SlideShare a Scribd company logo
1 of 17
City Council
September 18, 2012
Avenue P Background
• True neighborhood with many residents having lived
  there for generations
• Most houses built in 1940’s and 1950’s
• Long history of flooding
   • reports dating back decades
   • exacerbated by continued development with increased
     impervious cover
Avenue P Background
• 2000 Master Drainage Plan
   • Developed by Freese & Nichols, Inc.
   • Analyzed 57 drainage problem areas
   • Top 25 problem areas ranked/prioritized according to
      •   amount and velocity of flow
      •   capacity of existing facilities
      •   traffic issues (disruption/emergency response)
      •   history of flooded structures
      •   cost-benefit analysis
   • Avenue P Drainage Problem Area Ranked #2
Avenue P Background
• Ave P neighborhood meeting – September 19, 2011
   • Attendees
      •   Then-City Manager Harold Dominguez
      •   City Councilman Johnny Silvas
      •   City Engineer Clinton Bailey
      •   Approximately 25 area residents
   • Area residents discussed history of neighborhood
     drainage issues
   • City Officials discussed remediation options and
     funding opportunities
Avenue P Background
• City Council meeting – November 1, 2011
   • Presentation on Capital Planning Projects
      • Top 5 drainage problems presented
   • Council approved funding ($1.7 million) for Ave P
      • $700,000 from fiscal year 2011-2012
      • $1,000,000 from fiscal year 2012-2013
Avenue P Flooding
Avenue P Flooding
Avenue P Flooding
Avenue P Flooding
Avenue P Flooding
Avenue P Flooding
Avenue P Flooding
Drainage Areas


                         W Avenue N

                   Cemeteries

             ASU




                                      S Bryant Blvd




                                                      Chadbourne
Johnson St




                                                          S
Avenue P Drainage Improvement Project
                • Take drainage underground from S. Bryant Blvd to
                  the east side of S. Chadbourne St.


                                                           End
                    Begin

                                 Avenue P




                                                                     S Chadbourne
S Bryant Blvd
Avenue P Drainage Improvement Project
• 2,300 linear feet of storm drain under Ave P
• 300 linear feet of improved open channel
• Curb inlets along Avenue P to pick up street drainage
• Storm drain crosses under S Chadbourne St.
• Discharges into an open channel on the east side of
 S Chadbourne St.
• Flows directly into the Red Arroyo
S Bryant Boulevard Culvert
Project Timeline
2012
  •    Mid-October – Complete design
  •    November – Advertise for bid
  •    Early December – Open and award bid
  •    Mid-late December – Begin construction
2013
  • Late summer – Project completion

More Related Content

What's hot

Huntington Levee Community Meeting: Oct. 26. 2016
Huntington Levee Community Meeting: Oct. 26. 2016Huntington Levee Community Meeting: Oct. 26. 2016
Huntington Levee Community Meeting: Oct. 26. 2016Fairfax County
 
Powell School & Twin Oaks Garden Community Meeting Presentation (June 25, 2014)
Powell School & Twin Oaks Garden Community Meeting Presentation (June 25, 2014)Powell School & Twin Oaks Garden Community Meeting Presentation (June 25, 2014)
Powell School & Twin Oaks Garden Community Meeting Presentation (June 25, 2014)DC Department of General Services
 
Clean Rivers, Clean Lake 8 -- New Projects on KK and Menomonee Rivers -- Dave...
Clean Rivers, Clean Lake 8 -- New Projects on KK and Menomonee Rivers -- Dave...Clean Rivers, Clean Lake 8 -- New Projects on KK and Menomonee Rivers -- Dave...
Clean Rivers, Clean Lake 8 -- New Projects on KK and Menomonee Rivers -- Dave...Sweet Water
 
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...Fairfax County
 
Huntington Levee Community Meeting
Huntington Levee Community MeetingHuntington Levee Community Meeting
Huntington Levee Community MeetingFairfax County
 
Tucker Avenue Neighborhood - Community Meeting 3-11-2020
Tucker Avenue Neighborhood - Community Meeting 3-11-2020Tucker Avenue Neighborhood - Community Meeting 3-11-2020
Tucker Avenue Neighborhood - Community Meeting 3-11-2020Fairfax County
 
Projects(Nov 17 2010)
Projects(Nov 17 2010)Projects(Nov 17 2010)
Projects(Nov 17 2010)Ora Berman
 
Ripley Streetscape Document
Ripley Streetscape DocumentRipley Streetscape Document
Ripley Streetscape DocumentJ03Van
 
Singapore Managing Stormwater For Water Resource And Flood Control 水资源介绍
Singapore Managing   Stormwater For Water Resource And Flood Control  水资源介绍Singapore Managing   Stormwater For Water Resource And Flood Control  水资源介绍
Singapore Managing Stormwater For Water Resource And Flood Control 水资源介绍dreamsion
 
Marina barrage (09/10s2)
Marina barrage (09/10s2)Marina barrage (09/10s2)
Marina barrage (09/10s2)gn022010sem1
 
Tucker Avenue Neighborhood Stormwater Improvement Preliminary Design Review
Tucker Avenue Neighborhood  Stormwater Improvement Preliminary Design ReviewTucker Avenue Neighborhood  Stormwater Improvement Preliminary Design Review
Tucker Avenue Neighborhood Stormwater Improvement Preliminary Design ReviewFairfax County
 
Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013
Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013
Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013Fairfax County
 
Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)DC Department of General Services
 
Tucker Avenue Neighborhood Stormwater Project Community Meeting Sept 19, 2019
Tucker Avenue Neighborhood Stormwater Project Community Meeting Sept 19, 2019Tucker Avenue Neighborhood Stormwater Project Community Meeting Sept 19, 2019
Tucker Avenue Neighborhood Stormwater Project Community Meeting Sept 19, 2019Fairfax County
 
Franklin Park Chesterbrook Neighborhood Project Highlights
Franklin Park Chesterbrook Neighborhood Project HighlightsFranklin Park Chesterbrook Neighborhood Project Highlights
Franklin Park Chesterbrook Neighborhood Project HighlightsFairfax County
 
Big Dry Creek Greenway 2008
Big Dry Creek Greenway 2008Big Dry Creek Greenway 2008
Big Dry Creek Greenway 2008jmpflaum
 
public adminPresentation1
public adminPresentation1public adminPresentation1
public adminPresentation1Kelly Snay
 

What's hot (20)

Dugway Sewer Community Update: April 1, 2014
Dugway Sewer Community Update: April 1, 2014Dugway Sewer Community Update: April 1, 2014
Dugway Sewer Community Update: April 1, 2014
 
Huntington Levee Community Meeting: Oct. 26. 2016
Huntington Levee Community Meeting: Oct. 26. 2016Huntington Levee Community Meeting: Oct. 26. 2016
Huntington Levee Community Meeting: Oct. 26. 2016
 
Powell School & Twin Oaks Garden Community Meeting Presentation (June 25, 2014)
Powell School & Twin Oaks Garden Community Meeting Presentation (June 25, 2014)Powell School & Twin Oaks Garden Community Meeting Presentation (June 25, 2014)
Powell School & Twin Oaks Garden Community Meeting Presentation (June 25, 2014)
 
Clean Rivers, Clean Lake 8 -- New Projects on KK and Menomonee Rivers -- Dave...
Clean Rivers, Clean Lake 8 -- New Projects on KK and Menomonee Rivers -- Dave...Clean Rivers, Clean Lake 8 -- New Projects on KK and Menomonee Rivers -- Dave...
Clean Rivers, Clean Lake 8 -- New Projects on KK and Menomonee Rivers -- Dave...
 
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...
 
Making Connections Across Our Watersheds
Making Connections Across Our WatershedsMaking Connections Across Our Watersheds
Making Connections Across Our Watersheds
 
Huntington Levee Community Meeting
Huntington Levee Community MeetingHuntington Levee Community Meeting
Huntington Levee Community Meeting
 
Tucker Avenue Neighborhood - Community Meeting 3-11-2020
Tucker Avenue Neighborhood - Community Meeting 3-11-2020Tucker Avenue Neighborhood - Community Meeting 3-11-2020
Tucker Avenue Neighborhood - Community Meeting 3-11-2020
 
Projects(Nov 17 2010)
Projects(Nov 17 2010)Projects(Nov 17 2010)
Projects(Nov 17 2010)
 
Ripley Streetscape Document
Ripley Streetscape DocumentRipley Streetscape Document
Ripley Streetscape Document
 
Singapore Managing Stormwater For Water Resource And Flood Control 水资源介绍
Singapore Managing   Stormwater For Water Resource And Flood Control  水资源介绍Singapore Managing   Stormwater For Water Resource And Flood Control  水资源介绍
Singapore Managing Stormwater For Water Resource And Flood Control 水资源介绍
 
Marina barrage (09/10s2)
Marina barrage (09/10s2)Marina barrage (09/10s2)
Marina barrage (09/10s2)
 
Sedimentary Petrology
Sedimentary PetrologySedimentary Petrology
Sedimentary Petrology
 
Tucker Avenue Neighborhood Stormwater Improvement Preliminary Design Review
Tucker Avenue Neighborhood  Stormwater Improvement Preliminary Design ReviewTucker Avenue Neighborhood  Stormwater Improvement Preliminary Design Review
Tucker Avenue Neighborhood Stormwater Improvement Preliminary Design Review
 
Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013
Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013
Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013
 
Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)
 
Tucker Avenue Neighborhood Stormwater Project Community Meeting Sept 19, 2019
Tucker Avenue Neighborhood Stormwater Project Community Meeting Sept 19, 2019Tucker Avenue Neighborhood Stormwater Project Community Meeting Sept 19, 2019
Tucker Avenue Neighborhood Stormwater Project Community Meeting Sept 19, 2019
 
Franklin Park Chesterbrook Neighborhood Project Highlights
Franklin Park Chesterbrook Neighborhood Project HighlightsFranklin Park Chesterbrook Neighborhood Project Highlights
Franklin Park Chesterbrook Neighborhood Project Highlights
 
Big Dry Creek Greenway 2008
Big Dry Creek Greenway 2008Big Dry Creek Greenway 2008
Big Dry Creek Greenway 2008
 
public adminPresentation1
public adminPresentation1public adminPresentation1
public adminPresentation1
 

Viewers also liked

City Council July 20, 2012 Budget Presentation
City Council July 20, 2012 Budget PresentationCity Council July 20, 2012 Budget Presentation
City Council July 20, 2012 Budget PresentationCity of San Angelo Texas
 
City council december 18, 2012 regular impound adoption_fee_ordinance amend
City council december 18, 2012 regular impound adoption_fee_ordinance amendCity council december 18, 2012 regular impound adoption_fee_ordinance amend
City council december 18, 2012 regular impound adoption_fee_ordinance amendCity of San Angelo Texas
 
City Council March 22 - Water Bill Online Payment
City Council March 22 - Water Bill Online PaymentCity Council March 22 - Water Bill Online Payment
City Council March 22 - Water Bill Online PaymentCity of San Angelo Texas
 
City Council March 22 - 50th Street & Grape Creek Road Construction
City Council March 22 -  50th Street & Grape Creek Road Construction City Council March 22 -  50th Street & Grape Creek Road Construction
City Council March 22 - 50th Street & Grape Creek Road Construction City of San Angelo Texas
 
West Texas Trade Summit 2011: International trade office Presentation
West Texas Trade Summit 2011: International trade office PresentationWest Texas Trade Summit 2011: International trade office Presentation
West Texas Trade Summit 2011: International trade office PresentationCity of San Angelo Texas
 
Gestão de obra sqqqqqqqqqqqqqq
Gestão de obra sqqqqqqqqqqqqqqGestão de obra sqqqqqqqqqqqqqq
Gestão de obra sqqqqqqqqqqqqqqArlete Freitas
 
O Segredo da Verdadeira Devocão para com a Santíssima Virgem Maria
O Segredo da Verdadeira Devocão para com a Santíssima Virgem MariaO Segredo da Verdadeira Devocão para com a Santíssima Virgem Maria
O Segredo da Verdadeira Devocão para com a Santíssima Virgem MariaFraternidade de Maria
 
Best android keek
Best android keekBest android keek
Best android keektelly989
 
Programa Día del Libro
Programa Día del LibroPrograma Día del Libro
Programa Día del Librofibyes
 
Gabriel carrero estudo de caso surui
Gabriel carrero   estudo de caso suruiGabriel carrero   estudo de caso surui
Gabriel carrero estudo de caso suruiIdesam
 

Viewers also liked (20)

April 2, 2013 City Council Agenda packet
April 2, 2013 City Council Agenda packetApril 2, 2013 City Council Agenda packet
April 2, 2013 City Council Agenda packet
 
City Council July 20, 2012 Budget Presentation
City Council July 20, 2012 Budget PresentationCity Council July 20, 2012 Budget Presentation
City Council July 20, 2012 Budget Presentation
 
City council december 18, 2012 regular impound adoption_fee_ordinance amend
City council december 18, 2012 regular impound adoption_fee_ordinance amendCity council december 18, 2012 regular impound adoption_fee_ordinance amend
City council december 18, 2012 regular impound adoption_fee_ordinance amend
 
City Council March 22, 2011 Agenda Packet
City Council March 22, 2011 Agenda PacketCity Council March 22, 2011 Agenda Packet
City Council March 22, 2011 Agenda Packet
 
City Council March 22 - Water Bill Online Payment
City Council March 22 - Water Bill Online PaymentCity Council March 22 - Water Bill Online Payment
City Council March 22 - Water Bill Online Payment
 
City Council March 22 - 50th Street & Grape Creek Road Construction
City Council March 22 -  50th Street & Grape Creek Road Construction City Council March 22 -  50th Street & Grape Creek Road Construction
City Council March 22 - 50th Street & Grape Creek Road Construction
 
West Texas Trade Summit 2011: International trade office Presentation
West Texas Trade Summit 2011: International trade office PresentationWest Texas Trade Summit 2011: International trade office Presentation
West Texas Trade Summit 2011: International trade office Presentation
 
City Council March 1 - Expansive Soils
City Council March 1 - Expansive SoilsCity Council March 1 - Expansive Soils
City Council March 1 - Expansive Soils
 
Gestão de obra sqqqqqqqqqqqqqq
Gestão de obra sqqqqqqqqqqqqqqGestão de obra sqqqqqqqqqqqqqq
Gestão de obra sqqqqqqqqqqqqqq
 
O Segredo da Verdadeira Devocão para com a Santíssima Virgem Maria
O Segredo da Verdadeira Devocão para com a Santíssima Virgem MariaO Segredo da Verdadeira Devocão para com a Santíssima Virgem Maria
O Segredo da Verdadeira Devocão para com a Santíssima Virgem Maria
 
Best android keek
Best android keekBest android keek
Best android keek
 
Eie rolling display
Eie rolling displayEie rolling display
Eie rolling display
 
Animals domestics x blog
Animals domestics x blogAnimals domestics x blog
Animals domestics x blog
 
ejemplosss
 ejemplosss ejemplosss
ejemplosss
 
Rastreadores
RastreadoresRastreadores
Rastreadores
 
Atividade01
Atividade01Atividade01
Atividade01
 
Programa Día del Libro
Programa Día del LibroPrograma Día del Libro
Programa Día del Libro
 
Emotions
Emotions Emotions
Emotions
 
Prasks apresentação
Prasks apresentaçãoPrasks apresentação
Prasks apresentação
 
Gabriel carrero estudo de caso surui
Gabriel carrero   estudo de caso suruiGabriel carrero   estudo de caso surui
Gabriel carrero estudo de caso surui
 

Similar to City Council 9-18-12 Avenue P

City Council Feb. 5, 2013 river project update
City Council Feb. 5, 2013 river project updateCity Council Feb. 5, 2013 river project update
City Council Feb. 5, 2013 river project updateCity of San Angelo Texas
 
Restoring Westmeadows Meander
Restoring Westmeadows MeanderRestoring Westmeadows Meander
Restoring Westmeadows MeanderTony Smith
 
Downtown Lebanon Visioning Study and Tunnel Project
Downtown Lebanon Visioning Study and Tunnel ProjectDowntown Lebanon Visioning Study and Tunnel Project
Downtown Lebanon Visioning Study and Tunnel ProjectCity of Lebanon
 
Flood mitigation council presentation 2 july 2013
Flood mitigation council presentation 2 july 2013Flood mitigation council presentation 2 july 2013
Flood mitigation council presentation 2 july 2013City Brandon
 
Strengthening the White River Watershed: CRO Retreat Pecha Kucha
Strengthening the White River Watershed: CRO Retreat Pecha KuchaStrengthening the White River Watershed: CRO Retreat Pecha Kucha
Strengthening the White River Watershed: CRO Retreat Pecha KuchaCommunityResilienceOrgs
 
Franklin, MA: DPW Upcoming Projects
Franklin, MA: DPW Upcoming ProjectsFranklin, MA: DPW Upcoming Projects
Franklin, MA: DPW Upcoming ProjectsFranklin Matters
 
River Road Meeting 3-10-05
River Road Meeting 3-10-05River Road Meeting 3-10-05
River Road Meeting 3-10-05HartTWI
 
Beneath Melbourne's Surface: Urban Hydrology & Utility Easements
Beneath Melbourne's Surface: Urban Hydrology & Utility EasementsBeneath Melbourne's Surface: Urban Hydrology & Utility Easements
Beneath Melbourne's Surface: Urban Hydrology & Utility EasementsTony Smith
 
Water Works Open House Presentation, Revised Design Concept - May 1st 2017
Water Works Open House Presentation, Revised Design Concept - May 1st 2017Water Works Open House Presentation, Revised Design Concept - May 1st 2017
Water Works Open House Presentation, Revised Design Concept - May 1st 2017Minneapolis Parks Foundation
 
Southside Green - Team 2
Southside Green - Team 2Southside Green - Team 2
Southside Green - Team 2M. Damon Weiss
 
CMAX Public Art
CMAX Public ArtCMAX Public Art
CMAX Public ArtCOTA BUS
 
Final public meeting presentation
Final public meeting presentationFinal public meeting presentation
Final public meeting presentationGunn Communications
 
Bay Crest Dredging Presentation 1-24-2024
Bay Crest Dredging Presentation 1-24-2024Bay Crest Dredging Presentation 1-24-2024
Bay Crest Dredging Presentation 1-24-2024marygracekamis
 

Similar to City Council 9-18-12 Avenue P (20)

City Council Feb. 5, 2013 river project update
City Council Feb. 5, 2013 river project updateCity Council Feb. 5, 2013 river project update
City Council Feb. 5, 2013 river project update
 
City council 7 16-13 river project
City council 7 16-13 river projectCity council 7 16-13 river project
City council 7 16-13 river project
 
The Highline
 The Highline The Highline
The Highline
 
Restoring Westmeadows Meander
Restoring Westmeadows MeanderRestoring Westmeadows Meander
Restoring Westmeadows Meander
 
Chicago lakeside developent lm 032414
Chicago lakeside developent lm 032414Chicago lakeside developent lm 032414
Chicago lakeside developent lm 032414
 
W Wright Sess8 102709
W Wright Sess8 102709W Wright Sess8 102709
W Wright Sess8 102709
 
Downtown Lebanon Visioning Study and Tunnel Project
Downtown Lebanon Visioning Study and Tunnel ProjectDowntown Lebanon Visioning Study and Tunnel Project
Downtown Lebanon Visioning Study and Tunnel Project
 
Flood mitigation council presentation 2 july 2013
Flood mitigation council presentation 2 july 2013Flood mitigation council presentation 2 july 2013
Flood mitigation council presentation 2 july 2013
 
Fairhill/MLK pre-construction public meeting 3-25-2015
Fairhill/MLK pre-construction public meeting 3-25-2015Fairhill/MLK pre-construction public meeting 3-25-2015
Fairhill/MLK pre-construction public meeting 3-25-2015
 
Strengthening the White River Watershed: CRO Retreat Pecha Kucha
Strengthening the White River Watershed: CRO Retreat Pecha KuchaStrengthening the White River Watershed: CRO Retreat Pecha Kucha
Strengthening the White River Watershed: CRO Retreat Pecha Kucha
 
Water Management
Water ManagementWater Management
Water Management
 
Franklin, MA: DPW Upcoming Projects
Franklin, MA: DPW Upcoming ProjectsFranklin, MA: DPW Upcoming Projects
Franklin, MA: DPW Upcoming Projects
 
River Road Meeting 3-10-05
River Road Meeting 3-10-05River Road Meeting 3-10-05
River Road Meeting 3-10-05
 
Beneath Melbourne's Surface: Urban Hydrology & Utility Easements
Beneath Melbourne's Surface: Urban Hydrology & Utility EasementsBeneath Melbourne's Surface: Urban Hydrology & Utility Easements
Beneath Melbourne's Surface: Urban Hydrology & Utility Easements
 
Water Works Open House Presentation, Revised Design Concept - May 1st 2017
Water Works Open House Presentation, Revised Design Concept - May 1st 2017Water Works Open House Presentation, Revised Design Concept - May 1st 2017
Water Works Open House Presentation, Revised Design Concept - May 1st 2017
 
Southside Green - Team 2
Southside Green - Team 2Southside Green - Team 2
Southside Green - Team 2
 
FG Gardiner New Simcoe Ramp - display boards
FG Gardiner   New Simcoe Ramp - display boardsFG Gardiner   New Simcoe Ramp - display boards
FG Gardiner New Simcoe Ramp - display boards
 
CMAX Public Art
CMAX Public ArtCMAX Public Art
CMAX Public Art
 
Final public meeting presentation
Final public meeting presentationFinal public meeting presentation
Final public meeting presentation
 
Bay Crest Dredging Presentation 1-24-2024
Bay Crest Dredging Presentation 1-24-2024Bay Crest Dredging Presentation 1-24-2024
Bay Crest Dredging Presentation 1-24-2024
 

More from City of San Angelo Texas

City council january 7, 2014 sidewalk agreement
City council january 7, 2014   sidewalk agreementCity council january 7, 2014   sidewalk agreement
City council january 7, 2014 sidewalk agreementCity of San Angelo Texas
 
City council january 7, 2014 bandits presentation
City council january 7, 2014   bandits presentationCity council january 7, 2014   bandits presentation
City council january 7, 2014 bandits presentationCity of San Angelo Texas
 
City council 12 17-13 downtown development plan
City council 12 17-13 downtown development planCity council 12 17-13 downtown development plan
City council 12 17-13 downtown development planCity of San Angelo Texas
 
City council 12 17-13 planning presentation
City council 12 17-13 planning presentationCity council 12 17-13 planning presentation
City council 12 17-13 planning presentationCity of San Angelo Texas
 
City council nov. 19, 2013 san angelo public housing authority
City council nov. 19, 2013   san angelo public housing  authorityCity council nov. 19, 2013   san angelo public housing  authority
City council nov. 19, 2013 san angelo public housing authorityCity of San Angelo Texas
 
City council nov. 19, 2013 cosadc budget presentation 11-19-13
City council nov. 19, 2013    cosadc budget presentation 11-19-13City council nov. 19, 2013    cosadc budget presentation 11-19-13
City council nov. 19, 2013 cosadc budget presentation 11-19-13City of San Angelo Texas
 
City council nov. 19, 2013 cosadc ballot language presentation
City council nov. 19, 2013    cosadc ballot language presentationCity council nov. 19, 2013    cosadc ballot language presentation
City council nov. 19, 2013 cosadc ballot language presentationCity of San Angelo Texas
 
San angelo city council 11 5-13 - west texas water partnership
San angelo city council 11 5-13 - west texas water partnershipSan angelo city council 11 5-13 - west texas water partnership
San angelo city council 11 5-13 - west texas water partnershipCity of San Angelo Texas
 
San angelo city council 11 5-13 - wastewater pilot
San angelo city council 11 5-13 - wastewater pilotSan angelo city council 11 5-13 - wastewater pilot
San angelo city council 11 5-13 - wastewater pilotCity of San Angelo Texas
 
San angelo city council 11 5-13 - solid waste collection and operation presen...
San angelo city council 11 5-13 - solid waste collection and operation presen...San angelo city council 11 5-13 - solid waste collection and operation presen...
San angelo city council 11 5-13 - solid waste collection and operation presen...City of San Angelo Texas
 
San angelo city council 11 5-13 - nasworthy presentation
San angelo city council 11 5-13 - nasworthy presentationSan angelo city council 11 5-13 - nasworthy presentation
San angelo city council 11 5-13 - nasworthy presentationCity of San Angelo Texas
 
San angelo city council 11 5-13 - economic development budget
San angelo city council 11 5-13 - economic development budgetSan angelo city council 11 5-13 - economic development budget
San angelo city council 11 5-13 - economic development budgetCity of San Angelo Texas
 

More from City of San Angelo Texas (20)

February 4, 2014 Agenda Packet
February 4, 2014 Agenda PacketFebruary 4, 2014 Agenda Packet
February 4, 2014 Agenda Packet
 
January 21, 2014 Agenda packet
January 21, 2014 Agenda packetJanuary 21, 2014 Agenda packet
January 21, 2014 Agenda packet
 
City council january 7, 2014 sidewalk agreement
City council january 7, 2014   sidewalk agreementCity council january 7, 2014   sidewalk agreement
City council january 7, 2014 sidewalk agreement
 
City council january 7, 2014 bandits presentation
City council january 7, 2014   bandits presentationCity council january 7, 2014   bandits presentation
City council january 7, 2014 bandits presentation
 
City council january 7, 2014 river fest
City council january 7, 2014   river festCity council january 7, 2014   river fest
City council january 7, 2014 river fest
 
January 7, 2014 Agenda Packet
January 7, 2014 Agenda PacketJanuary 7, 2014 Agenda Packet
January 7, 2014 Agenda Packet
 
City council 12 17-13 downtown development plan
City council 12 17-13 downtown development planCity council 12 17-13 downtown development plan
City council 12 17-13 downtown development plan
 
City council 12 17-13 planning presentation
City council 12 17-13 planning presentationCity council 12 17-13 planning presentation
City council 12 17-13 planning presentation
 
December 17, 2013 Agenda Packet
December 17, 2013 Agenda PacketDecember 17, 2013 Agenda Packet
December 17, 2013 Agenda Packet
 
December 3, 2013 Agenda packet
December 3, 2013 Agenda packetDecember 3, 2013 Agenda packet
December 3, 2013 Agenda packet
 
City council nov. 19, 2013 san angelo public housing authority
City council nov. 19, 2013   san angelo public housing  authorityCity council nov. 19, 2013   san angelo public housing  authority
City council nov. 19, 2013 san angelo public housing authority
 
City council nov. 19, 2013 planning
City council nov. 19, 2013   planningCity council nov. 19, 2013   planning
City council nov. 19, 2013 planning
 
City council nov. 19, 2013 cosadc budget presentation 11-19-13
City council nov. 19, 2013    cosadc budget presentation 11-19-13City council nov. 19, 2013    cosadc budget presentation 11-19-13
City council nov. 19, 2013 cosadc budget presentation 11-19-13
 
City council nov. 19, 2013 cosadc ballot language presentation
City council nov. 19, 2013    cosadc ballot language presentationCity council nov. 19, 2013    cosadc ballot language presentation
City council nov. 19, 2013 cosadc ballot language presentation
 
November 19, 2013 Agenda Packet
November 19, 2013 Agenda PacketNovember 19, 2013 Agenda Packet
November 19, 2013 Agenda Packet
 
San angelo city council 11 5-13 - west texas water partnership
San angelo city council 11 5-13 - west texas water partnershipSan angelo city council 11 5-13 - west texas water partnership
San angelo city council 11 5-13 - west texas water partnership
 
San angelo city council 11 5-13 - wastewater pilot
San angelo city council 11 5-13 - wastewater pilotSan angelo city council 11 5-13 - wastewater pilot
San angelo city council 11 5-13 - wastewater pilot
 
San angelo city council 11 5-13 - solid waste collection and operation presen...
San angelo city council 11 5-13 - solid waste collection and operation presen...San angelo city council 11 5-13 - solid waste collection and operation presen...
San angelo city council 11 5-13 - solid waste collection and operation presen...
 
San angelo city council 11 5-13 - nasworthy presentation
San angelo city council 11 5-13 - nasworthy presentationSan angelo city council 11 5-13 - nasworthy presentation
San angelo city council 11 5-13 - nasworthy presentation
 
San angelo city council 11 5-13 - economic development budget
San angelo city council 11 5-13 - economic development budgetSan angelo city council 11 5-13 - economic development budget
San angelo city council 11 5-13 - economic development budget
 

Recently uploaded

Croatia vs Italy UEFA Euro 2024 Croatia's Checkered Legacy on Display in New ...
Croatia vs Italy UEFA Euro 2024 Croatia's Checkered Legacy on Display in New ...Croatia vs Italy UEFA Euro 2024 Croatia's Checkered Legacy on Display in New ...
Croatia vs Italy UEFA Euro 2024 Croatia's Checkered Legacy on Display in New ...Eticketing.co
 
Dubai Call Girls Bikni O528786472 Call Girls Dubai Ebony
Dubai Call Girls Bikni O528786472 Call Girls Dubai EbonyDubai Call Girls Bikni O528786472 Call Girls Dubai Ebony
Dubai Call Girls Bikni O528786472 Call Girls Dubai Ebonyhf8803863
 
大学假文凭《原版英国Imperial文凭》帝国理工学院毕业证制作成绩单修改
大学假文凭《原版英国Imperial文凭》帝国理工学院毕业证制作成绩单修改大学假文凭《原版英国Imperial文凭》帝国理工学院毕业证制作成绩单修改
大学假文凭《原版英国Imperial文凭》帝国理工学院毕业证制作成绩单修改atducpo
 
8377087607 ☎, Cash On Delivery Call Girls Service In Hauz Khas Delhi Enjoy 24/7
8377087607 ☎, Cash On Delivery Call Girls Service In Hauz Khas Delhi Enjoy 24/78377087607 ☎, Cash On Delivery Call Girls Service In Hauz Khas Delhi Enjoy 24/7
8377087607 ☎, Cash On Delivery Call Girls Service In Hauz Khas Delhi Enjoy 24/7dollysharma2066
 
办理学位证(KCL文凭证书)伦敦国王学院毕业证成绩单原版一模一样
办理学位证(KCL文凭证书)伦敦国王学院毕业证成绩单原版一模一样办理学位证(KCL文凭证书)伦敦国王学院毕业证成绩单原版一模一样
办理学位证(KCL文凭证书)伦敦国王学院毕业证成绩单原版一模一样7pn7zv3i
 
ppt on Myself, Occupation and my Interest
ppt on Myself, Occupation and my Interestppt on Myself, Occupation and my Interest
ppt on Myself, Occupation and my InterestNagaissenValaydum
 
Interpreting the Secrets of Milan Night Chart
Interpreting the Secrets of Milan Night ChartInterpreting the Secrets of Milan Night Chart
Interpreting the Secrets of Milan Night ChartChart Kalyan
 
Call Girls in Dhaula Kuan 💯Call Us 🔝8264348440🔝
Call Girls in Dhaula Kuan 💯Call Us 🔝8264348440🔝Call Girls in Dhaula Kuan 💯Call Us 🔝8264348440🔝
Call Girls in Dhaula Kuan 💯Call Us 🔝8264348440🔝soniya singh
 
Atlanta Dream Exec Dan Gadd on Driving Fan Engagement and Growth, Serving the...
Atlanta Dream Exec Dan Gadd on Driving Fan Engagement and Growth, Serving the...Atlanta Dream Exec Dan Gadd on Driving Fan Engagement and Growth, Serving the...
Atlanta Dream Exec Dan Gadd on Driving Fan Engagement and Growth, Serving the...Neil Horowitz
 
Chennai Call Girls Anna Nagar Phone 🍆 8250192130 👅 celebrity escorts service
Chennai Call Girls Anna Nagar Phone 🍆 8250192130 👅 celebrity escorts serviceChennai Call Girls Anna Nagar Phone 🍆 8250192130 👅 celebrity escorts service
Chennai Call Girls Anna Nagar Phone 🍆 8250192130 👅 celebrity escorts servicevipmodelshub1
 
VIP Kolkata Call Girl Liluah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Liluah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Liluah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Liluah 👉 8250192130 Available With Roomdivyansh0kumar0
 
大学学位办理《原版美国USD学位证书》圣地亚哥大学毕业证制作成绩单修改
大学学位办理《原版美国USD学位证书》圣地亚哥大学毕业证制作成绩单修改大学学位办理《原版美国USD学位证书》圣地亚哥大学毕业证制作成绩单修改
大学学位办理《原版美国USD学位证书》圣地亚哥大学毕业证制作成绩单修改atducpo
 
Plan d'orientations stratégiques rugby féminin
Plan d'orientations stratégiques rugby fémininPlan d'orientations stratégiques rugby féminin
Plan d'orientations stratégiques rugby fémininThibaut TATRY
 
Tableaux 9ème étape circuit fédéral 2024
Tableaux 9ème étape circuit fédéral 2024Tableaux 9ème étape circuit fédéral 2024
Tableaux 9ème étape circuit fédéral 2024HechemLaameri
 
Resultados del Campeonato mundial de Marcha por equipos Antalya 2024
Resultados del Campeonato mundial de Marcha por equipos Antalya 2024Resultados del Campeonato mundial de Marcha por equipos Antalya 2024
Resultados del Campeonato mundial de Marcha por equipos Antalya 2024Judith Chuquipul
 
France's UEFA Euro 2024 Ambitions Amid Coman's Injury.docx
France's UEFA Euro 2024 Ambitions Amid Coman's Injury.docxFrance's UEFA Euro 2024 Ambitions Amid Coman's Injury.docx
France's UEFA Euro 2024 Ambitions Amid Coman's Injury.docxEuro Cup 2024 Tickets
 

Recently uploaded (20)

Croatia vs Italy UEFA Euro 2024 Croatia's Checkered Legacy on Display in New ...
Croatia vs Italy UEFA Euro 2024 Croatia's Checkered Legacy on Display in New ...Croatia vs Italy UEFA Euro 2024 Croatia's Checkered Legacy on Display in New ...
Croatia vs Italy UEFA Euro 2024 Croatia's Checkered Legacy on Display in New ...
 
Dubai Call Girls Bikni O528786472 Call Girls Dubai Ebony
Dubai Call Girls Bikni O528786472 Call Girls Dubai EbonyDubai Call Girls Bikni O528786472 Call Girls Dubai Ebony
Dubai Call Girls Bikni O528786472 Call Girls Dubai Ebony
 
大学假文凭《原版英国Imperial文凭》帝国理工学院毕业证制作成绩单修改
大学假文凭《原版英国Imperial文凭》帝国理工学院毕业证制作成绩单修改大学假文凭《原版英国Imperial文凭》帝国理工学院毕业证制作成绩单修改
大学假文凭《原版英国Imperial文凭》帝国理工学院毕业证制作成绩单修改
 
8377087607 ☎, Cash On Delivery Call Girls Service In Hauz Khas Delhi Enjoy 24/7
8377087607 ☎, Cash On Delivery Call Girls Service In Hauz Khas Delhi Enjoy 24/78377087607 ☎, Cash On Delivery Call Girls Service In Hauz Khas Delhi Enjoy 24/7
8377087607 ☎, Cash On Delivery Call Girls Service In Hauz Khas Delhi Enjoy 24/7
 
Stunning ➥8448380779▻ Call Girls In Delhi Cantt Delhi NCR
Stunning ➥8448380779▻ Call Girls In Delhi Cantt Delhi NCRStunning ➥8448380779▻ Call Girls In Delhi Cantt Delhi NCR
Stunning ➥8448380779▻ Call Girls In Delhi Cantt Delhi NCR
 
FULL ENJOY Call Girls In Savitri Nagar (Delhi) Call Us 9953056974
FULL ENJOY Call Girls In  Savitri Nagar (Delhi) Call Us 9953056974FULL ENJOY Call Girls In  Savitri Nagar (Delhi) Call Us 9953056974
FULL ENJOY Call Girls In Savitri Nagar (Delhi) Call Us 9953056974
 
办理学位证(KCL文凭证书)伦敦国王学院毕业证成绩单原版一模一样
办理学位证(KCL文凭证书)伦敦国王学院毕业证成绩单原版一模一样办理学位证(KCL文凭证书)伦敦国王学院毕业证成绩单原版一模一样
办理学位证(KCL文凭证书)伦敦国王学院毕业证成绩单原版一模一样
 
ppt on Myself, Occupation and my Interest
ppt on Myself, Occupation and my Interestppt on Myself, Occupation and my Interest
ppt on Myself, Occupation and my Interest
 
young Call girls in Moolchand 🔝 9953056974 🔝 Delhi escort Service
young Call girls in Moolchand 🔝 9953056974 🔝 Delhi escort Serviceyoung Call girls in Moolchand 🔝 9953056974 🔝 Delhi escort Service
young Call girls in Moolchand 🔝 9953056974 🔝 Delhi escort Service
 
Interpreting the Secrets of Milan Night Chart
Interpreting the Secrets of Milan Night ChartInterpreting the Secrets of Milan Night Chart
Interpreting the Secrets of Milan Night Chart
 
Call Girls in Dhaula Kuan 💯Call Us 🔝8264348440🔝
Call Girls in Dhaula Kuan 💯Call Us 🔝8264348440🔝Call Girls in Dhaula Kuan 💯Call Us 🔝8264348440🔝
Call Girls in Dhaula Kuan 💯Call Us 🔝8264348440🔝
 
Atlanta Dream Exec Dan Gadd on Driving Fan Engagement and Growth, Serving the...
Atlanta Dream Exec Dan Gadd on Driving Fan Engagement and Growth, Serving the...Atlanta Dream Exec Dan Gadd on Driving Fan Engagement and Growth, Serving the...
Atlanta Dream Exec Dan Gadd on Driving Fan Engagement and Growth, Serving the...
 
Chennai Call Girls Anna Nagar Phone 🍆 8250192130 👅 celebrity escorts service
Chennai Call Girls Anna Nagar Phone 🍆 8250192130 👅 celebrity escorts serviceChennai Call Girls Anna Nagar Phone 🍆 8250192130 👅 celebrity escorts service
Chennai Call Girls Anna Nagar Phone 🍆 8250192130 👅 celebrity escorts service
 
VIP Kolkata Call Girl Liluah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Liluah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Liluah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Liluah 👉 8250192130 Available With Room
 
大学学位办理《原版美国USD学位证书》圣地亚哥大学毕业证制作成绩单修改
大学学位办理《原版美国USD学位证书》圣地亚哥大学毕业证制作成绩单修改大学学位办理《原版美国USD学位证书》圣地亚哥大学毕业证制作成绩单修改
大学学位办理《原版美国USD学位证书》圣地亚哥大学毕业证制作成绩单修改
 
Plan d'orientations stratégiques rugby féminin
Plan d'orientations stratégiques rugby fémininPlan d'orientations stratégiques rugby féminin
Plan d'orientations stratégiques rugby féminin
 
Call Girls In RK Puram 📱 9999965857 🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICE
Call Girls In RK Puram 📱  9999965857  🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICECall Girls In RK Puram 📱  9999965857  🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICE
Call Girls In RK Puram 📱 9999965857 🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICE
 
Tableaux 9ème étape circuit fédéral 2024
Tableaux 9ème étape circuit fédéral 2024Tableaux 9ème étape circuit fédéral 2024
Tableaux 9ème étape circuit fédéral 2024
 
Resultados del Campeonato mundial de Marcha por equipos Antalya 2024
Resultados del Campeonato mundial de Marcha por equipos Antalya 2024Resultados del Campeonato mundial de Marcha por equipos Antalya 2024
Resultados del Campeonato mundial de Marcha por equipos Antalya 2024
 
France's UEFA Euro 2024 Ambitions Amid Coman's Injury.docx
France's UEFA Euro 2024 Ambitions Amid Coman's Injury.docxFrance's UEFA Euro 2024 Ambitions Amid Coman's Injury.docx
France's UEFA Euro 2024 Ambitions Amid Coman's Injury.docx
 

City Council 9-18-12 Avenue P

  • 2. Avenue P Background • True neighborhood with many residents having lived there for generations • Most houses built in 1940’s and 1950’s • Long history of flooding • reports dating back decades • exacerbated by continued development with increased impervious cover
  • 3. Avenue P Background • 2000 Master Drainage Plan • Developed by Freese & Nichols, Inc. • Analyzed 57 drainage problem areas • Top 25 problem areas ranked/prioritized according to • amount and velocity of flow • capacity of existing facilities • traffic issues (disruption/emergency response) • history of flooded structures • cost-benefit analysis • Avenue P Drainage Problem Area Ranked #2
  • 4. Avenue P Background • Ave P neighborhood meeting – September 19, 2011 • Attendees • Then-City Manager Harold Dominguez • City Councilman Johnny Silvas • City Engineer Clinton Bailey • Approximately 25 area residents • Area residents discussed history of neighborhood drainage issues • City Officials discussed remediation options and funding opportunities
  • 5. Avenue P Background • City Council meeting – November 1, 2011 • Presentation on Capital Planning Projects • Top 5 drainage problems presented • Council approved funding ($1.7 million) for Ave P • $700,000 from fiscal year 2011-2012 • $1,000,000 from fiscal year 2012-2013
  • 13. Drainage Areas W Avenue N Cemeteries ASU S Bryant Blvd Chadbourne Johnson St S
  • 14. Avenue P Drainage Improvement Project • Take drainage underground from S. Bryant Blvd to the east side of S. Chadbourne St. End Begin Avenue P S Chadbourne S Bryant Blvd
  • 15. Avenue P Drainage Improvement Project • 2,300 linear feet of storm drain under Ave P • 300 linear feet of improved open channel • Curb inlets along Avenue P to pick up street drainage • Storm drain crosses under S Chadbourne St. • Discharges into an open channel on the east side of S Chadbourne St. • Flows directly into the Red Arroyo
  • 17. Project Timeline 2012 • Mid-October – Complete design • November – Advertise for bid • Early December – Open and award bid • Mid-late December – Begin construction 2013 • Late summer – Project completion