SlideShare a Scribd company logo
4M CHANGE
Presented By : Hardil Shah
What is 4M change?
1. MAN
2. MACHINE
3. MATERIAL
4. METHOD
Purpose of 4M Change
• To closely monitor process and effect of
change on product.
Man
• If new Person join.
• Person is on leave for more than 1 month.
• Shift time extended
• If person is sick.
Machine
• Machine Change.
• Engineering change in Machine.
• Preventive Maintenance planned.
• Break down maintenance done on machine.
• Fixture change in machine.
• Removing or adding external process on machine
Material
• New Supplier or change current supplier
• New Material for approval source of trial.
• Same Supplier but mixing combination change.
Method
• Any Deviation form Process control (Process Parameter Change)
• Process Sequence Change.
• Additional process implemented.
• New technology implemented
Type of 4M change
1. Planned (Permanent)
2. Un Planned (Temporary)
Planned (Permanent) Type Change
• The Change that is done due to some
unavoidable reason.
Unplanned (Temporary) Type Change
• The change that discussed before change and
pre planned.
Criteria of 4M change
• Set up
• Containment
• Retro active
Setup
• First Part Approval report
Containment
• To Closely monitor running production
Retroactive
• To trace back from where problem arise in
production.
Criteria : 4 M Change
MAN MATERIAL METHOD MACHINE
Extended shift working (
over 2 shifts ) -
unplanned
Source of supply
change for controlled
item- planned
Any deviation from Process control
standard - planned
Machine Change - planned
Manpower change
( regular)
Different spec /
Grade of incoming
controlled material
from approved
source for trials -
planned
Process sequence change -Unplanned Breakdown Maint. Which
affects process / quality of
product - unplanned
Person left shift job due
to sickness
Material
Composition change-
Planned
New technology introduction - planned Fixture change - such as enamel
applicator - planned
New joinee - planned Material
Combination Change-
Planned
Additional process adopted - planned Preventive maintanence. -
planned
On Leave For More than
one Month
Inspection equipment change - planned
Traceability
• Traceability or unique Identification is very
important for further assessment of product.
• To check product deforms after time interval.

More Related Content

What's hot

Apqp ppt
Apqp pptApqp ppt
Apqp ppt
sbtharan
 
Training ppt for control plan
Training ppt for control plan   Training ppt for control plan
Training ppt for control plan
Jitesh Gaurav
 
APQP Training presentation
APQP Training  presentationAPQP Training  presentation
APQP Training presentation
Qualsys Ltd
 
Jishu hozen
Jishu  hozenJishu  hozen
Jishu hozen
QC Labs
 
List of mandatory IATF 16949 documents
List of mandatory IATF 16949 documents List of mandatory IATF 16949 documents
List of mandatory IATF 16949 documents
Global Manager Group
 
TPM: Autonomous Maintenance
TPM: Autonomous MaintenanceTPM: Autonomous Maintenance
TPM: Autonomous Maintenance
Operational Excellence Consulting
 
Ppap training-presentation
Ppap training-presentationPpap training-presentation
Ppap training-presentationRanvijay Akela
 
PPAP
PPAPPPAP
PPAP
JEETQA
 
8D analysis presentation
8D analysis presentation8D analysis presentation
8D analysis presentation
PRASHANT KSHIRSAGAR
 
MRM - Management Review Meeting Presentation
MRM - Management Review Meeting PresentationMRM - Management Review Meeting Presentation
MRM - Management Review Meeting Presentation
Engr. Syed Noor Mustafa Shah
 
Advanced Product Quality Planning presentation
Advanced Product Quality Planning presentationAdvanced Product Quality Planning presentation
Advanced Product Quality Planning presentation
PRASHANT KSHIRSAGAR
 
Autonomous maintenance Jishu Hozen
Autonomous maintenance Jishu HozenAutonomous maintenance Jishu Hozen
Autonomous maintenance Jishu Hozen
ChetanMehta39
 
My machine camp
My machine campMy machine camp
My machine camp
Jitesh Gaurav
 
Dwm ppt
Dwm pptDwm ppt
Dwm ppt
gurmukh singh
 
Msil quality system audit sheet
Msil quality system audit sheetMsil quality system audit sheet
Msil quality system audit sheet
Amit Mishra
 
IATF 16949 Webinar Slides 3.7.17
IATF 16949 Webinar Slides 3.7.17IATF 16949 Webinar Slides 3.7.17
IATF 16949 Webinar Slides 3.7.17
Sara Gulo
 
5S Training
5S Training5S Training
5S Training
Ansar Lawi
 
5S Audit Checklists for Manufacturing & Office
5S Audit Checklists for Manufacturing & Office5S Audit Checklists for Manufacturing & Office
5S Audit Checklists for Manufacturing & Office
Operational Excellence Consulting
 
Autonomous Maintenance (AM)
Autonomous Maintenance (AM)Autonomous Maintenance (AM)
Autonomous Maintenance (AM)
Pramod A
 
IATF PPT.pdf
IATF PPT.pdfIATF PPT.pdf
IATF PPT.pdf
puneetyadav159342
 

What's hot (20)

Apqp ppt
Apqp pptApqp ppt
Apqp ppt
 
Training ppt for control plan
Training ppt for control plan   Training ppt for control plan
Training ppt for control plan
 
APQP Training presentation
APQP Training  presentationAPQP Training  presentation
APQP Training presentation
 
Jishu hozen
Jishu  hozenJishu  hozen
Jishu hozen
 
List of mandatory IATF 16949 documents
List of mandatory IATF 16949 documents List of mandatory IATF 16949 documents
List of mandatory IATF 16949 documents
 
TPM: Autonomous Maintenance
TPM: Autonomous MaintenanceTPM: Autonomous Maintenance
TPM: Autonomous Maintenance
 
Ppap training-presentation
Ppap training-presentationPpap training-presentation
Ppap training-presentation
 
PPAP
PPAPPPAP
PPAP
 
8D analysis presentation
8D analysis presentation8D analysis presentation
8D analysis presentation
 
MRM - Management Review Meeting Presentation
MRM - Management Review Meeting PresentationMRM - Management Review Meeting Presentation
MRM - Management Review Meeting Presentation
 
Advanced Product Quality Planning presentation
Advanced Product Quality Planning presentationAdvanced Product Quality Planning presentation
Advanced Product Quality Planning presentation
 
Autonomous maintenance Jishu Hozen
Autonomous maintenance Jishu HozenAutonomous maintenance Jishu Hozen
Autonomous maintenance Jishu Hozen
 
My machine camp
My machine campMy machine camp
My machine camp
 
Dwm ppt
Dwm pptDwm ppt
Dwm ppt
 
Msil quality system audit sheet
Msil quality system audit sheetMsil quality system audit sheet
Msil quality system audit sheet
 
IATF 16949 Webinar Slides 3.7.17
IATF 16949 Webinar Slides 3.7.17IATF 16949 Webinar Slides 3.7.17
IATF 16949 Webinar Slides 3.7.17
 
5S Training
5S Training5S Training
5S Training
 
5S Audit Checklists for Manufacturing & Office
5S Audit Checklists for Manufacturing & Office5S Audit Checklists for Manufacturing & Office
5S Audit Checklists for Manufacturing & Office
 
Autonomous Maintenance (AM)
Autonomous Maintenance (AM)Autonomous Maintenance (AM)
Autonomous Maintenance (AM)
 
IATF PPT.pdf
IATF PPT.pdfIATF PPT.pdf
IATF PPT.pdf
 

Similar to Change Management - 4 m change

Good Manufacturing Practices by InstantGMP
Good Manufacturing Practices by InstantGMPGood Manufacturing Practices by InstantGMP
Good Manufacturing Practices by InstantGMP
Atlantic Training, LLC.
 
IEM UNIT 4 PLANT LOCATION.ppt
IEM UNIT 4 PLANT LOCATION.pptIEM UNIT 4 PLANT LOCATION.ppt
IEM UNIT 4 PLANT LOCATION.ppt
Raja Manyam
 
Unit iii operations management
Unit iii operations managementUnit iii operations management
Unit iii operations management
Management
 
CCF PPT By Amit Gupta.pptx
CCF PPT By Amit Gupta.pptxCCF PPT By Amit Gupta.pptx
CCF PPT By Amit Gupta.pptx
amitgupta273294
 
Production and operation management.pptx
Production and operation management.pptxProduction and operation management.pptx
Production and operation management.pptx
jaydipsavaj68
 
OPERATIONS MANAGEMENT- Full Slides.pptx
OPERATIONS MANAGEMENT- Full Slides.pptxOPERATIONS MANAGEMENT- Full Slides.pptx
OPERATIONS MANAGEMENT- Full Slides.pptx
ThusharaVinay
 
Pharmaceutical Production Planning and control
Pharmaceutical Production Planning and controlPharmaceutical Production Planning and control
Pharmaceutical Production Planning and control
RaviTeja Netha
 
APQP-PPAP[1].ppt for engineering products
APQP-PPAP[1].ppt for engineering productsAPQP-PPAP[1].ppt for engineering products
APQP-PPAP[1].ppt for engineering products
INSTITUTE OF ENGINEERING /BKC
 
GMP Training: Handling of deviation
GMP Training: Handling of deviationGMP Training: Handling of deviation
GMP Training: Handling of deviation
Dr. Amsavel A
 
Pilot plant scaleup.pptx
Pilot plant scaleup.pptxPilot plant scaleup.pptx
Pilot plant scaleup.pptx
ANANDGADAD2
 
CASE STUDY ON CHANGE CONTROL
CASE STUDY ON CHANGE CONTROLCASE STUDY ON CHANGE CONTROL
CASE STUDY ON CHANGE CONTROL
JAYA PRAKASH VELUCHURI
 
Ppap la
Ppap laPpap la
Ppap la
Paul Robere
 
QUALITY MANAGEMNT SYSTEMS: Change Control (CC)
QUALITY MANAGEMNT SYSTEMS: Change Control (CC)QUALITY MANAGEMNT SYSTEMS: Change Control (CC)
QUALITY MANAGEMNT SYSTEMS: Change Control (CC)
Dr Ajay Kumar Tiwari
 
Change control request
Change control requestChange control request
Change control request
Tilahun Alemayehu
 
Production planing & control
Production planing & controlProduction planing & control
Production planing & control
PRIYABAMBALE
 
Advanced Product Quality Planning And Control Plans Based On APQP 2 Nd Edition
Advanced Product Quality Planning And Control Plans Based On APQP 2 Nd EditionAdvanced Product Quality Planning And Control Plans Based On APQP 2 Nd Edition
Advanced Product Quality Planning And Control Plans Based On APQP 2 Nd Edition
Scott Faria
 
Production planning
Production planningProduction planning
Production planning
David Jaison
 
SMED - 6.pptx.pptx
SMED - 6.pptx.pptxSMED - 6.pptx.pptx
SMED - 6.pptx.pptx
ssuser820b7a
 
Software testing regression testing
Software testing  regression testingSoftware testing  regression testing
Software testing regression testing
GaneshKumarKanthiah
 

Similar to Change Management - 4 m change (20)

Good Manufacturing Practices by InstantGMP
Good Manufacturing Practices by InstantGMPGood Manufacturing Practices by InstantGMP
Good Manufacturing Practices by InstantGMP
 
GMP by InstantGMP
GMP by InstantGMPGMP by InstantGMP
GMP by InstantGMP
 
IEM UNIT 4 PLANT LOCATION.ppt
IEM UNIT 4 PLANT LOCATION.pptIEM UNIT 4 PLANT LOCATION.ppt
IEM UNIT 4 PLANT LOCATION.ppt
 
Unit iii operations management
Unit iii operations managementUnit iii operations management
Unit iii operations management
 
CCF PPT By Amit Gupta.pptx
CCF PPT By Amit Gupta.pptxCCF PPT By Amit Gupta.pptx
CCF PPT By Amit Gupta.pptx
 
Production and operation management.pptx
Production and operation management.pptxProduction and operation management.pptx
Production and operation management.pptx
 
OPERATIONS MANAGEMENT- Full Slides.pptx
OPERATIONS MANAGEMENT- Full Slides.pptxOPERATIONS MANAGEMENT- Full Slides.pptx
OPERATIONS MANAGEMENT- Full Slides.pptx
 
Pharmaceutical Production Planning and control
Pharmaceutical Production Planning and controlPharmaceutical Production Planning and control
Pharmaceutical Production Planning and control
 
APQP-PPAP[1].ppt for engineering products
APQP-PPAP[1].ppt for engineering productsAPQP-PPAP[1].ppt for engineering products
APQP-PPAP[1].ppt for engineering products
 
GMP Training: Handling of deviation
GMP Training: Handling of deviationGMP Training: Handling of deviation
GMP Training: Handling of deviation
 
Pilot plant scaleup.pptx
Pilot plant scaleup.pptxPilot plant scaleup.pptx
Pilot plant scaleup.pptx
 
CASE STUDY ON CHANGE CONTROL
CASE STUDY ON CHANGE CONTROLCASE STUDY ON CHANGE CONTROL
CASE STUDY ON CHANGE CONTROL
 
Ppap la
Ppap laPpap la
Ppap la
 
QUALITY MANAGEMNT SYSTEMS: Change Control (CC)
QUALITY MANAGEMNT SYSTEMS: Change Control (CC)QUALITY MANAGEMNT SYSTEMS: Change Control (CC)
QUALITY MANAGEMNT SYSTEMS: Change Control (CC)
 
Change control request
Change control requestChange control request
Change control request
 
Production planing & control
Production planing & controlProduction planing & control
Production planing & control
 
Advanced Product Quality Planning And Control Plans Based On APQP 2 Nd Edition
Advanced Product Quality Planning And Control Plans Based On APQP 2 Nd EditionAdvanced Product Quality Planning And Control Plans Based On APQP 2 Nd Edition
Advanced Product Quality Planning And Control Plans Based On APQP 2 Nd Edition
 
Production planning
Production planningProduction planning
Production planning
 
SMED - 6.pptx.pptx
SMED - 6.pptx.pptxSMED - 6.pptx.pptx
SMED - 6.pptx.pptx
 
Software testing regression testing
Software testing  regression testingSoftware testing  regression testing
Software testing regression testing
 

Recently uploaded

Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
Kamal Acharya
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 

Recently uploaded (20)

Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 

Change Management - 4 m change

  • 1. 4M CHANGE Presented By : Hardil Shah
  • 2. What is 4M change? 1. MAN 2. MACHINE 3. MATERIAL 4. METHOD
  • 3. Purpose of 4M Change • To closely monitor process and effect of change on product.
  • 4. Man • If new Person join. • Person is on leave for more than 1 month. • Shift time extended • If person is sick. Machine • Machine Change. • Engineering change in Machine. • Preventive Maintenance planned. • Break down maintenance done on machine. • Fixture change in machine. • Removing or adding external process on machine
  • 5. Material • New Supplier or change current supplier • New Material for approval source of trial. • Same Supplier but mixing combination change. Method • Any Deviation form Process control (Process Parameter Change) • Process Sequence Change. • Additional process implemented. • New technology implemented
  • 6. Type of 4M change 1. Planned (Permanent) 2. Un Planned (Temporary)
  • 7. Planned (Permanent) Type Change • The Change that is done due to some unavoidable reason. Unplanned (Temporary) Type Change • The change that discussed before change and pre planned.
  • 8. Criteria of 4M change • Set up • Containment • Retro active
  • 9. Setup • First Part Approval report Containment • To Closely monitor running production Retroactive • To trace back from where problem arise in production.
  • 10. Criteria : 4 M Change MAN MATERIAL METHOD MACHINE Extended shift working ( over 2 shifts ) - unplanned Source of supply change for controlled item- planned Any deviation from Process control standard - planned Machine Change - planned Manpower change ( regular) Different spec / Grade of incoming controlled material from approved source for trials - planned Process sequence change -Unplanned Breakdown Maint. Which affects process / quality of product - unplanned Person left shift job due to sickness Material Composition change- Planned New technology introduction - planned Fixture change - such as enamel applicator - planned New joinee - planned Material Combination Change- Planned Additional process adopted - planned Preventive maintanence. - planned On Leave For More than one Month Inspection equipment change - planned
  • 11. Traceability • Traceability or unique Identification is very important for further assessment of product. • To check product deforms after time interval.