The document provides an overview of the Critical Chain/Buffer Management (CC/BM) project scheduling approach. It discusses six key steps: 1) using aggressive activity estimates, 2) constructing an as-late-as-possible schedule, 3) identifying the critical chain, 4) determining buffer positions, 5) determining buffer sizes, and 6) inserting buffers into the schedule. The approach aims to protect the project deadline by introducing buffers at different positions, including a project buffer, feeding buffers, and resource buffers.