CONSTRUCTION SITE VIS
10 November’2014
SHAILJA KUMARI
B.ARCH,5th YEAR
AIT-SAP
Site Location: Jaypee Wish
Town,Noida Expressway,Noida
TOWER CRANE
The tower crane is a modern form of a balance crane. When fixed
to the ground, tower cranes will often give the best combination of
height and lifting capacity and are also used when constructing
tall buildings.
Fig. Tower Crane
COUNTERWEIGHT CABIN
Fig.1 Boom concrete machine
•All it started with the Boom concrete machine through which
concrete is poured into the frame or where it is required.
•What a concrete pump machine consists of:
 Axle boom
A loose pipe from which concrete comes out
A truck attach to boom to make it transportable.
BATCH MIXER
AXLE BOOM
Through batch mixer
concrete is filled into
pump for pouring
purpose
AXLE
CONCRETE
POURING
PIPE
Now axle will open to its full
length or to desired length for
pouring of concrete
Fig.2,3 Process of concrete pouring
Process of
concrete
pouring
STEP1
STEP2
STEP3
STEP4
Now axle attains its complete
length
Axle movement is controlled
by shown below remote
REMOTE
AXL
E
Fig.4,5 Process of concrete pouring
Through batch mixer
concrete is poured into pump
machine
CONCRETE IS POURED
CONCRETE IS POURED
Fig.6,7 Process of concrete pouring
AXL
E
Fig.8 Process of concrete pouring
Now pump machine is ready
to pour concrete through
concrete pouring pipe
CONCRETE POURING PIPE
It is a very useful construction equipment as concrete needs at
high depth or at higher heights.
Axle boom needs maintenance time to time e.g. greasing of axle
and greasing at axle joints
The most basic type of crane consists of a steel truss or
telescopic boom mounted on a mobile platform, which could be a
rail, wheeled, or even on a cat truck. The boom is hinged at the
bottom and can be either raised or lowered by cables or hydraulic
cylinders.
AXLE
BOOM
CABIN
CRANE
PART
Fig. mobile crane
Fig. Static batch plant
Above picture shows a balcony of static batch plant of concrete.
It has two parts one is front part consists of all machinery and
control system.
Other part is resource part where we put all aggregate to mix with
cement and water in order to form concrete mix.
AGGREGATE
BATCH PLANT
CONTROL SYSTEM.
Fig. Process of making concrete mix
Fig. Process of making concrete mix
Fig. Cube test for concrete mix(for 28 days)
Fig. Site of pile foundation
Here we saw ramming of earth after pile were inserted into the
earth.
Then we have saw reinforcement of piles laid on site
Then we managed to get sizes of the piles as shown pictures
below.
We saw some pumps to for layment of concrete and water then
we have seen coordination among equipments on the
construction site.
REINFORCEMENT OF PILES
sizes and moulds of the pile
sizes and moulds of the pile
PUMP

Construction site visit

  • 1.
    CONSTRUCTION SITE VIS 10November’2014 SHAILJA KUMARI B.ARCH,5th YEAR AIT-SAP Site Location: Jaypee Wish Town,Noida Expressway,Noida
  • 2.
    TOWER CRANE The towercrane is a modern form of a balance crane. When fixed to the ground, tower cranes will often give the best combination of height and lifting capacity and are also used when constructing tall buildings. Fig. Tower Crane COUNTERWEIGHT CABIN
  • 3.
    Fig.1 Boom concretemachine •All it started with the Boom concrete machine through which concrete is poured into the frame or where it is required. •What a concrete pump machine consists of:  Axle boom A loose pipe from which concrete comes out A truck attach to boom to make it transportable.
  • 4.
    BATCH MIXER AXLE BOOM Throughbatch mixer concrete is filled into pump for pouring purpose AXLE CONCRETE POURING PIPE Now axle will open to its full length or to desired length for pouring of concrete Fig.2,3 Process of concrete pouring
  • 5.
  • 6.
    Now axle attainsits complete length Axle movement is controlled by shown below remote REMOTE AXL E Fig.4,5 Process of concrete pouring
  • 7.
    Through batch mixer concreteis poured into pump machine CONCRETE IS POURED CONCRETE IS POURED Fig.6,7 Process of concrete pouring
  • 8.
    AXL E Fig.8 Process ofconcrete pouring Now pump machine is ready to pour concrete through concrete pouring pipe CONCRETE POURING PIPE It is a very useful construction equipment as concrete needs at high depth or at higher heights. Axle boom needs maintenance time to time e.g. greasing of axle and greasing at axle joints
  • 9.
    The most basictype of crane consists of a steel truss or telescopic boom mounted on a mobile platform, which could be a rail, wheeled, or even on a cat truck. The boom is hinged at the bottom and can be either raised or lowered by cables or hydraulic cylinders. AXLE BOOM CABIN CRANE PART Fig. mobile crane
  • 10.
    Fig. Static batchplant Above picture shows a balcony of static batch plant of concrete. It has two parts one is front part consists of all machinery and control system. Other part is resource part where we put all aggregate to mix with cement and water in order to form concrete mix.
  • 11.
  • 12.
    Fig. Process ofmaking concrete mix
  • 13.
    Fig. Process ofmaking concrete mix
  • 14.
    Fig. Cube testfor concrete mix(for 28 days)
  • 15.
    Fig. Site ofpile foundation Here we saw ramming of earth after pile were inserted into the earth. Then we have saw reinforcement of piles laid on site Then we managed to get sizes of the piles as shown pictures below. We saw some pumps to for layment of concrete and water then we have seen coordination among equipments on the construction site.
  • 16.
    REINFORCEMENT OF PILES sizesand moulds of the pile
  • 17.
    sizes and mouldsof the pile PUMP