The document discusses various procurement options including:
1) Traditional design-bid-build (DBB), design-build (DB), and novated design-build where the design team is transferred to the contractor.
2) Integrated options like package deal, turnkey, develop and construct, and design-build-leaseback.
3) Management options where the architect's role is separated into project manager, design manager, and design architect to better integrate design and construction.
This presentation includes information about legal project management fundamentals, creating a framework for legal project management (define, plan, monitor and manage, review and improve), ethics and the law, conflicts from outside counsel and the general counsel.
QUESTION :
Taylor’s University is intending to build a branch campus in Kota Kinabalu, Sabah. Based on Taylor’s University plan they require the branch campus to be operational in mid-2019. Your quantity surveying firm, Innovative Cost Consultant Sdn. Bhd., of which you are a director, has been appointed to provide advice on the procurement system and the tendering methods that are to be adopted in carrying out the project.
The management of the University has informed you that the following requirements are of priority:
i) Cost to completion to be within the budget fixed.
ii) Timely delivery of the facility in order to commence operation in mid- 2019.
You are required to prepare a report to Taylor’s University recommending the procurement system and the tendering method to be adopted.
In your report you shall consider the procurement systems commonly used. You shall list out and explain the advantages and disadvantages of each system before making your recommendation.
As for the tendering methods, you shall consider all the three methods; i.e. open, selective and direct negotiation methods. Similarly you are to describe the advantages and disadvantages of each method before arriving at your recommendation.
Your report shall clearly explain your reasons for your recommendations.
Based on the above recommendations you are also required to prepare a simple programme or schedule in a form of bar chart showing the various activities commencing from the confirmation of the procurement system until completion of the project.
Early contractor involvement (eci) procurement approach spm talk 2016teohwooisin
ECI is a project procurement approach whereby contractors are engaged early to effectively tap on their expertise especially in the aspects buildability, constructability, construction schedule and planning, designs and alternative proposals, value engineering, and latest construction technologies. The presentation will cover the scope of ECI, how ECI could fit into different procurement methods such as Design & Build and traditional procurement, the ECI process and the important considerations in implementing ECI, and the drivers and benefits of ECI. In addition, the ECI models for public sector projects and lessons learned from past ECI cases will also be covered.
This presentation includes information about legal project management fundamentals, creating a framework for legal project management (define, plan, monitor and manage, review and improve), ethics and the law, conflicts from outside counsel and the general counsel.
QUESTION :
Taylor’s University is intending to build a branch campus in Kota Kinabalu, Sabah. Based on Taylor’s University plan they require the branch campus to be operational in mid-2019. Your quantity surveying firm, Innovative Cost Consultant Sdn. Bhd., of which you are a director, has been appointed to provide advice on the procurement system and the tendering methods that are to be adopted in carrying out the project.
The management of the University has informed you that the following requirements are of priority:
i) Cost to completion to be within the budget fixed.
ii) Timely delivery of the facility in order to commence operation in mid- 2019.
You are required to prepare a report to Taylor’s University recommending the procurement system and the tendering method to be adopted.
In your report you shall consider the procurement systems commonly used. You shall list out and explain the advantages and disadvantages of each system before making your recommendation.
As for the tendering methods, you shall consider all the three methods; i.e. open, selective and direct negotiation methods. Similarly you are to describe the advantages and disadvantages of each method before arriving at your recommendation.
Your report shall clearly explain your reasons for your recommendations.
Based on the above recommendations you are also required to prepare a simple programme or schedule in a form of bar chart showing the various activities commencing from the confirmation of the procurement system until completion of the project.
Early contractor involvement (eci) procurement approach spm talk 2016teohwooisin
ECI is a project procurement approach whereby contractors are engaged early to effectively tap on their expertise especially in the aspects buildability, constructability, construction schedule and planning, designs and alternative proposals, value engineering, and latest construction technologies. The presentation will cover the scope of ECI, how ECI could fit into different procurement methods such as Design & Build and traditional procurement, the ECI process and the important considerations in implementing ECI, and the drivers and benefits of ECI. In addition, the ECI models for public sector projects and lessons learned from past ECI cases will also be covered.
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)OECD Governance
Presented at the OECD expert meeting "Construction Risk Management in Infrastructure Procurement: The Loss of Appetite for Fixed-Price Contracts", held on 17 May 2023 at the OECD, Paris and online.
ACE is a mentoring program designed to bring together Chicago's best architecture, engineering, and construction companies to mentor high school teens. The students learn about the building process through weekly activities organized by the mentors.
To get the best results on a design-build project, the owner’s role is as important as that of the design-builder. View this Slideshare to discover six areas where an owner’s early involvement is critical to realize ultimate success.
A Strategic Approach: GenAI in EducationPeter Windle
Artificial Intelligence (AI) technologies such as Generative AI, Image Generators and Large Language Models have had a dramatic impact on teaching, learning and assessment over the past 18 months. The most immediate threat AI posed was to Academic Integrity with Higher Education Institutes (HEIs) focusing their efforts on combating the use of GenAI in assessment. Guidelines were developed for staff and students, policies put in place too. Innovative educators have forged paths in the use of Generative AI for teaching, learning and assessments leading to pockets of transformation springing up across HEIs, often with little or no top-down guidance, support or direction.
This Gasta posits a strategic approach to integrating AI into HEIs to prepare staff, students and the curriculum for an evolving world and workplace. We will highlight the advantages of working with these technologies beyond the realm of teaching, learning and assessment by considering prompt engineering skills, industry impact, curriculum changes, and the need for staff upskilling. In contrast, not engaging strategically with Generative AI poses risks, including falling behind peers, missed opportunities and failing to ensure our graduates remain employable. The rapid evolution of AI technologies necessitates a proactive and strategic approach if we are to remain relevant.
Unit 8 - Information and Communication Technology (Paper I).pdfThiyagu K
This slides describes the basic concepts of ICT, basics of Email, Emerging Technology and Digital Initiatives in Education. This presentations aligns with the UGC Paper I syllabus.
How to Make a Field invisible in Odoo 17Celine George
It is possible to hide or invisible some fields in odoo. Commonly using “invisible” attribute in the field definition to invisible the fields. This slide will show how to make a field invisible in odoo 17.
Macroeconomics- Movie Location
This will be used as part of your Personal Professional Portfolio once graded.
Objective:
Prepare a presentation or a paper using research, basic comparative analysis, data organization and application of economic information. You will make an informed assessment of an economic climate outside of the United States to accomplish an entertainment industry objective.
Read| The latest issue of The Challenger is here! We are thrilled to announce that our school paper has qualified for the NATIONAL SCHOOLS PRESS CONFERENCE (NSPC) 2024. Thank you for your unwavering support and trust. Dive into the stories that made us stand out!
The Roman Empire A Historical Colossus.pdfkaushalkr1407
The Roman Empire, a vast and enduring power, stands as one of history's most remarkable civilizations, leaving an indelible imprint on the world. It emerged from the Roman Republic, transitioning into an imperial powerhouse under the leadership of Augustus Caesar in 27 BCE. This transformation marked the beginning of an era defined by unprecedented territorial expansion, architectural marvels, and profound cultural influence.
The empire's roots lie in the city of Rome, founded, according to legend, by Romulus in 753 BCE. Over centuries, Rome evolved from a small settlement to a formidable republic, characterized by a complex political system with elected officials and checks on power. However, internal strife, class conflicts, and military ambitions paved the way for the end of the Republic. Julius Caesar’s dictatorship and subsequent assassination in 44 BCE created a power vacuum, leading to a civil war. Octavian, later Augustus, emerged victorious, heralding the Roman Empire’s birth.
Under Augustus, the empire experienced the Pax Romana, a 200-year period of relative peace and stability. Augustus reformed the military, established efficient administrative systems, and initiated grand construction projects. The empire's borders expanded, encompassing territories from Britain to Egypt and from Spain to the Euphrates. Roman legions, renowned for their discipline and engineering prowess, secured and maintained these vast territories, building roads, fortifications, and cities that facilitated control and integration.
The Roman Empire’s society was hierarchical, with a rigid class system. At the top were the patricians, wealthy elites who held significant political power. Below them were the plebeians, free citizens with limited political influence, and the vast numbers of slaves who formed the backbone of the economy. The family unit was central, governed by the paterfamilias, the male head who held absolute authority.
Culturally, the Romans were eclectic, absorbing and adapting elements from the civilizations they encountered, particularly the Greeks. Roman art, literature, and philosophy reflected this synthesis, creating a rich cultural tapestry. Latin, the Roman language, became the lingua franca of the Western world, influencing numerous modern languages.
Roman architecture and engineering achievements were monumental. They perfected the arch, vault, and dome, constructing enduring structures like the Colosseum, Pantheon, and aqueducts. These engineering marvels not only showcased Roman ingenuity but also served practical purposes, from public entertainment to water supply.
1. Procurement (CONS6817) Lara Tookey
PROCUREMENT – SESSION #3
Evaluation of Separated and Integrated variations
Introduction to Management techniques
2. Procurement (CONS6817) Lara Tookey
Today:
• Review of the Traditional (DBB) and Design &
Build (DB) procurement options
• Evaluate alternative integrated procurement
options in relation to client objectives
• Introduce Management procurement
options
3. Procurement (CONS6817) Lara Tookey
user
owner
developer
design team
contractor
subcontractor
supplier
Procurement system
financiers
4. Procurement (CONS6817) Lara Tookey
DBB Process
• Client conceives project
• Client hires archi/enge
• A/E provides budget / feasibility
• A/E designs project
• GC bids for project
• C hires GC
• GC hires sub contractors & manages
construction
5. Procurement (CONS6817) Lara Tookey
Defining characteristics
• Linear / Sequential process
• Design led - Bespoke results
• Detail design drawings completed – time
consuming
• Has no input from contractor – limitations?
• Competitive tendering on completed briefing
documents
• Q/A – all parties are self governed
6. Procurement (CONS6817) Lara Tookey
• Considered to be a transparent process
therefore fair
• Reasonable price certainty therefore Fixed
price contract
• Subject to design changes and flexibility
• Well understood process
• Well defined relationships
7. Procurement (CONS6817) Lara Tookey
• Client not heavily involved in construction
process
• Reduces risk to client – no uncertainty
• Contractor does not start construction
process until design / tender process is
complete.
• Changes easy to arrange (dependant on
progress of works)
8. Procurement (CONS6817) Lara Tookey
Quick overview of DB Process
• Client assembles team of advisors
• Project manager – process and brief
• Quantity Surveyor – establishment of budget
• Lawyer – propose contractual arrangements
Only as
required by
the client
9. Procurement (CONS6817) Lara Tookey
DB Process
• O contracts with a single entity to provide the
design and to construct the project (according
to that design).
• The contract could be negotiated with a single
design-builder or result from competitive
proposals.
• Call for proposals (tendering stage)
• Sent to short list of capable D&B contractors
• Response includes
• Statement of capability
• Sketch plan
• Pricing structure
10. Procurement (CONS6817) Lara Tookey
• DB provides the owner with a single point of contact
for project responsibilities, eliminating the need to
assist in resolving designer – contractor disputes.
• With the contractor playing a major role in design,
costs are typically defined to a greater degree.
• The DB’lder makes many decisions that the owner
would make under DBB, due to delegated and
increased authority.
• DB contracts with all A/E firms and subcontractors.
11. Procurement (CONS6817) Lara Tookey
Defining characteristics
• Single point of responsibility
• QA & performance responsibility issues?
• Early determination of final price and schedule.
• Lump sum / Guaranteed maximum price / priced
schedule
• Contractor can manage the design & build
phases overlap and give better control over the
end date.
• Clearer assignment of risk
• Innovative technical solutions
12. Procurement (CONS6817) Lara Tookey
• Can take time to negotiate the contract
• (design needs to be advanced enough for the
client to know what they are buying).
• No certainty that a “best price” has been
achieved.
• Rushing to a contract price before the brief is
clear can lead to later scope creep and
budget blow out.
• Hard to specify quality levels in the contract.
13. Procurement (CONS6817) Lara Tookey
• Differing objectives & priorities
• Different levels of experience
• Different attitudes to the risks they are
willing to take
Clients
>>DEPARTMENT of CONSTRUCTION
15. Procurement (CONS6817) Lara Tookey
Same as Design Build, BUT
• The Client selects a design team and works
with them through brief and sketch plan
phases (sometimes through developed
design).
• A sketch / developed design / outline
specification are produced by this design team.
16. Procurement (CONS6817) Lara Tookey
Novated Design Build
• Through a bid or negotiation process a contract
is agreed with a contractor to finalise the design
and construction of the building.
• As part of that agreement the contract(s) between
the designers and the client are transferred
(novated) to the contractor.
• The contractor selected then takes
responsibility for the development of the
construction details (working drawings) and
construction.
• The design team are ‘novated’ to the contractor.
Novate ~ Law the substitution of a new obligation for an old one by mutual agreement
between the parties
17. Procurement (CONS6817) Lara Tookey
Novated Design Build
Feasibility
Design
Construction
SketchPlan
Developed
Design
Construction
Drawings
Appointment
of design team Appointment of
Contractor
Design team novated from client to
contractor
18. Procurement (CONS6817) Lara Tookey
Today:
• Review of the Traditional (DBB) and Design &
Build (DB) procurement options
• Evaluate alternative integrated
procurement options in relation to client
objectives
• Introduce Management procurement
options
20. Procurement (CONS6817) Lara Tookey
Package Deal
• The precursor & originator of DB.
• Clients wanted to purchase a total package (off
the shelf).
• To satisfy need for speed and economical pricing
• May include land
• May be:
Standard house design e.g. Jenian Homes, Lockwood
Homes etc
Standard sheds or farm buildings e.g. Skyline,
Totalspan
21. Procurement (CONS6817) Lara Tookey
Difference between DB and PD
• Design & Build
• Provides bespoke design solution to suit clients
specific requirements.
• Package Deal
• Uses a proprietary building system in order to
produce a scheme.
• The building type is often modular so that its
size can be adjusted.
22. Procurement (CONS6817) Lara Tookey
Turnkey
• A variant which includes the process plant
within the building.
• Used for projects (more industrial) that are
designed, built, and put into operation
before the project is turned over to the
owner.
23. Procurement (CONS6817) Lara Tookey
• The company providing the turnkey service
may:
• Secure the land for the project;
• Perform / coordinate all aspects of the design;
• Arrange / administer the construction contract;
• Manage construction;
• Staff & train the personal to operate the facility;
• Turn the project over to the owner.
24. Procurement (CONS6817) Lara Tookey
Develop & Construct
• The contractor also acts as the developer, or
the developer also acts as the contractor and
takes responsibility for the development,
design and construction phases
• A common variant to this in NZ is the ‘design-
build-leaseback’ approach to developing
industrial buildings.
25. Procurement (CONS6817) Lara Tookey
User
Owner
Developer
Designer
Contractor
Subcontractor
Supplier
Financiers
So Far………..
27. Procurement (CONS6817) Lara Tookey
Develop & Construct
• The developer has their own construction
team and plays the role of the construction
contractor as well as that of developer.
• Example:
• Manson Developments
• Multiplex
• Industrial building developers
28. Procurement (CONS6817) Lara Tookey
Develop & Construct examples
Lumley Building
Manson Developments
Delloite Centre
Brookfield Multiplex
30. Procurement (CONS6817) Lara Tookey
Design – Build - Leaseback
• Typically initiated by developer / contractor
• most often for industrial buildings
• Developer finds client (C1) who wishes to lease
a custom designed building.
• Developer puts together a development
proposal which includes C1 as lessee.
• Developer then sells the development to an
investor (C2) as a complete package including
the tenant (C1).
31. Procurement (CONS6817) Lara Tookey
Design – Build - Leaseback
User (tenant)
owner
Developer / contractor
subcontractor
supplier
financiers
Lease
agreement
transferred
from
developer
to owner
Contract to purchase the building
with tenant in place
Lease agreement initially established
between developer and tenant
32. Procurement (CONS6817) Lara Tookey
Today:
• Review of the Traditional (DBB) and Design &
Build (DB) procurement options
• Evaluate alternative integrated procurement
options in relation to client objectives
• Introduce Management procurement
options
35. Procurement (CONS6817) Lara Tookey
Traditional Role of the
Architect
Architect
Clients
Representative
Project Manager
Design Team
Leader Architect (Engineer) to
the Contract
Designer
36. Procurement (CONS6817) Lara Tookey
Separation of management and
design functions
• Project Manager
• Responsible for managing the overall process and
coordinating the design team and the construction
team
• May also be the design manager
• Design Architect
• Lead designer
• May also be design manager
• Design Manager
• Responsible for coordinating all members of the design
team
37. Procurement (CONS6817) Lara Tookey
Service offered by Manager
• Based on a fee
• Coordination
• Planning
• Controlling
• Managing design
• Managing construction
• Ensures contractor part of client team from outset
• Maximum construction experience fed into design.
38. Procurement (CONS6817) Lara Tookey
Integration of Design &
Construction
Objectives can include:
• Need for contractor input into design phase:
• Build efficiency
• Incorporation of proprietary systems of contractor
or subcontractor
• Construction programming requirements effect
design
• Fast tracking requirements
• Coordination of the design outputs with overlapping
construction programme
• Construction contractor as project manager
39. Procurement (CONS6817) Lara Tookey
Used when…..
• Project is large & complex
• Fast-track procurement required
• Client wishes to select designer separately
• Often a result of a competition
• Work is not sufficiently designed prior to
construction
• Design and technology designed in tandem – early
contractor involvement essential
40. Procurement (CONS6817) Lara Tookey
Used when…..
• Project is organisationally complex
• Flexibility is required throughout
• Less adversarial approach is preferred
• Choice of competitive tendering for each element
is preferred
• Target price rather than fixed lump sum accepted.
42. Procurement (CONS6817) Lara Tookey
Office Building Whittaker Place
• Project Managers: Carson
Group
• Architects: Warren &
Mahoney
Included Design Management function
43. Procurement (CONS6817) Lara Tookey
Sky City Casino & Tower
• Project Managers: Carson
Group (now Coffey
Projects)
• Design Managers: Beca
• Architects: Moller
Architects
• Management Contractor:
Fletcher Construction
Fee plus GMP & gainshare
44. Procurement (CONS6817) Lara Tookey
Te Papa – Museum of New Zealand
• Project Managers: Carson Group
• Architects: Jasmax
• Construction Managers: Carson
Group
Construction packages included,
• moving existing buildings
• ground consolidation and foundations,
• main building,
• major services packages,
• fit out & displays
45. Procurement (CONS6817) Lara Tookey
These management
orientated systems are
normally an overlay of a
separated or integrated
system (most often separated)