SlideShare a Scribd company logo
1. About SOCET

   Silver Oak College of Engineering and Technology (SOCET) is established in June 2009 and is
   located near Bhavik Publication, Gota Cross road, S.G. Highway, Ahmedabad.
   This is a Degree Engineering College, leading to Bachelor’s Degree in Engineering.
   The College is approved by AICTE, Govt. Of India, and is affiliated with Gujarat Technological
   University.
   This College also runs IGNOU Courses.


                     Silver Oak College of Engineering and Technology




                                          Front View



                   S O C E T           C I V I L                                         1
2. Location of Site/Address
    352,353 A , Nr. Bhavik Publications,
    Opp. Bhagwat Vidyapith,
    Near Gota Cross Road,
    Ahmedabad- 382481.


    Phone:        +91-79-30180000/1/2/3
    Fax:          +91-79-30180005
    Email:        info@socet.edu.in
    Web:          www.socet.edu.in




                                             Key Plan



                    S O C E T              C I V I L    2
3. Background of Contractor

    Contractor Name : Mr. Bharat Patel
    Phone :               +91-9904599666
    Qualification :       12th (Comm.) Pass
    Native Place :        Amreli, Gujarat, India
    Mr. Bharat Patel has 8 years of experience in Construction Technology (Civil Field).
    He has 5 years of experience in making Cement Concrete Road & R.C.C. Road.
    Mr. Bharat Patel has own consultancy named “Patel Developers”.


    This consultancy located at;
           B/104, Akshar Residency,
           Nr. Itihas Bunglow,
           Nikol-Naroda Road,
           Ahmedabad-382350
    This consultancy includes R.C.C., Asphalt Road & Power Block Contractor type of civil
    engineering works.




                      S O C E T          C I V I L                                         3
4. Description of Concrete Road Construction




                        Layout Plan of Concrete Road




               S O C E T      C I V I L                4
5. Materials Used
Cement
Ordinary Portland cement (OPC)
        This should comply with the requirements of IS 269-1976 “Specification for Ordinary and Low-
        Heat Portland Cement (Third Revision)”, or of IS 8112 -1976 “Specification or High Strength
        Ordinary Portland Cement.”
        Ordinary Portland cement and High Strength Ordinary Portland Cement are most widely used for
        concrete pavements.
Rapid hardening Portland cement
        This should comply with the requirement of IS: 8041E-l976 “Emergency Specification for Rapid
        Hardening Portland Cement.”
        In general, this cement would be used only where time is a critical factor and the road is required
        to be opened to traffic at an earlier date than would be possible if Ordinary Portland Cement or
        High Strength Ordinary Portland Cement is used.
Aggregates
        In general, Aggregates should comply with IS : 383-1970 “Specification for Coarse and Fine
        Aggregates from Natural Sources for Concrete (Second Revision)” with special reference to the
        additional requirements stipulated for use in road works excepting in the case of Los Angeles
        Abrasion Test limit.
        The Los Angeles Abrasion Test limits shall be not more than 35 % and 50 % for concrete wearing
        course and sub-base course respectively.
        Maximum size of aggregate should not exceed 1/4th of the pavement slab thickness.
        In case of pavements having reinforcement, Maximum size of aggregate should not exceed 1/4th
        of minimum clear spacing between reinforcing bars.
Water
        Water used in mixing or curing of concrete shall be clean and free from injurious amounts of oil,
        salt, acid, vegetable matter or other substances harmful to the finished concrete.
        It shall meet the requirements stipulated in clause 4.3. Of IS: 456-1978 “Code of Practice for Plain
        and Reinforced Concrete (Second Revision)”.
        Potable waters are generally considered satisfactory for mixing or curing.




                         S O C E T            C I V I L                                             5
Reinforcement
Steel wire fabric
       This shall conform to the requirements of IS: 1566-1967 “Specification for Hard-drawn Steel Wire
       Fabric for Concrete Reinforcement.”
Bar mats
       The steel in bar mats shall conform to the requirement of IS: 432-1966 “Specification for Mild
       Steel and Medium Tensile Steel Bars and Hard-drawn Steel Wire for Concrete Reinforcement.”
       The bars shall be of the size and spacing shown on the plans.
       All junctions of longitudinal and transverse bars shall be securely tied or welded together.
Dowel & Tie Bars
       Dowel and tie bars shall be plain round steel bars conforming to the requirements of IS: 432-1966.
Pre-Moulded Joint Filler
       Pre-Moulded joint filler shall be of the thickness shown on the drawings within a tolerance of ±1.5
       mm.
       It shall be 25 mm less in depth than the thickness of the slab, within a tolerance of ±3 mm and of
       the full width between road forms.
       Holes to accommodate dowel bars shall be accurately bored or punched out.
       The joint filler shall comply with the requirements of IS: 1838-1961 “Specification for Preformed
       Fillers for Expansion Joint in Concrete, Non-extruding and Resilient Type (Bitumen-impregnated
       Fiber).”
Joint Sealing Compound
       The sealing compound shall comply with the requirements of the IS: 1834-1961 “Specification for
       Hot Applied Sealing Compounds for Joints in Concrete.”




                        S O C E T            C I V I L                                                6
Cross section of Road




                                    Cross section of Road




                               Concrete Road Cross section




                        S O C E T     C I V I L              7
6. Leveling Detail For Concrete Road




                                     Leveling Detail For Road



7. Cost Analysis
    The total road constructed is divided into 17 blocks.
    In 1 block, the quantity is used includes the materials such as Cement, Sand, Aggregates, Metal
    Aggregates, R.C.C., etc. is estimated up to 6467.17 m³.
    For 17 blocks, total quantity is about 6467.17 m³ x 17.
    Total estimated amount of cement road construction is about Rs. 1, 24,652.00 (INR).



                     S O C E T            C I V I L                                           8
8. List of Equipment
      A list of tools, equipment and appliances required for the different phases of concrete road
      construction is given below.
      This list pertains to semi-mechanized type of construction only, as practiced most in this country.


Sub-grade and Sub-base Compaction
      Compaction equipment - Three wheeled or tandem roller, pneumatic roller, vibratory roller or
      sheep-foot roller
      Watering devices - Water Lorries, bhisties/water carriers or watering cans
Preparation of Sub-base for Concreting and Formwork
      Scratch templates or strike boards
      Bulk-heads
      Pick axes, shovels and spades
      Formwork and iron stakes
Concrete Manufacture
      Shovels and spades
      Sieving screens
      Weigh batcher
      Aggregate measuring boxes (only where volume batching of aggregates is permitted as a special
      case)
      Water pump
      Water measures
      Concrete mixer
Transportation, Laying and Compaction of Concrete
      Wheel barrows/iron pans
      Wooden bridges
      Spades
      Concrete vibrators (both internal and screed board types)
      Wooden hand tampers




                          S O C E T         C I V I L                                             9
Finishing Operations - Surface and Joints
      Wooden bridges
      Floats (longitudinal and long-handled wooden floats)
      Templates
      Three-meter long straight edges including one master straight edge
      Graduated wedge gauges
      Mild steel sections and blocks for making joint grooves
      Edging tools including double-edging tools
      Canvas belts
      Long handled brooms
      Diamond cutter (when making saw-cut joints)
      Grinder (for grinding local high spots)
Curing
      Hessian cloth burlap or polyethylene sheeting
      Watering devices (for ponding operation)
Cleaning and Sealing of Joints
      Iron raker
      Coir brush
      Cycle pump/pneumatic air blower
      Kerosene stove
      Thermometer
      Transferring pot
      Painter’s brush
      Pouring kettle
      Scraper




                         S O C E T          C I V I L                      10
9. Site Preparation

      Before construction begins, the construction site must be carefully prepared.

      This includes preparing the grade, establishing control mechanisms (the string line), and placing
      dowel baskets.

Preparing the grade, or roadbed

      The majority of concrete pavement failures are not caused by failure of the concrete slab but by
      problems with the materials beneath the slab.
      These problems can include poor drainage, unstable or no uniform materials, or poor compaction.

      Adequate preparation of the roadbed the sub grade, sub-base, and base is essential for a strong,
      durable concrete pavement system.

Sub grade

      Earth has been graded to the desired elevation. (In county and municipal paving projects with low
      traffic volumes, concrete is often placed directly on the prepared earth sub grade.)

Sub base

      A course of material is placed on the sub grade to provide drainage and stability.

Three kinds of sub bases may be used based on the need to balance drain ability and stability:

      Granular sub base is the most drainable sub base.

      It is a mixture of granular material that is uniformly shaped and minimally compacted. It does not
      provide significant structural support; no construction traffic is allowed on a granular sub base.

      Modified sub base is moderately drainable.

      It contains a greater percentage of crushed particles and a denser gradation than granular sub base,
      providing more stability.

      Special backfill provides more stability and support but is the least drainable. It is generally a uniform
      mixture of crushed concrete or crushed limestone, or a mixture of gravel, sand, and soil, with or
      without crushed stone.

      Special backfill or modified sub base is often used under pavement in urban areas to support


                        S O C E T             C I V I L                                               11
construction traffic.

Base

       A course of fairly rigid material, sometimes cement- or asphalt-treated, that is placed on the sub base
       to provide a stable platform for the concrete pavement slab.

Grading

       First the site is graded to cut high points and fill low areas to the desired roadway profile elevations.
       Generally, cut material can be used as embankment fill.
       However, peat, organic silt, or soil with high organic content should not be used; borrow material
       should be used instead.

Stabilization

       Stable soils are generally defined as those that can support loads. Loam or clay loam of glacial till
       origin or clean sand is typically desirable.

       Just as important as the soil’s quality, however, is its uniformity. During excavation, localized pockets
       of various kinds of soil may be encountered where water absorption rates, densities, and expansion
       and contraction rates may vary.

       These pockets lead to different levels of support.

       To stabilize the sub grade so that it will provide uniform support to the rest of the pavement structure,
       localized pockets of undesirable material should be removed and replaced with the dominant soil
       type or with select backfill, or the soil should be treated with additives.

       Typical stabilizing materials are select soils or back-fill—loam or clay loam, clean sand, or other
       stable soil material excavated from road cuts or borrow sites.




                          S O C E T            C I V I L                                                 12
10. Proportioning of Concrete Mixed
Proportioning on the Basis of Strength
     As the stresses induced in concrete pavements are mainly flexural, it is desirable that their design
     is based on the flexural strength of concrete.
     For economical design, the design value adopted for flexural strength of pavement concrete shall
     not be less than 40 kg/sq. cm at 28 days.
     The mix shall be so designed as to ensure the minimum structural strength in the field with the
     desired tolerance level.
     The paving concrete mix should preferably be designed in the laboratory and controlled in the
     field on the basis of its flexural strength.
     Where this is not possible, correlation between flexural and compressive strengths should first be
     established on the basis of actual tests on additional samples made for the purpose at the time of
     designing the mix in the laboratory and quality control then exercised on the basis of compressive
     strength, so long as the materials and mix proportions remain substantially unaltered.
Approximate Proportions
     The approximate proportions by weight (or by volume, only in unavoidable cases) necessary to
     produce concrete satisfying the above conditions using aggregates from the sources designated
     may be furnished in the tender documents, for guidance only, it being expressly understood that
     this information is only for the convenience of the bidder.
Field Mix
     After the award of the contract, the proportions, that is, the field mix, determined by the laboratory
     for the particular aggregates approved by the engineer shall govern.
     These proportions will be corrected and adjusted by the engineer to compensate for moisture
     content in the aggregates or fluctuations in the grading of coarse and fine aggregates at the time of
     use.
     Where fine aggregate is permitted to be measured volumetrically, due allowance should be made
     for its bulking.
Water Content & Workability
     The water content per batch of concrete should be maintained constantly except for suitable
     allowances to be made for free moisture and absorption by aggregates determined from time to
     time during construction.



                        S O C E T             C I V I L                                           13
Adjustments for workability shall be made by variations in the ratio of the course to fine aggregate
     or improving upon their grading without change in cement content or water cement ratio.
     The slump of the concrete mix for pavements compacted by vibration should not be more than 25
     mm, preferably between 0 and 12 mm, and that by manual compaction not more than 50 mm.
     No price adjustment would be permissible for variations in the gradations of the aggregates or in
     the ratio of course to fine aggregates necessitated from adjustment at site.



11. Construction Process
Storage of Concrete
     Cement shall not be stored for a long time and should be used normally within six months of its
     date of receipt.
     Even during this period of storage it is essential that cement shall be protected from moisture by
     storing it in suitable sheds.
     A storage shed with a concrete floor laid on a well-drained foundation may be satisfactory.
     Cement in bags shall be stored on boards raised above the floor level for the purpose of
     ventilation, and the bags shall not touch the walls of the shed.


Handling of Concrete
     Aggregates from different sources and/or of different grading shall not be stacked together.
     Each separate size of coarse aggregate shall be stacked separately.
     If aggregates are stored in conical stacks, segregation will be increased by the rolling of the
     coarser particles down the sides of the stacks.
     To avoid this, stacks should be built up in approximately horizontal layers.
     Dry fine aggregate segregates and gets blown away easily; it may be helpful to moisten it.
     The aggregates shall be handled from the stacks and fed into the mixer in such a manner as to
     secure the stipulated grading of the material.
     Aggregates that have become mixed with earth or other foreign material shall not be used. They
     shall be washed clean before use.




                        S O C E T           C I V I L                                             14
Forms
Steel Form Used




                                              Steel Forms


      The steel forms shall be mild steel channel sections of depth equal to the thickness of the
      pavement.
      The sections shall have a length of at least 3 m except on curves of less than 45 m radius, where
      shorter sections may be used.
      When set to grade and staked in place, the maximum deviation of the top surface of any section
      from a straight line shall not exceed 3 mm in the vertical plane and 5 mm in the horizontal plane.
      The method of connection between sections shall be such that the joint formed shall be free from
      difference in level, play or movement in any direction.
      The use of bent, twisted or worn-out forms will not be permitted. At least three stake pockets for
      bracing pins or stakes shall be provided for each 3 m of form and the bracing and support must be
      ample to prevent springing of the forms under the pressure of concrete or the weight or thrust of
      machinery operating on the forms.
      The supply of forms shall be sufficient to permit their remaining in place for 12 hours after the
      concrete has been placed, or longer if necessary in the opinion of the Engineer-in-charge.


                       S O C E T            C I V I L                                              15
Setting of Forms
      The forms shall be jointed neatly and shall be set with exactness to the required grade and
      alignment. Both before and after the forms are placed and set, the sub-grade or sub-base under the
      forms shall be thoroughly tamped in an approved manner.
      Sufficient rigidity shall be obtained to support the forms in such a position that during the entire
      operation of compacting and finishing of concrete they shall not at any time deviate more than 3
      mm from a straight edge 3 m in length.
      Forms which show a variation from the required rigidity or alignment and levels shown in the
      drawing, shall he reset or removed, as directed.
      The length and number of stakes shall be such as to maintain the forms at the correct line and
      grade.
      All forms shall be cleaned and oiled each time before they are used.
      Forms shall be set for about 200 m ahead of the actual placing of concrete.




                       S O C E T            C I V I L                                            16
12. Transporting & Placing of Concrete




                            Slip Formworks


              S O C E T     C I V I L        17
The concrete shall be mixed in quantities required for immediate use and shall be deposited on the
sub-grade/sub-base to the required depth and width of the pavement section, in successive batches
and in continuous operation without the use of intermediate forms or bulk-heads between joints.
Care shall be taken to see that no segregation of materials results whilst the concrete is being
transported from the mixer to the place where it is deposited.
The usual method of transport of concrete in India is in pans as head loads or in small wheel
barrows.
The spreading shall be as uniform as possible to avoid rehandling of the concrete. Where,
however, a certain amount of re-distribution is necessary, it shall be done with shovels and not
with rakes.
While being placed, the concrete shall be rodded with suitable tools for slab thicknesses of 12.5
cm and less, so that formation of voids or honeycomb pockets is prevented.
The concrete shall be particularly well placed and tapped against the forms and along all joints.
For higher thicknesses an internal vibrator shall be employed in lieu of rodding of the concrete.
To effect adequate compaction, the concrete shall be placed with appropriate surcharge over the
final slab thickness.
The amount of surcharge will depend on the mode of placement of concrete and shall be
determined by trial.
In general, the required surcharge is about 20 per cent of the required slab thickness.
Any portion of the batch of concrete that becomes segregated white depositing it on sub-grade
shall be thoroughly mixed with the main body of the batch during the process of spreading.
In case of unavoidable interruption, a full depth transverse joint shall be made at the point of
stoppage of work provided the section on which the work has been suspended is about 2 to 3 m
tong.
In placing of concrete for two course construction, necessitated by either positioning of the
reinforcement, a richer mix for the wearing surface, or when thickness of the concrete is beyond
20 cm, the bottom layer of concrete shall be struck off to the required levels by a vibrating screed
working on the side forms with notches corresponding to the depth of the top course of concrete.
The vibrating screed should have a vibrating unit mounted on it similar to that of the screed used
for compaction of the final surface of concrete. The time lag between lying of the two courses
shall not exceed the initial setting time of cement.




                  S O C E T            C I V I L                                            18
13. Types of Joints in Concrete Road
There are three main types of joints.
   1. Contraction Joints
   2. Construction Joints
   3. Isolation Joints



       There are three basic joint types used in concrete pavement: contraction, construction and
       isolation.
       Specific design requirements for each type depend upon the joint's orientation to the direction of
       the roadway (transverse or longitudinal). Another important factor is load transfer.
       Except for some isolation joints, all joints provide a means to mechanically connect slabs. The
       connection helps to spread a load applied on one slab onto slabs along its perimeter.
       This decreases the stress within the concrete and increases the longevity of the joint and slab(s).
       The efficiency of the mechanical connection is expressed as load transfer efficiency.



   1. Construction Joints




       Contraction joints are necessary to control natural cracking from stresses caused by concrete
       shrinkage, thermal contraction, and moisture or thermal gradients within the concrete.
       Typically transverse contraction joints are cut at a right angle to the pavement centerline and
       edges.



                         S O C E T           C I V I L                                           19
However, some agencies skew transverse contraction joints to decrease dynamic loading across
  the joints by eliminating the simultaneous crossing of each wheel on a vehicle’s axle.
   Contraction joints are usually sawed into the concrete, but they might be formed or tooled on
  smaller projects.
  The details below show the different types of contraction joints and their dimensions.


2. Construction Joints




  Construction joints join concrete that is paved at different times.
  Transverse construction joints are necessary at the end of a paving segment or at a placement
  interruption for a driveway, cross road or bridge.
  Longitudinal construction joints join lanes that are paved at different times, or join through-lanes
  to curb and gutter or auxiliary lanes. The details below show the different types of construction
  joints and their dimensions.




                      S O C E T          C I V I L                                           20
3. Isolation Joints




   Isolation joints separate the pavement from objects or structures, and allow independent
   movement of the pavement, object or structure without any connection that could cause damage.
   Isolation joints are used where a pavement abuts certain manholes, drainage fixtures, sidewalks
   and buildings, and intersects other pavements or bridges.
   The details below show the different types of isolation joints and their dimensions.




                    S O C E T            C I V I L                                        21
Load Transfer Devices- DOWELS




                                     Cross Section of Dowel Joints
     Transverse expansion joints shall be equipped with dowels of the dimension and at the spacing
     and location indicated on the drawing.
     They shall be firmly supported in place, accurately aligned parallel to the sub-grade/sub-base,
     parallel to each other and parallel to the centre line of the pavement, by means of appropriate
     dowel supports.
     The dowel supports shall ensure that the dowels are not displaced during construction.
     One-half of each dowel shall be painted with a thin film of bitumen and equipped with a tight
     fitting metal sleeve of the dimensions shown on the drawing to provide space for the dowel when
     pavement expands and the joint closes.
     This sleeve shall be partly filled with cotton waste to prevent it being pushed too far on the dowel
     during construction.
     These sleeves are not required on dowels, if used, in dummy contraction or construction joints.
     Dowel bars transfer heavy loads across joints in the pavement, preventing faulting at the joint that
     can lead to pavement damage.

     Practices vary from state to state, but dowel bars are typically required in eight-inch or thicker
     pavements.

     Dowels must be positioned and aligned perfectly so that, as joints open in winter and close in
     summer with contraction and expansion of the concrete, the pavement on either side of the joints
     can move in a straight line along the smooth dowels.

     If a dowel bar is not aligned truly across the joint, the pavement can’t move and a stress results.
     The stress can crack the pavement.




                       S O C E T            C I V I L                                               22
Without dowels, the slab on either side of a joint tends to move up and down; that is, there is little
“load transfer” at the joint.




Dowels help provide load transfer at the joint.




                   S O C E T           C I V I L                                             23
Basket placement
     After the sub base has been properly trimmed and inspected, dowel baskets are set on the road bed,
     perpendicular to the pavement edge or at a slight skew.
     The bars should be located at the mid-depth of the slab and carefully aligned, horizontally and
     vertically.

     As mentioned above, location and alignment of the bars is critical. If they are too close to the edge,
     the paving equipment will snag them.

     When the bars are correctly aligned, the baskets must be secured with stakes. Practices vary from
     state to state, but a minimum of eight stakes (for 12- or 14-foot lane widths) are placed on the leave
     side of the basket wire to secure the basket against movement.

     The location of dowel centers is then marked on both sides of the roadbed, either by setting pins or
     painting marks. The markers indicate where joints should be sawed, ensuring that they will be sawed
     across the center of the dowel assembly.



Final check
     Dowel positions should be checked from three perspectives:

     Sight down the grade to make sure all dowels is parallel to center line.

     Sight across the dowel baskets to make sure all dowels is level. The basket assemblies should be
     parallel to and aligned with each other.

     Sight across the basket, imagining a line from the pin or mark on one side to the pin or mark on the
     other side. Make sure the middle of the dowels falls exactly along that line.

     After dowels have been placed, an inspector should check basket spacing, alignment, and skew.




                       S O C E T            C I V I L                                            24
14. Compaction and Finishing of the top Surface

   Since PCC is an open-graded mix design, finishing takes on a different meaning than standard
   concrete pavement.
   Finishing and compaction are the most crucial steps to producing a durable pavement. Properly
   finishing PCC provides a uniform and level surface that prevents surface raveling of the aggregate,
   while remaining aethstetically pleasing to the public.
   Dry, poorly finished slabs can ravel and appear to have failed even though they are structurally
   sound. Properly finished PCC provides a surface suitable for wheelchair and rollerblade use and
   an ideal surface for recreational trails.
   Many methods exist to finish and compact PCC and they range from those that strictly are for
   finishing, to those that only provide compaction, but most operations provide some degree of both.
   Historically, PCC is struck off ¾ in. to 1 in. above the forms using a shim and vibratory screen as
   shown in Figure.
   Then the shims are removed and the pavement is compacted to final grade using a weighted roller
   as in Figure.




                                  Strike off with a vibratory screed




                      S O C E T            C I V I L                                         25
Compacting using a weight roller

Most recently, roller screeds have been used to finish many PCC pavements.
Roller screeds have been used for many years on traditional concrete, and provide a rapid method
to produce smooth PCC pavements.
Roller screeds are hydraulically driven, stainless steel tubes that rotate against the direction of
placement. Small width slabs (<15 ft.) can easily be finished with a manual roller screed such as
the screed used to finish the pervious test slab at the Road facility.




                   Finishing using a manual roller screed, finished surface


                  S O C E T            C I V I L                                          26
Finishing using a power screed




      Figure shows striking a slab off ¾ in. above the final thickness using a hand-held vibrating screed.

      The shims were then removed and compaction was achieved using a plate compactor on top of a
      sheet of plywood.

      The entire sidewalk at the hospital site was finished using this method and has weathered its first
      winter without any raveling.

Striking off using a vibrating screed




                       S O C E T            C I V I L                                            27
Compaction using plywood and a plate compactor




                         Compaction using plywood and a plate compactor

     PCC edge raveling can be minimized by using a standard edging tool around the forms.
     The edging also adds to the aesthetics of the finished PCC.
     Figure shows use of an edging tool at the Road placement.




                      S O C E T           C I V I L                                         28
15. Making Grooves

Avoid too much water

      The right amount of water is carefully measured at the plant. Extra water weakens the mix. More
      water makes it easier to work with right away, but will lead to a weaker slab.

      If you're mixing your own concrete, do this test: Plow a groove in a mound of concrete with a
      shovel or hoe.

      The groove should be fairly smooth and hold its shape. If it's rough and chunky, add a smidgen of
      water. If it caves in, add more dry concrete.

Don't delay floating




   Bull float in action: Use a bull float to flatten large areas immediately after placing the concrete.



                       S O C E T             C I V I L                                             29
Close up of Groove

Purpose: Used to tool control joints in plastic concrete (as an alternative to saw cutting).




Close-up of groove: A groove has a blade (typically 1-in.) on the underside that cuts the groove

       Grooves are usually made of bronze or stainless steel and have a V-shaped bit that cuts the groove.
       Like edger’s, they come with wood or comfort-grip handles.

       The most common groove size is 6 inches long and 4 1/2 inches wide, but many other sizes are
       available, ranging from 2 to 8 inches wide and 3 to 10 inches long.

       However, more important is the dimension of the bit, which can be anywhere from 1/2 inch to 2
       inches deep and 1/8 to 1 inch wide. Bi-directional grooves are also available and have double-end
       bits that give you the flexibility to cut forward or backward.




                         S O C E T            C I V I L                                            30
Finish with a broom




           Broom the finish: A stiff broom creates a slightly roughened concrete surface

     A smooth, steel trowel finish is too slippery for outdoor concrete.

     Instead, drag a broom over the concrete. You'll get a nonslip texture and hide imperfections left by
     floating or troweling.

     You can use a plain old push broom, but a special concrete broom cuts finer lines.

     The sooner you start, the rougher the finish. Make your first pass about 15 minutes after floating.
     If the texture is too rough, smooth it over with a mag float and try again in 15 minutes.

     Drag the broom over the concrete in parallel, slightly overlapping strokes. You may have to rinse
     off the broom occasionally to avoid a too-rough finish.




                      S O C E T            C I V I L                                            31
16. Curing of Concrete
   Immediately after the finishing operations have been completed, the entire surface of the newly
   laid concrete shall be covered against rapid drying, and cured.
   Failure to provide sufficient cover material of the stipulated type, or inadequate supplies of water
   for curing shall be adequate cause for immediate.


1. Initial Curing
   After completion of the finishing operations, the surface of the pavement shall be entirely covered
   with wet hessian cloth, burlap or jute mats.
   The coverings used shall be of such length (or width) that when laid wilt extend at least 500 mm
   beyond the edges of the slab, shall be so placed that the entire surface and both the edges of the
   stab are completely covered.
   They shall be placed as soon as the concrete has set sufficiently to prevent marring of the surface.
   Prior to their being placed, the coverings shall be thoroughly wetted with water and placed with
   the wettest side down.
   They shall be so weighed down as to cause them to remain in intimate contact with the surface
   covered.
   They shall be maintained fully wetted and in position for 24 hours after the concrete has been
   placed, or until the concrete is sufficiently hard to be walked upon without suffering any damage.
   To maintain the coverings wet, water shall be gently sprayed so as to avoid damage to the fresh
   concrete.
   If it becomes necessary to remove the coverings for any reason, the concrete stab shall not be kept
   exposed for a period of more than half an hour.
   Worn coverings or coverings with holes shall not be permitted.
   Coverings reclaimed from previous use other than curing concrete shall be thoroughly washed
   prior to use for curing purposes.
   If the covering is furnished in strips, the strips shall be laid to overlap at least 150 mm.




                     S O C E T             C I V I L                                              32
2. Final Curing
      Upon the removal of the covering the slab shall be thoroughly wetted and then cured by one of the
      following methods of final curing:
Curing with wet earth
      Exposed edges of the slab shall be banked with a substantial berm of earth.
      Upon the slab shall then be laid a system of transverse and longitudinal dykes of clay about 50
      mm high, covered with a blanket of sandy soil free from stones to prevent the drying up and
      cracking of clay.
      The rest of the slab shall then be covered with sufficient sandy soil so as to produce a blanket of
      earth not less than 40 mm depths after wetting.
      The earth covering shall be thoroughly wetted white it is being placed on the surface and against
      the sides of the slab and kept thoroughly saturated with water for 14 days and thoroughly wetted
      down during the morning of the 15th day and shall thereafter remain in place until the concrete has
      attained the required strength and permission is given to open the pavement to traffic.
      When such permission is granted, the covering shall be removed and the pavement swept clean.
      If the earth covering becomes displaced during the curing period, it shall be replaced to the
      original depth and re-saturated.


   3. Impervious membrane method
      The membrane shall consist of a practically colorless impervious liquid of a type approved by the
      Engineer-in-charge.
      The use of any membrane material which would impart a slippery surface to the pavement or alter
      its natural color will not be permitted.
      Liquid shall be applied under pressure with a spray nozzle in such a manner as to cover the entire
      surface with a uniform film, and shall be of such character that it will harden within 30 minutes
      after application.
      The amount of liquid applied shall be ample to seal the surface of the pavement thoroughly.
      The liquid shall be applied immediately after the finishing of the surface and before the cement
      has set, or, if the pavement is first covered with burlap or hessian cloth or the like, it may be
      applied upon their removal.
      The impervious coating used for membrane curing shall be such that when applied to the surface
      of test slabs made of cement sand mortar in the manner prescribed for the use of the materials in



                           S O C E T         C I V I L                                          33
the field, the mortar shall retain at least 90 per cent of the mixing water when exposed for 144
      hours to temperatures between 32 to 38°C at a relative humidity of 30 % to 50 %.

Insulating

      If air temperatures drop quickly during the first night after placement, the concrete surface will cool
      quickly com-pared to the rest of the concrete.

      Such extreme temperature variations in the slab can cause concrete to change volume at different
      rates (differential thermal contraction), which in turn can cause tensile stress and random cracking in
      the slab.

      Covering the new concrete can help reduce extreme variations in temperature throughout the depth
      of the slab.



Removing of Forms
      Forms shall not be removed from freshly placed concrete until it has set, or at least 12 hours,
      whichever is later.
      They shall be carefully removed in such a manner that no damage is done to the edges of the
      pavement.
      After the forms have been removed, time slab edges shall be cleaned and any limited honey-
      combed areas pointed up with 1:2 cement sand mortar, after which the sides of the slab shall be
      covered with earth to the level of the top of the stab for final curing.
      Slabs with excessive honey-combing as a result of inadequate compaction shall be removed
      between nearest transverse joints.




                        S O C E T            C I V I L                                             34
17. Protection of Concrete

  1. Protection against drying out




     The quality of hardened concrete, and in particular, the durability of the surface, depends directly on
     the protection of the fresh concrete against drying out.

     It is detrimental both to the strength and to the shrinkage (risk of cracks forming) and also to the
     durability when the fresh concrete loses water.

     As a result of their large exposed areas, pavements are greatly subjected to drying out.

     E.g. at an ambient temperature of 20°C, a relative humidity of 60 %, a temperature of the concrete of
     25°C and a wind speed of 25 km/h, 1litre of water will evaporate every hour from every m2 of
     pavement surface.

     Note that the upper surface layer (a few cm thick) of the concrete only contains about 4 liters of water
     per m2.
     A curing compound is usually used to protect road concrete against drying out.
     In case of an exposed aggregate finish, the setting retarder must also have the property that it protects
     the concrete against drying out.
     If not, the concrete must be covered with a plastic sheet as soon as the setting retarder is applied.
     As stated above, subsequent to the removal of the skin of concrete mortar, the concrete is protected
     against drying out a second time by spraying a curing compound or by covering the surface with a
     plastic sheet.
     The latter method is particularly used in urban areas on colored exposed aggregate concrete.




                        S O C E T             C I V I L                                                  35
2. Protection against rain




   Concreting is stopped if it rains. Furthermore, the necessary measures have to be taken to prevent that the
   concrete surface is washed out by rain.
   This applies both to freshly spread concrete that has not been compacted yet and to smoothed concrete.

   Plastic sheets or mobile shelters are suitable means of protection.



3. Protection against frost




                      S O C E T              C I V I L                                              36
When concrete is placed in cold weather the pavement surface has to be effectively protected against
   frost in such a way that the temperature at the surface of the concrete does not drop below + 1 ºC for
   72 hours after placement.

   This protection can consist of, for example, non-woven geotextile or polystyrene foam plates with
   ballast.

4. Protection against mechanical influences (traffic signposting)




   Every necessary measure shall be taken to protect the fresh concrete from damage due to all kinds of
   mechanical influences (Car, Bicycle, Pedestrian, Animals, Bikes, etc.)




                     S O C E T            C I V I L                                            37
18. Advantages of Concrete Road
Durability and maintenance free life:
       Concrete roads have a long service life of forty years, whereas asphalt roads last for ten years. Moreover,
       during this service life concrete road do not require frequent repair or patching work like asphalt roads.
Vehicles consume less fuel:
       A vehicle, when run over a concrete road, consumes 15-20% less fuel than that on asphalt roads. This is
       because of the fact that a concrete road does not get deflected under the wheels of loaded trucks.
Resistant to automobile fuel spillage and extreme weather:
       Unlike asphalt roads, concrete roads do not get damaged by the leaking oils from the vehicles or by the
       extreme weather conditions like excess rain or extreme heat.
Greener process:
       Asphalt (bitumen) produces lots of highly polluting gases at the time of melting it for paving. Also, less fuel
       consumption by the vehicle running on a concrete road means less pollution.
Saving of natural resources:
       Asphalt (bitumen) is produced from imported petroleum, the reserve of which is becoming reduced
       drastically. On the other hand, concrete (cement) is produced from abundantly available limestone.




                          S O C E T               C I V I L                                                   38
19. Special Measures of Concrete

  1. Workability period

     It must always be ensured that the concrete is processed as quickly as possible, certainly within 2 hours
     after batching including the surface treatment and the protection measures.

     In hot, dry weather an even shorter workability time has to be observed (maximum 90 minutes).
     Unless special precautions are taken that have been approved by the manager of the works, concrete can
     only be laid if the air temperature at 1.5 m above ground under thermometer shelter does not exceed
     25°C.

     Furthermore, all necessary measures shall be taken to keep the water content of the concrete as
     constant as possible from the time of batching until completion of the placement.



  2. Paving interruptions

     Whenever the supply of concrete is interrupted, the driver of the paving machine shall immediately
     take the necessary measures to lower the speed of the paving train and to ensure that the machine
     stops as little possible.

     For a short interruption, the machine should be stopped before the deposited concrete in the vibrating
     chamber has dropped to such a level that the vibrators become visible. If the supply is interrupted for
     more than 60 minutes (45 min. in hot weather), a construction joint has to be made.

     Upon a long-lasting defect of the paving equipment, the supply of fresh concrete has to be stopped
     immediately and an attempt must be made to complete the current paving phase.

     If the circumstances and the elapsed workability time no longer make a proper completion
     possible, the concrete, that has been deposited but not yet finished, has to be removed.

     To achieve a continuous profile, particular care is taken of the execution of the construction
     joints, both at the end of the day and every time work is resumed.

     The concrete is compacted preferably with a separate vibrating needle before the paving machine is
     passing in order to obtain properly compacted concrete on both sides of the joint.




                        S O C E T           C I V I L                                               39
3. Placement of concrete on a slope




   When placing concrete on a slope of less than 4 % it is recommended to work uphill, in order to
   prevent tension cracks at the surface.

   Furthermore, the consistency of the concrete and the working speed of the paver have to be adapted to
   the working conditions.

   However, if the longitudinal slope is more than 4 %, unevenness can occur as concrete falls back when
   the machines have passed. In that case, a suitable composition of the concrete mix has to be realized and
   it is recommended to work downhill.

   It must be ensured that enough concrete is deposited in front of the paving machine to prevent the
   concrete from sliding down.

   Concrete pavements have been successfully executed on slopes of 10 to 12 %. At one time the slope
   was even 18%.




                     S O C E T              C I V I L                                             40
20. Weather Consideration

  1. Hot, dry weather paving
Definition

     Temperatures generally above 90°F (32°C), low relative humidity, high wind speed, sunny conditions

Challenges

     Concrete loses moisture more rapidly during hauling and placing.

     Aggregate stockpiles dry out, affecting moisture consistency between batches.

     The pavement sub base dries out before the mixture is placed, then absorbs water from the mixture.

     Rapid water evaporation at the pavement surface can result in shrinkage cracks.

     It’s more difficult to entrain air when temperatures are high. Entrained air is important for pavement
     Durability.

     Concrete sets rapidly, perhaps twice as fast, making finishing more difficult.

     Sawing operations must proceed more rapidly. Additional saws may be required.

     Once heat-related problems develop, it may be too late to fix them.
Precautions

     If possible, do not pave in very hot, dry weather.

     Pave in the morning, evening, or night when air temperatures are cooler.

     Maintain uniform moisture in stockpiles.
     Use retarders in the mixture to slow hydration.
     Use fly ash and slag in the mixture.

     Keep sub base, forms, and equipment damp and cool.

     Apply curing compound as soon as possible. Additional compound may be required.




                      S O C E T             C I V I L                                            41
2. Cold weather paving

Definition

     Air temperature of 50°F or less (10°C) for more than half of any 24-hour period, or when the
     average daily air temperature is less than 40°F (5°C) for three consecutive days.

Challenges

     During cold weather, hydration slows, slowing strength development.
     Concrete cools faster at the surface than inside the slab, causing stress in the slab.
     If the stress is severe enough, the slab will crack randomly.

Precautions

     Do not pave on frozen sub grade.
     Do not use aggregates with frozen lumps.
     Heat materials to raise concrete temperature and promote hydration.
     Minimize use of fly ash and slag.
     Do not pave if the concrete cannot reach adequate strength before it freezes.
     For the first two to three days, protect concrete from freezing with insulating material.

  3. Rain

Challenges

     Before final set, rain can damage the new pavement surface by leaving imprints or washing away
     paste at the surface.

     After final set, rain can induce rapid cooling at the surface, leading to rapid development of thermal
     restraint stresses and possibly early-age, uncontrolled cracking.
Precautions

     If it starts to rain during operations, take the following actions:
     Stop batching and placing operations and cover the fresh concrete immediately with protective
     coverings like polyethylene sheeting or burlap. (Do not try to remove extra surface water first. Do not
     add dry cement to the surface.)



                       S O C E T              C I V I L                                           42
As soon as the surface has dried, apply curing membrane.
After the curing period, diamond grinding may be required to remove surface blemishes and provide
texture to any surface exposed to rain where damage has occurred.




                 S O C E T           C I V I L                                          43

More Related Content

What's hot

Benkelman beam
Benkelman beamBenkelman beam
Benkelman beam
Priyansh Singh
 
HIGHWAY CONSTRUCTION MATERIAL & PRACTICE
HIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICEHIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICE
HIGHWAY CONSTRUCTION MATERIAL & PRACTICE
Fresher Thinking
 
Construction of flexible pavement in brief.
Construction of flexible pavement in brief.Construction of flexible pavement in brief.
Construction of flexible pavement in brief.
AJINKYA THAKRE
 
PAVEMENT DESIGN & TYPES
PAVEMENT DESIGN & TYPES PAVEMENT DESIGN & TYPES
PAVEMENT DESIGN & TYPES
Mahendra meena
 
ppt on pwd cement concrete road pavement
ppt on pwd cement concrete road pavementppt on pwd cement concrete road pavement
ppt on pwd cement concrete road pavement
NIWASHISH VISWAS
 
Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavementsHARITSEHRAWAT
 
Unit 5
Unit 5Unit 5
Soil stabilisation (1)
Soil stabilisation (1)Soil stabilisation (1)
Soil stabilisation (1)
Safiullah Khan
 
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESHPRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
Imrul Quesh
 
Introduction to highway engineering
Introduction to highway engineeringIntroduction to highway engineering
Introduction to highway engineering
Aavani Thampi
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
pradip dangar
 
DESIGN PROJECT FOR PAVEMENT
DESIGN PROJECT FOR PAVEMENTDESIGN PROJECT FOR PAVEMENT
DESIGN PROJECT FOR PAVEMENT
Sukhdarshan Singh
 
L4 engineering surveys for highways 1.3
L4 engineering surveys for highways 1.3 L4 engineering surveys for highways 1.3
L4 engineering surveys for highways 1.3
Sachin PatiL
 
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
VATSAL PATEL
 
Pavement ppt
Pavement pptPavement ppt
Pavement ppt
Harsha Singh
 
Embankment
EmbankmentEmbankment
Embankment
civilguna
 
Construction of flexible pavements
Construction of flexible pavementsConstruction of flexible pavements
Construction of flexible pavements
pradip dangar
 
Summer Training Report On Bituminous (Asphalt) Road
Summer Training Report On Bituminous (Asphalt) RoadSummer Training Report On Bituminous (Asphalt) Road
Summer Training Report On Bituminous (Asphalt) Road
shashanksingh593
 
Construction of flexible pavement
Construction of flexible pavementConstruction of flexible pavement
Construction of flexible pavement
UTU Dehradun
 
Types of joints in rigid pavement
Types of joints in rigid pavementTypes of joints in rigid pavement
Types of joints in rigid pavement
Bhavya Jaiswal
 

What's hot (20)

Benkelman beam
Benkelman beamBenkelman beam
Benkelman beam
 
HIGHWAY CONSTRUCTION MATERIAL & PRACTICE
HIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICEHIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICE
HIGHWAY CONSTRUCTION MATERIAL & PRACTICE
 
Construction of flexible pavement in brief.
Construction of flexible pavement in brief.Construction of flexible pavement in brief.
Construction of flexible pavement in brief.
 
PAVEMENT DESIGN & TYPES
PAVEMENT DESIGN & TYPES PAVEMENT DESIGN & TYPES
PAVEMENT DESIGN & TYPES
 
ppt on pwd cement concrete road pavement
ppt on pwd cement concrete road pavementppt on pwd cement concrete road pavement
ppt on pwd cement concrete road pavement
 
Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavements
 
Unit 5
Unit 5Unit 5
Unit 5
 
Soil stabilisation (1)
Soil stabilisation (1)Soil stabilisation (1)
Soil stabilisation (1)
 
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESHPRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
 
Introduction to highway engineering
Introduction to highway engineeringIntroduction to highway engineering
Introduction to highway engineering
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
 
DESIGN PROJECT FOR PAVEMENT
DESIGN PROJECT FOR PAVEMENTDESIGN PROJECT FOR PAVEMENT
DESIGN PROJECT FOR PAVEMENT
 
L4 engineering surveys for highways 1.3
L4 engineering surveys for highways 1.3 L4 engineering surveys for highways 1.3
L4 engineering surveys for highways 1.3
 
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
 
Pavement ppt
Pavement pptPavement ppt
Pavement ppt
 
Embankment
EmbankmentEmbankment
Embankment
 
Construction of flexible pavements
Construction of flexible pavementsConstruction of flexible pavements
Construction of flexible pavements
 
Summer Training Report On Bituminous (Asphalt) Road
Summer Training Report On Bituminous (Asphalt) RoadSummer Training Report On Bituminous (Asphalt) Road
Summer Training Report On Bituminous (Asphalt) Road
 
Construction of flexible pavement
Construction of flexible pavementConstruction of flexible pavement
Construction of flexible pavement
 
Types of joints in rigid pavement
Types of joints in rigid pavementTypes of joints in rigid pavement
Types of joints in rigid pavement
 

Viewers also liked

4. wbm roads 10 sep
4. wbm roads 10 sep4. wbm roads 10 sep
4. wbm roads 10 sep
Prathamesh Kulkarni
 
cement road construction in the rural areas
cement road construction in the rural areas cement road construction in the rural areas
cement road construction in the rural areas
Anshul Shakya
 
Roads & Pavements
Roads & PavementsRoads & Pavements
Roads & Pavements
Aaqib Iqbal
 
transportation
transportationtransportation
transportation
Navneet Singh
 
PROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONPROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTION
GLA University
 
road construction project
road construction projectroad construction project
road construction project
nishant singh
 
Design and construction of concrete roads
Design and construction of concrete roadsDesign and construction of concrete roads
Design and construction of concrete roadsOlukayode Alao
 
Types of highways
Types of highwaysTypes of highways
Types of highways
Sushant Waghmare
 
BITUMINOUS ROAD PPT
BITUMINOUS ROAD PPTBITUMINOUS ROAD PPT
BITUMINOUS ROAD PPT
shubham paliwal
 
Cal-EPA RPPC Presentation
Cal-EPA RPPC PresentationCal-EPA RPPC Presentation
Cal-EPA RPPC Presentation
Aleesha Pruett
 
Vietnam Bus System Ho Chi Minh City
Vietnam Bus System Ho Chi Minh CityVietnam Bus System Ho Chi Minh City
Vietnam Bus System Ho Chi Minh City
James Barlow
 
Roadwork from CPWD specification
Roadwork from CPWD specificationRoadwork from CPWD specification
Roadwork from CPWD specification
Rajiva Gupta
 
cement concrete road construction procedure
cement concrete road construction procedure cement concrete road construction procedure
cement concrete road construction procedure
jaknap123456
 
India : Construction equipment Sector Report_August 2013
India : Construction equipment Sector Report_August 2013India : Construction equipment Sector Report_August 2013
India : Construction equipment Sector Report_August 2013India Brand Equity Foundation
 
Roads & bridges
Roads & bridgesRoads & bridges
Roads & bridges
Monu Prashar
 
Adler clark 4e ppt 07
Adler clark 4e ppt 07Adler clark 4e ppt 07
Adler clark 4e ppt 07arpsychology
 
Value Engineering for Roads & Highways Project
Value Engineering for Roads & Highways ProjectValue Engineering for Roads & Highways Project
Value Engineering for Roads & Highways Project
ajmal4
 
Trucks and Hauling Equipment
Trucks and Hauling EquipmentTrucks and Hauling Equipment
Trucks and Hauling Equipment
Construction Tech. and Mgmt., VNIT Nagpur
 

Viewers also liked (20)

4. wbm roads 10 sep
4. wbm roads 10 sep4. wbm roads 10 sep
4. wbm roads 10 sep
 
cement road construction in the rural areas
cement road construction in the rural areas cement road construction in the rural areas
cement road construction in the rural areas
 
Roads & Pavements
Roads & PavementsRoads & Pavements
Roads & Pavements
 
transportation
transportationtransportation
transportation
 
PROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONPROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTION
 
road construction project
road construction projectroad construction project
road construction project
 
Design and construction of concrete roads
Design and construction of concrete roadsDesign and construction of concrete roads
Design and construction of concrete roads
 
Types of highways
Types of highwaysTypes of highways
Types of highways
 
BITUMINOUS ROAD PPT
BITUMINOUS ROAD PPTBITUMINOUS ROAD PPT
BITUMINOUS ROAD PPT
 
Cal-EPA RPPC Presentation
Cal-EPA RPPC PresentationCal-EPA RPPC Presentation
Cal-EPA RPPC Presentation
 
Concrete Tools
Concrete Tools Concrete Tools
Concrete Tools
 
Vietnam Bus System Ho Chi Minh City
Vietnam Bus System Ho Chi Minh CityVietnam Bus System Ho Chi Minh City
Vietnam Bus System Ho Chi Minh City
 
Roadwork from CPWD specification
Roadwork from CPWD specificationRoadwork from CPWD specification
Roadwork from CPWD specification
 
cement concrete road construction procedure
cement concrete road construction procedure cement concrete road construction procedure
cement concrete road construction procedure
 
India : Construction equipment Sector Report_August 2013
India : Construction equipment Sector Report_August 2013India : Construction equipment Sector Report_August 2013
India : Construction equipment Sector Report_August 2013
 
Roads & bridges
Roads & bridgesRoads & bridges
Roads & bridges
 
Adler clark 4e ppt 07
Adler clark 4e ppt 07Adler clark 4e ppt 07
Adler clark 4e ppt 07
 
Value Engineering for Roads & Highways Project
Value Engineering for Roads & Highways ProjectValue Engineering for Roads & Highways Project
Value Engineering for Roads & Highways Project
 
Road drainage
Road drainageRoad drainage
Road drainage
 
Trucks and Hauling Equipment
Trucks and Hauling EquipmentTrucks and Hauling Equipment
Trucks and Hauling Equipment
 

Similar to Concrete Road

RCC-.pdf
RCC-.pdfRCC-.pdf
RCC-.pdf
NehaPaliwal31
 
Types of pavement construction procedure
Types of pavement construction procedureTypes of pavement construction procedure
Types of pavement construction procedure
Bhavik A Shah
 
Experimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor SlabExperimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor Slab
IRJET Journal
 
Rigid pavements
Rigid pavements Rigid pavements
Rigid pavements
pradip dangar
 
Design of concrete pavement
Design of concrete pavementDesign of concrete pavement
Design of concrete pavement
Aminat Aliu
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
sfQyoom
 
Construction of Road
Construction of RoadConstruction of Road
Construction of Road
Aman Shakya
 
Industrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERINGIndustrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERING
JAPJEETSINGH13
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concreteMylene Delmoro
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concreteMylene Delmoro
 
Fibre reinforced and ferrocement car park pavers by R Sri Ravindrarajah
Fibre reinforced and ferrocement car park pavers by R Sri RavindrarajahFibre reinforced and ferrocement car park pavers by R Sri Ravindrarajah
Fibre reinforced and ferrocement car park pavers by R Sri Ravindrarajah
Sriravindrarajah Rasiah
 
road drainage
road drainageroad drainage
road drainage
Durgeshsahu42
 
Retrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck LevelRetrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck Level
IRJET Journal
 
PDL’s Construction Development (Technical) Training Session-I_Structural.pptx
PDL’s Construction Development (Technical) Training Session-I_Structural.pptxPDL’s Construction Development (Technical) Training Session-I_Structural.pptx
PDL’s Construction Development (Technical) Training Session-I_Structural.pptx
ChristopherThomas578171
 
IRJET - Design of Improved Drainage System using Pervious Concrete
IRJET  -  	  Design of Improved Drainage System using Pervious ConcreteIRJET  -  	  Design of Improved Drainage System using Pervious Concrete
IRJET - Design of Improved Drainage System using Pervious Concrete
IRJET Journal
 
Florida installation manual(frsa) manual de instalacion
Florida installation manual(frsa) manual de instalacion Florida installation manual(frsa) manual de instalacion
Florida installation manual(frsa) manual de instalacion
Luis Gonzalez
 

Similar to Concrete Road (20)

RCC-.pdf
RCC-.pdfRCC-.pdf
RCC-.pdf
 
Types of pavement construction procedure
Types of pavement construction procedureTypes of pavement construction procedure
Types of pavement construction procedure
 
Experimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor SlabExperimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor Slab
 
Rigid pavements
Rigid pavements Rigid pavements
Rigid pavements
 
Design of concrete pavement
Design of concrete pavementDesign of concrete pavement
Design of concrete pavement
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 
5878 5
5878 55878 5
5878 5
 
Construction of Road
Construction of RoadConstruction of Road
Construction of Road
 
Industrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERINGIndustrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERING
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concrete
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concrete
 
Fibre reinforced and ferrocement car park pavers by R Sri Ravindrarajah
Fibre reinforced and ferrocement car park pavers by R Sri RavindrarajahFibre reinforced and ferrocement car park pavers by R Sri Ravindrarajah
Fibre reinforced and ferrocement car park pavers by R Sri Ravindrarajah
 
road drainage
road drainageroad drainage
road drainage
 
Retrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck LevelRetrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck Level
 
5491
54915491
5491
 
PDL’s Construction Development (Technical) Training Session-I_Structural.pptx
PDL’s Construction Development (Technical) Training Session-I_Structural.pptxPDL’s Construction Development (Technical) Training Session-I_Structural.pptx
PDL’s Construction Development (Technical) Training Session-I_Structural.pptx
 
Zandy ppt.
Zandy ppt.Zandy ppt.
Zandy ppt.
 
IRJET - Design of Improved Drainage System using Pervious Concrete
IRJET  -  	  Design of Improved Drainage System using Pervious ConcreteIRJET  -  	  Design of Improved Drainage System using Pervious Concrete
IRJET - Design of Improved Drainage System using Pervious Concrete
 
Florida installation manual(frsa) manual de instalacion
Florida installation manual(frsa) manual de instalacion Florida installation manual(frsa) manual de instalacion
Florida installation manual(frsa) manual de instalacion
 
4880 4
4880 44880 4
4880 4
 

Recently uploaded

Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
TechSoup
 
Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)
rosedainty
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
EverAndrsGuerraGuerr
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
Anna Sz.
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
GeoBlogs
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
Special education needs
 
How to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERPHow to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERP
Celine George
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
joachimlavalley1
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
EduSkills OECD
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
Sandy Millin
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
Celine George
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
Jisc
 
Basic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumersBasic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumers
PedroFerreira53928
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 
Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
Delapenabediema
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
PedroFerreira53928
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
beazzy04
 

Recently uploaded (20)

Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
 
Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
 
How to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERPHow to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERP
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
 
Basic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumersBasic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumers
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 
Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
 

Concrete Road

  • 1. 1. About SOCET Silver Oak College of Engineering and Technology (SOCET) is established in June 2009 and is located near Bhavik Publication, Gota Cross road, S.G. Highway, Ahmedabad. This is a Degree Engineering College, leading to Bachelor’s Degree in Engineering. The College is approved by AICTE, Govt. Of India, and is affiliated with Gujarat Technological University. This College also runs IGNOU Courses. Silver Oak College of Engineering and Technology Front View S O C E T C I V I L 1
  • 2. 2. Location of Site/Address 352,353 A , Nr. Bhavik Publications, Opp. Bhagwat Vidyapith, Near Gota Cross Road, Ahmedabad- 382481. Phone: +91-79-30180000/1/2/3 Fax: +91-79-30180005 Email: info@socet.edu.in Web: www.socet.edu.in Key Plan S O C E T C I V I L 2
  • 3. 3. Background of Contractor Contractor Name : Mr. Bharat Patel Phone : +91-9904599666 Qualification : 12th (Comm.) Pass Native Place : Amreli, Gujarat, India Mr. Bharat Patel has 8 years of experience in Construction Technology (Civil Field). He has 5 years of experience in making Cement Concrete Road & R.C.C. Road. Mr. Bharat Patel has own consultancy named “Patel Developers”. This consultancy located at; B/104, Akshar Residency, Nr. Itihas Bunglow, Nikol-Naroda Road, Ahmedabad-382350 This consultancy includes R.C.C., Asphalt Road & Power Block Contractor type of civil engineering works. S O C E T C I V I L 3
  • 4. 4. Description of Concrete Road Construction Layout Plan of Concrete Road S O C E T C I V I L 4
  • 5. 5. Materials Used Cement Ordinary Portland cement (OPC) This should comply with the requirements of IS 269-1976 “Specification for Ordinary and Low- Heat Portland Cement (Third Revision)”, or of IS 8112 -1976 “Specification or High Strength Ordinary Portland Cement.” Ordinary Portland cement and High Strength Ordinary Portland Cement are most widely used for concrete pavements. Rapid hardening Portland cement This should comply with the requirement of IS: 8041E-l976 “Emergency Specification for Rapid Hardening Portland Cement.” In general, this cement would be used only where time is a critical factor and the road is required to be opened to traffic at an earlier date than would be possible if Ordinary Portland Cement or High Strength Ordinary Portland Cement is used. Aggregates In general, Aggregates should comply with IS : 383-1970 “Specification for Coarse and Fine Aggregates from Natural Sources for Concrete (Second Revision)” with special reference to the additional requirements stipulated for use in road works excepting in the case of Los Angeles Abrasion Test limit. The Los Angeles Abrasion Test limits shall be not more than 35 % and 50 % for concrete wearing course and sub-base course respectively. Maximum size of aggregate should not exceed 1/4th of the pavement slab thickness. In case of pavements having reinforcement, Maximum size of aggregate should not exceed 1/4th of minimum clear spacing between reinforcing bars. Water Water used in mixing or curing of concrete shall be clean and free from injurious amounts of oil, salt, acid, vegetable matter or other substances harmful to the finished concrete. It shall meet the requirements stipulated in clause 4.3. Of IS: 456-1978 “Code of Practice for Plain and Reinforced Concrete (Second Revision)”. Potable waters are generally considered satisfactory for mixing or curing. S O C E T C I V I L 5
  • 6. Reinforcement Steel wire fabric This shall conform to the requirements of IS: 1566-1967 “Specification for Hard-drawn Steel Wire Fabric for Concrete Reinforcement.” Bar mats The steel in bar mats shall conform to the requirement of IS: 432-1966 “Specification for Mild Steel and Medium Tensile Steel Bars and Hard-drawn Steel Wire for Concrete Reinforcement.” The bars shall be of the size and spacing shown on the plans. All junctions of longitudinal and transverse bars shall be securely tied or welded together. Dowel & Tie Bars Dowel and tie bars shall be plain round steel bars conforming to the requirements of IS: 432-1966. Pre-Moulded Joint Filler Pre-Moulded joint filler shall be of the thickness shown on the drawings within a tolerance of ±1.5 mm. It shall be 25 mm less in depth than the thickness of the slab, within a tolerance of ±3 mm and of the full width between road forms. Holes to accommodate dowel bars shall be accurately bored or punched out. The joint filler shall comply with the requirements of IS: 1838-1961 “Specification for Preformed Fillers for Expansion Joint in Concrete, Non-extruding and Resilient Type (Bitumen-impregnated Fiber).” Joint Sealing Compound The sealing compound shall comply with the requirements of the IS: 1834-1961 “Specification for Hot Applied Sealing Compounds for Joints in Concrete.” S O C E T C I V I L 6
  • 7. Cross section of Road Cross section of Road Concrete Road Cross section S O C E T C I V I L 7
  • 8. 6. Leveling Detail For Concrete Road Leveling Detail For Road 7. Cost Analysis The total road constructed is divided into 17 blocks. In 1 block, the quantity is used includes the materials such as Cement, Sand, Aggregates, Metal Aggregates, R.C.C., etc. is estimated up to 6467.17 m³. For 17 blocks, total quantity is about 6467.17 m³ x 17. Total estimated amount of cement road construction is about Rs. 1, 24,652.00 (INR). S O C E T C I V I L 8
  • 9. 8. List of Equipment A list of tools, equipment and appliances required for the different phases of concrete road construction is given below. This list pertains to semi-mechanized type of construction only, as practiced most in this country. Sub-grade and Sub-base Compaction Compaction equipment - Three wheeled or tandem roller, pneumatic roller, vibratory roller or sheep-foot roller Watering devices - Water Lorries, bhisties/water carriers or watering cans Preparation of Sub-base for Concreting and Formwork Scratch templates or strike boards Bulk-heads Pick axes, shovels and spades Formwork and iron stakes Concrete Manufacture Shovels and spades Sieving screens Weigh batcher Aggregate measuring boxes (only where volume batching of aggregates is permitted as a special case) Water pump Water measures Concrete mixer Transportation, Laying and Compaction of Concrete Wheel barrows/iron pans Wooden bridges Spades Concrete vibrators (both internal and screed board types) Wooden hand tampers S O C E T C I V I L 9
  • 10. Finishing Operations - Surface and Joints Wooden bridges Floats (longitudinal and long-handled wooden floats) Templates Three-meter long straight edges including one master straight edge Graduated wedge gauges Mild steel sections and blocks for making joint grooves Edging tools including double-edging tools Canvas belts Long handled brooms Diamond cutter (when making saw-cut joints) Grinder (for grinding local high spots) Curing Hessian cloth burlap or polyethylene sheeting Watering devices (for ponding operation) Cleaning and Sealing of Joints Iron raker Coir brush Cycle pump/pneumatic air blower Kerosene stove Thermometer Transferring pot Painter’s brush Pouring kettle Scraper S O C E T C I V I L 10
  • 11. 9. Site Preparation Before construction begins, the construction site must be carefully prepared. This includes preparing the grade, establishing control mechanisms (the string line), and placing dowel baskets. Preparing the grade, or roadbed The majority of concrete pavement failures are not caused by failure of the concrete slab but by problems with the materials beneath the slab. These problems can include poor drainage, unstable or no uniform materials, or poor compaction. Adequate preparation of the roadbed the sub grade, sub-base, and base is essential for a strong, durable concrete pavement system. Sub grade Earth has been graded to the desired elevation. (In county and municipal paving projects with low traffic volumes, concrete is often placed directly on the prepared earth sub grade.) Sub base A course of material is placed on the sub grade to provide drainage and stability. Three kinds of sub bases may be used based on the need to balance drain ability and stability: Granular sub base is the most drainable sub base. It is a mixture of granular material that is uniformly shaped and minimally compacted. It does not provide significant structural support; no construction traffic is allowed on a granular sub base. Modified sub base is moderately drainable. It contains a greater percentage of crushed particles and a denser gradation than granular sub base, providing more stability. Special backfill provides more stability and support but is the least drainable. It is generally a uniform mixture of crushed concrete or crushed limestone, or a mixture of gravel, sand, and soil, with or without crushed stone. Special backfill or modified sub base is often used under pavement in urban areas to support S O C E T C I V I L 11
  • 12. construction traffic. Base A course of fairly rigid material, sometimes cement- or asphalt-treated, that is placed on the sub base to provide a stable platform for the concrete pavement slab. Grading First the site is graded to cut high points and fill low areas to the desired roadway profile elevations. Generally, cut material can be used as embankment fill. However, peat, organic silt, or soil with high organic content should not be used; borrow material should be used instead. Stabilization Stable soils are generally defined as those that can support loads. Loam or clay loam of glacial till origin or clean sand is typically desirable. Just as important as the soil’s quality, however, is its uniformity. During excavation, localized pockets of various kinds of soil may be encountered where water absorption rates, densities, and expansion and contraction rates may vary. These pockets lead to different levels of support. To stabilize the sub grade so that it will provide uniform support to the rest of the pavement structure, localized pockets of undesirable material should be removed and replaced with the dominant soil type or with select backfill, or the soil should be treated with additives. Typical stabilizing materials are select soils or back-fill—loam or clay loam, clean sand, or other stable soil material excavated from road cuts or borrow sites. S O C E T C I V I L 12
  • 13. 10. Proportioning of Concrete Mixed Proportioning on the Basis of Strength As the stresses induced in concrete pavements are mainly flexural, it is desirable that their design is based on the flexural strength of concrete. For economical design, the design value adopted for flexural strength of pavement concrete shall not be less than 40 kg/sq. cm at 28 days. The mix shall be so designed as to ensure the minimum structural strength in the field with the desired tolerance level. The paving concrete mix should preferably be designed in the laboratory and controlled in the field on the basis of its flexural strength. Where this is not possible, correlation between flexural and compressive strengths should first be established on the basis of actual tests on additional samples made for the purpose at the time of designing the mix in the laboratory and quality control then exercised on the basis of compressive strength, so long as the materials and mix proportions remain substantially unaltered. Approximate Proportions The approximate proportions by weight (or by volume, only in unavoidable cases) necessary to produce concrete satisfying the above conditions using aggregates from the sources designated may be furnished in the tender documents, for guidance only, it being expressly understood that this information is only for the convenience of the bidder. Field Mix After the award of the contract, the proportions, that is, the field mix, determined by the laboratory for the particular aggregates approved by the engineer shall govern. These proportions will be corrected and adjusted by the engineer to compensate for moisture content in the aggregates or fluctuations in the grading of coarse and fine aggregates at the time of use. Where fine aggregate is permitted to be measured volumetrically, due allowance should be made for its bulking. Water Content & Workability The water content per batch of concrete should be maintained constantly except for suitable allowances to be made for free moisture and absorption by aggregates determined from time to time during construction. S O C E T C I V I L 13
  • 14. Adjustments for workability shall be made by variations in the ratio of the course to fine aggregate or improving upon their grading without change in cement content or water cement ratio. The slump of the concrete mix for pavements compacted by vibration should not be more than 25 mm, preferably between 0 and 12 mm, and that by manual compaction not more than 50 mm. No price adjustment would be permissible for variations in the gradations of the aggregates or in the ratio of course to fine aggregates necessitated from adjustment at site. 11. Construction Process Storage of Concrete Cement shall not be stored for a long time and should be used normally within six months of its date of receipt. Even during this period of storage it is essential that cement shall be protected from moisture by storing it in suitable sheds. A storage shed with a concrete floor laid on a well-drained foundation may be satisfactory. Cement in bags shall be stored on boards raised above the floor level for the purpose of ventilation, and the bags shall not touch the walls of the shed. Handling of Concrete Aggregates from different sources and/or of different grading shall not be stacked together. Each separate size of coarse aggregate shall be stacked separately. If aggregates are stored in conical stacks, segregation will be increased by the rolling of the coarser particles down the sides of the stacks. To avoid this, stacks should be built up in approximately horizontal layers. Dry fine aggregate segregates and gets blown away easily; it may be helpful to moisten it. The aggregates shall be handled from the stacks and fed into the mixer in such a manner as to secure the stipulated grading of the material. Aggregates that have become mixed with earth or other foreign material shall not be used. They shall be washed clean before use. S O C E T C I V I L 14
  • 15. Forms Steel Form Used Steel Forms The steel forms shall be mild steel channel sections of depth equal to the thickness of the pavement. The sections shall have a length of at least 3 m except on curves of less than 45 m radius, where shorter sections may be used. When set to grade and staked in place, the maximum deviation of the top surface of any section from a straight line shall not exceed 3 mm in the vertical plane and 5 mm in the horizontal plane. The method of connection between sections shall be such that the joint formed shall be free from difference in level, play or movement in any direction. The use of bent, twisted or worn-out forms will not be permitted. At least three stake pockets for bracing pins or stakes shall be provided for each 3 m of form and the bracing and support must be ample to prevent springing of the forms under the pressure of concrete or the weight or thrust of machinery operating on the forms. The supply of forms shall be sufficient to permit their remaining in place for 12 hours after the concrete has been placed, or longer if necessary in the opinion of the Engineer-in-charge. S O C E T C I V I L 15
  • 16. Setting of Forms The forms shall be jointed neatly and shall be set with exactness to the required grade and alignment. Both before and after the forms are placed and set, the sub-grade or sub-base under the forms shall be thoroughly tamped in an approved manner. Sufficient rigidity shall be obtained to support the forms in such a position that during the entire operation of compacting and finishing of concrete they shall not at any time deviate more than 3 mm from a straight edge 3 m in length. Forms which show a variation from the required rigidity or alignment and levels shown in the drawing, shall he reset or removed, as directed. The length and number of stakes shall be such as to maintain the forms at the correct line and grade. All forms shall be cleaned and oiled each time before they are used. Forms shall be set for about 200 m ahead of the actual placing of concrete. S O C E T C I V I L 16
  • 17. 12. Transporting & Placing of Concrete Slip Formworks S O C E T C I V I L 17
  • 18. The concrete shall be mixed in quantities required for immediate use and shall be deposited on the sub-grade/sub-base to the required depth and width of the pavement section, in successive batches and in continuous operation without the use of intermediate forms or bulk-heads between joints. Care shall be taken to see that no segregation of materials results whilst the concrete is being transported from the mixer to the place where it is deposited. The usual method of transport of concrete in India is in pans as head loads or in small wheel barrows. The spreading shall be as uniform as possible to avoid rehandling of the concrete. Where, however, a certain amount of re-distribution is necessary, it shall be done with shovels and not with rakes. While being placed, the concrete shall be rodded with suitable tools for slab thicknesses of 12.5 cm and less, so that formation of voids or honeycomb pockets is prevented. The concrete shall be particularly well placed and tapped against the forms and along all joints. For higher thicknesses an internal vibrator shall be employed in lieu of rodding of the concrete. To effect adequate compaction, the concrete shall be placed with appropriate surcharge over the final slab thickness. The amount of surcharge will depend on the mode of placement of concrete and shall be determined by trial. In general, the required surcharge is about 20 per cent of the required slab thickness. Any portion of the batch of concrete that becomes segregated white depositing it on sub-grade shall be thoroughly mixed with the main body of the batch during the process of spreading. In case of unavoidable interruption, a full depth transverse joint shall be made at the point of stoppage of work provided the section on which the work has been suspended is about 2 to 3 m tong. In placing of concrete for two course construction, necessitated by either positioning of the reinforcement, a richer mix for the wearing surface, or when thickness of the concrete is beyond 20 cm, the bottom layer of concrete shall be struck off to the required levels by a vibrating screed working on the side forms with notches corresponding to the depth of the top course of concrete. The vibrating screed should have a vibrating unit mounted on it similar to that of the screed used for compaction of the final surface of concrete. The time lag between lying of the two courses shall not exceed the initial setting time of cement. S O C E T C I V I L 18
  • 19. 13. Types of Joints in Concrete Road There are three main types of joints. 1. Contraction Joints 2. Construction Joints 3. Isolation Joints There are three basic joint types used in concrete pavement: contraction, construction and isolation. Specific design requirements for each type depend upon the joint's orientation to the direction of the roadway (transverse or longitudinal). Another important factor is load transfer. Except for some isolation joints, all joints provide a means to mechanically connect slabs. The connection helps to spread a load applied on one slab onto slabs along its perimeter. This decreases the stress within the concrete and increases the longevity of the joint and slab(s). The efficiency of the mechanical connection is expressed as load transfer efficiency. 1. Construction Joints Contraction joints are necessary to control natural cracking from stresses caused by concrete shrinkage, thermal contraction, and moisture or thermal gradients within the concrete. Typically transverse contraction joints are cut at a right angle to the pavement centerline and edges. S O C E T C I V I L 19
  • 20. However, some agencies skew transverse contraction joints to decrease dynamic loading across the joints by eliminating the simultaneous crossing of each wheel on a vehicle’s axle. Contraction joints are usually sawed into the concrete, but they might be formed or tooled on smaller projects. The details below show the different types of contraction joints and their dimensions. 2. Construction Joints Construction joints join concrete that is paved at different times. Transverse construction joints are necessary at the end of a paving segment or at a placement interruption for a driveway, cross road or bridge. Longitudinal construction joints join lanes that are paved at different times, or join through-lanes to curb and gutter or auxiliary lanes. The details below show the different types of construction joints and their dimensions. S O C E T C I V I L 20
  • 21. 3. Isolation Joints Isolation joints separate the pavement from objects or structures, and allow independent movement of the pavement, object or structure without any connection that could cause damage. Isolation joints are used where a pavement abuts certain manholes, drainage fixtures, sidewalks and buildings, and intersects other pavements or bridges. The details below show the different types of isolation joints and their dimensions. S O C E T C I V I L 21
  • 22. Load Transfer Devices- DOWELS Cross Section of Dowel Joints Transverse expansion joints shall be equipped with dowels of the dimension and at the spacing and location indicated on the drawing. They shall be firmly supported in place, accurately aligned parallel to the sub-grade/sub-base, parallel to each other and parallel to the centre line of the pavement, by means of appropriate dowel supports. The dowel supports shall ensure that the dowels are not displaced during construction. One-half of each dowel shall be painted with a thin film of bitumen and equipped with a tight fitting metal sleeve of the dimensions shown on the drawing to provide space for the dowel when pavement expands and the joint closes. This sleeve shall be partly filled with cotton waste to prevent it being pushed too far on the dowel during construction. These sleeves are not required on dowels, if used, in dummy contraction or construction joints. Dowel bars transfer heavy loads across joints in the pavement, preventing faulting at the joint that can lead to pavement damage. Practices vary from state to state, but dowel bars are typically required in eight-inch or thicker pavements. Dowels must be positioned and aligned perfectly so that, as joints open in winter and close in summer with contraction and expansion of the concrete, the pavement on either side of the joints can move in a straight line along the smooth dowels. If a dowel bar is not aligned truly across the joint, the pavement can’t move and a stress results. The stress can crack the pavement. S O C E T C I V I L 22
  • 23. Without dowels, the slab on either side of a joint tends to move up and down; that is, there is little “load transfer” at the joint. Dowels help provide load transfer at the joint. S O C E T C I V I L 23
  • 24. Basket placement After the sub base has been properly trimmed and inspected, dowel baskets are set on the road bed, perpendicular to the pavement edge or at a slight skew. The bars should be located at the mid-depth of the slab and carefully aligned, horizontally and vertically. As mentioned above, location and alignment of the bars is critical. If they are too close to the edge, the paving equipment will snag them. When the bars are correctly aligned, the baskets must be secured with stakes. Practices vary from state to state, but a minimum of eight stakes (for 12- or 14-foot lane widths) are placed on the leave side of the basket wire to secure the basket against movement. The location of dowel centers is then marked on both sides of the roadbed, either by setting pins or painting marks. The markers indicate where joints should be sawed, ensuring that they will be sawed across the center of the dowel assembly. Final check Dowel positions should be checked from three perspectives: Sight down the grade to make sure all dowels is parallel to center line. Sight across the dowel baskets to make sure all dowels is level. The basket assemblies should be parallel to and aligned with each other. Sight across the basket, imagining a line from the pin or mark on one side to the pin or mark on the other side. Make sure the middle of the dowels falls exactly along that line. After dowels have been placed, an inspector should check basket spacing, alignment, and skew. S O C E T C I V I L 24
  • 25. 14. Compaction and Finishing of the top Surface Since PCC is an open-graded mix design, finishing takes on a different meaning than standard concrete pavement. Finishing and compaction are the most crucial steps to producing a durable pavement. Properly finishing PCC provides a uniform and level surface that prevents surface raveling of the aggregate, while remaining aethstetically pleasing to the public. Dry, poorly finished slabs can ravel and appear to have failed even though they are structurally sound. Properly finished PCC provides a surface suitable for wheelchair and rollerblade use and an ideal surface for recreational trails. Many methods exist to finish and compact PCC and they range from those that strictly are for finishing, to those that only provide compaction, but most operations provide some degree of both. Historically, PCC is struck off ¾ in. to 1 in. above the forms using a shim and vibratory screen as shown in Figure. Then the shims are removed and the pavement is compacted to final grade using a weighted roller as in Figure. Strike off with a vibratory screed S O C E T C I V I L 25
  • 26. Compacting using a weight roller Most recently, roller screeds have been used to finish many PCC pavements. Roller screeds have been used for many years on traditional concrete, and provide a rapid method to produce smooth PCC pavements. Roller screeds are hydraulically driven, stainless steel tubes that rotate against the direction of placement. Small width slabs (<15 ft.) can easily be finished with a manual roller screed such as the screed used to finish the pervious test slab at the Road facility. Finishing using a manual roller screed, finished surface S O C E T C I V I L 26
  • 27. Finishing using a power screed Figure shows striking a slab off ¾ in. above the final thickness using a hand-held vibrating screed. The shims were then removed and compaction was achieved using a plate compactor on top of a sheet of plywood. The entire sidewalk at the hospital site was finished using this method and has weathered its first winter without any raveling. Striking off using a vibrating screed S O C E T C I V I L 27
  • 28. Compaction using plywood and a plate compactor Compaction using plywood and a plate compactor PCC edge raveling can be minimized by using a standard edging tool around the forms. The edging also adds to the aesthetics of the finished PCC. Figure shows use of an edging tool at the Road placement. S O C E T C I V I L 28
  • 29. 15. Making Grooves Avoid too much water The right amount of water is carefully measured at the plant. Extra water weakens the mix. More water makes it easier to work with right away, but will lead to a weaker slab. If you're mixing your own concrete, do this test: Plow a groove in a mound of concrete with a shovel or hoe. The groove should be fairly smooth and hold its shape. If it's rough and chunky, add a smidgen of water. If it caves in, add more dry concrete. Don't delay floating Bull float in action: Use a bull float to flatten large areas immediately after placing the concrete. S O C E T C I V I L 29
  • 30. Close up of Groove Purpose: Used to tool control joints in plastic concrete (as an alternative to saw cutting). Close-up of groove: A groove has a blade (typically 1-in.) on the underside that cuts the groove Grooves are usually made of bronze or stainless steel and have a V-shaped bit that cuts the groove. Like edger’s, they come with wood or comfort-grip handles. The most common groove size is 6 inches long and 4 1/2 inches wide, but many other sizes are available, ranging from 2 to 8 inches wide and 3 to 10 inches long. However, more important is the dimension of the bit, which can be anywhere from 1/2 inch to 2 inches deep and 1/8 to 1 inch wide. Bi-directional grooves are also available and have double-end bits that give you the flexibility to cut forward or backward. S O C E T C I V I L 30
  • 31. Finish with a broom Broom the finish: A stiff broom creates a slightly roughened concrete surface A smooth, steel trowel finish is too slippery for outdoor concrete. Instead, drag a broom over the concrete. You'll get a nonslip texture and hide imperfections left by floating or troweling. You can use a plain old push broom, but a special concrete broom cuts finer lines. The sooner you start, the rougher the finish. Make your first pass about 15 minutes after floating. If the texture is too rough, smooth it over with a mag float and try again in 15 minutes. Drag the broom over the concrete in parallel, slightly overlapping strokes. You may have to rinse off the broom occasionally to avoid a too-rough finish. S O C E T C I V I L 31
  • 32. 16. Curing of Concrete Immediately after the finishing operations have been completed, the entire surface of the newly laid concrete shall be covered against rapid drying, and cured. Failure to provide sufficient cover material of the stipulated type, or inadequate supplies of water for curing shall be adequate cause for immediate. 1. Initial Curing After completion of the finishing operations, the surface of the pavement shall be entirely covered with wet hessian cloth, burlap or jute mats. The coverings used shall be of such length (or width) that when laid wilt extend at least 500 mm beyond the edges of the slab, shall be so placed that the entire surface and both the edges of the stab are completely covered. They shall be placed as soon as the concrete has set sufficiently to prevent marring of the surface. Prior to their being placed, the coverings shall be thoroughly wetted with water and placed with the wettest side down. They shall be so weighed down as to cause them to remain in intimate contact with the surface covered. They shall be maintained fully wetted and in position for 24 hours after the concrete has been placed, or until the concrete is sufficiently hard to be walked upon without suffering any damage. To maintain the coverings wet, water shall be gently sprayed so as to avoid damage to the fresh concrete. If it becomes necessary to remove the coverings for any reason, the concrete stab shall not be kept exposed for a period of more than half an hour. Worn coverings or coverings with holes shall not be permitted. Coverings reclaimed from previous use other than curing concrete shall be thoroughly washed prior to use for curing purposes. If the covering is furnished in strips, the strips shall be laid to overlap at least 150 mm. S O C E T C I V I L 32
  • 33. 2. Final Curing Upon the removal of the covering the slab shall be thoroughly wetted and then cured by one of the following methods of final curing: Curing with wet earth Exposed edges of the slab shall be banked with a substantial berm of earth. Upon the slab shall then be laid a system of transverse and longitudinal dykes of clay about 50 mm high, covered with a blanket of sandy soil free from stones to prevent the drying up and cracking of clay. The rest of the slab shall then be covered with sufficient sandy soil so as to produce a blanket of earth not less than 40 mm depths after wetting. The earth covering shall be thoroughly wetted white it is being placed on the surface and against the sides of the slab and kept thoroughly saturated with water for 14 days and thoroughly wetted down during the morning of the 15th day and shall thereafter remain in place until the concrete has attained the required strength and permission is given to open the pavement to traffic. When such permission is granted, the covering shall be removed and the pavement swept clean. If the earth covering becomes displaced during the curing period, it shall be replaced to the original depth and re-saturated. 3. Impervious membrane method The membrane shall consist of a practically colorless impervious liquid of a type approved by the Engineer-in-charge. The use of any membrane material which would impart a slippery surface to the pavement or alter its natural color will not be permitted. Liquid shall be applied under pressure with a spray nozzle in such a manner as to cover the entire surface with a uniform film, and shall be of such character that it will harden within 30 minutes after application. The amount of liquid applied shall be ample to seal the surface of the pavement thoroughly. The liquid shall be applied immediately after the finishing of the surface and before the cement has set, or, if the pavement is first covered with burlap or hessian cloth or the like, it may be applied upon their removal. The impervious coating used for membrane curing shall be such that when applied to the surface of test slabs made of cement sand mortar in the manner prescribed for the use of the materials in S O C E T C I V I L 33
  • 34. the field, the mortar shall retain at least 90 per cent of the mixing water when exposed for 144 hours to temperatures between 32 to 38°C at a relative humidity of 30 % to 50 %. Insulating If air temperatures drop quickly during the first night after placement, the concrete surface will cool quickly com-pared to the rest of the concrete. Such extreme temperature variations in the slab can cause concrete to change volume at different rates (differential thermal contraction), which in turn can cause tensile stress and random cracking in the slab. Covering the new concrete can help reduce extreme variations in temperature throughout the depth of the slab. Removing of Forms Forms shall not be removed from freshly placed concrete until it has set, or at least 12 hours, whichever is later. They shall be carefully removed in such a manner that no damage is done to the edges of the pavement. After the forms have been removed, time slab edges shall be cleaned and any limited honey- combed areas pointed up with 1:2 cement sand mortar, after which the sides of the slab shall be covered with earth to the level of the top of the stab for final curing. Slabs with excessive honey-combing as a result of inadequate compaction shall be removed between nearest transverse joints. S O C E T C I V I L 34
  • 35. 17. Protection of Concrete 1. Protection against drying out The quality of hardened concrete, and in particular, the durability of the surface, depends directly on the protection of the fresh concrete against drying out. It is detrimental both to the strength and to the shrinkage (risk of cracks forming) and also to the durability when the fresh concrete loses water. As a result of their large exposed areas, pavements are greatly subjected to drying out. E.g. at an ambient temperature of 20°C, a relative humidity of 60 %, a temperature of the concrete of 25°C and a wind speed of 25 km/h, 1litre of water will evaporate every hour from every m2 of pavement surface. Note that the upper surface layer (a few cm thick) of the concrete only contains about 4 liters of water per m2. A curing compound is usually used to protect road concrete against drying out. In case of an exposed aggregate finish, the setting retarder must also have the property that it protects the concrete against drying out. If not, the concrete must be covered with a plastic sheet as soon as the setting retarder is applied. As stated above, subsequent to the removal of the skin of concrete mortar, the concrete is protected against drying out a second time by spraying a curing compound or by covering the surface with a plastic sheet. The latter method is particularly used in urban areas on colored exposed aggregate concrete. S O C E T C I V I L 35
  • 36. 2. Protection against rain Concreting is stopped if it rains. Furthermore, the necessary measures have to be taken to prevent that the concrete surface is washed out by rain. This applies both to freshly spread concrete that has not been compacted yet and to smoothed concrete. Plastic sheets or mobile shelters are suitable means of protection. 3. Protection against frost S O C E T C I V I L 36
  • 37. When concrete is placed in cold weather the pavement surface has to be effectively protected against frost in such a way that the temperature at the surface of the concrete does not drop below + 1 ºC for 72 hours after placement. This protection can consist of, for example, non-woven geotextile or polystyrene foam plates with ballast. 4. Protection against mechanical influences (traffic signposting) Every necessary measure shall be taken to protect the fresh concrete from damage due to all kinds of mechanical influences (Car, Bicycle, Pedestrian, Animals, Bikes, etc.) S O C E T C I V I L 37
  • 38. 18. Advantages of Concrete Road Durability and maintenance free life: Concrete roads have a long service life of forty years, whereas asphalt roads last for ten years. Moreover, during this service life concrete road do not require frequent repair or patching work like asphalt roads. Vehicles consume less fuel: A vehicle, when run over a concrete road, consumes 15-20% less fuel than that on asphalt roads. This is because of the fact that a concrete road does not get deflected under the wheels of loaded trucks. Resistant to automobile fuel spillage and extreme weather: Unlike asphalt roads, concrete roads do not get damaged by the leaking oils from the vehicles or by the extreme weather conditions like excess rain or extreme heat. Greener process: Asphalt (bitumen) produces lots of highly polluting gases at the time of melting it for paving. Also, less fuel consumption by the vehicle running on a concrete road means less pollution. Saving of natural resources: Asphalt (bitumen) is produced from imported petroleum, the reserve of which is becoming reduced drastically. On the other hand, concrete (cement) is produced from abundantly available limestone. S O C E T C I V I L 38
  • 39. 19. Special Measures of Concrete 1. Workability period It must always be ensured that the concrete is processed as quickly as possible, certainly within 2 hours after batching including the surface treatment and the protection measures. In hot, dry weather an even shorter workability time has to be observed (maximum 90 minutes). Unless special precautions are taken that have been approved by the manager of the works, concrete can only be laid if the air temperature at 1.5 m above ground under thermometer shelter does not exceed 25°C. Furthermore, all necessary measures shall be taken to keep the water content of the concrete as constant as possible from the time of batching until completion of the placement. 2. Paving interruptions Whenever the supply of concrete is interrupted, the driver of the paving machine shall immediately take the necessary measures to lower the speed of the paving train and to ensure that the machine stops as little possible. For a short interruption, the machine should be stopped before the deposited concrete in the vibrating chamber has dropped to such a level that the vibrators become visible. If the supply is interrupted for more than 60 minutes (45 min. in hot weather), a construction joint has to be made. Upon a long-lasting defect of the paving equipment, the supply of fresh concrete has to be stopped immediately and an attempt must be made to complete the current paving phase. If the circumstances and the elapsed workability time no longer make a proper completion possible, the concrete, that has been deposited but not yet finished, has to be removed. To achieve a continuous profile, particular care is taken of the execution of the construction joints, both at the end of the day and every time work is resumed. The concrete is compacted preferably with a separate vibrating needle before the paving machine is passing in order to obtain properly compacted concrete on both sides of the joint. S O C E T C I V I L 39
  • 40. 3. Placement of concrete on a slope When placing concrete on a slope of less than 4 % it is recommended to work uphill, in order to prevent tension cracks at the surface. Furthermore, the consistency of the concrete and the working speed of the paver have to be adapted to the working conditions. However, if the longitudinal slope is more than 4 %, unevenness can occur as concrete falls back when the machines have passed. In that case, a suitable composition of the concrete mix has to be realized and it is recommended to work downhill. It must be ensured that enough concrete is deposited in front of the paving machine to prevent the concrete from sliding down. Concrete pavements have been successfully executed on slopes of 10 to 12 %. At one time the slope was even 18%. S O C E T C I V I L 40
  • 41. 20. Weather Consideration 1. Hot, dry weather paving Definition Temperatures generally above 90°F (32°C), low relative humidity, high wind speed, sunny conditions Challenges Concrete loses moisture more rapidly during hauling and placing. Aggregate stockpiles dry out, affecting moisture consistency between batches. The pavement sub base dries out before the mixture is placed, then absorbs water from the mixture. Rapid water evaporation at the pavement surface can result in shrinkage cracks. It’s more difficult to entrain air when temperatures are high. Entrained air is important for pavement Durability. Concrete sets rapidly, perhaps twice as fast, making finishing more difficult. Sawing operations must proceed more rapidly. Additional saws may be required. Once heat-related problems develop, it may be too late to fix them. Precautions If possible, do not pave in very hot, dry weather. Pave in the morning, evening, or night when air temperatures are cooler. Maintain uniform moisture in stockpiles. Use retarders in the mixture to slow hydration. Use fly ash and slag in the mixture. Keep sub base, forms, and equipment damp and cool. Apply curing compound as soon as possible. Additional compound may be required. S O C E T C I V I L 41
  • 42. 2. Cold weather paving Definition Air temperature of 50°F or less (10°C) for more than half of any 24-hour period, or when the average daily air temperature is less than 40°F (5°C) for three consecutive days. Challenges During cold weather, hydration slows, slowing strength development. Concrete cools faster at the surface than inside the slab, causing stress in the slab. If the stress is severe enough, the slab will crack randomly. Precautions Do not pave on frozen sub grade. Do not use aggregates with frozen lumps. Heat materials to raise concrete temperature and promote hydration. Minimize use of fly ash and slag. Do not pave if the concrete cannot reach adequate strength before it freezes. For the first two to three days, protect concrete from freezing with insulating material. 3. Rain Challenges Before final set, rain can damage the new pavement surface by leaving imprints or washing away paste at the surface. After final set, rain can induce rapid cooling at the surface, leading to rapid development of thermal restraint stresses and possibly early-age, uncontrolled cracking. Precautions If it starts to rain during operations, take the following actions: Stop batching and placing operations and cover the fresh concrete immediately with protective coverings like polyethylene sheeting or burlap. (Do not try to remove extra surface water first. Do not add dry cement to the surface.) S O C E T C I V I L 42
  • 43. As soon as the surface has dried, apply curing membrane. After the curing period, diamond grinding may be required to remove surface blemishes and provide texture to any surface exposed to rain where damage has occurred. S O C E T C I V I L 43