SlideShare a Scribd company logo
1 of 3
Download to read offline
CONTACT WILD WELL
+1.281.784.4700 // wildwell.com
2202 Oil Center Court
Houston, TX 77073
Blowout During Fracture
Stimulation Operations
EVENT SUMMARY
This incident occurred while fracturing operations were ongoing. It was
reported to be on stage 19 of a planned 24 stages. The failure occurred on
the wing valve on the tubing head where it flanges up to the wellhead body.
This left no mechanism to isolate the flow and the returning water and sand
mixture quickly cut the valve and wellhead body.
The initial site assessment noted the following challenges:
ƒ There was a full frac spread on location along with electric line
equipment and live perforating guns.
ƒ Significant water run-off was already occurring on location.
ƒ There was another wellhead adjacent to the subject well.
ƒ Wellhead body damage was present from the exiting flow.
WWC personnel were successful in the installation of a new wellhead and
securing the well. This was completed with no incidents in a total time frame
from dispatch to resolution in 5 days.
OPERATIONAL SUMMARY
Most well control operations involve
multiple phases to achieve the
ultimate goal of regaining control of
the well. The following operational
phases were completed for this
project to reach the final resolution.
CS004
Case Study
BACKGROUND:
Wild Well Control (WWC)
Personnel responded to
a blowout on a fracture
stimulation job in south Texas.
This project was completed
using some existing tools in
a new way to effectively save
the client precious time and
money on the intervention
efforts.
2202 Oil Center Court
Houston, TX 77073
CONTACT WILD WELL +1.281.784.4700 // wildwell.com
WELLHEAD ACCESS
Upon arrival to the wellsite, it was noted that the subject well was blowing from
the cellar area. A full frac spread was on location along with the supporting
electric line (e-line) equipment. The well was flowing back predominantly water
and WWC personnel seized this opportunity to begin to clear equipment form the
site. Gas monitoring was utilized to ensure the environment was safe to begin to
rig down the frac iron around location. This facilitated the removal of all fracturing
and e-line equipment from the pad with no issues.
The water flow on location was controlled by digging a trench to the reserve pit,
where it could be captured and hauled off as required. This also allowed well
control personnel to assess the actual damage to the wellhead by connecting the
cellar to the trench. After confirmation that the wellhead was compromised and
unusable, the area was excavated to allow it to be removed. This excavation was
aided by a diversion technique using a joint of casing. This diversion allowed well
control personnel to work heavy equipment at the well while minimizing any risk
from the well flow.
WELLHEAD PREPARATION AND INSTALLATION
Upon excavation of the area around the wellhead, plans were implemented to
make a cut to remove it from the casing. In the past, an Abrasive Jet Cutter (AJC)
was the preferred method for wellhead removal during a blowout. There are still
many application were this is the only viable method. However, in this case, WWC
personnel offered the option to utilize a Diamond Wire Saw (DWS) to make the
cut. This involved no real additional support equipment outside of the cutter itself
and the hydraulic power unit. The AJC requires sand and pumping equipment,
along with an Athey wagon for the typical deployment.
The DWS was utilized and enhanced the speed of the intervention operations.
This cut was made successfully through 2 casing strings and the old wellhead
was safely removed. The casing strings were then cut again at the appropriate
location to facilitate the new wellhead installation. A slip lock wellhead was
selected for this application to eliminate any hot work at the wellhead.
CS004
Blowout During Fracture Stimulation Operations
Case Study
2202 Oil Center Court
Houston, TX 77073
CONTACT WILD WELL +1.281.784.4700 // wildwell.com
CAPPING AND KILL OPERATIONS
Upon installation of the new wellhead, several options were
developed to install a capping device. The well was showing
signs of slug flow nearing the time of capping. This allowed
WWC personnel to install a tubing head and manual gate valves.
Had this not occurred, the wellhead and casing space-out was
prepped for a BOP capping option as well as a contingency.
The installation of the tubing head was preferred by the client
and was landed on the casing head. The manual valves were
closed securing the well. The client planned to set bridge plugs in
the casing and WWC personnel were released from the project.
Blowout During Fracture Stimulation Operations
Case Study
CS004

More Related Content

Similar to CS004-Blowout-During-Fracture-Stimulation-Operations.pdf

Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15John Grover
 
SPE171748 Surface Safety System for ZADCO (4).pdf
SPE171748 Surface Safety System for ZADCO (4).pdfSPE171748 Surface Safety System for ZADCO (4).pdf
SPE171748 Surface Safety System for ZADCO (4).pdfJalal Neshat
 
Horizontal vertical christmas tree ppt
Horizontal vertical christmas tree pptHorizontal vertical christmas tree ppt
Horizontal vertical christmas tree pptAmar Gaikwad
 
Spe26043 (fluid entry)
Spe26043 (fluid entry)Spe26043 (fluid entry)
Spe26043 (fluid entry)Gregg Linville
 
SPE26043 (Fluid Entry)
SPE26043 (Fluid Entry)SPE26043 (Fluid Entry)
SPE26043 (Fluid Entry)Gregg Linville
 
Gadsen Drive Emergency Gravity Sewer Repairs
Gadsen Drive Emergency Gravity Sewer RepairsGadsen Drive Emergency Gravity Sewer Repairs
Gadsen Drive Emergency Gravity Sewer RepairsFairfax County
 
Waynewood II Force Main Replacement
Waynewood II Force Main ReplacementWaynewood II Force Main Replacement
Waynewood II Force Main ReplacementFairfax County
 
26-grover-john-draft
26-grover-john-draft26-grover-john-draft
26-grover-john-draftJohn Grover
 
Sequence of well completion part 1
Sequence of well completion part 1Sequence of well completion part 1
Sequence of well completion part 1Elsayed Amer
 
Sequence of well completion part 1
Sequence of well completion part 1Sequence of well completion part 1
Sequence of well completion part 1Elsayed Amer
 
OSEA 2006 - Precom Impact final
OSEA 2006 - Precom Impact finalOSEA 2006 - Precom Impact final
OSEA 2006 - Precom Impact finalJohn Grover
 
Hydrovac Contractors Bay Area Unleashing the Power of Hydro Excavation.pdf
Hydrovac Contractors Bay Area Unleashing the Power of Hydro Excavation.pdfHydrovac Contractors Bay Area Unleashing the Power of Hydro Excavation.pdf
Hydrovac Contractors Bay Area Unleashing the Power of Hydro Excavation.pdfTec
 
Well Complection - Basic-1.pptx
Well Complection - Basic-1.pptxWell Complection - Basic-1.pptx
Well Complection - Basic-1.pptx4twerdefwef
 
M station Additional HCl Storage TanKs
 M station Additional HCl Storage TanKs M station Additional HCl Storage TanKs
M station Additional HCl Storage TanKsAhmad Moharram
 
Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Angelo Indelicato
 
26-grover-john-final
26-grover-john-final26-grover-john-final
26-grover-john-finalJohn Grover
 

Similar to CS004-Blowout-During-Fracture-Stimulation-Operations.pdf (20)

Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15
 
SPE171748 Surface Safety System for ZADCO (4).pdf
SPE171748 Surface Safety System for ZADCO (4).pdfSPE171748 Surface Safety System for ZADCO (4).pdf
SPE171748 Surface Safety System for ZADCO (4).pdf
 
Horizontal vertical christmas tree ppt
Horizontal vertical christmas tree pptHorizontal vertical christmas tree ppt
Horizontal vertical christmas tree ppt
 
Well work over
Well work overWell work over
Well work over
 
DAO 2000-98 Section 45
DAO 2000-98 Section 45DAO 2000-98 Section 45
DAO 2000-98 Section 45
 
Spe26043 (fluid entry)
Spe26043 (fluid entry)Spe26043 (fluid entry)
Spe26043 (fluid entry)
 
SPE26043 (Fluid Entry)
SPE26043 (Fluid Entry)SPE26043 (Fluid Entry)
SPE26043 (Fluid Entry)
 
Well intervention
Well  interventionWell  intervention
Well intervention
 
Gadsen Drive Emergency Gravity Sewer Repairs
Gadsen Drive Emergency Gravity Sewer RepairsGadsen Drive Emergency Gravity Sewer Repairs
Gadsen Drive Emergency Gravity Sewer Repairs
 
Waynewood II Force Main Replacement
Waynewood II Force Main ReplacementWaynewood II Force Main Replacement
Waynewood II Force Main Replacement
 
26-grover-john-draft
26-grover-john-draft26-grover-john-draft
26-grover-john-draft
 
Sequence of well completion part 1
Sequence of well completion part 1Sequence of well completion part 1
Sequence of well completion part 1
 
Sequence of well completion part 1
Sequence of well completion part 1Sequence of well completion part 1
Sequence of well completion part 1
 
OSEA 2006 - Precom Impact final
OSEA 2006 - Precom Impact finalOSEA 2006 - Precom Impact final
OSEA 2006 - Precom Impact final
 
Hydrovac Contractors Bay Area Unleashing the Power of Hydro Excavation.pdf
Hydrovac Contractors Bay Area Unleashing the Power of Hydro Excavation.pdfHydrovac Contractors Bay Area Unleashing the Power of Hydro Excavation.pdf
Hydrovac Contractors Bay Area Unleashing the Power of Hydro Excavation.pdf
 
Well Complection - Basic-1.pptx
Well Complection - Basic-1.pptxWell Complection - Basic-1.pptx
Well Complection - Basic-1.pptx
 
M station Additional HCl Storage TanKs
 M station Additional HCl Storage TanKs M station Additional HCl Storage TanKs
M station Additional HCl Storage TanKs
 
Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...
 
Community Meeting: 21st & Bainbridge
Community Meeting: 21st & BainbridgeCommunity Meeting: 21st & Bainbridge
Community Meeting: 21st & Bainbridge
 
26-grover-john-final
26-grover-john-final26-grover-john-final
26-grover-john-final
 

More from Jalal Neshat

Hydraulics Summary to optimization of drill bit hydraulics
Hydraulics Summary to optimization of drill bit hydraulicsHydraulics Summary to optimization of drill bit hydraulics
Hydraulics Summary to optimization of drill bit hydraulicsJalal Neshat
 
DSSSSSSSSSSGGGGGGGGGGGGGHHLKKSSSSSSSSSGHHH
DSSSSSSSSSSGGGGGGGGGGGGGHHLKKSSSSSSSSSGHHHDSSSSSSSSSSGGGGGGGGGGGGGHHLKKSSSSSSSSSGHHH
DSSSSSSSSSSGGGGGGGGGGGGGHHLKKSSSSSSSSSGHHHJalal Neshat
 
274-Article Text-1503-1-10-20230609.pdf
274-Article Text-1503-1-10-20230609.pdf274-Article Text-1503-1-10-20230609.pdf
274-Article Text-1503-1-10-20230609.pdfJalal Neshat
 
CamScanner 09-30-2023 09.22.pdf
CamScanner 09-30-2023 09.22.pdfCamScanner 09-30-2023 09.22.pdf
CamScanner 09-30-2023 09.22.pdfJalal Neshat
 
fenrg-11-1120635-1.pdf
fenrg-11-1120635-1.pdffenrg-11-1120635-1.pdf
fenrg-11-1120635-1.pdfJalal Neshat
 
pdfcoffee.com_i-openwells-basics-training-3-pdf-free.pdf
pdfcoffee.com_i-openwells-basics-training-3-pdf-free.pdfpdfcoffee.com_i-openwells-basics-training-3-pdf-free.pdf
pdfcoffee.com_i-openwells-basics-training-3-pdf-free.pdfJalal Neshat
 
WildWell_TechDataBook-2018web.pdf
WildWell_TechDataBook-2018web.pdfWildWell_TechDataBook-2018web.pdf
WildWell_TechDataBook-2018web.pdfJalal Neshat
 
M-Hashemi 2281657930 CV.docx
M-Hashemi 2281657930 CV.docxM-Hashemi 2281657930 CV.docx
M-Hashemi 2281657930 CV.docxJalal Neshat
 
s00254-004-1088-y.pdf
s00254-004-1088-y.pdfs00254-004-1088-y.pdf
s00254-004-1088-y.pdfJalal Neshat
 
Mud_volcanoes_in_the_South_Caspian_basin_Nature_an.pdf
Mud_volcanoes_in_the_South_Caspian_basin_Nature_an.pdfMud_volcanoes_in_the_South_Caspian_basin_Nature_an.pdf
Mud_volcanoes_in_the_South_Caspian_basin_Nature_an.pdfJalal Neshat
 
Back-off Procedure.docx
Back-off Procedure.docxBack-off Procedure.docx
Back-off Procedure.docxJalal Neshat
 

More from Jalal Neshat (17)

Hydraulics Summary to optimization of drill bit hydraulics
Hydraulics Summary to optimization of drill bit hydraulicsHydraulics Summary to optimization of drill bit hydraulics
Hydraulics Summary to optimization of drill bit hydraulics
 
DSSSSSSSSSSGGGGGGGGGGGGGHHLKKSSSSSSSSSGHHH
DSSSSSSSSSSGGGGGGGGGGGGGHHLKKSSSSSSSSSGHHHDSSSSSSSSSSGGGGGGGGGGGGGHHLKKSSSSSSSSSGHHH
DSSSSSSSSSSGGGGGGGGGGGGGHHLKKSSSSSSSSSGHHH
 
274-Article Text-1503-1-10-20230609.pdf
274-Article Text-1503-1-10-20230609.pdf274-Article Text-1503-1-10-20230609.pdf
274-Article Text-1503-1-10-20230609.pdf
 
CamScanner 09-30-2023 09.22.pdf
CamScanner 09-30-2023 09.22.pdfCamScanner 09-30-2023 09.22.pdf
CamScanner 09-30-2023 09.22.pdf
 
fenrg-11-1120635-1.pdf
fenrg-11-1120635-1.pdffenrg-11-1120635-1.pdf
fenrg-11-1120635-1.pdf
 
7285665.pdf
7285665.pdf7285665.pdf
7285665.pdf
 
pdfcoffee.com_i-openwells-basics-training-3-pdf-free.pdf
pdfcoffee.com_i-openwells-basics-training-3-pdf-free.pdfpdfcoffee.com_i-openwells-basics-training-3-pdf-free.pdf
pdfcoffee.com_i-openwells-basics-training-3-pdf-free.pdf
 
WildWell_TechDataBook-2018web.pdf
WildWell_TechDataBook-2018web.pdfWildWell_TechDataBook-2018web.pdf
WildWell_TechDataBook-2018web.pdf
 
M-Hashemi 2281657930 CV.docx
M-Hashemi 2281657930 CV.docxM-Hashemi 2281657930 CV.docx
M-Hashemi 2281657930 CV.docx
 
s00254-004-1088-y.pdf
s00254-004-1088-y.pdfs00254-004-1088-y.pdf
s00254-004-1088-y.pdf
 
192282-MS.pdf
192282-MS.pdf192282-MS.pdf
192282-MS.pdf
 
Rig Equipment
Rig EquipmentRig Equipment
Rig Equipment
 
Mud_volcanoes_in_the_South_Caspian_basin_Nature_an.pdf
Mud_volcanoes_in_the_South_Caspian_basin_Nature_an.pdfMud_volcanoes_in_the_South_Caspian_basin_Nature_an.pdf
Mud_volcanoes_in_the_South_Caspian_basin_Nature_an.pdf
 
Back-off Procedure.docx
Back-off Procedure.docxBack-off Procedure.docx
Back-off Procedure.docx
 
preview-dd.pdf
preview-dd.pdfpreview-dd.pdf
preview-dd.pdf
 
Chapter_6-OCW.pdf
Chapter_6-OCW.pdfChapter_6-OCW.pdf
Chapter_6-OCW.pdf
 
Colored inversion
Colored inversionColored inversion
Colored inversion
 

Recently uploaded

result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

CS004-Blowout-During-Fracture-Stimulation-Operations.pdf

  • 1. CONTACT WILD WELL +1.281.784.4700 // wildwell.com 2202 Oil Center Court Houston, TX 77073 Blowout During Fracture Stimulation Operations EVENT SUMMARY This incident occurred while fracturing operations were ongoing. It was reported to be on stage 19 of a planned 24 stages. The failure occurred on the wing valve on the tubing head where it flanges up to the wellhead body. This left no mechanism to isolate the flow and the returning water and sand mixture quickly cut the valve and wellhead body. The initial site assessment noted the following challenges: ƒ There was a full frac spread on location along with electric line equipment and live perforating guns. ƒ Significant water run-off was already occurring on location. ƒ There was another wellhead adjacent to the subject well. ƒ Wellhead body damage was present from the exiting flow. WWC personnel were successful in the installation of a new wellhead and securing the well. This was completed with no incidents in a total time frame from dispatch to resolution in 5 days. OPERATIONAL SUMMARY Most well control operations involve multiple phases to achieve the ultimate goal of regaining control of the well. The following operational phases were completed for this project to reach the final resolution. CS004 Case Study BACKGROUND: Wild Well Control (WWC) Personnel responded to a blowout on a fracture stimulation job in south Texas. This project was completed using some existing tools in a new way to effectively save the client precious time and money on the intervention efforts.
  • 2. 2202 Oil Center Court Houston, TX 77073 CONTACT WILD WELL +1.281.784.4700 // wildwell.com WELLHEAD ACCESS Upon arrival to the wellsite, it was noted that the subject well was blowing from the cellar area. A full frac spread was on location along with the supporting electric line (e-line) equipment. The well was flowing back predominantly water and WWC personnel seized this opportunity to begin to clear equipment form the site. Gas monitoring was utilized to ensure the environment was safe to begin to rig down the frac iron around location. This facilitated the removal of all fracturing and e-line equipment from the pad with no issues. The water flow on location was controlled by digging a trench to the reserve pit, where it could be captured and hauled off as required. This also allowed well control personnel to assess the actual damage to the wellhead by connecting the cellar to the trench. After confirmation that the wellhead was compromised and unusable, the area was excavated to allow it to be removed. This excavation was aided by a diversion technique using a joint of casing. This diversion allowed well control personnel to work heavy equipment at the well while minimizing any risk from the well flow. WELLHEAD PREPARATION AND INSTALLATION Upon excavation of the area around the wellhead, plans were implemented to make a cut to remove it from the casing. In the past, an Abrasive Jet Cutter (AJC) was the preferred method for wellhead removal during a blowout. There are still many application were this is the only viable method. However, in this case, WWC personnel offered the option to utilize a Diamond Wire Saw (DWS) to make the cut. This involved no real additional support equipment outside of the cutter itself and the hydraulic power unit. The AJC requires sand and pumping equipment, along with an Athey wagon for the typical deployment. The DWS was utilized and enhanced the speed of the intervention operations. This cut was made successfully through 2 casing strings and the old wellhead was safely removed. The casing strings were then cut again at the appropriate location to facilitate the new wellhead installation. A slip lock wellhead was selected for this application to eliminate any hot work at the wellhead. CS004 Blowout During Fracture Stimulation Operations Case Study
  • 3. 2202 Oil Center Court Houston, TX 77073 CONTACT WILD WELL +1.281.784.4700 // wildwell.com CAPPING AND KILL OPERATIONS Upon installation of the new wellhead, several options were developed to install a capping device. The well was showing signs of slug flow nearing the time of capping. This allowed WWC personnel to install a tubing head and manual gate valves. Had this not occurred, the wellhead and casing space-out was prepped for a BOP capping option as well as a contingency. The installation of the tubing head was preferred by the client and was landed on the casing head. The manual valves were closed securing the well. The client planned to set bridge plugs in the casing and WWC personnel were released from the project. Blowout During Fracture Stimulation Operations Case Study CS004