4M CHANGE
Presented By : Hardil Shah
What is 4M change?
1. MAN
2. MACHINE
3. MATERIAL
4. METHOD
Purpose of 4M Change
• To closely monitor process and effect of
change on product.
Man
• If new Person join.
• Person is on leave for more than 1 month.
• Shift time extended
• If person is sick.
Machine
• Machine Change.
• Engineering change in Machine.
• Preventive Maintenance planned.
• Break down maintenance done on machine.
• Fixture change in machine.
• Removing or adding external process on machine
Material
• New Supplier or change current supplier
• New Material for approval source of trial.
• Same Supplier but mixing combination change.
Method
• Any Deviation form Process control (Process Parameter Change)
• Process Sequence Change.
• Additional process implemented.
• New technology implemented
Type of 4M change
1. Planned (Permanent)
2. Un Planned (Temporary)
Planned (Permanent) Type Change
• The Change that is done due to some
unavoidable reason.
Unplanned (Temporary) Type Change
• The change that discussed before change and
pre planned.
Criteria of 4M change
• Set up
• Containment
• Retro active
Setup
• First Part Approval report
Containment
• To Closely monitor running production
Retroactive
• To trace back from where problem arise in
production.
Criteria : 4 M Change
MAN MATERIAL METHOD MACHINE
Extended shift working (
over 2 shifts ) -
unplanned
Source of supply
change for controlled
item- planned
Any deviation from Process control
standard - planned
Machine Change - planned
Manpower change
( regular)
Different spec /
Grade of incoming
controlled material
from approved
source for trials -
planned
Process sequence change -Unplanned Breakdown Maint. Which
affects process / quality of
product - unplanned
Person left shift job due
to sickness
Material
Composition change-
Planned
New technology introduction - planned Fixture change - such as enamel
applicator - planned
New joinee - planned Material
Combination Change-
Planned
Additional process adopted - planned Preventive maintanence. -
planned
On Leave For More than
one Month
Inspection equipment change - planned
Traceability
• Traceability or unique Identification is very
important for further assessment of product.
• To check product deforms after time interval.

Change Management - 4 m change

  • 1.
  • 2.
    What is 4Mchange? 1. MAN 2. MACHINE 3. MATERIAL 4. METHOD
  • 3.
    Purpose of 4MChange • To closely monitor process and effect of change on product.
  • 4.
    Man • If newPerson join. • Person is on leave for more than 1 month. • Shift time extended • If person is sick. Machine • Machine Change. • Engineering change in Machine. • Preventive Maintenance planned. • Break down maintenance done on machine. • Fixture change in machine. • Removing or adding external process on machine
  • 5.
    Material • New Supplieror change current supplier • New Material for approval source of trial. • Same Supplier but mixing combination change. Method • Any Deviation form Process control (Process Parameter Change) • Process Sequence Change. • Additional process implemented. • New technology implemented
  • 6.
    Type of 4Mchange 1. Planned (Permanent) 2. Un Planned (Temporary)
  • 7.
    Planned (Permanent) TypeChange • The Change that is done due to some unavoidable reason. Unplanned (Temporary) Type Change • The change that discussed before change and pre planned.
  • 8.
    Criteria of 4Mchange • Set up • Containment • Retro active
  • 9.
    Setup • First PartApproval report Containment • To Closely monitor running production Retroactive • To trace back from where problem arise in production.
  • 10.
    Criteria : 4M Change MAN MATERIAL METHOD MACHINE Extended shift working ( over 2 shifts ) - unplanned Source of supply change for controlled item- planned Any deviation from Process control standard - planned Machine Change - planned Manpower change ( regular) Different spec / Grade of incoming controlled material from approved source for trials - planned Process sequence change -Unplanned Breakdown Maint. Which affects process / quality of product - unplanned Person left shift job due to sickness Material Composition change- Planned New technology introduction - planned Fixture change - such as enamel applicator - planned New joinee - planned Material Combination Change- Planned Additional process adopted - planned Preventive maintanence. - planned On Leave For More than one Month Inspection equipment change - planned
  • 11.
    Traceability • Traceability orunique Identification is very important for further assessment of product. • To check product deforms after time interval.