01 tool box for the Care-Takers for maintenance 
 Project Consumption, 25 litres/inhabitant/day 
Total cost of the Project to be done: 31,635,000 F CFA Francs CFA 
Partner Amount Percentage 
Francs CFA US D 
Meluf Village Community 7,908,750 17,575 25% 
Principal Funder 23,726,250 71,178,750 75% 
Total Cost of Project 31,635,000 71,196,35 100% 
Meluf is a big village in Nso about 6 kilometres West of Kumbo along the Oku road. It is one 
of the biggest villages that move up Kumbo Town, the administrative headquarters of Bui 
Division. Meluf has a population of about 6.000 inhabitants. This Village accommodates 
fifteen primary schools and one big Technical High School, with a population of about 1600 
students. That means at least 2000 inhabitants of Meluf village are young people between age 
1to 18. Birth rate is about 10 %. 75% of the adult population is active. They are peasant 
farmers and petty traders. The execution of this project depends on this active population. 
THE POPULATION 
S/N VILLAGE PRESENT FUTURE 
1. MELUF 6000 12000 
ii 
 Protection of 02 Spring Catchments 
 Construction of 04 Low Points 
 Construction of 02 High Points 
 Construction of 02 Valve Chambers 
- Ø 63mm: 3.700m 
- Ø 32 mm : 400m 
- Ø 25 mm: 200m 
 Duration of Work: 6 Months 
2.00 Project Cost /Financing 
3.00 Identification of Partners 
3.10 Meluf Village Community 
Technical Report of Feasibility Studies for MELUF Water Supply Re-enforcement/Extension Project –Kumbo Central Council.
1.1 VILLAGE ADMINISTRATION AND INSTITUTIONS: 
Meluf Village is administered by Village Heads such as Shu-Fais, Fais, Sheys, yahs and 
Leaders of all Manjong Houses who are all under the Paramount Fon, His Royal Highness the 
Fon of Nso. The Village Council assist the village Development Association and 
administration in legal and developmental matters. 
1.2 DEVELOPMENT ACTIVITIES: 
The Community is trying to become self-reliant in some of their projects. The following 
projects have been achieved:-the building of: 
 Churches 
 Mosques 
 Primary Schools 
 Nursery Schools 
 Secondary Schools 
 High Schools 
 Health Centre 
 Existing Water Supply 
 Inter quarters/Village Roads 
 Bridges/Culverts Mfu/Manjong Houses etc 
3.20 Problem statement 
- The residents of Meluf Village especially children and women suffer from constant 
diarrhoea, dysentery and stomach problems due to lack of portable water. 
- Late coming to school is rampant among the children 
- Children are unable to study at home after school or do other domestic chores because they 
are tired and exhausted 
- Supper is served late in the night because the women had to fetch water from the far off 
stream after returning from the farms at the end of the day. 
- Growth amongst children is retarded 
5.10 Project Goals 
To reduce the impact and effect of inadequacy of water in Meluf Village Community and 
assure good health and sanitation for the inhabitants 
5.20 Project Objectives 
To re-enforce and provide portable water to the 1200 inhabitants of Meluf Village 
iii 
5.20.1 Specific Objectives and Results 
Technical Report of Feasibility Studies for MELUF Water Supply Re-enforcement/Extension Project –Kumbo Central Council.
By the end of the project, given sufficient funds and proper management, two water 
catchments will be constructed, 08 stand pipes will be erected with sufficient and healthy 
quality water to serve the rest of at least 12000 persons all year round. 
 A management and care-taker committee shall be trained to maintain the water 
 Water borne diseases shall be reduced by at least, 75% 
 School attendance and performance shall improve by more than 50% 
 Meals will be served at proper and appropriate times 
 Children will have time to carry out more domestic chores and study school lessons at 
 Hygiene and Sanitation will improve in the community. 
The Meluf water management Committee and the Village Development Association shall 
coordinate the execution of this project from inception to the end. Some experts (Hydro 
Engineers and Community development technicians) shall be hired to carry out the 
technical studies, sensitize and mobilize the community members as well as the training 
of the management committee. 
Community Contribution 
Masons and plumbers shall be hired to construct the catchments tanks and stand pipe 
installations. Unspecified labour shall be supplied by the able bodied community members. 
They shall do all the excavation, digging and backfilling of trenches and construction of sites 
under the foreman who shall be appointed. A ware house shall be constructed in site for the 
storage of material. There shall be a warehouse man who shall be responsible for the 
purchasing of all the material needed for giving them out to the site foreman as need arises. 
The community development technician shall be in charge of the organization and social 
mobilization of the community members. He/she shall educate and sensitize the community 
members on how to sustain and manage their resources. He/she shall move the community to 
elect a water management committee and train them. Community members shall create an 
account with the local micro-financial institution for the safe keeping of the project funds 
The executive community of the water committee shall be responsible for the judicious use of 
the project funds when the project is handed over to them. Bacteriological and chemical 
analysis of the water shall be carried out by the National Hydro Laboratories in Yaoundé to 
determine and assure water quality. 
The entire project is estimated at 31,635,000 francs CFA. From this amount, we hope to 
obtain from the community a contribution in kind to the amount of 3.665.000 francs CFA and 
in cash, the sum of 4.243.750 francs CFA. In other words, we are appealing to you and your 
organisation for the sum of 23,726,250 to enable us realise this project. You will find the cost 
estimates and other technical details in the project formulation which is enclosed. We should 
be very grateful if you would assist us in this project. We should also like to thank you in 
advance for your kind assistance 
iv 
scheme regularly. 
home. 
6.10 Measures 
Technical Report of Feasibility Studies for MELUF Water Supply Re-enforcement/Extension Project –Kumbo Central Council.
6.20 Sustainability 
The management community shall be trained to oversee the use and maintenance of the water 
scheme. This committee shall be elected for a period of three years renewable. 
 Recalcitrant and delinquent members shall not be re-elected. 
 Each household shall be levied a fixed amount of money each year for the 
 All project funds shall be reserved in a financial institution and only withdrawn for 
the purpose of maintenance when need arises. 
 However there shall be a permanent caretaker who shall be remunerated each month. 
 Committee members shall not be paid. Their services shall be voluntary. 
 The permanent caretaker shall be responsible for water quality control as well as 
construction of all the equipment and asset of the water scheme except money and 
bank books. 
The Meluf water management Committee and the village Development Association shall 
appoint a Project coordinator who shall oversee each and every step of this project. He/she 
shall coordinate the activities of all the stakeholders and report to hierarchy. He/she shall be 
answerable and responsible to the general coordinator who endorses and reports to the 
donors. Each stage or element of the project shall be evaluated to satisfaction before 
progressing to the next. The project will have to respect strictly the technical prescriptions as 
well as budgetary lines. At the end of the project a thorough technical inspection and 
financial auditing shall be made by hired experts before the project is handed over to the 
community. 
v 
maintenance of the scheme. 
Monitoring and Evaluation 
Technical Report of Feasibility Studies for MELUF Water Supply Re-enforcement/Extension Project –Kumbo Central Council.
1.3 REASON FOR THE APPEAL: 
The people of Meluf Village had their water before nineteen eighties from streams and springs 
flowing through the grass and forest area. This contaminated water was considered very clean 
during this period. 
The village initiated their Water Project in the early eighties because streams and springs were 
silted up by erosion, too much deforestation, grazing, and grass cutting and burning in search of 
farm, and building land. 
As time went on, this scheme became irregular in supplying water to the inhabitants due to 
shortages of water caused by rapid increase in the population. 
Some spring sources were again studied above the Village. The springs at Tahshwer, Mbohaveiy 
were studied and constructed to reinforce the system .The problem was not solved and the villagers 
kept on suffering worst during the dry season. 
It is against this background that the Water Management Committee, the Village Development 
Association and the Councillor of the area contacted the Technicians in April 2013 for the 
feasibility studies and Technical advice. A technical report was established on the 18/10/2013with 
an estimated cost of about 31,635,000 Frs. CFA. 
1.4 PRESENT WATER CONDITION OF THE VILLAGE: 
At the moment more than 75% of the population is living on polluted water. Water rationing has 
become the other of the day. Due to water shortages some people are fetching water from far off 
springs and streams which are exposed to pollution. 
3.0 SUPERVISION: 
3.0 Monitoring and Evaluation 
The Meluf village Development association and the Meluf water Development committee shall 
appoint a Water Project coordinator who shall oversee each and every step of this project. He/she 
shall coordinate the activities of all the stakeholders and report to hierarchy. He/she shall be 
answerable and responsible to the country coordinator who endorses and reports to the donors. 
Each stage or element of the project shall be evaluated to satisfaction before progressing to the 
next. The project will have to respect strictly the technical prescriptions as well as budgetary lines. 
At the end of the project a thorough technical inspection and financial auditing shall be made by 
hired experts before the project is handed over to the community. 
1 
. 
Technical Report of Feasibility Studies for MELUF Water Supply Re-enforcement/Extension Project –Kumbo Central Council.
3.1 TECHNICAL REPORT: 
This particular Water Supply Re-enforcement / Extension Scheme is being designed to function by 
gravity, that means water will flow from the two Spring Catchments to the Common Collection 
Chamber and to the Storage Tank 20m3 and from there to the Collection Points in the Village for 
the population for consumption through PVC pipes (N.P. 10) of various sizes. 
Galvanize pipes are used for installation of Catchment, Low points and High points, Collection 
Chamber, Storage Tank, Valve Chambers and Public Stand pipes, etc. 
3.2 PROJECT PROPOSED STRUCTURES: 
The Project structures to be done will include:- 
 02 Spring Catchments 
 04 Low Points 
 02 High Points 
 01 Storage Tank 20m3 
 02 Valve Chambers 
 08 Stand Pipes 
 01 Collection Chamber 
 4.3km pipeline/distribution network 
 43 Indication Pillars along the proposed pipe line. 
 01 Equipped tool box for Care-Taker for Maintenance 
 02 Spring Catchments Protection 
ESTIMATES OF COST AND QUANTITIES FOR THE WATER PROJECT AT 
MELUF VILLAGE KUMBO, BUI DIVISION, NORTH WEST REGION 
No List of works and supplies U Qty U.P T.P 
I Preliminary Works 
101 Studies Ls 1 250,000 250,000 
102 Site installation Ls 1 250,000 250,000 
SUB-TOTAL I 500,000 
II INFRASTRUCTURE 
201 Construction of catchments u 2 900,000 1,800,000 
202 Catchment protection ff 2 300,000 600,000 
203 Construction of Stream Crossing u 4 100,000 400,000 
204 Construction of valve chambers u 2 120,000 240,000 
205 Construction of stand pipes u 8 250,000 2,000,000 
206 Construction of low point u 2 130,000 260,000 
2 
4.00 Budget and Financing plan 
4.1 Budget 
Technical Report of Feasibility Studies for MELUF Water Supply Re-enforcement/Extension Project –Kumbo Central Council.
207 Construction of high points u 1 100,000 100,000 
Sub-Total II 5,400,000 
III PLUMBING WORK 
301 PVC Pipes D 63 mm NP 10 ml 1200 4,000 4,800,000 
302 PVC Pipes D 50 mm NP 10 ml 1800 3,000 5,400,000 
303 PVC Pipes D 32 mm NP 10 ml 1360 2,000 2,720,000 
304 PVC Pipes D 25 mm NP 10 ml 600 1,500 900,000 
305 GI Pipes D 1 and ½ inches ml 40 7,000 280,000 
Sub-Total III 14,100,000 
IV EXCAVATION AND BACKFILLING OF 
CO Operation Months Cost 
401 Excavation and Backfilling of Network ml 5000 100 500,000 
402 Excavation and Backfilling of Network ml 5000 100 500,000 
SUB-TOTAL IV 1,000,000 
V OTHERS SUPPLEMENTARY WORKS 
501 Training of management committee Is 1 200,000 200,000 
502 Bacteriogical and chemical analyses of water Is 1 400,000 400,000 
503 Supply of tool box Is 1 150,000 150,000 
504 Elaboration of technical plan Is 1 150,000 150,000 
505 Test run Is 1 100,000 100,000 
SUB-TOTAL V 1,000,000 
Total Excluding Taxes 22,000,000 
V.A.T=19.25% 9,635,000 
Total including Taxes 31,635,000 
Grand Total of the project 31,635,000 
Estimates Closed at: Thirty one Million Six Hundred and Thirty Five Thousand (31,635,000 F 
CFA) Francs CFA 
S/N Partner Amount Percentage 
Francs CFA US D 
1,581,750 3163.5 5% 
2. Principal Funder 30,053,250 60,106.5 95% 
Total Cost of Project 31,635,000 63,270 100% 
3 
NETWORK 
4.2 Financing Plan 
1, Meluf Village 
community 
5.0 Physical and Financial Evolution 
Technical Report of Feasibility Studies for MELUF Water Supply Re-enforcement/Extension Project –Kumbo Central Council.
DE 1 2 3 4 5 6 
101 Studies and Site Installations x 500,000 
102 Infrastructural works x x x 5,400,000 
103 Plumbing works x x 14,100,000 
104 Excavation and Backfilling of Network x x 1,000,000 
105 Training of Management Committee x 200,000 
106 Quality control of water x 400,000 
107 Tool box x 150,000 
108 Elaboration of Technical plan x x 150,000 
109 Test run x 100,000 
110 Documentation/Taxes on Resources x x x x x x 7,035,000 
111 Monitoring/Evaluation x x x x x x x x 2,000,000 
5.0 ANALYSIS OF CONSTRUCTION SEQUENCE OF PROJECT: 
5.1 SPRING CATCHMENT: 
Spring Sources are located above the level of the Village and can supply water to the Community 
by gravity. All Construction works of the Catchment will be of stone masonry except for the top 
slab and foundation that will be of re-enforced concrete. Control or inspection chamber will be 
attached to the catchment. 
5.2 PUBLIC STAND PIPES: 
The standpipes will be placed at 300 to 500 meters to serve public places like schools, Missions, 
Health Centres and market places according to technical requirements. 
5.3 HYDRAULIC INSTALLATION: 
The main pipeline and major branches of the pipeline will be installed with PVC pipes (N.P. 10) of 
various sizes. Galvanized pipes will be used at installation of Catchments, Storage tank, Valve 
Chambers, High points, Low points, Public Standpipes etc. 
4 
Technical Report of Feasibility Studies for MELUF Water Supply Re-enforcement/Extension Project –Kumbo Central Council.
6.0 FINAL REMARKS AND CONCLUSION 
The entire project is estimated at 31,635,000 francs CFA. We hope to obtain the population the 
contribution in kind and in cash to the sum of 1,581,750 francs CFA as required by Engineers 
Without Borders. (5%) We are appealing to you and your organisation for the sum of 30,053,250 
francs CFA, (75%) to enable us realizes this project. We therefore send this project to our various 
friends and benefactors to consider assisting us financially, materially and morally to execute this 
project. 
5 
Technical Report of Feasibility Studies for MELUF Water Supply Re-enforcement/Extension Project –Kumbo Central Council.

More Related Content

Viewers also liked

Kak lyudi schitayut_vremya
Kak lyudi schitayut_vremyaKak lyudi schitayut_vremya
Kak lyudi schitayut_vremyatahtabaev
 
Лекции Бизнес Инкубатора ВШЭ - Лекция Юлии Молчановой
Лекции Бизнес Инкубатора ВШЭ - Лекция Юлии МолчановойЛекции Бизнес Инкубатора ВШЭ - Лекция Юлии Молчановой
Лекции Бизнес Инкубатора ВШЭ - Лекция Юлии МолчановойNikolay Gerzhan
 
EL MOVIMIENTO DE LA TIERRA
EL MOVIMIENTO DE LA TIERRAEL MOVIMIENTO DE LA TIERRA
EL MOVIMIENTO DE LA TIERRAbel2014medina
 
Vlast i narod_rossyschkoy_imperii
Vlast i narod_rossyschkoy_imperiiVlast i narod_rossyschkoy_imperii
Vlast i narod_rossyschkoy_imperiitahtabaev
 
Zimny peyzazh
Zimny peyzazhZimny peyzazh
Zimny peyzazhtahtabaev
 
Nakhozhdenie chasti chisla_i_chisla_ro_ego_chasti
Nakhozhdenie chasti chisla_i_chisla_ro_ego_chastiNakhozhdenie chasti chisla_i_chisla_ro_ego_chasti
Nakhozhdenie chasti chisla_i_chisla_ro_ego_chastitahtabaev
 
Ekaterina velikaya
Ekaterina velikayaEkaterina velikaya
Ekaterina velikayatahtabaev
 

Viewers also liked (9)

Kak lyudi schitayut_vremya
Kak lyudi schitayut_vremyaKak lyudi schitayut_vremya
Kak lyudi schitayut_vremya
 
Лекции Бизнес Инкубатора ВШЭ - Лекция Юлии Молчановой
Лекции Бизнес Инкубатора ВШЭ - Лекция Юлии МолчановойЛекции Бизнес Инкубатора ВШЭ - Лекция Юлии Молчановой
Лекции Бизнес Инкубатора ВШЭ - Лекция Юлии Молчановой
 
EL MOVIMIENTO DE LA TIERRA
EL MOVIMIENTO DE LA TIERRAEL MOVIMIENTO DE LA TIERRA
EL MOVIMIENTO DE LA TIERRA
 
Vlast i narod_rossyschkoy_imperii
Vlast i narod_rossyschkoy_imperiiVlast i narod_rossyschkoy_imperii
Vlast i narod_rossyschkoy_imperii
 
Doli
DoliDoli
Doli
 
Ibrahim Tarek
Ibrahim TarekIbrahim Tarek
Ibrahim Tarek
 
Zimny peyzazh
Zimny peyzazhZimny peyzazh
Zimny peyzazh
 
Nakhozhdenie chasti chisla_i_chisla_ro_ego_chasti
Nakhozhdenie chasti chisla_i_chisla_ro_ego_chastiNakhozhdenie chasti chisla_i_chisla_ro_ego_chasti
Nakhozhdenie chasti chisla_i_chisla_ro_ego_chasti
 
Ekaterina velikaya
Ekaterina velikayaEkaterina velikaya
Ekaterina velikaya
 

Similar to Meluf water Committee project

Pader SCAP100 Stakeholder Engagement Report
Pader SCAP100 Stakeholder Engagement ReportPader SCAP100 Stakeholder Engagement Report
Pader SCAP100 Stakeholder Engagement ReportFesto Wasukira
 
Integrated Community Water-Sanitation for Luanda: June 11, 2013
 Integrated Community Water-Sanitation for Luanda: June 11, 2013 Integrated Community Water-Sanitation for Luanda: June 11, 2013
Integrated Community Water-Sanitation for Luanda: June 11, 2013Development Workshop Angola
 
M & E Power Point Presentation
M & E Power Point PresentationM & E Power Point Presentation
M & E Power Point PresentationBeryl Odhiambo
 
IndiaDWSGeneva.pdf
IndiaDWSGeneva.pdfIndiaDWSGeneva.pdf
IndiaDWSGeneva.pdfZiddamzzz
 
Session SDM - Juntopas.Thailand rural water supply 21
Session SDM - Juntopas.Thailand rural water supply 21Session SDM - Juntopas.Thailand rural water supply 21
Session SDM - Juntopas.Thailand rural water supply 21IRC
 
Community based water supply and management system case istanbul
Community based water supply and management system case istanbulCommunity based water supply and management system case istanbul
Community based water supply and management system case istanbulAnn Obae
 
Jal Jeevan Mission Concept.pptx
Jal Jeevan Mission Concept.pptxJal Jeevan Mission Concept.pptx
Jal Jeevan Mission Concept.pptxDevendraDhapola1
 
4. local participation in agricultural water management in the red river delta
4. local participation in agricultural water management in the red river delta4. local participation in agricultural water management in the red river delta
4. local participation in agricultural water management in the red river deltaCPWF Mekong
 
Project title Project Management
Project title Project Management Project title Project Management
Project title Project Management Tofik Yusuf
 
Clean Water Initiative Overview
Clean Water Initiative OverviewClean Water Initiative Overview
Clean Water Initiative Overviewtofcolchester
 
8 promising innovative initiatives at the 2015 World Water Forum
8 promising innovative initiatives at the 2015 World Water Forum8 promising innovative initiatives at the 2015 World Water Forum
8 promising innovative initiatives at the 2015 World Water Forumopen_resource by SUEZ
 

Similar to Meluf water Committee project (20)

Pader SCAP100 Stakeholder Engagement Report
Pader SCAP100 Stakeholder Engagement ReportPader SCAP100 Stakeholder Engagement Report
Pader SCAP100 Stakeholder Engagement Report
 
Proposed financing solution to the clean water challenge
Proposed financing solution to the clean water challengeProposed financing solution to the clean water challenge
Proposed financing solution to the clean water challenge
 
Integrated Community Water-Sanitation for Luanda: June 11, 2013
 Integrated Community Water-Sanitation for Luanda: June 11, 2013 Integrated Community Water-Sanitation for Luanda: June 11, 2013
Integrated Community Water-Sanitation for Luanda: June 11, 2013
 
M & E Power Point Presentation
M & E Power Point PresentationM & E Power Point Presentation
M & E Power Point Presentation
 
IndiaDWSGeneva.pdf
IndiaDWSGeneva.pdfIndiaDWSGeneva.pdf
IndiaDWSGeneva.pdf
 
Session SDM - Juntopas.Thailand rural water supply 21
Session SDM - Juntopas.Thailand rural water supply 21Session SDM - Juntopas.Thailand rural water supply 21
Session SDM - Juntopas.Thailand rural water supply 21
 
gturockers-5
gturockers-5gturockers-5
gturockers-5
 
Community based water supply and management system case istanbul
Community based water supply and management system case istanbulCommunity based water supply and management system case istanbul
Community based water supply and management system case istanbul
 
Jal Jeevan Mission Concept.pptx
Jal Jeevan Mission Concept.pptxJal Jeevan Mission Concept.pptx
Jal Jeevan Mission Concept.pptx
 
KgpKnights
KgpKnightsKgpKnights
KgpKnights
 
Coady presentation sri lanka
Coady presentation sri lankaCoady presentation sri lanka
Coady presentation sri lanka
 
explorers
explorersexplorers
explorers
 
4. local participation in agricultural water management in the red river delta
4. local participation in agricultural water management in the red river delta4. local participation in agricultural water management in the red river delta
4. local participation in agricultural water management in the red river delta
 
Project title Project Management
Project title Project Management Project title Project Management
Project title Project Management
 
Clean Water Initiative Overview
Clean Water Initiative OverviewClean Water Initiative Overview
Clean Water Initiative Overview
 
Operationalizing community-driven Multiple-Use Water Services (MUS) in South ...
Operationalizing community-driven Multiple-Use Water Services (MUS) in South ...Operationalizing community-driven Multiple-Use Water Services (MUS) in South ...
Operationalizing community-driven Multiple-Use Water Services (MUS) in South ...
 
SustSan workshop: Integrated Urban Water Management by Ankur Gupta
SustSan workshop:  Integrated Urban Water Management by Ankur GuptaSustSan workshop:  Integrated Urban Water Management by Ankur Gupta
SustSan workshop: Integrated Urban Water Management by Ankur Gupta
 
Swaksh1
Swaksh1Swaksh1
Swaksh1
 
Experience and situation of wate management in rural districts of Same & Kigo...
Experience and situation of wate management in rural districts of Same & Kigo...Experience and situation of wate management in rural districts of Same & Kigo...
Experience and situation of wate management in rural districts of Same & Kigo...
 
8 promising innovative initiatives at the 2015 World Water Forum
8 promising innovative initiatives at the 2015 World Water Forum8 promising innovative initiatives at the 2015 World Water Forum
8 promising innovative initiatives at the 2015 World Water Forum
 

Meluf water Committee project

  • 1. REPUBLIC OF CAMEROON REPUBLIQUE DU CAMEROUN PEACE – WORK – FATHERLAND PAIX – TRAVIAL – PATIRE FOR MELUF WATER SUPPLY RE-INFORCEMENT / EXTENSION PROJECT KUMBO CENTRAL SUB-DIVISION BUI DIVISION LOCAL AUTHORITY DATE: _______________ Prepared by: Integrated Rural Community Center for Agriculture(IRCCA) & Meluf Water Committee
  • 2.  Project title: Financial Assistance for the Re-enforcement/ Extension of Meluf village  Person/Persons responsible for the project:  The Proponent: IRCCA, Meluf water management committee, Meluf village Development Association and Tata John –senior civil engineering Technician.  Legal Holder of the project: the Inhabitants of Meluf Village  Project implementation: Meluf water management Committee. 1.10 Name and Address of Applicant Meluf village Community Kumbo Bui Division North-West Region, Cameroon C/O CM Meluf P.O. Box 15 Kumbo Phone ;(237) 678677269/243 757564 An application for financial assistance for the re-enforcement and extension of Meluf village water project We are through this project proposal appealing for financial assistance to enable us re-enforce and extend the Meluf village water to the whole community. TECHNICAL SPECIFICATION OF PROJECT Meluf Water re-enforcement and extension in Kumbo Central Sub-Division – Bui Division, North West Region – CAMEROON.  Type of Water Supply System: Gravitational  Present Population: 6.000 Inhabitants/ Future population 12000  Dry season output of the two spring sources: 0.5 Lt. /sec.  Network System: Existing Scheme (Water Supply Re-enforcements/Extension i water project. Meluf water management committee 1.20 Contact Person Ngong Edwin Nkainin C/O P.O. Box 15 Kumbo Phone ;(237) 678677269/ 243 757564 E-mail: nkainin@yahoo.com Dear Friend(s) and collaborators, Project). Technical Report of Feasibility Studies for MELUF Water Supply Re-enforcement/Extension Project –Kumbo Central Council.
  • 3. WORK REQUIRED  Construction of 02 Spring Catchments  Construction of 01 Storage Tank 20m3/inspection Chamber attached.  Construction of 08 Public Stand pipes  Construction of 01 Common Collection Chamber  Supply and Laying of PVC NP. 10 Pressure pipes (4.300m = 4.3km).  Construction of 43 indication pillars along the pipeline  Supply and equip 01 tool box for the Care-Takers for maintenance  Project Consumption, 25 litres/inhabitant/day Total cost of the Project to be done: 31,635,000 F CFA Francs CFA Partner Amount Percentage Francs CFA US D Meluf Village Community 7,908,750 17,575 25% Principal Funder 23,726,250 71,178,750 75% Total Cost of Project 31,635,000 71,196,35 100% Meluf is a big village in Nso about 6 kilometres West of Kumbo along the Oku road. It is one of the biggest villages that move up Kumbo Town, the administrative headquarters of Bui Division. Meluf has a population of about 6.000 inhabitants. This Village accommodates fifteen primary schools and one big Technical High School, with a population of about 1600 students. That means at least 2000 inhabitants of Meluf village are young people between age 1to 18. Birth rate is about 10 %. 75% of the adult population is active. They are peasant farmers and petty traders. The execution of this project depends on this active population. THE POPULATION S/N VILLAGE PRESENT FUTURE 1. MELUF 6000 12000 ii  Protection of 02 Spring Catchments  Construction of 04 Low Points  Construction of 02 High Points  Construction of 02 Valve Chambers - Ø 63mm: 3.700m - Ø 32 mm : 400m - Ø 25 mm: 200m  Duration of Work: 6 Months 2.00 Project Cost /Financing 3.00 Identification of Partners 3.10 Meluf Village Community Technical Report of Feasibility Studies for MELUF Water Supply Re-enforcement/Extension Project –Kumbo Central Council.
  • 4. 1.1 VILLAGE ADMINISTRATION AND INSTITUTIONS: Meluf Village is administered by Village Heads such as Shu-Fais, Fais, Sheys, yahs and Leaders of all Manjong Houses who are all under the Paramount Fon, His Royal Highness the Fon of Nso. The Village Council assist the village Development Association and administration in legal and developmental matters. 1.2 DEVELOPMENT ACTIVITIES: The Community is trying to become self-reliant in some of their projects. The following projects have been achieved:-the building of:  Churches  Mosques  Primary Schools  Nursery Schools  Secondary Schools  High Schools  Health Centre  Existing Water Supply  Inter quarters/Village Roads  Bridges/Culverts Mfu/Manjong Houses etc 3.20 Problem statement - The residents of Meluf Village especially children and women suffer from constant diarrhoea, dysentery and stomach problems due to lack of portable water. - Late coming to school is rampant among the children - Children are unable to study at home after school or do other domestic chores because they are tired and exhausted - Supper is served late in the night because the women had to fetch water from the far off stream after returning from the farms at the end of the day. - Growth amongst children is retarded 5.10 Project Goals To reduce the impact and effect of inadequacy of water in Meluf Village Community and assure good health and sanitation for the inhabitants 5.20 Project Objectives To re-enforce and provide portable water to the 1200 inhabitants of Meluf Village iii 5.20.1 Specific Objectives and Results Technical Report of Feasibility Studies for MELUF Water Supply Re-enforcement/Extension Project –Kumbo Central Council.
  • 5. By the end of the project, given sufficient funds and proper management, two water catchments will be constructed, 08 stand pipes will be erected with sufficient and healthy quality water to serve the rest of at least 12000 persons all year round.  A management and care-taker committee shall be trained to maintain the water  Water borne diseases shall be reduced by at least, 75%  School attendance and performance shall improve by more than 50%  Meals will be served at proper and appropriate times  Children will have time to carry out more domestic chores and study school lessons at  Hygiene and Sanitation will improve in the community. The Meluf water management Committee and the Village Development Association shall coordinate the execution of this project from inception to the end. Some experts (Hydro Engineers and Community development technicians) shall be hired to carry out the technical studies, sensitize and mobilize the community members as well as the training of the management committee. Community Contribution Masons and plumbers shall be hired to construct the catchments tanks and stand pipe installations. Unspecified labour shall be supplied by the able bodied community members. They shall do all the excavation, digging and backfilling of trenches and construction of sites under the foreman who shall be appointed. A ware house shall be constructed in site for the storage of material. There shall be a warehouse man who shall be responsible for the purchasing of all the material needed for giving them out to the site foreman as need arises. The community development technician shall be in charge of the organization and social mobilization of the community members. He/she shall educate and sensitize the community members on how to sustain and manage their resources. He/she shall move the community to elect a water management committee and train them. Community members shall create an account with the local micro-financial institution for the safe keeping of the project funds The executive community of the water committee shall be responsible for the judicious use of the project funds when the project is handed over to them. Bacteriological and chemical analysis of the water shall be carried out by the National Hydro Laboratories in Yaoundé to determine and assure water quality. The entire project is estimated at 31,635,000 francs CFA. From this amount, we hope to obtain from the community a contribution in kind to the amount of 3.665.000 francs CFA and in cash, the sum of 4.243.750 francs CFA. In other words, we are appealing to you and your organisation for the sum of 23,726,250 to enable us realise this project. You will find the cost estimates and other technical details in the project formulation which is enclosed. We should be very grateful if you would assist us in this project. We should also like to thank you in advance for your kind assistance iv scheme regularly. home. 6.10 Measures Technical Report of Feasibility Studies for MELUF Water Supply Re-enforcement/Extension Project –Kumbo Central Council.
  • 6. 6.20 Sustainability The management community shall be trained to oversee the use and maintenance of the water scheme. This committee shall be elected for a period of three years renewable.  Recalcitrant and delinquent members shall not be re-elected.  Each household shall be levied a fixed amount of money each year for the  All project funds shall be reserved in a financial institution and only withdrawn for the purpose of maintenance when need arises.  However there shall be a permanent caretaker who shall be remunerated each month.  Committee members shall not be paid. Their services shall be voluntary.  The permanent caretaker shall be responsible for water quality control as well as construction of all the equipment and asset of the water scheme except money and bank books. The Meluf water management Committee and the village Development Association shall appoint a Project coordinator who shall oversee each and every step of this project. He/she shall coordinate the activities of all the stakeholders and report to hierarchy. He/she shall be answerable and responsible to the general coordinator who endorses and reports to the donors. Each stage or element of the project shall be evaluated to satisfaction before progressing to the next. The project will have to respect strictly the technical prescriptions as well as budgetary lines. At the end of the project a thorough technical inspection and financial auditing shall be made by hired experts before the project is handed over to the community. v maintenance of the scheme. Monitoring and Evaluation Technical Report of Feasibility Studies for MELUF Water Supply Re-enforcement/Extension Project –Kumbo Central Council.
  • 7. 1.3 REASON FOR THE APPEAL: The people of Meluf Village had their water before nineteen eighties from streams and springs flowing through the grass and forest area. This contaminated water was considered very clean during this period. The village initiated their Water Project in the early eighties because streams and springs were silted up by erosion, too much deforestation, grazing, and grass cutting and burning in search of farm, and building land. As time went on, this scheme became irregular in supplying water to the inhabitants due to shortages of water caused by rapid increase in the population. Some spring sources were again studied above the Village. The springs at Tahshwer, Mbohaveiy were studied and constructed to reinforce the system .The problem was not solved and the villagers kept on suffering worst during the dry season. It is against this background that the Water Management Committee, the Village Development Association and the Councillor of the area contacted the Technicians in April 2013 for the feasibility studies and Technical advice. A technical report was established on the 18/10/2013with an estimated cost of about 31,635,000 Frs. CFA. 1.4 PRESENT WATER CONDITION OF THE VILLAGE: At the moment more than 75% of the population is living on polluted water. Water rationing has become the other of the day. Due to water shortages some people are fetching water from far off springs and streams which are exposed to pollution. 3.0 SUPERVISION: 3.0 Monitoring and Evaluation The Meluf village Development association and the Meluf water Development committee shall appoint a Water Project coordinator who shall oversee each and every step of this project. He/she shall coordinate the activities of all the stakeholders and report to hierarchy. He/she shall be answerable and responsible to the country coordinator who endorses and reports to the donors. Each stage or element of the project shall be evaluated to satisfaction before progressing to the next. The project will have to respect strictly the technical prescriptions as well as budgetary lines. At the end of the project a thorough technical inspection and financial auditing shall be made by hired experts before the project is handed over to the community. 1 . Technical Report of Feasibility Studies for MELUF Water Supply Re-enforcement/Extension Project –Kumbo Central Council.
  • 8. 3.1 TECHNICAL REPORT: This particular Water Supply Re-enforcement / Extension Scheme is being designed to function by gravity, that means water will flow from the two Spring Catchments to the Common Collection Chamber and to the Storage Tank 20m3 and from there to the Collection Points in the Village for the population for consumption through PVC pipes (N.P. 10) of various sizes. Galvanize pipes are used for installation of Catchment, Low points and High points, Collection Chamber, Storage Tank, Valve Chambers and Public Stand pipes, etc. 3.2 PROJECT PROPOSED STRUCTURES: The Project structures to be done will include:-  02 Spring Catchments  04 Low Points  02 High Points  01 Storage Tank 20m3  02 Valve Chambers  08 Stand Pipes  01 Collection Chamber  4.3km pipeline/distribution network  43 Indication Pillars along the proposed pipe line.  01 Equipped tool box for Care-Taker for Maintenance  02 Spring Catchments Protection ESTIMATES OF COST AND QUANTITIES FOR THE WATER PROJECT AT MELUF VILLAGE KUMBO, BUI DIVISION, NORTH WEST REGION No List of works and supplies U Qty U.P T.P I Preliminary Works 101 Studies Ls 1 250,000 250,000 102 Site installation Ls 1 250,000 250,000 SUB-TOTAL I 500,000 II INFRASTRUCTURE 201 Construction of catchments u 2 900,000 1,800,000 202 Catchment protection ff 2 300,000 600,000 203 Construction of Stream Crossing u 4 100,000 400,000 204 Construction of valve chambers u 2 120,000 240,000 205 Construction of stand pipes u 8 250,000 2,000,000 206 Construction of low point u 2 130,000 260,000 2 4.00 Budget and Financing plan 4.1 Budget Technical Report of Feasibility Studies for MELUF Water Supply Re-enforcement/Extension Project –Kumbo Central Council.
  • 9. 207 Construction of high points u 1 100,000 100,000 Sub-Total II 5,400,000 III PLUMBING WORK 301 PVC Pipes D 63 mm NP 10 ml 1200 4,000 4,800,000 302 PVC Pipes D 50 mm NP 10 ml 1800 3,000 5,400,000 303 PVC Pipes D 32 mm NP 10 ml 1360 2,000 2,720,000 304 PVC Pipes D 25 mm NP 10 ml 600 1,500 900,000 305 GI Pipes D 1 and ½ inches ml 40 7,000 280,000 Sub-Total III 14,100,000 IV EXCAVATION AND BACKFILLING OF CO Operation Months Cost 401 Excavation and Backfilling of Network ml 5000 100 500,000 402 Excavation and Backfilling of Network ml 5000 100 500,000 SUB-TOTAL IV 1,000,000 V OTHERS SUPPLEMENTARY WORKS 501 Training of management committee Is 1 200,000 200,000 502 Bacteriogical and chemical analyses of water Is 1 400,000 400,000 503 Supply of tool box Is 1 150,000 150,000 504 Elaboration of technical plan Is 1 150,000 150,000 505 Test run Is 1 100,000 100,000 SUB-TOTAL V 1,000,000 Total Excluding Taxes 22,000,000 V.A.T=19.25% 9,635,000 Total including Taxes 31,635,000 Grand Total of the project 31,635,000 Estimates Closed at: Thirty one Million Six Hundred and Thirty Five Thousand (31,635,000 F CFA) Francs CFA S/N Partner Amount Percentage Francs CFA US D 1,581,750 3163.5 5% 2. Principal Funder 30,053,250 60,106.5 95% Total Cost of Project 31,635,000 63,270 100% 3 NETWORK 4.2 Financing Plan 1, Meluf Village community 5.0 Physical and Financial Evolution Technical Report of Feasibility Studies for MELUF Water Supply Re-enforcement/Extension Project –Kumbo Central Council.
  • 10. DE 1 2 3 4 5 6 101 Studies and Site Installations x 500,000 102 Infrastructural works x x x 5,400,000 103 Plumbing works x x 14,100,000 104 Excavation and Backfilling of Network x x 1,000,000 105 Training of Management Committee x 200,000 106 Quality control of water x 400,000 107 Tool box x 150,000 108 Elaboration of Technical plan x x 150,000 109 Test run x 100,000 110 Documentation/Taxes on Resources x x x x x x 7,035,000 111 Monitoring/Evaluation x x x x x x x x 2,000,000 5.0 ANALYSIS OF CONSTRUCTION SEQUENCE OF PROJECT: 5.1 SPRING CATCHMENT: Spring Sources are located above the level of the Village and can supply water to the Community by gravity. All Construction works of the Catchment will be of stone masonry except for the top slab and foundation that will be of re-enforced concrete. Control or inspection chamber will be attached to the catchment. 5.2 PUBLIC STAND PIPES: The standpipes will be placed at 300 to 500 meters to serve public places like schools, Missions, Health Centres and market places according to technical requirements. 5.3 HYDRAULIC INSTALLATION: The main pipeline and major branches of the pipeline will be installed with PVC pipes (N.P. 10) of various sizes. Galvanized pipes will be used at installation of Catchments, Storage tank, Valve Chambers, High points, Low points, Public Standpipes etc. 4 Technical Report of Feasibility Studies for MELUF Water Supply Re-enforcement/Extension Project –Kumbo Central Council.
  • 11. 6.0 FINAL REMARKS AND CONCLUSION The entire project is estimated at 31,635,000 francs CFA. We hope to obtain the population the contribution in kind and in cash to the sum of 1,581,750 francs CFA as required by Engineers Without Borders. (5%) We are appealing to you and your organisation for the sum of 30,053,250 francs CFA, (75%) to enable us realizes this project. We therefore send this project to our various friends and benefactors to consider assisting us financially, materially and morally to execute this project. 5 Technical Report of Feasibility Studies for MELUF Water Supply Re-enforcement/Extension Project –Kumbo Central Council.