SlideShare a Scribd company logo
CHECK LIST FOR 26" HOLE, 18.5/8" CASING AND 17.1/2" HOLE
1. 18.5/8" casing materials
2. 3 jt, 18.5/8" casing coated
3. 5" Weatherford stinger for 18.5/8" Stab-in float shoe
4. 1 Pc. of 18.5/8 x 5" D/P centralizer.
5. 18.5/8" Casing running equipment's ( tong & unit ) and crew
6. 26" Mill Tooth Bit (New or used)
7. 1 X 26" Integral blades string stabilizer.
8. 17.1/2" insert new bit and operator
9. 2 x 17.1/2" string Roller Reamer (Bi-Way Directional)
10.9.5/8" performance motors and operator
CHECK LIST FOR 13.3/8" CASING AND 12.1/4" HOLE
1. 13.3/8" casing materials
2. 3 jt, 13.3/8" casing coated
3. 13.5/8" C.H.H and 12" W.bushing and test plug
4. Cement Recipe and program.
5. 13.3/8" Casing running equipment's and crew
6. 13.3/8" H.D.Clamp
7. 13.5/8" Running Flange and 13.3/8" Landing Jt
8. 13.3/8" Quick Latch Cmt and circ. Head (from E.W or D.Sch w/operator).
9. Weatherford Aerated mud drilling package and crew
10.Gyro Multi Shot Survey
11.Mud chemical and engineer for KCL-PHPA mud.
12.12.1/4" PDC bit and operator
13. 9.5/8" motors and operator
14. 8.1/4" MWD tools, unit and crew
15. 2 x 12.1/4" string Roller reamer (Bi-Way Directional)
16. 8" H-M Drilling Jar
CHECK LIST FOR 9.5/8" CASING AND 8.1/2" DEVIATED HOLE
1. 9.5/8" casing materials
2. 13.5/8" x 11" T.H.S and 10" W.Bushing and Test Plug
3. 9.5/8" Fluted Hanger, P.O.B and running tools
4. Crossover 9.5/8" New Vam Pin x NK3SB box
5. Cleaning equipment's and crew.
6. 9.5/8" casing running equipment's and crew ( C.C.P, Power tong and unit, Jam unit, PC
machine and Stabbing Guide).
7. Cement Recipe and program
8. FMC engineer for fluted hanger
9. Weatherford High power wrench for T.H.S and operator.
10. 9.5/8" Quick Latch Cmt and circ. Head.
11. 6.1/2" LWD tools, unit and crew
12. Additional rental 5" H.W.D.P (± 35 jt)
13. Gyro Steering tool, unit and crew ( w/ S.E.S and orienting sub)
14. 6.1/2" H-M drilling Jar
15. O.B.M cutting boxes
16. 200 bbl rectangular covered tank for waste O.B.M
17. 6.1/2" PDM motors and additional directional driller.
18. Horizontal Bucking Machine for M/U 3.1/2" D/P in stands
19. Hi "G" Dryer and crew (in case of O.B.M)
20. 5 trucks to back load aerated mud drilling package.
21. 2 trucks to back load MWD unit and tool.
22. 2.7/8" x 5" Variable Rams for BOP
CHECK LIST FOR 7" CASING LINER AND 6" HORIZONTAL HOLE
1. 7" Casing materials
2. 7" Liner Hanger complete set wit setting tool and cement manifold
3. Cleaning equipment's and crew for 7" casing.
4. 7" casing liner running equipment's and crew ( Power tong , unit, Jam unit, PC machine and
Stabbing Guide).
5. Cement Recipe and program
6. Liner Hanger engineer
7. 4.3/4" LWD tools.
8. Additional rental 3.1/2" H.W.D.P (± 21 jt)
9. 4.3/4" H-M drilling Jar
10. 4.3/4" PDM motors.
11. Cleaning crew for 2.7/8" and 3.1/2" of completion string.
12. Horizontal Bucking Machine for M/U 3.1/2" and 2.7/8" tubing of completion string
in stands
CHECK LIST FOR DUAL OR SINGLE COMPLETION STRING
1. Completion running programs and sketches.
2. Completion materials and well head (Christmases tree).
3. NRV's and Test Plugs.
4. Completion subassembly
5. Electric wire line unit and crew for perforate 7" casing, and correlate 7" single Hyd. pkr
and 9.5/8" Dual Hyd. Pkr (in case of Dual completion string)
6. 6" Spiral string mill.
7. Completion running equipment's and crew ( Power tong and unit, Jam unit, PC machine,
Stabbing Guide).
8. Completion engineer ( in case of Dual string)
9. FMC engineer for Tubing Hanger and Christmases tree
10. 2.7/8" x 3.1/2" Dual Variable rams for BOP ( in case of Dual completion string )
11. Slick wire line unit and crew .
12. Weatherford High power wrench for Christmases tree and operator.
13. Enough No's of 3.1/2" and 2.7/8" pup jts, tubing different lengths (especially 5 ft)

More Related Content

Similar to Check list for drilling new well

BWF Insternship Presentation
BWF Insternship PresentationBWF Insternship Presentation
BWF Insternship Presentation
Amanda Steel
 
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)coderweb
 
PAPER PLATE AND DONA MAKING MACHINE By Jagdamba Enterprises
PAPER PLATE AND DONA MAKING MACHINE By Jagdamba EnterprisesPAPER PLATE AND DONA MAKING MACHINE By Jagdamba Enterprises
PAPER PLATE AND DONA MAKING MACHINE By Jagdamba Enterprises
IndiaMART InterMESH Limited
 
Study of Time Reduction in Manufacturing of Screws Used in Twin Screw Pump
Study of Time Reduction in Manufacturing of Screws Used in Twin Screw PumpStudy of Time Reduction in Manufacturing of Screws Used in Twin Screw Pump
Study of Time Reduction in Manufacturing of Screws Used in Twin Screw Pump
IJMERJOURNAL
 
PUMPS.ppt
PUMPS.pptPUMPS.ppt
PUMPS.ppt
ssuserdb8927
 
All about paper Manufacturing: Paper Making Process
All about paper Manufacturing: Paper Making ProcessAll about paper Manufacturing: Paper Making Process
All about paper Manufacturing: Paper Making Process
Centre for Application of renewable Energy
 
Chart (Repaired).docx
Chart (Repaired).docxChart (Repaired).docx
Chart (Repaired).docx
dkdjs1
 
GSI Internship Portfolio
GSI Internship PortfolioGSI Internship Portfolio
GSI Internship PortfolioNicole Ripperda
 
Dtk group of industries 2013
Dtk group of industries 2013Dtk group of industries 2013
Dtk group of industries 2013Aamer Pathan
 
Design of pulse jet engine for UAV - 2
Design of pulse jet engine for UAV - 2Design of pulse jet engine for UAV - 2
Design of pulse jet engine for UAV - 2
ROSHAN SAH
 
MANUAL.pdf
MANUAL.pdfMANUAL.pdf
MANUAL.pdf
MahmoudAli66277
 
Internship report
Internship reportInternship report
Internship report
ANIL VISHNU B
 
article1433749720_Fozao et al
article1433749720_Fozao et alarticle1433749720_Fozao et al
article1433749720_Fozao et allionel mbanda
 
Kalpak Mechanical Engineering Project Portfolio
Kalpak Mechanical Engineering Project PortfolioKalpak Mechanical Engineering Project Portfolio
Kalpak Mechanical Engineering Project Portfolio
Kalpak Dhake
 
Cm602 pick and place machine introduction
Cm602 pick and place machine introductionCm602 pick and place machine introduction
Cm602 pick and place machine introduction
Lucy Xiao
 
Cm602 introduction
Cm602 introductionCm602 introduction
Cm602 introduction
Mark Tung
 
Cm602 pick and place machine introduction
Cm602 pick and place machine introductionCm602 pick and place machine introduction
Cm602 pick and place machine introduction
Carrie Zhang
 
Cm602 introduction
Cm602 introductionCm602 introduction
Cm602 introduction
Mira Yang
 

Similar to Check list for drilling new well (20)

ES3_Simpson
ES3_SimpsonES3_Simpson
ES3_Simpson
 
BWF Insternship Presentation
BWF Insternship PresentationBWF Insternship Presentation
BWF Insternship Presentation
 
C184 e037 b
C184 e037 bC184 e037 b
C184 e037 b
 
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
 
PAPER PLATE AND DONA MAKING MACHINE By Jagdamba Enterprises
PAPER PLATE AND DONA MAKING MACHINE By Jagdamba EnterprisesPAPER PLATE AND DONA MAKING MACHINE By Jagdamba Enterprises
PAPER PLATE AND DONA MAKING MACHINE By Jagdamba Enterprises
 
Study of Time Reduction in Manufacturing of Screws Used in Twin Screw Pump
Study of Time Reduction in Manufacturing of Screws Used in Twin Screw PumpStudy of Time Reduction in Manufacturing of Screws Used in Twin Screw Pump
Study of Time Reduction in Manufacturing of Screws Used in Twin Screw Pump
 
PUMPS.ppt
PUMPS.pptPUMPS.ppt
PUMPS.ppt
 
All about paper Manufacturing: Paper Making Process
All about paper Manufacturing: Paper Making ProcessAll about paper Manufacturing: Paper Making Process
All about paper Manufacturing: Paper Making Process
 
Chart (Repaired).docx
Chart (Repaired).docxChart (Repaired).docx
Chart (Repaired).docx
 
GSI Internship Portfolio
GSI Internship PortfolioGSI Internship Portfolio
GSI Internship Portfolio
 
Dtk group of industries 2013
Dtk group of industries 2013Dtk group of industries 2013
Dtk group of industries 2013
 
Design of pulse jet engine for UAV - 2
Design of pulse jet engine for UAV - 2Design of pulse jet engine for UAV - 2
Design of pulse jet engine for UAV - 2
 
MANUAL.pdf
MANUAL.pdfMANUAL.pdf
MANUAL.pdf
 
Internship report
Internship reportInternship report
Internship report
 
article1433749720_Fozao et al
article1433749720_Fozao et alarticle1433749720_Fozao et al
article1433749720_Fozao et al
 
Kalpak Mechanical Engineering Project Portfolio
Kalpak Mechanical Engineering Project PortfolioKalpak Mechanical Engineering Project Portfolio
Kalpak Mechanical Engineering Project Portfolio
 
Cm602 pick and place machine introduction
Cm602 pick and place machine introductionCm602 pick and place machine introduction
Cm602 pick and place machine introduction
 
Cm602 introduction
Cm602 introductionCm602 introduction
Cm602 introduction
 
Cm602 pick and place machine introduction
Cm602 pick and place machine introductionCm602 pick and place machine introduction
Cm602 pick and place machine introduction
 
Cm602 introduction
Cm602 introductionCm602 introduction
Cm602 introduction
 

More from amrhaggag

بنعمل ايه على الصفحة والجروب - أزاى نتعامل مع السكر 1 و 2 من واقع التجربة
بنعمل ايه على الصفحة والجروب - أزاى نتعامل مع السكر 1 و 2 من واقع التجربةبنعمل ايه على الصفحة والجروب - أزاى نتعامل مع السكر 1 و 2 من واقع التجربة
بنعمل ايه على الصفحة والجروب - أزاى نتعامل مع السكر 1 و 2 من واقع التجربة
amrhaggag
 
Drilling rig operations a to z rotary drilling rig components
Drilling rig operations  a to z rotary drilling rig componentsDrilling rig operations  a to z rotary drilling rig components
Drilling rig operations a to z rotary drilling rig components
amrhaggag
 
Drilling rig components ( illustrated glossary )
Drilling rig components ( illustrated glossary )Drilling rig components ( illustrated glossary )
Drilling rig components ( illustrated glossary )
amrhaggag
 
Directional drilling
Directional drillingDirectional drilling
Directional drilling
amrhaggag
 
rig drilling_equipment
 rig drilling_equipment rig drilling_equipment
rig drilling_equipment
amrhaggag
 
Wild well wc formulas and graphas
Wild well wc formulas and graphasWild well wc formulas and graphas
Wild well wc formulas and graphas
amrhaggag
 
Tubing standard
Tubing standardTubing standard
Tubing standard
amrhaggag
 
Sysdrill.pdf
Sysdrill.pdfSysdrill.pdf
Sysdrill.pdf
amrhaggag
 
DDMS
DDMSDDMS
DDMS
amrhaggag
 
Wait and weight vs. driller
Wait and weight vs. drillerWait and weight vs. driller
Wait and weight vs. driller
amrhaggag
 
Kill sheet
Kill sheetKill sheet
Kill sheet
amrhaggag
 
Directional survey hand book
Directional survey hand book Directional survey hand book
Directional survey hand book
amrhaggag
 
Wellhead
WellheadWellhead
Wellhead
amrhaggag
 
Wellhead specifications
Wellhead specificationsWellhead specifications
Wellhead specifications
amrhaggag
 
Well control intro presentation
Well control intro presentationWell control intro presentation
Well control intro presentation
amrhaggag
 
Oilfield glossary
Oilfield glossaryOilfield glossary
Oilfield glossary
amrhaggag
 
Land rig handbook
Land rig handbookLand rig handbook
Land rig handbook
amrhaggag
 
Intro to petroleum geology
Intro to petroleum geologyIntro to petroleum geology
Intro to petroleum geology
amrhaggag
 
Intro to oil well drilling ops pt 4
Intro to oil well drilling ops pt 4Intro to oil well drilling ops pt 4
Intro to oil well drilling ops pt 4
amrhaggag
 
Intro to oil well drilling ops pt 3
Intro to oil well drilling ops pt 3Intro to oil well drilling ops pt 3
Intro to oil well drilling ops pt 3
amrhaggag
 

More from amrhaggag (20)

بنعمل ايه على الصفحة والجروب - أزاى نتعامل مع السكر 1 و 2 من واقع التجربة
بنعمل ايه على الصفحة والجروب - أزاى نتعامل مع السكر 1 و 2 من واقع التجربةبنعمل ايه على الصفحة والجروب - أزاى نتعامل مع السكر 1 و 2 من واقع التجربة
بنعمل ايه على الصفحة والجروب - أزاى نتعامل مع السكر 1 و 2 من واقع التجربة
 
Drilling rig operations a to z rotary drilling rig components
Drilling rig operations  a to z rotary drilling rig componentsDrilling rig operations  a to z rotary drilling rig components
Drilling rig operations a to z rotary drilling rig components
 
Drilling rig components ( illustrated glossary )
Drilling rig components ( illustrated glossary )Drilling rig components ( illustrated glossary )
Drilling rig components ( illustrated glossary )
 
Directional drilling
Directional drillingDirectional drilling
Directional drilling
 
rig drilling_equipment
 rig drilling_equipment rig drilling_equipment
rig drilling_equipment
 
Wild well wc formulas and graphas
Wild well wc formulas and graphasWild well wc formulas and graphas
Wild well wc formulas and graphas
 
Tubing standard
Tubing standardTubing standard
Tubing standard
 
Sysdrill.pdf
Sysdrill.pdfSysdrill.pdf
Sysdrill.pdf
 
DDMS
DDMSDDMS
DDMS
 
Wait and weight vs. driller
Wait and weight vs. drillerWait and weight vs. driller
Wait and weight vs. driller
 
Kill sheet
Kill sheetKill sheet
Kill sheet
 
Directional survey hand book
Directional survey hand book Directional survey hand book
Directional survey hand book
 
Wellhead
WellheadWellhead
Wellhead
 
Wellhead specifications
Wellhead specificationsWellhead specifications
Wellhead specifications
 
Well control intro presentation
Well control intro presentationWell control intro presentation
Well control intro presentation
 
Oilfield glossary
Oilfield glossaryOilfield glossary
Oilfield glossary
 
Land rig handbook
Land rig handbookLand rig handbook
Land rig handbook
 
Intro to petroleum geology
Intro to petroleum geologyIntro to petroleum geology
Intro to petroleum geology
 
Intro to oil well drilling ops pt 4
Intro to oil well drilling ops pt 4Intro to oil well drilling ops pt 4
Intro to oil well drilling ops pt 4
 
Intro to oil well drilling ops pt 3
Intro to oil well drilling ops pt 3Intro to oil well drilling ops pt 3
Intro to oil well drilling ops pt 3
 

Recently uploaded

MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 

Recently uploaded (20)

MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 

Check list for drilling new well

  • 1. CHECK LIST FOR 26" HOLE, 18.5/8" CASING AND 17.1/2" HOLE 1. 18.5/8" casing materials 2. 3 jt, 18.5/8" casing coated 3. 5" Weatherford stinger for 18.5/8" Stab-in float shoe 4. 1 Pc. of 18.5/8 x 5" D/P centralizer. 5. 18.5/8" Casing running equipment's ( tong & unit ) and crew 6. 26" Mill Tooth Bit (New or used) 7. 1 X 26" Integral blades string stabilizer. 8. 17.1/2" insert new bit and operator 9. 2 x 17.1/2" string Roller Reamer (Bi-Way Directional) 10.9.5/8" performance motors and operator CHECK LIST FOR 13.3/8" CASING AND 12.1/4" HOLE 1. 13.3/8" casing materials 2. 3 jt, 13.3/8" casing coated 3. 13.5/8" C.H.H and 12" W.bushing and test plug 4. Cement Recipe and program. 5. 13.3/8" Casing running equipment's and crew 6. 13.3/8" H.D.Clamp 7. 13.5/8" Running Flange and 13.3/8" Landing Jt 8. 13.3/8" Quick Latch Cmt and circ. Head (from E.W or D.Sch w/operator). 9. Weatherford Aerated mud drilling package and crew 10.Gyro Multi Shot Survey 11.Mud chemical and engineer for KCL-PHPA mud. 12.12.1/4" PDC bit and operator 13. 9.5/8" motors and operator 14. 8.1/4" MWD tools, unit and crew 15. 2 x 12.1/4" string Roller reamer (Bi-Way Directional) 16. 8" H-M Drilling Jar CHECK LIST FOR 9.5/8" CASING AND 8.1/2" DEVIATED HOLE 1. 9.5/8" casing materials 2. 13.5/8" x 11" T.H.S and 10" W.Bushing and Test Plug 3. 9.5/8" Fluted Hanger, P.O.B and running tools 4. Crossover 9.5/8" New Vam Pin x NK3SB box 5. Cleaning equipment's and crew. 6. 9.5/8" casing running equipment's and crew ( C.C.P, Power tong and unit, Jam unit, PC machine and Stabbing Guide). 7. Cement Recipe and program 8. FMC engineer for fluted hanger 9. Weatherford High power wrench for T.H.S and operator. 10. 9.5/8" Quick Latch Cmt and circ. Head. 11. 6.1/2" LWD tools, unit and crew 12. Additional rental 5" H.W.D.P (± 35 jt)
  • 2. 13. Gyro Steering tool, unit and crew ( w/ S.E.S and orienting sub) 14. 6.1/2" H-M drilling Jar 15. O.B.M cutting boxes 16. 200 bbl rectangular covered tank for waste O.B.M 17. 6.1/2" PDM motors and additional directional driller. 18. Horizontal Bucking Machine for M/U 3.1/2" D/P in stands 19. Hi "G" Dryer and crew (in case of O.B.M) 20. 5 trucks to back load aerated mud drilling package. 21. 2 trucks to back load MWD unit and tool. 22. 2.7/8" x 5" Variable Rams for BOP CHECK LIST FOR 7" CASING LINER AND 6" HORIZONTAL HOLE 1. 7" Casing materials 2. 7" Liner Hanger complete set wit setting tool and cement manifold 3. Cleaning equipment's and crew for 7" casing. 4. 7" casing liner running equipment's and crew ( Power tong , unit, Jam unit, PC machine and Stabbing Guide). 5. Cement Recipe and program 6. Liner Hanger engineer 7. 4.3/4" LWD tools. 8. Additional rental 3.1/2" H.W.D.P (± 21 jt) 9. 4.3/4" H-M drilling Jar 10. 4.3/4" PDM motors. 11. Cleaning crew for 2.7/8" and 3.1/2" of completion string. 12. Horizontal Bucking Machine for M/U 3.1/2" and 2.7/8" tubing of completion string in stands CHECK LIST FOR DUAL OR SINGLE COMPLETION STRING 1. Completion running programs and sketches. 2. Completion materials and well head (Christmases tree). 3. NRV's and Test Plugs. 4. Completion subassembly 5. Electric wire line unit and crew for perforate 7" casing, and correlate 7" single Hyd. pkr and 9.5/8" Dual Hyd. Pkr (in case of Dual completion string) 6. 6" Spiral string mill. 7. Completion running equipment's and crew ( Power tong and unit, Jam unit, PC machine, Stabbing Guide). 8. Completion engineer ( in case of Dual string) 9. FMC engineer for Tubing Hanger and Christmases tree 10. 2.7/8" x 3.1/2" Dual Variable rams for BOP ( in case of Dual completion string ) 11. Slick wire line unit and crew . 12. Weatherford High power wrench for Christmases tree and operator. 13. Enough No's of 3.1/2" and 2.7/8" pup jts, tubing different lengths (especially 5 ft)