SlideShare a Scribd company logo
1 of 3
Download to read offline
Kuat Lentur Rencana untuk Penampang Komposit yang berperilaku Komposit Penuh.
Tidak ada Tumpuan Sementara
N :=

1
9.81

⋅ kg

kN := 1000⋅ N

psi :=

lb

ksi := 1000⋅ psi

2

N

MPa :=

in

2

mm

b

0.85fc’
t

C

a
y
T

d

d/2

Fy
Distribusi tegangan apabila sumbu
netral plastis (PNA) di beton

Diketahui
f'c := 28⋅ MPa
WF300x150x6.5x9

Kuat tekan beton 28 hari
Profil baja

Tinggi penampang

d := 350 ⋅ mm

Luas

Tebal web

tw := 6.5⋅ mm

Tebal flens

As := 46.78 ⋅ cm
tf := 9 ⋅ mm

Lebar flens

2

b f := 150 ⋅ mm

Jari-jari sudut flens-web r := 13⋅ mm

Slab beton bertulang di atas profil baja mempunyai ukuran
Lebar

b := 1830⋅ mm

Tebal

t := 100 ⋅ mm

Tumpuan sementara tidak digunakan, dan momen lentur (akibat beban kerja) adalah sbb:
Akibat berat sendiri balok baja

M beam := 17.6⋅ kN⋅ m

Akibat berat sendiri slab

M slab := 84.3⋅ kN⋅ m

Akibat beban hidup

M L := 95.4⋅ kN⋅ m

(abaikan kemungkinan tambahan beban pelaksanaan)
Mutu Baja Bj. 50

Fy := 290 ⋅ MPa

Modulus elastisitas baja E := 200000⋅ MPa
Ditanya: cek apakah kuat lentur rencana dengan menganggap perilaku komposit penuh .
Asumsikan pula bahwa perancah (formwork) dapat berfungsi sebagai tumpuan lateral bagi balok
baja, sebelum beton mengering.
Jawab
Kondisi Beton belum Kering
Sebelum beton mengering, hanya ada beban mati (pada soal, beban pelaksanaan dapat
diabaikan). Jadi, kombinasi pembebanan yang dipakai adalah:
M u := 1.4⋅ M beam + M slab
M u = 142.66 kN⋅ m

(

)

Momen terfaktor tersebut dipikul oleh balok baja saja (beton masih belum mengering). Pengecekan
kuat lentur rencana balok baja:
1
2
3
Modulus plastis
Zx := b f ⋅ tf ⋅ d − tf + ⋅ tw⋅ d − 2 ⋅ tf
Zx = 639.46 cm
4
Faktor tahanan lentur
φb := 0.85

(

)

(

)

φb ⋅ Fy ⋅ Zx = 157.63 kN⋅ m

Kuat lentur rencana

LTB tidak menentukan karena ditumpu lateral oleh perancah

KuatLentur :=

"Oke" if M u ≤ φb ⋅ Fy ⋅ Zx

KuatLentur = "Oke"

"Tidak Oke" otherwise
Kondisi Beton telah Kering
Sesudah beton mengering, penampang komposit telah terbentuk. Momen terfaktor yang harus
dipikul penampang komposit
M u := max⎡ 1.4⋅ M beam + M slab , 1.2⋅ M beam + M slab + 1.6⋅ M L⎤

⎣

(

)

(

)

⎦

M u = 274.92 kN⋅ m
Ac := b ⋅ t
Cek apakah penampang baja kompak
Luas slab beton

h := d − 2 ⋅ tf − 2 ⋅ r
h
= 47.08
tw
Penampang :=

2

Ac = 183000 mm

h = 306 mm
3.76⋅

E
Fy

"Kompak" if

= 98.74
h
tw

≤ 3.76⋅

E
Fy

Penampang = "Kompak"

"Tidak Kompak" otherwise
Catatan:
Bila penampang tidak kompak, perhitungan selanjutnya tidak berlaku. Yang berlaku adalah φb = 0.9 dan Mn
dihitung dengan menggunakan distribusi tegangan elastis yang berkaitan dengan leleh pertama pada
penampang baja.
Perilaku komposit penuh berarti resultan tekan C tidak ditentukan oleh ΣQn (kuat geser

penghubung geser), dan hanya ditentukan dari:
As⋅ Fy = 1356.62 kN
0.85⋅ f'c⋅ Ac = 4355.4 kN

(

C := min As⋅ Fy , 0.85⋅ f'c⋅ Ac

)

C = 1356.62 kN

total
PNA :=

"Di beton" if As⋅ Fy ≤ 0.85⋅ f'c⋅ Ac

PNA = "Di beton"

"Di baja" otherwise
Catatan:
Bila sumbu netral plastis (PNA) terletak di beton, maka distribusi tegangan akan sama seperti gambar pada soal. Bila
PNA terletak di baja, maka perhitungan di bawah ini tidak berlaku!

Tinggi beton yang tertekan

a :=

Lengan momen (jarak antara C dan T)

y :=

Kuat nominal penampang komposit

C

a = 31.15 mm

0.85⋅ f'c⋅ b
d
2

+t−

a

y = 259.43 mm

2

M n := C⋅ y

M n = 351.94 kN⋅ m

Kuat rencana penampang komposit adalah φb ⋅ M n = 299.15 kN⋅ m
KuatLentur :=

"Oke" if M u ≤ φb ⋅ M n
"Tidak Oke" otherwise

KuatLentur = "Oke"

More Related Content

What's hot

Laporan prancangan struktur
Laporan prancangan strukturLaporan prancangan struktur
Laporan prancangan strukturKomang Satriawan
 
Kuat tarik baja mengacu SNI 1729:2020
Kuat tarik baja mengacu SNI 1729:2020Kuat tarik baja mengacu SNI 1729:2020
Kuat tarik baja mengacu SNI 1729:2020Shaleh Afif Hasibuan
 
menghitung Momen Ultimate baja komposit
menghitung Momen Ultimate baja kompositmenghitung Momen Ultimate baja komposit
menghitung Momen Ultimate baja kompositShaleh Afif Hasibuan
 
Perencanaan struktur baja
Perencanaan struktur bajaPerencanaan struktur baja
Perencanaan struktur bajaAmi_Roy
 
Struktur Baja Metode LRFD
Struktur Baja Metode LRFDStruktur Baja Metode LRFD
Struktur Baja Metode LRFDMuhammad Umari
 
perhitungan jembatan
perhitungan jembatanperhitungan jembatan
perhitungan jembatanFarid Thahura
 
contoh soal menghitung momen ultimate pada balok
contoh soal menghitung momen ultimate pada balokcontoh soal menghitung momen ultimate pada balok
contoh soal menghitung momen ultimate pada balokShaleh Afif Hasibuan
 
Perencanaan gording Baja
Perencanaan gording BajaPerencanaan gording Baja
Perencanaan gording Bajabumi lohita
 
Beton prategang
Beton prategangBeton prategang
Beton prategangPoten Novo
 
Struktur baja-5 lentur-balok
Struktur baja-5 lentur-balokStruktur baja-5 lentur-balok
Struktur baja-5 lentur-balokLeticia Freidac
 
Materi kuliah beton sederhana
Materi kuliah beton sederhanaMateri kuliah beton sederhana
Materi kuliah beton sederhanaperkasa45
 
183013186 contoh-perhitungan-gempa-statik-ekuivalen
183013186 contoh-perhitungan-gempa-statik-ekuivalen183013186 contoh-perhitungan-gempa-statik-ekuivalen
183013186 contoh-perhitungan-gempa-statik-ekuivalenafat civik
 
Laporan tugas struktur baja
Laporan tugas struktur bajaLaporan tugas struktur baja
Laporan tugas struktur bajatanchul
 
Sni 1727 2013 tata cara pembebanan untuk rumah dan gedung
Sni 1727 2013 tata cara pembebanan untuk rumah dan gedungSni 1727 2013 tata cara pembebanan untuk rumah dan gedung
Sni 1727 2013 tata cara pembebanan untuk rumah dan gedungWSKT
 
Bab iii analisis geser
Bab iii analisis geserBab iii analisis geser
Bab iii analisis geserKetut Swandana
 
Perencanaan sambungan-profil-baja
Perencanaan sambungan-profil-bajaPerencanaan sambungan-profil-baja
Perencanaan sambungan-profil-bajaFajar Istu
 

What's hot (20)

Laporan prancangan struktur
Laporan prancangan strukturLaporan prancangan struktur
Laporan prancangan struktur
 
Kuat tarik baja mengacu SNI 1729:2020
Kuat tarik baja mengacu SNI 1729:2020Kuat tarik baja mengacu SNI 1729:2020
Kuat tarik baja mengacu SNI 1729:2020
 
menghitung Momen Ultimate baja komposit
menghitung Momen Ultimate baja kompositmenghitung Momen Ultimate baja komposit
menghitung Momen Ultimate baja komposit
 
Perencanaan struktur baja
Perencanaan struktur bajaPerencanaan struktur baja
Perencanaan struktur baja
 
Struktur Baja Metode LRFD
Struktur Baja Metode LRFDStruktur Baja Metode LRFD
Struktur Baja Metode LRFD
 
perhitungan jembatan
perhitungan jembatanperhitungan jembatan
perhitungan jembatan
 
contoh soal menghitung momen ultimate pada balok
contoh soal menghitung momen ultimate pada balokcontoh soal menghitung momen ultimate pada balok
contoh soal menghitung momen ultimate pada balok
 
1. analisis slab lantai jembatan
1. analisis slab lantai jembatan1. analisis slab lantai jembatan
1. analisis slab lantai jembatan
 
Perencanaan gording Baja
Perencanaan gording BajaPerencanaan gording Baja
Perencanaan gording Baja
 
Beton prategang
Beton prategangBeton prategang
Beton prategang
 
Struktur baja-5 lentur-balok
Struktur baja-5 lentur-balokStruktur baja-5 lentur-balok
Struktur baja-5 lentur-balok
 
Materi kuliah beton sederhana
Materi kuliah beton sederhanaMateri kuliah beton sederhana
Materi kuliah beton sederhana
 
Tabel baja-wf-lrfd
Tabel baja-wf-lrfdTabel baja-wf-lrfd
Tabel baja-wf-lrfd
 
183013186 contoh-perhitungan-gempa-statik-ekuivalen
183013186 contoh-perhitungan-gempa-statik-ekuivalen183013186 contoh-perhitungan-gempa-statik-ekuivalen
183013186 contoh-perhitungan-gempa-statik-ekuivalen
 
Laporan tugas struktur baja
Laporan tugas struktur bajaLaporan tugas struktur baja
Laporan tugas struktur baja
 
Sni 1727 2013 tata cara pembebanan untuk rumah dan gedung
Sni 1727 2013 tata cara pembebanan untuk rumah dan gedungSni 1727 2013 tata cara pembebanan untuk rumah dan gedung
Sni 1727 2013 tata cara pembebanan untuk rumah dan gedung
 
STRUKTUR JEMBATAN
STRUKTUR JEMBATANSTRUKTUR JEMBATAN
STRUKTUR JEMBATAN
 
Bab iii analisis geser
Bab iii analisis geserBab iii analisis geser
Bab iii analisis geser
 
Perencanaan sambungan-profil-baja
Perencanaan sambungan-profil-bajaPerencanaan sambungan-profil-baja
Perencanaan sambungan-profil-baja
 
Voided slab
Voided slabVoided slab
Voided slab
 

Viewers also liked

Baja - Balok Komposit
Baja - Balok Komposit Baja - Balok Komposit
Baja - Balok Komposit Yasmin Rosyad
 
Tugas komposit
Tugas kompositTugas komposit
Tugas kompositQiqi Aw
 
Tugas akhir-ps-1380-modifikasi
Tugas akhir-ps-1380-modifikasiTugas akhir-ps-1380-modifikasi
Tugas akhir-ps-1380-modifikasiFerry Afrizal
 
Penggunaan Kalkulator - Persamaan kuadratik
Penggunaan Kalkulator - Persamaan kuadratikPenggunaan Kalkulator - Persamaan kuadratik
Penggunaan Kalkulator - Persamaan kuadratikamimuin
 
Perhitungan Balok Baja dan Beton
Perhitungan Balok Baja dan BetonPerhitungan Balok Baja dan Beton
Perhitungan Balok Baja dan Betonasdihss
 
Jenis jenis turbin turbin pelton turbin francis dan turbin kaplan
Jenis jenis turbin turbin pelton turbin francis dan turbin kaplanJenis jenis turbin turbin pelton turbin francis dan turbin kaplan
Jenis jenis turbin turbin pelton turbin francis dan turbin kaplanAdy Purnomo
 
Analisis kapasitas dan perencanaan perkuatan jembatan rangka baja tumpuen
Analisis kapasitas dan perencanaan perkuatan jembatan rangka baja tumpuenAnalisis kapasitas dan perencanaan perkuatan jembatan rangka baja tumpuen
Analisis kapasitas dan perencanaan perkuatan jembatan rangka baja tumpuenIqlal Suriansyah
 
Penggunaan Kalkulator Saintifik - Persamaan serentak
Penggunaan Kalkulator Saintifik - Persamaan serentakPenggunaan Kalkulator Saintifik - Persamaan serentak
Penggunaan Kalkulator Saintifik - Persamaan serentakamimuin
 

Viewers also liked (9)

Baja - Balok Komposit
Baja - Balok Komposit Baja - Balok Komposit
Baja - Balok Komposit
 
Tugas komposit
Tugas kompositTugas komposit
Tugas komposit
 
Jembatan
JembatanJembatan
Jembatan
 
Tugas akhir-ps-1380-modifikasi
Tugas akhir-ps-1380-modifikasiTugas akhir-ps-1380-modifikasi
Tugas akhir-ps-1380-modifikasi
 
Penggunaan Kalkulator - Persamaan kuadratik
Penggunaan Kalkulator - Persamaan kuadratikPenggunaan Kalkulator - Persamaan kuadratik
Penggunaan Kalkulator - Persamaan kuadratik
 
Perhitungan Balok Baja dan Beton
Perhitungan Balok Baja dan BetonPerhitungan Balok Baja dan Beton
Perhitungan Balok Baja dan Beton
 
Jenis jenis turbin turbin pelton turbin francis dan turbin kaplan
Jenis jenis turbin turbin pelton turbin francis dan turbin kaplanJenis jenis turbin turbin pelton turbin francis dan turbin kaplan
Jenis jenis turbin turbin pelton turbin francis dan turbin kaplan
 
Analisis kapasitas dan perencanaan perkuatan jembatan rangka baja tumpuen
Analisis kapasitas dan perencanaan perkuatan jembatan rangka baja tumpuenAnalisis kapasitas dan perencanaan perkuatan jembatan rangka baja tumpuen
Analisis kapasitas dan perencanaan perkuatan jembatan rangka baja tumpuen
 
Penggunaan Kalkulator Saintifik - Persamaan serentak
Penggunaan Kalkulator Saintifik - Persamaan serentakPenggunaan Kalkulator Saintifik - Persamaan serentak
Penggunaan Kalkulator Saintifik - Persamaan serentak
 

Similar to Contoh baja

Contoh soal komposit
Contoh soal kompositContoh soal komposit
Contoh soal kompositkahar pasca
 
Lampiran perhit, pondasi
Lampiran perhit, pondasiLampiran perhit, pondasi
Lampiran perhit, pondasialpian nur
 
Tugas Besar Pondasi II
Tugas Besar Pondasi IITugas Besar Pondasi II
Tugas Besar Pondasi IIRendi Fahreza
 
Purlin bracing11
Purlin bracing11Purlin bracing11
Purlin bracing11wawanathar
 
PPT BIMA HUTARI.pptx
PPT BIMA HUTARI.pptxPPT BIMA HUTARI.pptx
PPT BIMA HUTARI.pptxGentaPermata2
 
Contoh wingwall
Contoh wingwallContoh wingwall
Contoh wingwalltanchul
 
gerakharmoniksederhana 2003
gerakharmoniksederhana 2003gerakharmoniksederhana 2003
gerakharmoniksederhana 2003Wisnu_Indah
 
Desain fondasi-tiang-pancang1
Desain fondasi-tiang-pancang1Desain fondasi-tiang-pancang1
Desain fondasi-tiang-pancang1Syah Rin
 
PPT PRAPRO AZRCHKM.pptx
PPT PRAPRO AZRCHKM.pptxPPT PRAPRO AZRCHKM.pptx
PPT PRAPRO AZRCHKM.pptxGentaPermata2
 
Pembebanan jembatan rangka (revisi profil baja)
Pembebanan jembatan rangka (revisi profil baja) Pembebanan jembatan rangka (revisi profil baja)
Pembebanan jembatan rangka (revisi profil baja) NitaMewaKameliaSiman
 
S struktur-batang lentur murni
S struktur-batang lentur murniS struktur-batang lentur murni
S struktur-batang lentur murniiky
 
Konstruksi gudang-baja
Konstruksi gudang-bajaKonstruksi gudang-baja
Konstruksi gudang-bajaekobudi27
 
Konstruksi gudang-baja
Konstruksi gudang-bajaKonstruksi gudang-baja
Konstruksi gudang-bajaasroel1995
 
Perhitungan balok prategang_pci_-girder
Perhitungan balok prategang_pci_-girderPerhitungan balok prategang_pci_-girder
Perhitungan balok prategang_pci_-girderjanahsiti
 
2. Perancangan Fondasi Dalam_CPT
2. Perancangan Fondasi Dalam_CPT 2. Perancangan Fondasi Dalam_CPT
2. Perancangan Fondasi Dalam_CPT tenggom
 

Similar to Contoh baja (20)

Contoh soal komposit
Contoh soal kompositContoh soal komposit
Contoh soal komposit
 
Lampiran perhit, pondasi
Lampiran perhit, pondasiLampiran perhit, pondasi
Lampiran perhit, pondasi
 
Teori pascatarik
Teori pascatarikTeori pascatarik
Teori pascatarik
 
Tugas Besar Pondasi II
Tugas Besar Pondasi IITugas Besar Pondasi II
Tugas Besar Pondasi II
 
Purlin bracing11
Purlin bracing11Purlin bracing11
Purlin bracing11
 
PPT BIMA HUTARI.pptx
PPT BIMA HUTARI.pptxPPT BIMA HUTARI.pptx
PPT BIMA HUTARI.pptx
 
Contoh wingwall
Contoh wingwallContoh wingwall
Contoh wingwall
 
gerakharmoniksederhana 2003
gerakharmoniksederhana 2003gerakharmoniksederhana 2003
gerakharmoniksederhana 2003
 
Desain fondasi-tiang-pancang1
Desain fondasi-tiang-pancang1Desain fondasi-tiang-pancang1
Desain fondasi-tiang-pancang1
 
PPT PRAPRO AZRCHKM.pptx
PPT PRAPRO AZRCHKM.pptxPPT PRAPRO AZRCHKM.pptx
PPT PRAPRO AZRCHKM.pptx
 
Pembebanan jembatan rangka (revisi profil baja)
Pembebanan jembatan rangka (revisi profil baja) Pembebanan jembatan rangka (revisi profil baja)
Pembebanan jembatan rangka (revisi profil baja)
 
1 pondasi
1 pondasi1 pondasi
1 pondasi
 
1 pondasi
1 pondasi1 pondasi
1 pondasi
 
S struktur-batang lentur murni
S struktur-batang lentur murniS struktur-batang lentur murni
S struktur-batang lentur murni
 
Bab 4 plat
Bab 4 platBab 4 plat
Bab 4 plat
 
Konstruksi gudang-baja
Konstruksi gudang-bajaKonstruksi gudang-baja
Konstruksi gudang-baja
 
Konstruksi gudang-baja
Konstruksi gudang-bajaKonstruksi gudang-baja
Konstruksi gudang-baja
 
2. pci girder
2. pci girder2. pci girder
2. pci girder
 
Perhitungan balok prategang_pci_-girder
Perhitungan balok prategang_pci_-girderPerhitungan balok prategang_pci_-girder
Perhitungan balok prategang_pci_-girder
 
2. Perancangan Fondasi Dalam_CPT
2. Perancangan Fondasi Dalam_CPT 2. Perancangan Fondasi Dalam_CPT
2. Perancangan Fondasi Dalam_CPT
 

More from Junaida Wally

Preparation of a piling paper
Preparation of a piling paperPreparation of a piling paper
Preparation of a piling paperJunaida Wally
 
Decision analysis applied to rock tunnel exploration 1978 baecher
Decision analysis applied to rock tunnel exploration 1978 baecherDecision analysis applied to rock tunnel exploration 1978 baecher
Decision analysis applied to rock tunnel exploration 1978 baecherJunaida Wally
 
2010 04 tunneling-to_the_future
2010 04 tunneling-to_the_future2010 04 tunneling-to_the_future
2010 04 tunneling-to_the_futureJunaida Wally
 
Structural design finite
Structural design finiteStructural design finite
Structural design finiteJunaida Wally
 
Ecg533 rock-tunnel-engineering
Ecg533 rock-tunnel-engineeringEcg533 rock-tunnel-engineering
Ecg533 rock-tunnel-engineeringJunaida Wally
 
583 24650 emperical method
583 24650 emperical method583 24650 emperical method
583 24650 emperical methodJunaida Wally
 
3 tunnels tunnel sous la manche c
3 tunnels tunnel sous la manche c 3 tunnels tunnel sous la manche c
3 tunnels tunnel sous la manche c Junaida Wally
 
Sni 03 2847-2002 (beton)
Sni 03 2847-2002 (beton)Sni 03 2847-2002 (beton)
Sni 03 2847-2002 (beton)Junaida Wally
 
Analysis of piles under earthquakes
Analysis of piles under earthquakesAnalysis of piles under earthquakes
Analysis of piles under earthquakesJunaida Wally
 
302 settlement of piled foundations
302 settlement of piled foundations302 settlement of piled foundations
302 settlement of piled foundationsJunaida Wally
 
Handout mer iv d iii
Handout mer iv d iiiHandout mer iv d iii
Handout mer iv d iiiJunaida Wally
 
Konstruksi baja-3 sambungan-baut
Konstruksi baja-3 sambungan-bautKonstruksi baja-3 sambungan-baut
Konstruksi baja-3 sambungan-bautJunaida Wally
 
Wide flange-shape-jisg3192
Wide flange-shape-jisg3192Wide flange-shape-jisg3192
Wide flange-shape-jisg3192Junaida Wally
 

More from Junaida Wally (20)

Preparation of a piling paper
Preparation of a piling paperPreparation of a piling paper
Preparation of a piling paper
 
Decision analysis applied to rock tunnel exploration 1978 baecher
Decision analysis applied to rock tunnel exploration 1978 baecherDecision analysis applied to rock tunnel exploration 1978 baecher
Decision analysis applied to rock tunnel exploration 1978 baecher
 
Chapter6
Chapter6Chapter6
Chapter6
 
2010 04 tunneling-to_the_future
2010 04 tunneling-to_the_future2010 04 tunneling-to_the_future
2010 04 tunneling-to_the_future
 
Structural design finite
Structural design finiteStructural design finite
Structural design finite
 
Cv15 nalisis method
Cv15 nalisis methodCv15 nalisis method
Cv15 nalisis method
 
Ecg533 rock-tunnel-engineering
Ecg533 rock-tunnel-engineeringEcg533 rock-tunnel-engineering
Ecg533 rock-tunnel-engineering
 
583 24650 emperical method
583 24650 emperical method583 24650 emperical method
583 24650 emperical method
 
3 tunnels tunnel sous la manche c
3 tunnels tunnel sous la manche c 3 tunnels tunnel sous la manche c
3 tunnels tunnel sous la manche c
 
Sni 03 2847-2002 (beton)
Sni 03 2847-2002 (beton)Sni 03 2847-2002 (beton)
Sni 03 2847-2002 (beton)
 
Pp no 29_th_2000
Pp no 29_th_2000Pp no 29_th_2000
Pp no 29_th_2000
 
Analysis of piles under earthquakes
Analysis of piles under earthquakesAnalysis of piles under earthquakes
Analysis of piles under earthquakes
 
Kaplan05analysis
Kaplan05analysisKaplan05analysis
Kaplan05analysis
 
302 settlement of piled foundations
302 settlement of piled foundations302 settlement of piled foundations
302 settlement of piled foundations
 
Bab ii1
Bab ii1Bab ii1
Bab ii1
 
Metode cross
Metode crossMetode cross
Metode cross
 
Handout mer iv d iii
Handout mer iv d iiiHandout mer iv d iii
Handout mer iv d iii
 
Konstruksi baja-3 sambungan-baut
Konstruksi baja-3 sambungan-bautKonstruksi baja-3 sambungan-baut
Konstruksi baja-3 sambungan-baut
 
Sni baja
Sni bajaSni baja
Sni baja
 
Wide flange-shape-jisg3192
Wide flange-shape-jisg3192Wide flange-shape-jisg3192
Wide flange-shape-jisg3192
 

Recently uploaded

443016507-Sediaan-obat-PHYCOPHYTA-MYOPHYTA-dan-MYCOPHYTA-pptx.pptx
443016507-Sediaan-obat-PHYCOPHYTA-MYOPHYTA-dan-MYCOPHYTA-pptx.pptx443016507-Sediaan-obat-PHYCOPHYTA-MYOPHYTA-dan-MYCOPHYTA-pptx.pptx
443016507-Sediaan-obat-PHYCOPHYTA-MYOPHYTA-dan-MYCOPHYTA-pptx.pptxErikaPutriJayantini
 
AKSI NYATA Numerasi Meningkatkan Kompetensi Murid_compressed (1) (1).pptx
AKSI NYATA  Numerasi  Meningkatkan Kompetensi Murid_compressed (1) (1).pptxAKSI NYATA  Numerasi  Meningkatkan Kompetensi Murid_compressed (1) (1).pptx
AKSI NYATA Numerasi Meningkatkan Kompetensi Murid_compressed (1) (1).pptxnursariheldaseptiana
 
SISTEM SARAF OTONOM_.SISTEM SARAF OTONOM
SISTEM SARAF OTONOM_.SISTEM SARAF OTONOMSISTEM SARAF OTONOM_.SISTEM SARAF OTONOM
SISTEM SARAF OTONOM_.SISTEM SARAF OTONOMhanyakaryawan1
 
PELAKSANAAN (dgn PT SBI) + Link2 Materi Pelatihan _"Teknik Perhitungan TKDN, ...
PELAKSANAAN (dgn PT SBI) + Link2 Materi Pelatihan _"Teknik Perhitungan TKDN, ...PELAKSANAAN (dgn PT SBI) + Link2 Materi Pelatihan _"Teknik Perhitungan TKDN, ...
PELAKSANAAN (dgn PT SBI) + Link2 Materi Pelatihan _"Teknik Perhitungan TKDN, ...Kanaidi ken
 
MODUL AJAR BAHASA INGGRIS KELAS 6 KURIKULUM MERDEKA.pdf
MODUL AJAR BAHASA INGGRIS KELAS 6 KURIKULUM MERDEKA.pdfMODUL AJAR BAHASA INGGRIS KELAS 6 KURIKULUM MERDEKA.pdf
MODUL AJAR BAHASA INGGRIS KELAS 6 KURIKULUM MERDEKA.pdfAndiCoc
 
MODUL AJAR SENI TARI KELAS 6 KURIKULUM MERDEKA.pdf
MODUL AJAR SENI TARI KELAS 6 KURIKULUM MERDEKA.pdfMODUL AJAR SENI TARI KELAS 6 KURIKULUM MERDEKA.pdf
MODUL AJAR SENI TARI KELAS 6 KURIKULUM MERDEKA.pdfAndiCoc
 
KISI-KISI SOAL DAN KARTU SOAL BAHASA INGGRIS.docx
KISI-KISI SOAL DAN KARTU SOAL BAHASA INGGRIS.docxKISI-KISI SOAL DAN KARTU SOAL BAHASA INGGRIS.docx
KISI-KISI SOAL DAN KARTU SOAL BAHASA INGGRIS.docxDewiUmbar
 
Modul 5 Simetri (simetri lipat, simetri putar)
Modul 5 Simetri (simetri lipat, simetri putar)Modul 5 Simetri (simetri lipat, simetri putar)
Modul 5 Simetri (simetri lipat, simetri putar)BashoriAlwi4
 
Materi Bab 6 Algoritma dan bahasa Pemrograman
Materi Bab 6 Algoritma dan bahasa  PemrogramanMateri Bab 6 Algoritma dan bahasa  Pemrograman
Materi Bab 6 Algoritma dan bahasa PemrogramanSaeranSaeran1
 
MODUL AJAR SENI MUSIK KELAS 6 KURIKULUM MERDEKA.pdf
MODUL AJAR SENI MUSIK KELAS 6 KURIKULUM MERDEKA.pdfMODUL AJAR SENI MUSIK KELAS 6 KURIKULUM MERDEKA.pdf
MODUL AJAR SENI MUSIK KELAS 6 KURIKULUM MERDEKA.pdfAndiCoc
 
Materi Asuransi Kesehatan di Indonesia ppt
Materi Asuransi Kesehatan di Indonesia pptMateri Asuransi Kesehatan di Indonesia ppt
Materi Asuransi Kesehatan di Indonesia pptParulianGultom2
 
Topik 4_Eksplorasi Konsep LK Kelompok_Pendidikan Berkelanjutan
Topik 4_Eksplorasi Konsep LK Kelompok_Pendidikan BerkelanjutanTopik 4_Eksplorasi Konsep LK Kelompok_Pendidikan Berkelanjutan
Topik 4_Eksplorasi Konsep LK Kelompok_Pendidikan BerkelanjutanAyuApriliyanti6
 
MODUL AJAR IPAS KELAS 5 KURIKULUM MERDEKA.pdf
MODUL AJAR IPAS KELAS 5 KURIKULUM MERDEKA.pdfMODUL AJAR IPAS KELAS 5 KURIKULUM MERDEKA.pdf
MODUL AJAR IPAS KELAS 5 KURIKULUM MERDEKA.pdfAndiCoc
 
Lokakarya tentang Kepemimpinan Sekolah 1.pptx
Lokakarya tentang Kepemimpinan Sekolah 1.pptxLokakarya tentang Kepemimpinan Sekolah 1.pptx
Lokakarya tentang Kepemimpinan Sekolah 1.pptxrani414352
 
Modul Ajar IPAS Kelas 4 Fase B Kurikulum Merdeka [abdiera.com]
Modul Ajar IPAS Kelas 4 Fase B Kurikulum Merdeka [abdiera.com]Modul Ajar IPAS Kelas 4 Fase B Kurikulum Merdeka [abdiera.com]
Modul Ajar IPAS Kelas 4 Fase B Kurikulum Merdeka [abdiera.com]Abdiera
 
contoh-kisi-kisi-bahasa-inggris-kelas-9.docx
contoh-kisi-kisi-bahasa-inggris-kelas-9.docxcontoh-kisi-kisi-bahasa-inggris-kelas-9.docx
contoh-kisi-kisi-bahasa-inggris-kelas-9.docxdedyfirgiawan
 
Materi Sistem Pernapasan Pada Manusia untuk kelas 5 SD
Materi Sistem Pernapasan Pada Manusia untuk kelas 5 SDMateri Sistem Pernapasan Pada Manusia untuk kelas 5 SD
Materi Sistem Pernapasan Pada Manusia untuk kelas 5 SDsulistyaningsihcahyo
 
Aksi Nyata Menyebarkan Pemahaman Merdeka Belajar.pdf
Aksi Nyata Menyebarkan Pemahaman Merdeka Belajar.pdfAksi Nyata Menyebarkan Pemahaman Merdeka Belajar.pdf
Aksi Nyata Menyebarkan Pemahaman Merdeka Belajar.pdfsubki124
 
Surat Pribadi dan Surat Dinas 7 SMP ppt.pdf
Surat Pribadi dan Surat Dinas 7 SMP ppt.pdfSurat Pribadi dan Surat Dinas 7 SMP ppt.pdf
Surat Pribadi dan Surat Dinas 7 SMP ppt.pdfEirinELS
 
PPT PENDIDIKAN KELAS RANGKAP MODUL 3 KELOMPOK 3.pptx
PPT PENDIDIKAN KELAS RANGKAP MODUL 3 KELOMPOK 3.pptxPPT PENDIDIKAN KELAS RANGKAP MODUL 3 KELOMPOK 3.pptx
PPT PENDIDIKAN KELAS RANGKAP MODUL 3 KELOMPOK 3.pptxJawahirIhsan
 

Recently uploaded (20)

443016507-Sediaan-obat-PHYCOPHYTA-MYOPHYTA-dan-MYCOPHYTA-pptx.pptx
443016507-Sediaan-obat-PHYCOPHYTA-MYOPHYTA-dan-MYCOPHYTA-pptx.pptx443016507-Sediaan-obat-PHYCOPHYTA-MYOPHYTA-dan-MYCOPHYTA-pptx.pptx
443016507-Sediaan-obat-PHYCOPHYTA-MYOPHYTA-dan-MYCOPHYTA-pptx.pptx
 
AKSI NYATA Numerasi Meningkatkan Kompetensi Murid_compressed (1) (1).pptx
AKSI NYATA  Numerasi  Meningkatkan Kompetensi Murid_compressed (1) (1).pptxAKSI NYATA  Numerasi  Meningkatkan Kompetensi Murid_compressed (1) (1).pptx
AKSI NYATA Numerasi Meningkatkan Kompetensi Murid_compressed (1) (1).pptx
 
SISTEM SARAF OTONOM_.SISTEM SARAF OTONOM
SISTEM SARAF OTONOM_.SISTEM SARAF OTONOMSISTEM SARAF OTONOM_.SISTEM SARAF OTONOM
SISTEM SARAF OTONOM_.SISTEM SARAF OTONOM
 
PELAKSANAAN (dgn PT SBI) + Link2 Materi Pelatihan _"Teknik Perhitungan TKDN, ...
PELAKSANAAN (dgn PT SBI) + Link2 Materi Pelatihan _"Teknik Perhitungan TKDN, ...PELAKSANAAN (dgn PT SBI) + Link2 Materi Pelatihan _"Teknik Perhitungan TKDN, ...
PELAKSANAAN (dgn PT SBI) + Link2 Materi Pelatihan _"Teknik Perhitungan TKDN, ...
 
MODUL AJAR BAHASA INGGRIS KELAS 6 KURIKULUM MERDEKA.pdf
MODUL AJAR BAHASA INGGRIS KELAS 6 KURIKULUM MERDEKA.pdfMODUL AJAR BAHASA INGGRIS KELAS 6 KURIKULUM MERDEKA.pdf
MODUL AJAR BAHASA INGGRIS KELAS 6 KURIKULUM MERDEKA.pdf
 
MODUL AJAR SENI TARI KELAS 6 KURIKULUM MERDEKA.pdf
MODUL AJAR SENI TARI KELAS 6 KURIKULUM MERDEKA.pdfMODUL AJAR SENI TARI KELAS 6 KURIKULUM MERDEKA.pdf
MODUL AJAR SENI TARI KELAS 6 KURIKULUM MERDEKA.pdf
 
KISI-KISI SOAL DAN KARTU SOAL BAHASA INGGRIS.docx
KISI-KISI SOAL DAN KARTU SOAL BAHASA INGGRIS.docxKISI-KISI SOAL DAN KARTU SOAL BAHASA INGGRIS.docx
KISI-KISI SOAL DAN KARTU SOAL BAHASA INGGRIS.docx
 
Modul 5 Simetri (simetri lipat, simetri putar)
Modul 5 Simetri (simetri lipat, simetri putar)Modul 5 Simetri (simetri lipat, simetri putar)
Modul 5 Simetri (simetri lipat, simetri putar)
 
Materi Bab 6 Algoritma dan bahasa Pemrograman
Materi Bab 6 Algoritma dan bahasa  PemrogramanMateri Bab 6 Algoritma dan bahasa  Pemrograman
Materi Bab 6 Algoritma dan bahasa Pemrograman
 
MODUL AJAR SENI MUSIK KELAS 6 KURIKULUM MERDEKA.pdf
MODUL AJAR SENI MUSIK KELAS 6 KURIKULUM MERDEKA.pdfMODUL AJAR SENI MUSIK KELAS 6 KURIKULUM MERDEKA.pdf
MODUL AJAR SENI MUSIK KELAS 6 KURIKULUM MERDEKA.pdf
 
Materi Asuransi Kesehatan di Indonesia ppt
Materi Asuransi Kesehatan di Indonesia pptMateri Asuransi Kesehatan di Indonesia ppt
Materi Asuransi Kesehatan di Indonesia ppt
 
Topik 4_Eksplorasi Konsep LK Kelompok_Pendidikan Berkelanjutan
Topik 4_Eksplorasi Konsep LK Kelompok_Pendidikan BerkelanjutanTopik 4_Eksplorasi Konsep LK Kelompok_Pendidikan Berkelanjutan
Topik 4_Eksplorasi Konsep LK Kelompok_Pendidikan Berkelanjutan
 
MODUL AJAR IPAS KELAS 5 KURIKULUM MERDEKA.pdf
MODUL AJAR IPAS KELAS 5 KURIKULUM MERDEKA.pdfMODUL AJAR IPAS KELAS 5 KURIKULUM MERDEKA.pdf
MODUL AJAR IPAS KELAS 5 KURIKULUM MERDEKA.pdf
 
Lokakarya tentang Kepemimpinan Sekolah 1.pptx
Lokakarya tentang Kepemimpinan Sekolah 1.pptxLokakarya tentang Kepemimpinan Sekolah 1.pptx
Lokakarya tentang Kepemimpinan Sekolah 1.pptx
 
Modul Ajar IPAS Kelas 4 Fase B Kurikulum Merdeka [abdiera.com]
Modul Ajar IPAS Kelas 4 Fase B Kurikulum Merdeka [abdiera.com]Modul Ajar IPAS Kelas 4 Fase B Kurikulum Merdeka [abdiera.com]
Modul Ajar IPAS Kelas 4 Fase B Kurikulum Merdeka [abdiera.com]
 
contoh-kisi-kisi-bahasa-inggris-kelas-9.docx
contoh-kisi-kisi-bahasa-inggris-kelas-9.docxcontoh-kisi-kisi-bahasa-inggris-kelas-9.docx
contoh-kisi-kisi-bahasa-inggris-kelas-9.docx
 
Materi Sistem Pernapasan Pada Manusia untuk kelas 5 SD
Materi Sistem Pernapasan Pada Manusia untuk kelas 5 SDMateri Sistem Pernapasan Pada Manusia untuk kelas 5 SD
Materi Sistem Pernapasan Pada Manusia untuk kelas 5 SD
 
Aksi Nyata Menyebarkan Pemahaman Merdeka Belajar.pdf
Aksi Nyata Menyebarkan Pemahaman Merdeka Belajar.pdfAksi Nyata Menyebarkan Pemahaman Merdeka Belajar.pdf
Aksi Nyata Menyebarkan Pemahaman Merdeka Belajar.pdf
 
Surat Pribadi dan Surat Dinas 7 SMP ppt.pdf
Surat Pribadi dan Surat Dinas 7 SMP ppt.pdfSurat Pribadi dan Surat Dinas 7 SMP ppt.pdf
Surat Pribadi dan Surat Dinas 7 SMP ppt.pdf
 
PPT PENDIDIKAN KELAS RANGKAP MODUL 3 KELOMPOK 3.pptx
PPT PENDIDIKAN KELAS RANGKAP MODUL 3 KELOMPOK 3.pptxPPT PENDIDIKAN KELAS RANGKAP MODUL 3 KELOMPOK 3.pptx
PPT PENDIDIKAN KELAS RANGKAP MODUL 3 KELOMPOK 3.pptx
 

Contoh baja

  • 1. Kuat Lentur Rencana untuk Penampang Komposit yang berperilaku Komposit Penuh. Tidak ada Tumpuan Sementara N := 1 9.81 ⋅ kg kN := 1000⋅ N psi := lb ksi := 1000⋅ psi 2 N MPa := in 2 mm b 0.85fc’ t C a y T d d/2 Fy Distribusi tegangan apabila sumbu netral plastis (PNA) di beton Diketahui f'c := 28⋅ MPa WF300x150x6.5x9 Kuat tekan beton 28 hari Profil baja Tinggi penampang d := 350 ⋅ mm Luas Tebal web tw := 6.5⋅ mm Tebal flens As := 46.78 ⋅ cm tf := 9 ⋅ mm Lebar flens 2 b f := 150 ⋅ mm Jari-jari sudut flens-web r := 13⋅ mm Slab beton bertulang di atas profil baja mempunyai ukuran Lebar b := 1830⋅ mm Tebal t := 100 ⋅ mm Tumpuan sementara tidak digunakan, dan momen lentur (akibat beban kerja) adalah sbb: Akibat berat sendiri balok baja M beam := 17.6⋅ kN⋅ m Akibat berat sendiri slab M slab := 84.3⋅ kN⋅ m Akibat beban hidup M L := 95.4⋅ kN⋅ m (abaikan kemungkinan tambahan beban pelaksanaan) Mutu Baja Bj. 50 Fy := 290 ⋅ MPa Modulus elastisitas baja E := 200000⋅ MPa
  • 2. Ditanya: cek apakah kuat lentur rencana dengan menganggap perilaku komposit penuh . Asumsikan pula bahwa perancah (formwork) dapat berfungsi sebagai tumpuan lateral bagi balok baja, sebelum beton mengering. Jawab Kondisi Beton belum Kering Sebelum beton mengering, hanya ada beban mati (pada soal, beban pelaksanaan dapat diabaikan). Jadi, kombinasi pembebanan yang dipakai adalah: M u := 1.4⋅ M beam + M slab M u = 142.66 kN⋅ m ( ) Momen terfaktor tersebut dipikul oleh balok baja saja (beton masih belum mengering). Pengecekan kuat lentur rencana balok baja: 1 2 3 Modulus plastis Zx := b f ⋅ tf ⋅ d − tf + ⋅ tw⋅ d − 2 ⋅ tf Zx = 639.46 cm 4 Faktor tahanan lentur φb := 0.85 ( ) ( ) φb ⋅ Fy ⋅ Zx = 157.63 kN⋅ m Kuat lentur rencana LTB tidak menentukan karena ditumpu lateral oleh perancah KuatLentur := "Oke" if M u ≤ φb ⋅ Fy ⋅ Zx KuatLentur = "Oke" "Tidak Oke" otherwise Kondisi Beton telah Kering Sesudah beton mengering, penampang komposit telah terbentuk. Momen terfaktor yang harus dipikul penampang komposit M u := max⎡ 1.4⋅ M beam + M slab , 1.2⋅ M beam + M slab + 1.6⋅ M L⎤ ⎣ ( ) ( ) ⎦ M u = 274.92 kN⋅ m Ac := b ⋅ t Cek apakah penampang baja kompak Luas slab beton h := d − 2 ⋅ tf − 2 ⋅ r h = 47.08 tw Penampang := 2 Ac = 183000 mm h = 306 mm 3.76⋅ E Fy "Kompak" if = 98.74 h tw ≤ 3.76⋅ E Fy Penampang = "Kompak" "Tidak Kompak" otherwise Catatan: Bila penampang tidak kompak, perhitungan selanjutnya tidak berlaku. Yang berlaku adalah φb = 0.9 dan Mn dihitung dengan menggunakan distribusi tegangan elastis yang berkaitan dengan leleh pertama pada penampang baja. Perilaku komposit penuh berarti resultan tekan C tidak ditentukan oleh ΣQn (kuat geser penghubung geser), dan hanya ditentukan dari: As⋅ Fy = 1356.62 kN 0.85⋅ f'c⋅ Ac = 4355.4 kN ( C := min As⋅ Fy , 0.85⋅ f'c⋅ Ac ) C = 1356.62 kN total
  • 3. PNA := "Di beton" if As⋅ Fy ≤ 0.85⋅ f'c⋅ Ac PNA = "Di beton" "Di baja" otherwise Catatan: Bila sumbu netral plastis (PNA) terletak di beton, maka distribusi tegangan akan sama seperti gambar pada soal. Bila PNA terletak di baja, maka perhitungan di bawah ini tidak berlaku! Tinggi beton yang tertekan a := Lengan momen (jarak antara C dan T) y := Kuat nominal penampang komposit C a = 31.15 mm 0.85⋅ f'c⋅ b d 2 +t− a y = 259.43 mm 2 M n := C⋅ y M n = 351.94 kN⋅ m Kuat rencana penampang komposit adalah φb ⋅ M n = 299.15 kN⋅ m KuatLentur := "Oke" if M u ≤ φb ⋅ M n "Tidak Oke" otherwise KuatLentur = "Oke"