SlideShare a Scribd company logo
1
<Insert Picture Here>
Concepts and Best Practices for the Risk Register in Primavera Risk
Analysis
Matt Candela
Senior Technical Support Engineer
3
The following is intended to outline our general product
direction. It is intended for information purposes only,
and may not be incorporated into any contract. It is
not a commitment to deliver any material, code, or
functionality, and should not be relied upon in making
purchasing decisions.
The development, release, and timing of any features
or functionality described for Oracle’s products remains
at the sole discretion of Oracle.
4
Agenda
• Demo of primary Risk Register functionality in Primavera
Risk Analysis (PRA)
• Detailed look at functionality
• Other options and considerations
• Overview of risk functionality in P6 R8
5
• Uncertainty is inherent to a task.
– Example: digging a trench is scheduled for 10 days. It may only
take 8, or could take up to 12.
• Risks are events that may or may not occur and could
affect a task.
– Example: there is a 5% chance of flooding, which could delay
the digging of the trench by 5 to 8 days.
Risk vs. Uncertainty
6
• Risk scoring
– Thresholds, scoring criteria
• Create risks and assign to tasks
– Qualitative, quantitative probabilities and impacts
– Risk scores generated
• Mitigation
– Post-mitigated probabilities, impacts and risk scores
• Build impacted risk plans
Primary Risk Register Functionality
7
Risk Scoring
• Scores are calculated using Probability and Impact
Scoring Diagram
• Determined by intersection of the probability and impact
8
Qualitative and Quantitative Risks
• Risks have both qualitative and quantitative values
– Quantitative used in impacted risk plan
– Qualitative used to determine risk scores
• Qualitative risks: quantitative values from thresholds
– For probability, low and high are averaged
– For impacts, low is min and high is max
• Quantitative risks: qualitative values determined by
average of min, max, and most likely impacts
9
Qualitative Risks - Example
• Risk HAZ is assigned a high schedule impact
• High schedule threshold is defined as 20 to 40 days in
the risk scoring options
10
Qualitative Risks - Example
• Risk is assigned to a task on Quantitative tab
• Schedule impact is min 20 days and max 40
11
Quantitative Risks - Example
• Risk ACC is quantified and assigned to task 3
• Cost impact is min $50,000 and max $100,000, average
is $75,000
12
Quantitative Risks - Example
• $75,000 is within medium cost threshold
• Qualitative cost impact is medium
13
Qualitative and Quantitative Risks Assigned to
Multiple Tasks
• Qualitative: impacts spread across the tasks, per
following Risk Register options:
– “Spread the risk duration across multiple impacts”
– “Spread the risk costs across multiple impacts”
• Quantitative: impact averages will be summed to
determine qualitative value
14
Mitigation
• Mitigation Response of Avoid, Transfer, or Reduce
allows for post-mitigation values and score.
• Title and Total Cost optional for simple mitigation plan
15
Mitigation - Detailed Actions
• Qualitative tab > Mitigation tab > Use Detailed Actions
• Multiple mitigation actions with additional fields available
16
Mitigation - Detailed Actions
• Total Cost calculated as sum of details actions costs
– Excluding actions set to Rejected
• Post-mitigated values taken from an action
– Rejected actions are not considered
– Action with latest finish date is used
– Tie goes to action with the lowest score
17
• Mitigation Response set to Accept: any other response
allows for mitigation
• Use Detailed Actions is selected: post-mitigated values
taken from an action
• Risk is quantified: post-mitigated values must be set on
Quantitative tab
Post-Mitigated Options Grayed Out
18
Building an Impacted Plan
• (Task ID):B is the original task with no risk impact
– Duration and duration uncertainty of the original task
19
Building an Impacted Plan
• (Task ID):(Risk ID) is the risk event
– Task existence for probability, duration uncertainty for schedule
impact, resource uncertainty (ZCRI) for cost impact
– Zero remaining duration
20
Building an Impacted Plan
• (Task ID) is the summary for base task and risk event
– Logic from original task
– Resource assignments from original task, unless “Cost Impacts
include duration costs” is selected in Risk Register options
21
Correlation
• Available on Risk View tab when a risk is assigned to
multiple tasks
• Impact Ranges 90% correlation, Event Existence 100%
22
Link in Series
• Available on Task View tab when a task has multiple
risks assigned
• When unchecked, risks are in parallel
23
Link in Series - Example 1
• Risks are linked in series
• Cumulative effect, both impact schedule
24
Link in Series - Example 2
• Risks are not linked in series, occur in parallel
• Only longest duration affects schedule
25
Assigning a Risk to a Summary Task
• Risk will impact sub task with latest finish date
• Potential for confusion over which task risk will impact
and/or unexpected impact
26
Assigning a Risk to a Hammock Task
• Crash may occur or impacts may be incorrect
• Ability to do so has been removed in version 8.7.0029
27
Other Considerations and FAQs
• Opportunity on task near Data Date
– Opportunities work by pulling back start date, impact may be
incorrect
• What do risk start and finish dates affect?
– Proximity, exposure plan
• Is there a way to quickly assign a risk to a large number
of tasks?
– Filter on Risk View tab or use “Impacted Task ID(s)” column:
IDs separated by comma, no space
28
• Web only
• Risk scoring
– Thresholds, scoring criteria
• Create risks and assign to tasks
– Qualitative probabilities and impacts
– Risk scores generated
• Mitigation
– Post-mitigated probabilities, impacts and risk scores
Primary P6 R8 Risk Functionality
29
Primary P6 R8 Functionality
Define risk scoring under “Administer…Enterprise Data”
30
Primary P6 R8 Functionality
Select “Risks” on Projects View to create and assign risks
31
Primary P6 R8 Functionality
Use “Response Plans” tab for mitigation
32
Importing a Project from P6 R8 into PRA
• Requires Primavera Risk Analysis 8.7.0029 or later
• Requires Web Services Utility with appropriate settings
– See “Using Web Services to connect” in PRA help
• Run Connection Wizard in PRA
• Use “File…Primavera…Import Primavera P6 Project”
from PRA, no option from P6 R8 Web
• Risks only included in single project import
33
34

More Related Content

What's hot

Schedule analysis what could possibly go wrong - Oracle Primavera Collaborat...
Schedule analysis what could possibly go wrong  - Oracle Primavera Collaborat...Schedule analysis what could possibly go wrong  - Oracle Primavera Collaborat...
Schedule analysis what could possibly go wrong - Oracle Primavera Collaborat...
p6academy
 
Monte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk AnalysisMonte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk Analysis
Intaver Insititute
 
Qualitative & Quantitative Analysis
Qualitative & Quantitative AnalysisQualitative & Quantitative Analysis
Qualitative & Quantitative Analysis
Alin Veronika
 
Qualitative risk analysis
Qualitative risk analysisQualitative risk analysis
Qualitative risk analysis
sonali talkar
 
Decision and risk analysis
Decision and risk analysisDecision and risk analysis
Decision and risk analysis
Indra Biswakarma
 
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Project Controls Expo
 
Risk Management
Risk ManagementRisk Management
Risk Management
rajuinstru
 
Monte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk AnalysisMonte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk Analysis
Intaver Insititute
 
Project risk analysis in Construction Industry
Project risk analysis in Construction IndustryProject risk analysis in Construction Industry
Project risk analysis in Construction Industry
Intaver Insititute
 
Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...
Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...
Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...
Liana Underwood
 
Terry Johns: Uncertainty - understanding the impact and the importance of rec...
Terry Johns: Uncertainty - understanding the impact and the importance of rec...Terry Johns: Uncertainty - understanding the impact and the importance of rec...
Terry Johns: Uncertainty - understanding the impact and the importance of rec...
Association for Project Management
 
How Risk Events and Uncertainties can affect your project
How Risk Events and Uncertainties can affect your projectHow Risk Events and Uncertainties can affect your project
How Risk Events and Uncertainties can affect your project
Intaver Insititute
 
Session B3 - Introduction to Project Cost and Schedule Risk Analysis
Session B3 - Introduction to Project Cost and Schedule Risk AnalysisSession B3 - Introduction to Project Cost and Schedule Risk Analysis
Session B3 - Introduction to Project Cost and Schedule Risk Analysis
Project Controls Expo
 
Risk Analysis of Linear Projects
Risk Analysis of Linear ProjectsRisk Analysis of Linear Projects
Risk Analysis of Linear Projects
Intaver Insititute
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
BECM, RUET, Bangladesh
 
Risk Management in Sprint Environment
Risk Management in Sprint EnvironmentRisk Management in Sprint Environment
Risk Management in Sprint Environment
Mike Wienold
 
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Intaver Insititute
 
Risk analysis
Risk analysisRisk analysis
Risk analysis
BECM, RUET, Bangladesh
 
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Project Risk Analysis: Creating and Managing Risk Adjusted Project SchedulesProject Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Intaver Insititute
 
Project Auditing
Project AuditingProject Auditing
Project Auditing
BECM, RUET, Bangladesh
 

What's hot (20)

Schedule analysis what could possibly go wrong - Oracle Primavera Collaborat...
Schedule analysis what could possibly go wrong  - Oracle Primavera Collaborat...Schedule analysis what could possibly go wrong  - Oracle Primavera Collaborat...
Schedule analysis what could possibly go wrong - Oracle Primavera Collaborat...
 
Monte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk AnalysisMonte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk Analysis
 
Qualitative & Quantitative Analysis
Qualitative & Quantitative AnalysisQualitative & Quantitative Analysis
Qualitative & Quantitative Analysis
 
Qualitative risk analysis
Qualitative risk analysisQualitative risk analysis
Qualitative risk analysis
 
Decision and risk analysis
Decision and risk analysisDecision and risk analysis
Decision and risk analysis
 
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Monte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk AnalysisMonte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk Analysis
 
Project risk analysis in Construction Industry
Project risk analysis in Construction IndustryProject risk analysis in Construction Industry
Project risk analysis in Construction Industry
 
Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...
Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...
Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...
 
Terry Johns: Uncertainty - understanding the impact and the importance of rec...
Terry Johns: Uncertainty - understanding the impact and the importance of rec...Terry Johns: Uncertainty - understanding the impact and the importance of rec...
Terry Johns: Uncertainty - understanding the impact and the importance of rec...
 
How Risk Events and Uncertainties can affect your project
How Risk Events and Uncertainties can affect your projectHow Risk Events and Uncertainties can affect your project
How Risk Events and Uncertainties can affect your project
 
Session B3 - Introduction to Project Cost and Schedule Risk Analysis
Session B3 - Introduction to Project Cost and Schedule Risk AnalysisSession B3 - Introduction to Project Cost and Schedule Risk Analysis
Session B3 - Introduction to Project Cost and Schedule Risk Analysis
 
Risk Analysis of Linear Projects
Risk Analysis of Linear ProjectsRisk Analysis of Linear Projects
Risk Analysis of Linear Projects
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Risk Management in Sprint Environment
Risk Management in Sprint EnvironmentRisk Management in Sprint Environment
Risk Management in Sprint Environment
 
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
 
Risk analysis
Risk analysisRisk analysis
Risk analysis
 
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Project Risk Analysis: Creating and Managing Risk Adjusted Project SchedulesProject Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
 
Project Auditing
Project AuditingProject Auditing
Project Auditing
 

Similar to Concepts and best practices for the risk register in primavera risk analysis

Project risk management
Project risk managementProject risk management
Project risk management
Dewang Agrawal
 
Basic risk management presentation 17th june 2015
Basic risk management presentation 17th june 2015Basic risk management presentation 17th june 2015
Basic risk management presentation 17th june 2015
Association for Project Management
 
Project Risk management
Project Risk management Project Risk management
Project Risk management
CMA (Dr.) Ashok Panigrahi
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
Intaver Insititute
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
Intaver Insititute
 
Risk management
Risk managementRisk management
Risk management
tumetr1
 
RiskyProject Software
RiskyProject SoftwareRiskyProject Software
RiskyProject Software
Intaver Insititute
 
2. Risk Management Analysis and Register.pptx
2. Risk Management Analysis and Register.pptx2. Risk Management Analysis and Register.pptx
2. Risk Management Analysis and Register.pptx
robmente
 
Risk Management
Risk ManagementRisk Management
Risk Management
Saqib Raza
 
Project Risk mgt ch3 supplimentary.ppt n
Project Risk mgt ch3 supplimentary.ppt nProject Risk mgt ch3 supplimentary.ppt n
Project Risk mgt ch3 supplimentary.ppt n
Kevin117905
 
Risk Management Best Practices
Risk Management Best PracticesRisk Management Best Practices
Risk Management Best Practices
PMILebanonChapter
 
Riskmanagement software Engineering1.ppt
Riskmanagement software Engineering1.pptRiskmanagement software Engineering1.ppt
Riskmanagement software Engineering1.ppt
sirishaYerraboina1
 
Project risk analysis
Project risk analysisProject risk analysis
Project risk analysis
SUBHASISHMAHAKUD
 
Session 18 -2 PMP 4th edition
Session 18 -2  PMP 4th editionSession 18 -2  PMP 4th edition
Session 18 -2 PMP 4th edition
محمد عصمت عبد الرازق
 
05-risk_assesment.ppt
05-risk_assesment.ppt05-risk_assesment.ppt
05-risk_assesment.ppt
KareemRasmy1
 
PROJECT RISK MANAGEMENT.pdf
PROJECT RISK MANAGEMENT.pdfPROJECT RISK MANAGEMENT.pdf
PROJECT RISK MANAGEMENT.pdf
MUST
 
Risk-Management-05012023-025512pm.ppt
Risk-Management-05012023-025512pm.pptRisk-Management-05012023-025512pm.ppt
Risk-Management-05012023-025512pm.ppt
YasirShaikh34
 
Risk management concepts and learning
Risk management   concepts and learningRisk management   concepts and learning
Risk management concepts and learning
Vanita Ahuja
 
Project risk management
Project risk managementProject risk management
Project risk management
BarnatuCoffee
 
PROJECT RISK MANAGEMENT
PROJECT  RISK  MANAGEMENTPROJECT  RISK  MANAGEMENT
PROJECT RISK MANAGEMENT
Neenu Babu
 

Similar to Concepts and best practices for the risk register in primavera risk analysis (20)

Project risk management
Project risk managementProject risk management
Project risk management
 
Basic risk management presentation 17th june 2015
Basic risk management presentation 17th june 2015Basic risk management presentation 17th june 2015
Basic risk management presentation 17th june 2015
 
Project Risk management
Project Risk management Project Risk management
Project Risk management
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
 
Risk management
Risk managementRisk management
Risk management
 
RiskyProject Software
RiskyProject SoftwareRiskyProject Software
RiskyProject Software
 
2. Risk Management Analysis and Register.pptx
2. Risk Management Analysis and Register.pptx2. Risk Management Analysis and Register.pptx
2. Risk Management Analysis and Register.pptx
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Project Risk mgt ch3 supplimentary.ppt n
Project Risk mgt ch3 supplimentary.ppt nProject Risk mgt ch3 supplimentary.ppt n
Project Risk mgt ch3 supplimentary.ppt n
 
Risk Management Best Practices
Risk Management Best PracticesRisk Management Best Practices
Risk Management Best Practices
 
Riskmanagement software Engineering1.ppt
Riskmanagement software Engineering1.pptRiskmanagement software Engineering1.ppt
Riskmanagement software Engineering1.ppt
 
Project risk analysis
Project risk analysisProject risk analysis
Project risk analysis
 
Session 18 -2 PMP 4th edition
Session 18 -2  PMP 4th editionSession 18 -2  PMP 4th edition
Session 18 -2 PMP 4th edition
 
05-risk_assesment.ppt
05-risk_assesment.ppt05-risk_assesment.ppt
05-risk_assesment.ppt
 
PROJECT RISK MANAGEMENT.pdf
PROJECT RISK MANAGEMENT.pdfPROJECT RISK MANAGEMENT.pdf
PROJECT RISK MANAGEMENT.pdf
 
Risk-Management-05012023-025512pm.ppt
Risk-Management-05012023-025512pm.pptRisk-Management-05012023-025512pm.ppt
Risk-Management-05012023-025512pm.ppt
 
Risk management concepts and learning
Risk management   concepts and learningRisk management   concepts and learning
Risk management concepts and learning
 
Project risk management
Project risk managementProject risk management
Project risk management
 
PROJECT RISK MANAGEMENT
PROJECT  RISK  MANAGEMENTPROJECT  RISK  MANAGEMENT
PROJECT RISK MANAGEMENT
 

Recently uploaded

Freshworks Rethinks NoSQL for Rapid Scaling & Cost-Efficiency
Freshworks Rethinks NoSQL for Rapid Scaling & Cost-EfficiencyFreshworks Rethinks NoSQL for Rapid Scaling & Cost-Efficiency
Freshworks Rethinks NoSQL for Rapid Scaling & Cost-Efficiency
ScyllaDB
 
Driving Business Innovation: Latest Generative AI Advancements & Success Story
Driving Business Innovation: Latest Generative AI Advancements & Success StoryDriving Business Innovation: Latest Generative AI Advancements & Success Story
Driving Business Innovation: Latest Generative AI Advancements & Success Story
Safe Software
 
WeTestAthens: Postman's AI & Automation Techniques
WeTestAthens: Postman's AI & Automation TechniquesWeTestAthens: Postman's AI & Automation Techniques
WeTestAthens: Postman's AI & Automation Techniques
Postman
 
GNSS spoofing via SDR (Criptored Talks 2024)
GNSS spoofing via SDR (Criptored Talks 2024)GNSS spoofing via SDR (Criptored Talks 2024)
GNSS spoofing via SDR (Criptored Talks 2024)
Javier Junquera
 
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with SlackLet's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
shyamraj55
 
5th LF Energy Power Grid Model Meet-up Slides
5th LF Energy Power Grid Model Meet-up Slides5th LF Energy Power Grid Model Meet-up Slides
5th LF Energy Power Grid Model Meet-up Slides
DanBrown980551
 
Monitoring and Managing Anomaly Detection on OpenShift.pdf
Monitoring and Managing Anomaly Detection on OpenShift.pdfMonitoring and Managing Anomaly Detection on OpenShift.pdf
Monitoring and Managing Anomaly Detection on OpenShift.pdf
Tosin Akinosho
 
Your One-Stop Shop for Python Success: Top 10 US Python Development Providers
Your One-Stop Shop for Python Success: Top 10 US Python Development ProvidersYour One-Stop Shop for Python Success: Top 10 US Python Development Providers
Your One-Stop Shop for Python Success: Top 10 US Python Development Providers
akankshawande
 
HCL Notes and Domino License Cost Reduction in the World of DLAU
HCL Notes and Domino License Cost Reduction in the World of DLAUHCL Notes and Domino License Cost Reduction in the World of DLAU
HCL Notes and Domino License Cost Reduction in the World of DLAU
panagenda
 
“Temporal Event Neural Networks: A More Efficient Alternative to the Transfor...
“Temporal Event Neural Networks: A More Efficient Alternative to the Transfor...“Temporal Event Neural Networks: A More Efficient Alternative to the Transfor...
“Temporal Event Neural Networks: A More Efficient Alternative to the Transfor...
Edge AI and Vision Alliance
 
Choosing The Best AWS Service For Your Website + API.pptx
Choosing The Best AWS Service For Your Website + API.pptxChoosing The Best AWS Service For Your Website + API.pptx
Choosing The Best AWS Service For Your Website + API.pptx
Brandon Minnick, MBA
 
Introduction of Cybersecurity with OSS at Code Europe 2024
Introduction of Cybersecurity with OSS  at Code Europe 2024Introduction of Cybersecurity with OSS  at Code Europe 2024
Introduction of Cybersecurity with OSS at Code Europe 2024
Hiroshi SHIBATA
 
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy SurveyTrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc
 
AWS Cloud Cost Optimization Presentation.pptx
AWS Cloud Cost Optimization Presentation.pptxAWS Cloud Cost Optimization Presentation.pptx
AWS Cloud Cost Optimization Presentation.pptx
HarisZaheer8
 
Fueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte WebinarFueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte Webinar
Zilliz
 
Skybuffer SAM4U tool for SAP license adoption
Skybuffer SAM4U tool for SAP license adoptionSkybuffer SAM4U tool for SAP license adoption
Skybuffer SAM4U tool for SAP license adoption
Tatiana Kojar
 
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdfHow to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
Chart Kalyan
 
SAP S/4 HANA sourcing and procurement to Public cloud
SAP S/4 HANA sourcing and procurement to Public cloudSAP S/4 HANA sourcing and procurement to Public cloud
SAP S/4 HANA sourcing and procurement to Public cloud
maazsz111
 
Best 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERPBest 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERP
Pixlogix Infotech
 
Digital Banking in the Cloud: How Citizens Bank Unlocked Their Mainframe
Digital Banking in the Cloud: How Citizens Bank Unlocked Their MainframeDigital Banking in the Cloud: How Citizens Bank Unlocked Their Mainframe
Digital Banking in the Cloud: How Citizens Bank Unlocked Their Mainframe
Precisely
 

Recently uploaded (20)

Freshworks Rethinks NoSQL for Rapid Scaling & Cost-Efficiency
Freshworks Rethinks NoSQL for Rapid Scaling & Cost-EfficiencyFreshworks Rethinks NoSQL for Rapid Scaling & Cost-Efficiency
Freshworks Rethinks NoSQL for Rapid Scaling & Cost-Efficiency
 
Driving Business Innovation: Latest Generative AI Advancements & Success Story
Driving Business Innovation: Latest Generative AI Advancements & Success StoryDriving Business Innovation: Latest Generative AI Advancements & Success Story
Driving Business Innovation: Latest Generative AI Advancements & Success Story
 
WeTestAthens: Postman's AI & Automation Techniques
WeTestAthens: Postman's AI & Automation TechniquesWeTestAthens: Postman's AI & Automation Techniques
WeTestAthens: Postman's AI & Automation Techniques
 
GNSS spoofing via SDR (Criptored Talks 2024)
GNSS spoofing via SDR (Criptored Talks 2024)GNSS spoofing via SDR (Criptored Talks 2024)
GNSS spoofing via SDR (Criptored Talks 2024)
 
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with SlackLet's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
 
5th LF Energy Power Grid Model Meet-up Slides
5th LF Energy Power Grid Model Meet-up Slides5th LF Energy Power Grid Model Meet-up Slides
5th LF Energy Power Grid Model Meet-up Slides
 
Monitoring and Managing Anomaly Detection on OpenShift.pdf
Monitoring and Managing Anomaly Detection on OpenShift.pdfMonitoring and Managing Anomaly Detection on OpenShift.pdf
Monitoring and Managing Anomaly Detection on OpenShift.pdf
 
Your One-Stop Shop for Python Success: Top 10 US Python Development Providers
Your One-Stop Shop for Python Success: Top 10 US Python Development ProvidersYour One-Stop Shop for Python Success: Top 10 US Python Development Providers
Your One-Stop Shop for Python Success: Top 10 US Python Development Providers
 
HCL Notes and Domino License Cost Reduction in the World of DLAU
HCL Notes and Domino License Cost Reduction in the World of DLAUHCL Notes and Domino License Cost Reduction in the World of DLAU
HCL Notes and Domino License Cost Reduction in the World of DLAU
 
“Temporal Event Neural Networks: A More Efficient Alternative to the Transfor...
“Temporal Event Neural Networks: A More Efficient Alternative to the Transfor...“Temporal Event Neural Networks: A More Efficient Alternative to the Transfor...
“Temporal Event Neural Networks: A More Efficient Alternative to the Transfor...
 
Choosing The Best AWS Service For Your Website + API.pptx
Choosing The Best AWS Service For Your Website + API.pptxChoosing The Best AWS Service For Your Website + API.pptx
Choosing The Best AWS Service For Your Website + API.pptx
 
Introduction of Cybersecurity with OSS at Code Europe 2024
Introduction of Cybersecurity with OSS  at Code Europe 2024Introduction of Cybersecurity with OSS  at Code Europe 2024
Introduction of Cybersecurity with OSS at Code Europe 2024
 
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy SurveyTrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy Survey
 
AWS Cloud Cost Optimization Presentation.pptx
AWS Cloud Cost Optimization Presentation.pptxAWS Cloud Cost Optimization Presentation.pptx
AWS Cloud Cost Optimization Presentation.pptx
 
Fueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte WebinarFueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte Webinar
 
Skybuffer SAM4U tool for SAP license adoption
Skybuffer SAM4U tool for SAP license adoptionSkybuffer SAM4U tool for SAP license adoption
Skybuffer SAM4U tool for SAP license adoption
 
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdfHow to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
 
SAP S/4 HANA sourcing and procurement to Public cloud
SAP S/4 HANA sourcing and procurement to Public cloudSAP S/4 HANA sourcing and procurement to Public cloud
SAP S/4 HANA sourcing and procurement to Public cloud
 
Best 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERPBest 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERP
 
Digital Banking in the Cloud: How Citizens Bank Unlocked Their Mainframe
Digital Banking in the Cloud: How Citizens Bank Unlocked Their MainframeDigital Banking in the Cloud: How Citizens Bank Unlocked Their Mainframe
Digital Banking in the Cloud: How Citizens Bank Unlocked Their Mainframe
 

Concepts and best practices for the risk register in primavera risk analysis

  • 1. 1
  • 2. <Insert Picture Here> Concepts and Best Practices for the Risk Register in Primavera Risk Analysis Matt Candela Senior Technical Support Engineer
  • 3. 3 The following is intended to outline our general product direction. It is intended for information purposes only, and may not be incorporated into any contract. It is not a commitment to deliver any material, code, or functionality, and should not be relied upon in making purchasing decisions. The development, release, and timing of any features or functionality described for Oracle’s products remains at the sole discretion of Oracle.
  • 4. 4 Agenda • Demo of primary Risk Register functionality in Primavera Risk Analysis (PRA) • Detailed look at functionality • Other options and considerations • Overview of risk functionality in P6 R8
  • 5. 5 • Uncertainty is inherent to a task. – Example: digging a trench is scheduled for 10 days. It may only take 8, or could take up to 12. • Risks are events that may or may not occur and could affect a task. – Example: there is a 5% chance of flooding, which could delay the digging of the trench by 5 to 8 days. Risk vs. Uncertainty
  • 6. 6 • Risk scoring – Thresholds, scoring criteria • Create risks and assign to tasks – Qualitative, quantitative probabilities and impacts – Risk scores generated • Mitigation – Post-mitigated probabilities, impacts and risk scores • Build impacted risk plans Primary Risk Register Functionality
  • 7. 7 Risk Scoring • Scores are calculated using Probability and Impact Scoring Diagram • Determined by intersection of the probability and impact
  • 8. 8 Qualitative and Quantitative Risks • Risks have both qualitative and quantitative values – Quantitative used in impacted risk plan – Qualitative used to determine risk scores • Qualitative risks: quantitative values from thresholds – For probability, low and high are averaged – For impacts, low is min and high is max • Quantitative risks: qualitative values determined by average of min, max, and most likely impacts
  • 9. 9 Qualitative Risks - Example • Risk HAZ is assigned a high schedule impact • High schedule threshold is defined as 20 to 40 days in the risk scoring options
  • 10. 10 Qualitative Risks - Example • Risk is assigned to a task on Quantitative tab • Schedule impact is min 20 days and max 40
  • 11. 11 Quantitative Risks - Example • Risk ACC is quantified and assigned to task 3 • Cost impact is min $50,000 and max $100,000, average is $75,000
  • 12. 12 Quantitative Risks - Example • $75,000 is within medium cost threshold • Qualitative cost impact is medium
  • 13. 13 Qualitative and Quantitative Risks Assigned to Multiple Tasks • Qualitative: impacts spread across the tasks, per following Risk Register options: – “Spread the risk duration across multiple impacts” – “Spread the risk costs across multiple impacts” • Quantitative: impact averages will be summed to determine qualitative value
  • 14. 14 Mitigation • Mitigation Response of Avoid, Transfer, or Reduce allows for post-mitigation values and score. • Title and Total Cost optional for simple mitigation plan
  • 15. 15 Mitigation - Detailed Actions • Qualitative tab > Mitigation tab > Use Detailed Actions • Multiple mitigation actions with additional fields available
  • 16. 16 Mitigation - Detailed Actions • Total Cost calculated as sum of details actions costs – Excluding actions set to Rejected • Post-mitigated values taken from an action – Rejected actions are not considered – Action with latest finish date is used – Tie goes to action with the lowest score
  • 17. 17 • Mitigation Response set to Accept: any other response allows for mitigation • Use Detailed Actions is selected: post-mitigated values taken from an action • Risk is quantified: post-mitigated values must be set on Quantitative tab Post-Mitigated Options Grayed Out
  • 18. 18 Building an Impacted Plan • (Task ID):B is the original task with no risk impact – Duration and duration uncertainty of the original task
  • 19. 19 Building an Impacted Plan • (Task ID):(Risk ID) is the risk event – Task existence for probability, duration uncertainty for schedule impact, resource uncertainty (ZCRI) for cost impact – Zero remaining duration
  • 20. 20 Building an Impacted Plan • (Task ID) is the summary for base task and risk event – Logic from original task – Resource assignments from original task, unless “Cost Impacts include duration costs” is selected in Risk Register options
  • 21. 21 Correlation • Available on Risk View tab when a risk is assigned to multiple tasks • Impact Ranges 90% correlation, Event Existence 100%
  • 22. 22 Link in Series • Available on Task View tab when a task has multiple risks assigned • When unchecked, risks are in parallel
  • 23. 23 Link in Series - Example 1 • Risks are linked in series • Cumulative effect, both impact schedule
  • 24. 24 Link in Series - Example 2 • Risks are not linked in series, occur in parallel • Only longest duration affects schedule
  • 25. 25 Assigning a Risk to a Summary Task • Risk will impact sub task with latest finish date • Potential for confusion over which task risk will impact and/or unexpected impact
  • 26. 26 Assigning a Risk to a Hammock Task • Crash may occur or impacts may be incorrect • Ability to do so has been removed in version 8.7.0029
  • 27. 27 Other Considerations and FAQs • Opportunity on task near Data Date – Opportunities work by pulling back start date, impact may be incorrect • What do risk start and finish dates affect? – Proximity, exposure plan • Is there a way to quickly assign a risk to a large number of tasks? – Filter on Risk View tab or use “Impacted Task ID(s)” column: IDs separated by comma, no space
  • 28. 28 • Web only • Risk scoring – Thresholds, scoring criteria • Create risks and assign to tasks – Qualitative probabilities and impacts – Risk scores generated • Mitigation – Post-mitigated probabilities, impacts and risk scores Primary P6 R8 Risk Functionality
  • 29. 29 Primary P6 R8 Functionality Define risk scoring under “Administer…Enterprise Data”
  • 30. 30 Primary P6 R8 Functionality Select “Risks” on Projects View to create and assign risks
  • 31. 31 Primary P6 R8 Functionality Use “Response Plans” tab for mitigation
  • 32. 32 Importing a Project from P6 R8 into PRA • Requires Primavera Risk Analysis 8.7.0029 or later • Requires Web Services Utility with appropriate settings – See “Using Web Services to connect” in PRA help • Run Connection Wizard in PRA • Use “File…Primavera…Import Primavera P6 Project” from PRA, no option from P6 R8 Web • Risks only included in single project import
  • 33. 33
  • 34. 34