The document outlines commissioning procedures for conveyors in 3 steps:
1) Pre-start checks that ensure all components like belts, guards, idlers and safety devices are properly installed and functioning.
2) Running checks that test the empty operation of the conveyor by monitoring startup, speed, sensors and alignment.
3) Intermediate checks that load test the conveyor over extended periods to check for proper operation and identify any issues under load like misalignment or component failure. Records of the commissioning process are to be maintained.