SlideShare a Scribd company logo
Chapter 3
Chapter Three
Planning and Development Process
By Yimam Alemu
December 16, 2020
By Yimam Alemu Chapter 3 December 16, 2020 1 / 55
Chapter 3
Outline
1 Methodology of HEPP Development
2 Surveys needed for hydro power plants
3 Selection of Site for a Hydroelectric Power Plant
4 Types of Development
5 Efficiency of hydropower
By Yimam Alemu Chapter 3 December 16, 2020 2 / 55
Chapter 3
Learning Objectives
At the end of this chapter the students should be able to:
Understand the methodology of HEPP development Understand elements and equip-
ment’s needed to be taken into consideration while designing a hydroelectric power
plant.
Understand factors should be considered while selecting the site for a hydroelectric
power plant.
Understand the different types of developments of hydroelectric power plant.
Understand the environmental, social and economic analysis of HEPP.
By Yimam Alemu Chapter 3 December 16, 2020 3 / 55
Chapter 3
Methodology of HEPP Development
Methodology of HEPP Development
Site Survey: Hydrological and geological Survey.
Regulations and Environmental Concerns
Feasible Supply(feasibility study)
Estimation of Potential
Turbine Selection
Costing and Payback
By Yimam Alemu Chapter 3 December 16, 2020 4 / 55
Chapter 3
Methodology of HEPP Development
Measuring parameters
Measurement of river(water body flow data.)
Measurement of head ( Power and available head )
Topographical and geological condition of site
Site accessibility – need to be address during planning stage
Power transmission point distance – determine power loss
Power demand assessment
By Yimam Alemu Chapter 3 December 16, 2020 5 / 55
Chapter 3
Methodology of HEPP Development
Hydrological Survey
Power demand assessment
To measure the flow-rate vs time at a given site
The more robust option is to find out the flowrate by working out the volume of water
that was entering the river.
This uses the rainfall data from metrology office for two lean seasons.
By Yimam Alemu Chapter 3 December 16, 2020 6 / 55
Chapter 3
Methodology of HEPP Development
Flow Rate Measurement
There are numerous ways to measure flow rate, such as:
Bucket Method
Float Method
Weirs
Meters
By Yimam Alemu Chapter 3 December 16, 2020 7 / 55
Chapter 3
Methodology of HEPP Development
1.Bucket method
The Bucket method is a simple way to measure the flow rate using household items.
It requires a stopwatch, a large bucket, and preferably two to three people to measure
the flow rate using the bucket method:
Direct measurement with a bucket
Good for small flow in conduit.
By Yimam Alemu Chapter 3 December 16, 2020 8 / 55
Chapter 3
Methodology of HEPP Development
Cont....
Measure the volume of the bucket or container
Find a location along the stream that has a waterfall
With a stopwatch, time how long it takes the waterfall to fill the bucket with water
Record the time it takes to fill the bucket.
Figure: Bucket measuring method
By Yimam Alemu Chapter 3 December 16, 2020 9 / 55
Chapter 3
Methodology of HEPP Development
2. Float Measuring Method
Figure: Float measuring method
By Yimam Alemu Chapter 3 December 16, 2020 10 / 55
Chapter 3
Methodology of HEPP Development
Cont....
The float method (also known as the cross-sectional method) is used to measure the
flow rate for larger streams and rivers.
Locate a spot in the stream that will act as the cross section of the stream.
Using a meter stick, or some other means of measurement, measure the depth of the
stream at equal intervals along the width of the stream.
Decide on a length of the stream, typically longer than the width of the river, to send
a floating object down.
Using a stopwatch, measure the time it takes the float to travel down the length of
stream.
By Yimam Alemu Chapter 3 December 16, 2020 11 / 55
Chapter 3
Methodology of HEPP Development
3. Weir Measuring Method
Weirs are small dams that can be used in measuring flow rate for small to medium
sized streams (a few meters or wider).
They allow overflow of the stream to pour over the top of the weir, creating a waterfall.
Weirs increase the change in elevation making the streamflow more consistent which
makes flow rate measurements more precise.
By Yimam Alemu Chapter 3 December 16, 2020 12 / 55
Chapter 3
Methodology of HEPP Development
Figure: Weir measuring method
By Yimam Alemu Chapter 3 December 16, 2020 13 / 55
Chapter 3
Methodology of HEPP Development
Figure: Weir measuring method
By Yimam Alemu Chapter 3 December 16, 2020 14 / 55
Chapter 3
Methodology of HEPP Development
4.Meters
Meters are devices that measure the stream flow by directly measuring the current.
There are many different types of meters, the most common is the Pygmy meter, the
vortex meter, the flow probe, and the current meter:
Measured by Electromagnetic current or propeller type current meter.
By Yimam Alemu Chapter 3 December 16, 2020 15 / 55
Chapter 3
Methodology of HEPP Development
Measuring Instruments
Altimeter: – for altitude measurement
GPS: for location coordinate
Camera: for capturing the location image
Current meter: measuring the flow of water
Distance meter
Depth meter: depth of the water body
Clinometer measures vertical slope, usually the angle between the ground or the
observer and a tall object
Compass
Hand level
By Yimam Alemu Chapter 3 December 16, 2020 16 / 55
Chapter 3
Methodology of HEPP Development
Various studies during the preliminary site survey
Hydrological studies : Overall rain fall ,run off data ,principal river flow data , flood
characteristics, from record of gov’t. department . Min ,avg and flood details.
Topological studies : Tachometric survey and survey required depending upon the
existing info and maps.
Geological studies : Overall geological characteristics and local features for trans-
portation of material.
Power demand assessment : Overall power demand scenario in the project near by
area and existing infrastructure for power evacuation.
By Yimam Alemu Chapter 3 December 16, 2020 17 / 55
Chapter 3
Methodology of HEPP Development
Site Survey
Pre Feasibility Report
Basic Design
Various Graphs and Pictures
By Yimam Alemu Chapter 3 December 16, 2020 18 / 55
Chapter 3
Surveys needed for hydro power plants
Surveys needed for hydro power plants
The following surveys are carried out for a hydro plant installation.
General surveys
Special surveys
By Yimam Alemu Chapter 3 December 16, 2020 19 / 55
Chapter 3
Surveys needed for hydro power plants
A) General surveys
They constitute the following:
1. Topographical surveys such as
i) The dam site topographical survey plans including the area of accommodate dam,
spillway, outlet works, diversion works etc.
ii) The reservoir submergence plans Contour plan of
a) Surge tanks
b) Tunnels
c) Penstock
d) Tail race channels.
iii) River surveys
iv) For a barrage structure detailed survey maps to cover the area under the barrage.
By Yimam Alemu Chapter 3 December 16, 2020 20 / 55
Chapter 3
Surveys needed for hydro power plants
Cont....
2. Geological and foundation investigations.
A study should be carried out for the following:
i) Seismic condition of the region
ii) Water flow in reservoir
iii) Sub-surface conditions
iv) Foundation investigations for dams.
By Yimam Alemu Chapter 3 December 16, 2020 21 / 55
Chapter 3
Surveys needed for hydro power plants
Cont....
3. Metrological and hydrological studies:
The following data should be collected
i Precipitation, evaporation.
ii Water flows such as maximum and minimum water flows.
iii Rainfall-run off relation data.
iv Mean latitude, and longitude, mean elevation, mean monthly temperature.
v Location of raingauge station near power plant site.
By Yimam Alemu Chapter 3 December 16, 2020 22 / 55
Chapter 3
Surveys needed for hydro power plants
Cont....
4. Construction material investigations:
Data should be collected for the following:
i Materials to be used for
a) Concrete and masonry dams
b) Earth and rock fill dams.
ii Tests to be carried out for materials.
By Yimam Alemu Chapter 3 December 16, 2020 23 / 55
Chapter 3
Surveys needed for hydro power plants
Cont....
5. Transportation and communication:
Data should be collected for the following:
Road, water and rail routes
Telephone and telegraph lines.
6. Environmental considerations
Navigation
Fish culture.
By Yimam Alemu Chapter 3 December 16, 2020 24 / 55
Chapter 3
Surveys needed for hydro power plants
B) Special surveys
Special surveys include the following:
1. Load surveys: They are made of
i Power-station capacity
ii Power to be generated
iii Details for major loads to be served
iv Peak load
v Load factor
vi Future energy demand
vii Inter connection with other power systems
By Yimam Alemu Chapter 3 December 16, 2020 25 / 55
Chapter 3
Surveys needed for hydro power plants
Cont....
2. Lay-out studies: This includes the following
i Type of power plant such as storage type, run of river plant,pumped storage type etc.
ii Structural components like
a) Dams
b) Canals
c) Tunnels
d) Penstock
e) Draft tube
f) Surge tanks
g) Power house
h) Switch yard
By Yimam Alemu Chapter 3 December 16, 2020 26 / 55
Chapter 3
Surveys needed for hydro power plants
Pre feasibility report
Pre feasibility report is required to investigate weather project is technically or finan-
cially feasible or not.
Aim of PFR is to examine next step to project formulation
Preparation of PFRs involves
Conceptual planning,
Preparation of project and equipment layouts,
Infrastructure requirement,
Environmental and geological studies,
Power evacuation arrangement, cost estimates and
economic evaluation.
By Yimam Alemu Chapter 3 December 16, 2020 27 / 55
Chapter 3
Surveys needed for hydro power plants
Cont....
Executive summary
Introduction
Project location
Map
Project description
Salient feature
Hydrology
Climate
Catchment area
Rainfall
By Yimam Alemu Chapter 3 December 16, 2020 28 / 55
Chapter 3
Surveys needed for hydro power plants
Cont....
When designing a hydroelectric power plant a number of elements and equipment’s
need to be taken into consideration.
Site selection
Technical data
Intake position
Penstock length and diameter
Turbine and generator systems
Electrical and control equipment
The Power House
Distribution system
By Yimam Alemu Chapter 3 December 16, 2020 29 / 55
Chapter 3
Surveys needed for hydro power plants
Cont....
Based on the firm power:
Dams, canals, intakes, penstocks, tailraces and power houses are designed by civil
engineers.
Mechanical Engineers design the hydraulic turbines.
Electrical Engineers design the generators, transformers, the switch yards and the
protection system.
♣ Firm power is also one of the main factors that decides the feasibility of HPP.
By Yimam Alemu Chapter 3 December 16, 2020 30 / 55
Chapter 3
Surveys needed for hydro power plants
Cont....
Civil Engineers, Mechanical Engineers, Electrical Engineers, Geologists, Economists,
Ecologists, Sociologists and many other experts combine their skills in order to develop
an optimum design considering technical, financial, environmental and social aspects
of hydropower development.
Feasibility study contains:
Site visit and selection
Capacity analysis
Economic analysis
Environmental impact analysis
♣ Feasibility study is the first step in HPP construction.
By Yimam Alemu Chapter 3 December 16, 2020 31 / 55
Chapter 3
Selection of Site for a Hydroelectric Power Plant
Selection of Site for a Hydroelectric Power Plant
The following factors should be considered while selecting the site for a hydroelectric
plant.
1 Availability of water
2 Water storage capacity
3 Available water head
4 Accessibility of the site
5 Distance from the load Centre
6 Water pollution
7 Sedimentation
8 Large catchment area
9 Availability of Land
By Yimam Alemu Chapter 3 December 16, 2020 32 / 55
Chapter 3
Selection of Site for a Hydroelectric Power Plant
1.Availability of water
The recorded observation should be taken over a number of years to know within
reasonable limits the maximum and minimum variations from the average discharge.
The river flow data should be based on daily, weekly, monthly and yearly flow over a
number of years.
Then the curves or graphs can be plotted between river flow and time. These are
known as hygrographs and flow duration curves.
By Yimam Alemu Chapter 3 December 16, 2020 33 / 55
Chapter 3
Selection of Site for a Hydroelectric Power Plant
2. Water Storage capacity:
The output of a hydropower plant is not uniform due to wide variations of rain fall. To
have a uniform power output, a water storage is needed so that excess flow at certain
times may be stored to make it available at the times of low flow.
Since storage of water in a reservoir at a height or building of dam across the river is
essential in order to have continuous supply during the dry season.
The storage capacity can be determined from the Hydrograph, Mass Curve or by using
analytical methods.
By Yimam Alemu Chapter 3 December 16, 2020 34 / 55
Chapter 3
Selection of Site for a Hydroelectric Power Plant
3. Available water head
Available water head depends upon the topography of the area.
The level of water in the reservoir for a proposed plant should always be within limits
throughout the year.
Availability of head of water has considerable effect on the cost and economy of power
generation.
An increase in effective head reduces the quantity of water to be stored and handled
by penstocks, screens and turbines and therefore capital cost of the plant is reduced.
By Yimam Alemu Chapter 3 December 16, 2020 35 / 55
Chapter 3
Selection of Site for a Hydroelectric Power Plant
4. Distance from Load Center
Most of the time the electric power generated in a hydro-electric power plant has to be
used some considerable distance from the site of plant.
For this reason, to be economical on transmission of electric power, the routes and the
distances should be carefully considered since the cost of erection of transmission lines
and their maintenance will depend upon the route selected.
Power plant should be set up near the load center, this will reduce the cost of mainte-
nance of transmission line
By Yimam Alemu Chapter 3 December 16, 2020 36 / 55
Chapter 3
Selection of Site for a Hydroelectric Power Plant
5. Accessibility of the Site
The site where hydroelectric plant is to be constructed should be easily accessible.
This is important if the electric power generated is to be utilized at or near the plant
site.
The site selected should have transportation facilities of rail and road.
By Yimam Alemu Chapter 3 December 16, 2020 37 / 55
Chapter 3
Selection of Site for a Hydroelectric Power Plant
6. Water Pollution
Polluted water may cause excessive corrosion and damage to the metallic structures.
This may render the operation of the plant unreliable and uneconomic
It is necessary to see that the water is of good quality and will not cause such troubles.
By Yimam Alemu Chapter 3 December 16, 2020 38 / 55
Chapter 3
Selection of Site for a Hydroelectric Power Plant
7. Sedimentation
Gradual deposition of silt may reduce the capacity of the storage reservoir and may
also cause damage to the turbine blades.
Silting from forest covered areas is negligible. On the other hand the regions subject
to violent storms and not protected by vegetation contribute lot of silt to the run off
By Yimam Alemu Chapter 3 December 16, 2020 39 / 55
Chapter 3
Selection of Site for a Hydroelectric Power Plant
8. Large Catchment Area
The reservoir must have a large catchment area so that level of water in the reservoir
may not fall below the minimum required in dry season.
By Yimam Alemu Chapter 3 December 16, 2020 40 / 55
Chapter 3
Selection of Site for a Hydroelectric Power Plant
9. Type of the land of the site
The land to be selected for the site should be cheap in cost and rocky in order to
withstand the weight of the large building and heavy machinery.
There should be a stream diversion during period of construction.
The necessary requirements of the foundation rocks for a masonry dam are as follows:
The rock should be strong enough to withstand the stresses transmitted from the dam
structure as well as the thrust of the water when the reservoir is full.
The rock in the foundation of the dam should be reasonably impervious
The rock should remain stable under all conditions.
By Yimam Alemu Chapter 3 December 16, 2020 41 / 55
Chapter 3
Selection of Site for a Hydroelectric Power Plant
Main design parameters
The power capacity of a hydropower plant is primarily a function of two main variables
of the water
Water flow
Hydraulic head
Design flow is the maximum flow for which your hydro system is designed.
It will likely be less than the maximum flow of the stream (especially during the rainy
season) or more than the minimum flow during dry season.
If a system is to be independent of any other energy or utility backup, the design flow
should be the flow that is available 95 percent of the time or more.
By Yimam Alemu Chapter 3 December 16, 2020 42 / 55
Chapter 3
Selection of Site for a Hydroelectric Power Plant
Cont....
Therefore, a stand-alone system such as a micro hydropower system should be designed
according to the flow that is available year-round; this is usually the flow during the
dry season.
Reserved flow: it is the minimum flow required to avoid aquatic life damage in the
water stream.
Firm flow: The firm flow is defined as the flow being available X% of the time, where
X is a percentage specified by the user and usually equal to 95%.
By Yimam Alemu Chapter 3 December 16, 2020 43 / 55
Chapter 3
Types of Development
Types of Development
In studying the subject hydropower engineering it is important to understand the
different types of development.
Run-off river development
Diversion and canal development
Storage regulation development
Pumped storage development
Single purpose development
Multi purpose development
Cascaded development
By Yimam Alemu Chapter 3 December 16, 2020 44 / 55
Chapter 3
Types of Development
1. Run-off river development
A dam with short penstock (supply pipe) directs the water to the turbine using the
natural flow of the river.
By Yimam Alemu Chapter 3 December 16, 2020 45 / 55
Chapter 3
Types of Development
2. Diversion and canal development
The water is diverted from the natural channel into canal, thus changing the natural flow
of the water in the stream for a considerable distance.
By Yimam Alemu Chapter 3 December 16, 2020 46 / 55
Chapter 3
Types of Development
3. Storage regulation development
An extensive impoundment at the power plant or at the reservoir up stream of the
power plant permits changing the flow of the river by storing the water during high
flow periods to enlarge the water available during the low flow periods, thus supplying
the demand for energy in a more efficient manner.
Storage refers to long time impounding of water to meet the seasonal fluctuation in
water availability and the fluctuations in energy demand.
Pondage refers to short-time impounding of water to meet short-time changes of de-
mand.
By Yimam Alemu Chapter 3 December 16, 2020 47 / 55
Chapter 3
Types of Development
4. Pumped storage development
Water is pumped from lower reservoir to a higher reservoir during period of low energy
demand. The water then run down through turbine to produce power to meet peak
demand.
By Yimam Alemu Chapter 3 December 16, 2020 48 / 55
Chapter 3
Types of Development
5. Single and multi purpose development
In single-purpose development the water is used only for the purpose of producing
electricity.
In multi-purpose development hydropower production is just one of many purposes for
which the water resource is used.
e.g. irrigation, flood control, navigation, industrial water supply, etc
By Yimam Alemu Chapter 3 December 16, 2020 49 / 55
Chapter 3
Types of Development
6. Cascaded development
By Yimam Alemu Chapter 3 December 16, 2020 50 / 55
Chapter 3
Types of Development
Cont....
Example:
Gibe III 1870 MW
The Gibe III dam is part of the Gibe cascade, a series of dams including the existing
Gibe I dam (184 MW) and Gibe II power station (420 MW) as well as the planned
Gibe IV (1472 MW) and Gibe V (560 MW) dams.
By Yimam Alemu Chapter 3 December 16, 2020 51 / 55
Chapter 3
Efficiency of hydropower
Efficiency of hydropower
The potential for energy production in a hydropower plant is determined by the fol-
lowing parameters:-
The amount of water available
Water loss due to flood spill, bypass requirements or leakage
Head
Hydraulic losses in water transport due to friction and water velocity change.
The efficiency in energy conversion of electro mechanical equipments.
By Yimam Alemu Chapter 3 December 16, 2020 52 / 55
Chapter 3
Efficiency of hydropower
Cont....
In hydropower plant the energy transformation
Potential energy(stored water in dam)
Kinetic energy(water falling from height)
Mechanical energy(Turbines)
Electrical energy(Generator)
The energy transformation in modern hydropower plants is highly efficient usually well
over 90%.
By Yimam Alemu Chapter 3 December 16, 2020 53 / 55
Chapter 3
Efficiency of hydropower
Cont....
Efficiency of hydropower plant is dependent on
Hydraulic loss (intake, turbine, tailrace)
Mechanical and electrical loss (turbines and generators)
Absorption of sediments
Due to heat in the water and generator
The total efficiency of a hydropower plant is determined by the sum of these three loss
components.
Hydraulic losses, it can be reduced by increasing turbine capacity or reservoir capacity
for better regulation of flow.
Head loss, it can be reduced by increasing the area of headrace and tailrace, by de-
creasing roughness in the pipes.
By avoiding too many changes in flow velocity and direction.
By Yimam Alemu Chapter 3 December 16, 2020 54 / 55
Chapter 3
Questions
Thank You!
By Yimam Alemu Chapter 3 December 16, 2020 55 / 55

More Related Content

What's hot

Basics of Hydro power plant
Basics of  Hydro power plant Basics of  Hydro power plant
Basics of Hydro power plant Prasad Vejendla
 
Baglihar hydro electric power plant
Baglihar hydro electric power plantBaglihar hydro electric power plant
Baglihar hydro electric power plantRaja Katoch
 
Presentation of hydro power plant
Presentation of hydro power plantPresentation of hydro power plant
Presentation of hydro power plantNazakatHussain15
 
Pre-Feasibility Study of a 1000 MW Pumped Storage Plant in Saudi Arabia
Pre-Feasibility Study of a 1000 MW Pumped Storage Plant in Saudi ArabiaPre-Feasibility Study of a 1000 MW Pumped Storage Plant in Saudi Arabia
Pre-Feasibility Study of a 1000 MW Pumped Storage Plant in Saudi ArabiaSNC-Lavalin
 
200118 chapter 8 hydromechanical
200118 chapter 8 hydromechanical200118 chapter 8 hydromechanical
200118 chapter 8 hydromechanicalBinu Karki
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plantYuri Melliza
 
Hydroelectricpowerplant 290916
Hydroelectricpowerplant 290916Hydroelectricpowerplant 290916
Hydroelectricpowerplant 290916PALANIVEL SUBBIAH
 
PRINCIPLES OF HYDROPOWER ENGINEERING
PRINCIPLES OF HYDROPOWERENGINEERINGPRINCIPLES OF HYDROPOWERENGINEERING
PRINCIPLES OF HYDROPOWER ENGINEERINGArkan Hamza Gardi
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plantajay kumar
 
Hydrolic power plant.ppt
Hydrolic power plant.pptHydrolic power plant.ppt
Hydrolic power plant.pptMd. Sumon Ahmed
 
Run of River and Pumped Storage Plants
Run of River and Pumped Storage PlantsRun of River and Pumped Storage Plants
Run of River and Pumped Storage PlantsSatish Taji
 
To study working of each component of hydro power plant?
To study working of each component of hydro power plant?To study working of each component of hydro power plant?
To study working of each component of hydro power plant?Salman Jailani
 
Hydraulic Turbines
Hydraulic TurbinesHydraulic Turbines
Hydraulic TurbinesYimam Alemu
 
Design and Construction of a Hydraulic Ram Pump; by Shuaibu Ndache MOHAMMED
Design and Construction of a Hydraulic Ram Pump; by Shuaibu Ndache MOHAMMEDDesign and Construction of a Hydraulic Ram Pump; by Shuaibu Ndache MOHAMMED
Design and Construction of a Hydraulic Ram Pump; by Shuaibu Ndache MOHAMMEDFatin62c
 

What's hot (20)

Basics of Hydro power plant
Basics of  Hydro power plant Basics of  Hydro power plant
Basics of Hydro power plant
 
Baglihar hydro electric power plant
Baglihar hydro electric power plantBaglihar hydro electric power plant
Baglihar hydro electric power plant
 
Presentation of hydro power plant
Presentation of hydro power plantPresentation of hydro power plant
Presentation of hydro power plant
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
Pre-Feasibility Study of a 1000 MW Pumped Storage Plant in Saudi Arabia
Pre-Feasibility Study of a 1000 MW Pumped Storage Plant in Saudi ArabiaPre-Feasibility Study of a 1000 MW Pumped Storage Plant in Saudi Arabia
Pre-Feasibility Study of a 1000 MW Pumped Storage Plant in Saudi Arabia
 
200118 chapter 8 hydromechanical
200118 chapter 8 hydromechanical200118 chapter 8 hydromechanical
200118 chapter 8 hydromechanical
 
Water distribution system
Water distribution systemWater distribution system
Water distribution system
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
 
Hydroelectricpowerplant 290916
Hydroelectricpowerplant 290916Hydroelectricpowerplant 290916
Hydroelectricpowerplant 290916
 
PRINCIPLES OF HYDROPOWER ENGINEERING
PRINCIPLES OF HYDROPOWERENGINEERINGPRINCIPLES OF HYDROPOWERENGINEERING
PRINCIPLES OF HYDROPOWER ENGINEERING
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
Hydrolic power plant.ppt
Hydrolic power plant.pptHydrolic power plant.ppt
Hydrolic power plant.ppt
 
Water hammer in hydropower plant
Water hammer in hydropower plantWater hammer in hydropower plant
Water hammer in hydropower plant
 
Hydroelectric power
Hydroelectric power Hydroelectric power
Hydroelectric power
 
Run of River and Pumped Storage Plants
Run of River and Pumped Storage PlantsRun of River and Pumped Storage Plants
Run of River and Pumped Storage Plants
 
To study working of each component of hydro power plant?
To study working of each component of hydro power plant?To study working of each component of hydro power plant?
To study working of each component of hydro power plant?
 
904787
904787904787
904787
 
HYDRO POWER PLANT
HYDRO POWER PLANT HYDRO POWER PLANT
HYDRO POWER PLANT
 
Hydraulic Turbines
Hydraulic TurbinesHydraulic Turbines
Hydraulic Turbines
 
Design and Construction of a Hydraulic Ram Pump; by Shuaibu Ndache MOHAMMED
Design and Construction of a Hydraulic Ram Pump; by Shuaibu Ndache MOHAMMEDDesign and Construction of a Hydraulic Ram Pump; by Shuaibu Ndache MOHAMMED
Design and Construction of a Hydraulic Ram Pump; by Shuaibu Ndache MOHAMMED
 

Similar to Planning and Development process

DSD-INT 2022 Modelling the impact of dam operation on flood management using ...
DSD-INT 2022 Modelling the impact of dam operation on flood management using ...DSD-INT 2022 Modelling the impact of dam operation on flood management using ...
DSD-INT 2022 Modelling the impact of dam operation on flood management using ...Deltares
 
Lecture 3-Water Resources Monitoring.ppt
Lecture 3-Water Resources Monitoring.pptLecture 3-Water Resources Monitoring.ppt
Lecture 3-Water Resources Monitoring.pptLawrence Omai
 
Selection of drains coverings type in eastern of egypt
Selection of drains coverings type in eastern of egyptSelection of drains coverings type in eastern of egypt
Selection of drains coverings type in eastern of egypteSAT Publishing House
 
IRJET- Irrigation in Hilly Areas by Capillary Lift
IRJET- Irrigation in Hilly Areas by Capillary LiftIRJET- Irrigation in Hilly Areas by Capillary Lift
IRJET- Irrigation in Hilly Areas by Capillary LiftIRJET Journal
 
SIBE2013-Paper-A 3-Dimensional Numerical Study Of Flow Patterns Around Three ...
SIBE2013-Paper-A 3-Dimensional Numerical Study Of Flow Patterns Around Three ...SIBE2013-Paper-A 3-Dimensional Numerical Study Of Flow Patterns Around Three ...
SIBE2013-Paper-A 3-Dimensional Numerical Study Of Flow Patterns Around Three ...Fitra Adinata
 
Chimoio_Water_Supply_Project_FinalDesign(1).pdf
Chimoio_Water_Supply_Project_FinalDesign(1).pdfChimoio_Water_Supply_Project_FinalDesign(1).pdf
Chimoio_Water_Supply_Project_FinalDesign(1).pdfAmmar475682
 
Reconnaissance for Hydrographic Survey Project
Reconnaissance for Hydrographic  Survey ProjectReconnaissance for Hydrographic  Survey Project
Reconnaissance for Hydrographic Survey ProjectNzar Braim
 
SWMM Presentation.pptx of NIT srinager kashmir
SWMM Presentation.pptx of NIT srinager kashmirSWMM Presentation.pptx of NIT srinager kashmir
SWMM Presentation.pptx of NIT srinager kashmirmujtabamalik84
 
Download-manuals-surface water-software-processingofstreamflowdata
 Download-manuals-surface water-software-processingofstreamflowdata Download-manuals-surface water-software-processingofstreamflowdata
Download-manuals-surface water-software-processingofstreamflowdatahydrologyproject0
 
Download-manuals-surface water-software-processingofstreamflowdata
 Download-manuals-surface water-software-processingofstreamflowdata Download-manuals-surface water-software-processingofstreamflowdata
Download-manuals-surface water-software-processingofstreamflowdatahydrologyproject0
 
Lecture 2 hydrological and demand survey
Lecture 2 hydrological and demand survey Lecture 2 hydrological and demand survey
Lecture 2 hydrological and demand survey shahabuddin khan
 
Hydro_scout_guide_ET_may10.pdf
Hydro_scout_guide_ET_may10.pdfHydro_scout_guide_ET_may10.pdf
Hydro_scout_guide_ET_may10.pdfttaulo
 
New design approach for drains coverings
New design approach for drains coveringsNew design approach for drains coverings
New design approach for drains coveringseSAT Journals
 
New design approach for drains coverings
New design approach for drains coveringsNew design approach for drains coverings
New design approach for drains coveringseSAT Publishing House
 
manual-road-drainage-chapter-5 (1).pdf
manual-road-drainage-chapter-5 (1).pdfmanual-road-drainage-chapter-5 (1).pdf
manual-road-drainage-chapter-5 (1).pdfRastaXaimaca
 
H Fuyana_Research Presantation 2015
H Fuyana_Research Presantation 2015H Fuyana_Research Presantation 2015
H Fuyana_Research Presantation 2015Hlosokuhle Fuyana
 

Similar to Planning and Development process (20)

DSD-INT 2022 Modelling the impact of dam operation on flood management using ...
DSD-INT 2022 Modelling the impact of dam operation on flood management using ...DSD-INT 2022 Modelling the impact of dam operation on flood management using ...
DSD-INT 2022 Modelling the impact of dam operation on flood management using ...
 
Lecture 3-Water Resources Monitoring.ppt
Lecture 3-Water Resources Monitoring.pptLecture 3-Water Resources Monitoring.ppt
Lecture 3-Water Resources Monitoring.ppt
 
Selection of drains coverings type in eastern of egypt
Selection of drains coverings type in eastern of egyptSelection of drains coverings type in eastern of egypt
Selection of drains coverings type in eastern of egypt
 
IRJET- Irrigation in Hilly Areas by Capillary Lift
IRJET- Irrigation in Hilly Areas by Capillary LiftIRJET- Irrigation in Hilly Areas by Capillary Lift
IRJET- Irrigation in Hilly Areas by Capillary Lift
 
SIBE2013-Paper-A 3-Dimensional Numerical Study Of Flow Patterns Around Three ...
SIBE2013-Paper-A 3-Dimensional Numerical Study Of Flow Patterns Around Three ...SIBE2013-Paper-A 3-Dimensional Numerical Study Of Flow Patterns Around Three ...
SIBE2013-Paper-A 3-Dimensional Numerical Study Of Flow Patterns Around Three ...
 
Chimoio_Water_Supply_Project_FinalDesign(1).pdf
Chimoio_Water_Supply_Project_FinalDesign(1).pdfChimoio_Water_Supply_Project_FinalDesign(1).pdf
Chimoio_Water_Supply_Project_FinalDesign(1).pdf
 
Reconnaissance for Hydrographic Survey Project
Reconnaissance for Hydrographic  Survey ProjectReconnaissance for Hydrographic  Survey Project
Reconnaissance for Hydrographic Survey Project
 
SWMM Presentation.pptx of NIT srinager kashmir
SWMM Presentation.pptx of NIT srinager kashmirSWMM Presentation.pptx of NIT srinager kashmir
SWMM Presentation.pptx of NIT srinager kashmir
 
Download-manuals-surface water-software-processingofstreamflowdata
 Download-manuals-surface water-software-processingofstreamflowdata Download-manuals-surface water-software-processingofstreamflowdata
Download-manuals-surface water-software-processingofstreamflowdata
 
Download-manuals-surface water-software-processingofstreamflowdata
 Download-manuals-surface water-software-processingofstreamflowdata Download-manuals-surface water-software-processingofstreamflowdata
Download-manuals-surface water-software-processingofstreamflowdata
 
Lecture 2 hydrological and demand survey
Lecture 2 hydrological and demand survey Lecture 2 hydrological and demand survey
Lecture 2 hydrological and demand survey
 
Hydro_scout_guide_ET_may10.pdf
Hydro_scout_guide_ET_may10.pdfHydro_scout_guide_ET_may10.pdf
Hydro_scout_guide_ET_may10.pdf
 
New design approach for drains coverings
New design approach for drains coveringsNew design approach for drains coverings
New design approach for drains coverings
 
New design approach for drains coverings
New design approach for drains coveringsNew design approach for drains coverings
New design approach for drains coverings
 
Stream flow
Stream flow Stream flow
Stream flow
 
Chapter 2.pdf
Chapter 2.pdfChapter 2.pdf
Chapter 2.pdf
 
K1303077376
K1303077376K1303077376
K1303077376
 
Introduction to Engineering Hydrology
Introduction to Engineering HydrologyIntroduction to Engineering Hydrology
Introduction to Engineering Hydrology
 
manual-road-drainage-chapter-5 (1).pdf
manual-road-drainage-chapter-5 (1).pdfmanual-road-drainage-chapter-5 (1).pdf
manual-road-drainage-chapter-5 (1).pdf
 
H Fuyana_Research Presantation 2015
H Fuyana_Research Presantation 2015H Fuyana_Research Presantation 2015
H Fuyana_Research Presantation 2015
 

More from Yimam Alemu

Three phase induction motors
 Three phase induction motors Three phase induction motors
Three phase induction motorsYimam Alemu
 
Synchronous Generators
Synchronous GeneratorsSynchronous Generators
Synchronous GeneratorsYimam Alemu
 
Principles of Electromechanical Energy Conversion
Principles of Electromechanical Energy ConversionPrinciples of Electromechanical Energy Conversion
Principles of Electromechanical Energy ConversionYimam Alemu
 
Chapter two-Classification of Hydroelectric Power Plants
Chapter two-Classification of Hydroelectric Power PlantsChapter two-Classification of Hydroelectric Power Plants
Chapter two-Classification of Hydroelectric Power PlantsYimam Alemu
 

More from Yimam Alemu (11)

Three phase induction motors
 Three phase induction motors Three phase induction motors
Three phase induction motors
 
DC Motors
DC MotorsDC Motors
DC Motors
 
Transformers
TransformersTransformers
Transformers
 
Synchronous Generators
Synchronous GeneratorsSynchronous Generators
Synchronous Generators
 
Principles of Electromechanical Energy Conversion
Principles of Electromechanical Energy ConversionPrinciples of Electromechanical Energy Conversion
Principles of Electromechanical Energy Conversion
 
Chapter 5
Chapter 5Chapter 5
Chapter 5
 
Chapter 4
Chapter 4Chapter 4
Chapter 4
 
Chapter 2
Chapter 2Chapter 2
Chapter 2
 
Chapter 3
Chapter 3Chapter 3
Chapter 3
 
Chapter 1
Chapter 1Chapter 1
Chapter 1
 
Chapter two-Classification of Hydroelectric Power Plants
Chapter two-Classification of Hydroelectric Power PlantsChapter two-Classification of Hydroelectric Power Plants
Chapter two-Classification of Hydroelectric Power Plants
 

Recently uploaded

2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edgePaco Orozco
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdfKamal Acharya
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industriesMuhammadTufail242431
 
Danfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdfDanfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdfNurvisNavarroSanchez
 
fundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projectionfundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projectionjeevanprasad8
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxViniHema
 
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical SolutionsRS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical SolutionsAtif Razi
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Aryaabh.arya
 
Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfAbrahamGadissa
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdfKamal Acharya
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdfKamal Acharya
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfPipe Restoration Solutions
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Electivekarthi keyan
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234AafreenAbuthahir2
 
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringC Sai Kiran
 
fluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answerfluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answerapareshmondalnita
 
Introduction to Casting Processes in Manufacturing
Introduction to Casting Processes in ManufacturingIntroduction to Casting Processes in Manufacturing
Introduction to Casting Processes in Manufacturingssuser0811ec
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdfKamal Acharya
 
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docxThe Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docxCenterEnamel
 

Recently uploaded (20)

2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdf
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
Danfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdfDanfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdf
 
fundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projectionfundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projection
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical SolutionsRS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdf
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
fluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answerfluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answer
 
Introduction to Casting Processes in Manufacturing
Introduction to Casting Processes in ManufacturingIntroduction to Casting Processes in Manufacturing
Introduction to Casting Processes in Manufacturing
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docxThe Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
 

Planning and Development process

  • 1. Chapter 3 Chapter Three Planning and Development Process By Yimam Alemu December 16, 2020 By Yimam Alemu Chapter 3 December 16, 2020 1 / 55
  • 2. Chapter 3 Outline 1 Methodology of HEPP Development 2 Surveys needed for hydro power plants 3 Selection of Site for a Hydroelectric Power Plant 4 Types of Development 5 Efficiency of hydropower By Yimam Alemu Chapter 3 December 16, 2020 2 / 55
  • 3. Chapter 3 Learning Objectives At the end of this chapter the students should be able to: Understand the methodology of HEPP development Understand elements and equip- ment’s needed to be taken into consideration while designing a hydroelectric power plant. Understand factors should be considered while selecting the site for a hydroelectric power plant. Understand the different types of developments of hydroelectric power plant. Understand the environmental, social and economic analysis of HEPP. By Yimam Alemu Chapter 3 December 16, 2020 3 / 55
  • 4. Chapter 3 Methodology of HEPP Development Methodology of HEPP Development Site Survey: Hydrological and geological Survey. Regulations and Environmental Concerns Feasible Supply(feasibility study) Estimation of Potential Turbine Selection Costing and Payback By Yimam Alemu Chapter 3 December 16, 2020 4 / 55
  • 5. Chapter 3 Methodology of HEPP Development Measuring parameters Measurement of river(water body flow data.) Measurement of head ( Power and available head ) Topographical and geological condition of site Site accessibility – need to be address during planning stage Power transmission point distance – determine power loss Power demand assessment By Yimam Alemu Chapter 3 December 16, 2020 5 / 55
  • 6. Chapter 3 Methodology of HEPP Development Hydrological Survey Power demand assessment To measure the flow-rate vs time at a given site The more robust option is to find out the flowrate by working out the volume of water that was entering the river. This uses the rainfall data from metrology office for two lean seasons. By Yimam Alemu Chapter 3 December 16, 2020 6 / 55
  • 7. Chapter 3 Methodology of HEPP Development Flow Rate Measurement There are numerous ways to measure flow rate, such as: Bucket Method Float Method Weirs Meters By Yimam Alemu Chapter 3 December 16, 2020 7 / 55
  • 8. Chapter 3 Methodology of HEPP Development 1.Bucket method The Bucket method is a simple way to measure the flow rate using household items. It requires a stopwatch, a large bucket, and preferably two to three people to measure the flow rate using the bucket method: Direct measurement with a bucket Good for small flow in conduit. By Yimam Alemu Chapter 3 December 16, 2020 8 / 55
  • 9. Chapter 3 Methodology of HEPP Development Cont.... Measure the volume of the bucket or container Find a location along the stream that has a waterfall With a stopwatch, time how long it takes the waterfall to fill the bucket with water Record the time it takes to fill the bucket. Figure: Bucket measuring method By Yimam Alemu Chapter 3 December 16, 2020 9 / 55
  • 10. Chapter 3 Methodology of HEPP Development 2. Float Measuring Method Figure: Float measuring method By Yimam Alemu Chapter 3 December 16, 2020 10 / 55
  • 11. Chapter 3 Methodology of HEPP Development Cont.... The float method (also known as the cross-sectional method) is used to measure the flow rate for larger streams and rivers. Locate a spot in the stream that will act as the cross section of the stream. Using a meter stick, or some other means of measurement, measure the depth of the stream at equal intervals along the width of the stream. Decide on a length of the stream, typically longer than the width of the river, to send a floating object down. Using a stopwatch, measure the time it takes the float to travel down the length of stream. By Yimam Alemu Chapter 3 December 16, 2020 11 / 55
  • 12. Chapter 3 Methodology of HEPP Development 3. Weir Measuring Method Weirs are small dams that can be used in measuring flow rate for small to medium sized streams (a few meters or wider). They allow overflow of the stream to pour over the top of the weir, creating a waterfall. Weirs increase the change in elevation making the streamflow more consistent which makes flow rate measurements more precise. By Yimam Alemu Chapter 3 December 16, 2020 12 / 55
  • 13. Chapter 3 Methodology of HEPP Development Figure: Weir measuring method By Yimam Alemu Chapter 3 December 16, 2020 13 / 55
  • 14. Chapter 3 Methodology of HEPP Development Figure: Weir measuring method By Yimam Alemu Chapter 3 December 16, 2020 14 / 55
  • 15. Chapter 3 Methodology of HEPP Development 4.Meters Meters are devices that measure the stream flow by directly measuring the current. There are many different types of meters, the most common is the Pygmy meter, the vortex meter, the flow probe, and the current meter: Measured by Electromagnetic current or propeller type current meter. By Yimam Alemu Chapter 3 December 16, 2020 15 / 55
  • 16. Chapter 3 Methodology of HEPP Development Measuring Instruments Altimeter: – for altitude measurement GPS: for location coordinate Camera: for capturing the location image Current meter: measuring the flow of water Distance meter Depth meter: depth of the water body Clinometer measures vertical slope, usually the angle between the ground or the observer and a tall object Compass Hand level By Yimam Alemu Chapter 3 December 16, 2020 16 / 55
  • 17. Chapter 3 Methodology of HEPP Development Various studies during the preliminary site survey Hydrological studies : Overall rain fall ,run off data ,principal river flow data , flood characteristics, from record of gov’t. department . Min ,avg and flood details. Topological studies : Tachometric survey and survey required depending upon the existing info and maps. Geological studies : Overall geological characteristics and local features for trans- portation of material. Power demand assessment : Overall power demand scenario in the project near by area and existing infrastructure for power evacuation. By Yimam Alemu Chapter 3 December 16, 2020 17 / 55
  • 18. Chapter 3 Methodology of HEPP Development Site Survey Pre Feasibility Report Basic Design Various Graphs and Pictures By Yimam Alemu Chapter 3 December 16, 2020 18 / 55
  • 19. Chapter 3 Surveys needed for hydro power plants Surveys needed for hydro power plants The following surveys are carried out for a hydro plant installation. General surveys Special surveys By Yimam Alemu Chapter 3 December 16, 2020 19 / 55
  • 20. Chapter 3 Surveys needed for hydro power plants A) General surveys They constitute the following: 1. Topographical surveys such as i) The dam site topographical survey plans including the area of accommodate dam, spillway, outlet works, diversion works etc. ii) The reservoir submergence plans Contour plan of a) Surge tanks b) Tunnels c) Penstock d) Tail race channels. iii) River surveys iv) For a barrage structure detailed survey maps to cover the area under the barrage. By Yimam Alemu Chapter 3 December 16, 2020 20 / 55
  • 21. Chapter 3 Surveys needed for hydro power plants Cont.... 2. Geological and foundation investigations. A study should be carried out for the following: i) Seismic condition of the region ii) Water flow in reservoir iii) Sub-surface conditions iv) Foundation investigations for dams. By Yimam Alemu Chapter 3 December 16, 2020 21 / 55
  • 22. Chapter 3 Surveys needed for hydro power plants Cont.... 3. Metrological and hydrological studies: The following data should be collected i Precipitation, evaporation. ii Water flows such as maximum and minimum water flows. iii Rainfall-run off relation data. iv Mean latitude, and longitude, mean elevation, mean monthly temperature. v Location of raingauge station near power plant site. By Yimam Alemu Chapter 3 December 16, 2020 22 / 55
  • 23. Chapter 3 Surveys needed for hydro power plants Cont.... 4. Construction material investigations: Data should be collected for the following: i Materials to be used for a) Concrete and masonry dams b) Earth and rock fill dams. ii Tests to be carried out for materials. By Yimam Alemu Chapter 3 December 16, 2020 23 / 55
  • 24. Chapter 3 Surveys needed for hydro power plants Cont.... 5. Transportation and communication: Data should be collected for the following: Road, water and rail routes Telephone and telegraph lines. 6. Environmental considerations Navigation Fish culture. By Yimam Alemu Chapter 3 December 16, 2020 24 / 55
  • 25. Chapter 3 Surveys needed for hydro power plants B) Special surveys Special surveys include the following: 1. Load surveys: They are made of i Power-station capacity ii Power to be generated iii Details for major loads to be served iv Peak load v Load factor vi Future energy demand vii Inter connection with other power systems By Yimam Alemu Chapter 3 December 16, 2020 25 / 55
  • 26. Chapter 3 Surveys needed for hydro power plants Cont.... 2. Lay-out studies: This includes the following i Type of power plant such as storage type, run of river plant,pumped storage type etc. ii Structural components like a) Dams b) Canals c) Tunnels d) Penstock e) Draft tube f) Surge tanks g) Power house h) Switch yard By Yimam Alemu Chapter 3 December 16, 2020 26 / 55
  • 27. Chapter 3 Surveys needed for hydro power plants Pre feasibility report Pre feasibility report is required to investigate weather project is technically or finan- cially feasible or not. Aim of PFR is to examine next step to project formulation Preparation of PFRs involves Conceptual planning, Preparation of project and equipment layouts, Infrastructure requirement, Environmental and geological studies, Power evacuation arrangement, cost estimates and economic evaluation. By Yimam Alemu Chapter 3 December 16, 2020 27 / 55
  • 28. Chapter 3 Surveys needed for hydro power plants Cont.... Executive summary Introduction Project location Map Project description Salient feature Hydrology Climate Catchment area Rainfall By Yimam Alemu Chapter 3 December 16, 2020 28 / 55
  • 29. Chapter 3 Surveys needed for hydro power plants Cont.... When designing a hydroelectric power plant a number of elements and equipment’s need to be taken into consideration. Site selection Technical data Intake position Penstock length and diameter Turbine and generator systems Electrical and control equipment The Power House Distribution system By Yimam Alemu Chapter 3 December 16, 2020 29 / 55
  • 30. Chapter 3 Surveys needed for hydro power plants Cont.... Based on the firm power: Dams, canals, intakes, penstocks, tailraces and power houses are designed by civil engineers. Mechanical Engineers design the hydraulic turbines. Electrical Engineers design the generators, transformers, the switch yards and the protection system. ♣ Firm power is also one of the main factors that decides the feasibility of HPP. By Yimam Alemu Chapter 3 December 16, 2020 30 / 55
  • 31. Chapter 3 Surveys needed for hydro power plants Cont.... Civil Engineers, Mechanical Engineers, Electrical Engineers, Geologists, Economists, Ecologists, Sociologists and many other experts combine their skills in order to develop an optimum design considering technical, financial, environmental and social aspects of hydropower development. Feasibility study contains: Site visit and selection Capacity analysis Economic analysis Environmental impact analysis ♣ Feasibility study is the first step in HPP construction. By Yimam Alemu Chapter 3 December 16, 2020 31 / 55
  • 32. Chapter 3 Selection of Site for a Hydroelectric Power Plant Selection of Site for a Hydroelectric Power Plant The following factors should be considered while selecting the site for a hydroelectric plant. 1 Availability of water 2 Water storage capacity 3 Available water head 4 Accessibility of the site 5 Distance from the load Centre 6 Water pollution 7 Sedimentation 8 Large catchment area 9 Availability of Land By Yimam Alemu Chapter 3 December 16, 2020 32 / 55
  • 33. Chapter 3 Selection of Site for a Hydroelectric Power Plant 1.Availability of water The recorded observation should be taken over a number of years to know within reasonable limits the maximum and minimum variations from the average discharge. The river flow data should be based on daily, weekly, monthly and yearly flow over a number of years. Then the curves or graphs can be plotted between river flow and time. These are known as hygrographs and flow duration curves. By Yimam Alemu Chapter 3 December 16, 2020 33 / 55
  • 34. Chapter 3 Selection of Site for a Hydroelectric Power Plant 2. Water Storage capacity: The output of a hydropower plant is not uniform due to wide variations of rain fall. To have a uniform power output, a water storage is needed so that excess flow at certain times may be stored to make it available at the times of low flow. Since storage of water in a reservoir at a height or building of dam across the river is essential in order to have continuous supply during the dry season. The storage capacity can be determined from the Hydrograph, Mass Curve or by using analytical methods. By Yimam Alemu Chapter 3 December 16, 2020 34 / 55
  • 35. Chapter 3 Selection of Site for a Hydroelectric Power Plant 3. Available water head Available water head depends upon the topography of the area. The level of water in the reservoir for a proposed plant should always be within limits throughout the year. Availability of head of water has considerable effect on the cost and economy of power generation. An increase in effective head reduces the quantity of water to be stored and handled by penstocks, screens and turbines and therefore capital cost of the plant is reduced. By Yimam Alemu Chapter 3 December 16, 2020 35 / 55
  • 36. Chapter 3 Selection of Site for a Hydroelectric Power Plant 4. Distance from Load Center Most of the time the electric power generated in a hydro-electric power plant has to be used some considerable distance from the site of plant. For this reason, to be economical on transmission of electric power, the routes and the distances should be carefully considered since the cost of erection of transmission lines and their maintenance will depend upon the route selected. Power plant should be set up near the load center, this will reduce the cost of mainte- nance of transmission line By Yimam Alemu Chapter 3 December 16, 2020 36 / 55
  • 37. Chapter 3 Selection of Site for a Hydroelectric Power Plant 5. Accessibility of the Site The site where hydroelectric plant is to be constructed should be easily accessible. This is important if the electric power generated is to be utilized at or near the plant site. The site selected should have transportation facilities of rail and road. By Yimam Alemu Chapter 3 December 16, 2020 37 / 55
  • 38. Chapter 3 Selection of Site for a Hydroelectric Power Plant 6. Water Pollution Polluted water may cause excessive corrosion and damage to the metallic structures. This may render the operation of the plant unreliable and uneconomic It is necessary to see that the water is of good quality and will not cause such troubles. By Yimam Alemu Chapter 3 December 16, 2020 38 / 55
  • 39. Chapter 3 Selection of Site for a Hydroelectric Power Plant 7. Sedimentation Gradual deposition of silt may reduce the capacity of the storage reservoir and may also cause damage to the turbine blades. Silting from forest covered areas is negligible. On the other hand the regions subject to violent storms and not protected by vegetation contribute lot of silt to the run off By Yimam Alemu Chapter 3 December 16, 2020 39 / 55
  • 40. Chapter 3 Selection of Site for a Hydroelectric Power Plant 8. Large Catchment Area The reservoir must have a large catchment area so that level of water in the reservoir may not fall below the minimum required in dry season. By Yimam Alemu Chapter 3 December 16, 2020 40 / 55
  • 41. Chapter 3 Selection of Site for a Hydroelectric Power Plant 9. Type of the land of the site The land to be selected for the site should be cheap in cost and rocky in order to withstand the weight of the large building and heavy machinery. There should be a stream diversion during period of construction. The necessary requirements of the foundation rocks for a masonry dam are as follows: The rock should be strong enough to withstand the stresses transmitted from the dam structure as well as the thrust of the water when the reservoir is full. The rock in the foundation of the dam should be reasonably impervious The rock should remain stable under all conditions. By Yimam Alemu Chapter 3 December 16, 2020 41 / 55
  • 42. Chapter 3 Selection of Site for a Hydroelectric Power Plant Main design parameters The power capacity of a hydropower plant is primarily a function of two main variables of the water Water flow Hydraulic head Design flow is the maximum flow for which your hydro system is designed. It will likely be less than the maximum flow of the stream (especially during the rainy season) or more than the minimum flow during dry season. If a system is to be independent of any other energy or utility backup, the design flow should be the flow that is available 95 percent of the time or more. By Yimam Alemu Chapter 3 December 16, 2020 42 / 55
  • 43. Chapter 3 Selection of Site for a Hydroelectric Power Plant Cont.... Therefore, a stand-alone system such as a micro hydropower system should be designed according to the flow that is available year-round; this is usually the flow during the dry season. Reserved flow: it is the minimum flow required to avoid aquatic life damage in the water stream. Firm flow: The firm flow is defined as the flow being available X% of the time, where X is a percentage specified by the user and usually equal to 95%. By Yimam Alemu Chapter 3 December 16, 2020 43 / 55
  • 44. Chapter 3 Types of Development Types of Development In studying the subject hydropower engineering it is important to understand the different types of development. Run-off river development Diversion and canal development Storage regulation development Pumped storage development Single purpose development Multi purpose development Cascaded development By Yimam Alemu Chapter 3 December 16, 2020 44 / 55
  • 45. Chapter 3 Types of Development 1. Run-off river development A dam with short penstock (supply pipe) directs the water to the turbine using the natural flow of the river. By Yimam Alemu Chapter 3 December 16, 2020 45 / 55
  • 46. Chapter 3 Types of Development 2. Diversion and canal development The water is diverted from the natural channel into canal, thus changing the natural flow of the water in the stream for a considerable distance. By Yimam Alemu Chapter 3 December 16, 2020 46 / 55
  • 47. Chapter 3 Types of Development 3. Storage regulation development An extensive impoundment at the power plant or at the reservoir up stream of the power plant permits changing the flow of the river by storing the water during high flow periods to enlarge the water available during the low flow periods, thus supplying the demand for energy in a more efficient manner. Storage refers to long time impounding of water to meet the seasonal fluctuation in water availability and the fluctuations in energy demand. Pondage refers to short-time impounding of water to meet short-time changes of de- mand. By Yimam Alemu Chapter 3 December 16, 2020 47 / 55
  • 48. Chapter 3 Types of Development 4. Pumped storage development Water is pumped from lower reservoir to a higher reservoir during period of low energy demand. The water then run down through turbine to produce power to meet peak demand. By Yimam Alemu Chapter 3 December 16, 2020 48 / 55
  • 49. Chapter 3 Types of Development 5. Single and multi purpose development In single-purpose development the water is used only for the purpose of producing electricity. In multi-purpose development hydropower production is just one of many purposes for which the water resource is used. e.g. irrigation, flood control, navigation, industrial water supply, etc By Yimam Alemu Chapter 3 December 16, 2020 49 / 55
  • 50. Chapter 3 Types of Development 6. Cascaded development By Yimam Alemu Chapter 3 December 16, 2020 50 / 55
  • 51. Chapter 3 Types of Development Cont.... Example: Gibe III 1870 MW The Gibe III dam is part of the Gibe cascade, a series of dams including the existing Gibe I dam (184 MW) and Gibe II power station (420 MW) as well as the planned Gibe IV (1472 MW) and Gibe V (560 MW) dams. By Yimam Alemu Chapter 3 December 16, 2020 51 / 55
  • 52. Chapter 3 Efficiency of hydropower Efficiency of hydropower The potential for energy production in a hydropower plant is determined by the fol- lowing parameters:- The amount of water available Water loss due to flood spill, bypass requirements or leakage Head Hydraulic losses in water transport due to friction and water velocity change. The efficiency in energy conversion of electro mechanical equipments. By Yimam Alemu Chapter 3 December 16, 2020 52 / 55
  • 53. Chapter 3 Efficiency of hydropower Cont.... In hydropower plant the energy transformation Potential energy(stored water in dam) Kinetic energy(water falling from height) Mechanical energy(Turbines) Electrical energy(Generator) The energy transformation in modern hydropower plants is highly efficient usually well over 90%. By Yimam Alemu Chapter 3 December 16, 2020 53 / 55
  • 54. Chapter 3 Efficiency of hydropower Cont.... Efficiency of hydropower plant is dependent on Hydraulic loss (intake, turbine, tailrace) Mechanical and electrical loss (turbines and generators) Absorption of sediments Due to heat in the water and generator The total efficiency of a hydropower plant is determined by the sum of these three loss components. Hydraulic losses, it can be reduced by increasing turbine capacity or reservoir capacity for better regulation of flow. Head loss, it can be reduced by increasing the area of headrace and tailrace, by de- creasing roughness in the pipes. By avoiding too many changes in flow velocity and direction. By Yimam Alemu Chapter 3 December 16, 2020 54 / 55
  • 55. Chapter 3 Questions Thank You! By Yimam Alemu Chapter 3 December 16, 2020 55 / 55