Capital Budgeting

    Chapter 12
• Capital budgeting: process by which
  organization evaluates and selects long-term
  investment projects
  – Ex. Investments in capital equipment, purchase or
    lease of buildings, purchase or lease of vehicles,
    etc.
• There are various techniques used to make
  capital budgeting decisions.
Payback
• Small businesses use this method because it is
  simple
• Requires calculation of number of years
  required to pay back original investment
• Payback-based decisions:
  – Between two mutually exclusive investment projects,
    choose project with shortest payback period
  – Set a predetermined standard
     • Ex. “Accept all projects with payback of less than 5 years and
       reject all others”
Payback
• Poor method on which to rely for allocation of scarce capital
  resources because:
    1.   Payback ignores time value of money
    2.   Payback ignores expected cash flows beyond payback period.
• Ex.:      PROJECT A                                PROJECT B
            Cost = $100,000                         Cost = $100,000
            Expected Future Cash Flow:        Expected Future Cash Flow:
            Year 1 $50,000                        Year 1 $100,000
            Year 2 $50,000                          Year 2 $5,000
            Year 3 $110,000                         Year 3 $5,000
            Year 4 and thereafter: None       Year 4 and thereafter: None
            Total = $210,000                        Total = $110,000
            Payback = 2 years                       Payback = 1 year
-Payback period for Project B is shorter, but Project A provides higher return
-Project A is superior to Project B.
Net Present Value
• Difference between present value of expected
  future benefits of project to present value of
  expected cost of project
• If NPV is positive (if present value of benefits
  exceeds present value of cost), then project is
  accepted.
• If NPV is negative (if present value of costs exceeds
  present value of benefits), then project is rejected.
• NPV = PVB – PVC
   – Where NPV = net present value
               PVB = present value of benefits
              PVC = present value of costs
Net Present Value
• Between two mutually exclusive projects, choose project
  with highest net present value.
• Ex.: Consider Project A and Project B and 12% discount rate

   PVBa = ($50,000)(0.893) + ($50,000)(0.797) + ($110,000)(0.712)
   PVBa = $162,820
   PVBb = ($100,000)(0.893) + ($5,000)(0.792) + ($5,000)(0.712)
   PVBb = $96,820
   PVCa = PVCb = $100,000

   NPVa = $162,000 – $100,000 = $62,800
   NPVb = $96,820 – $100,000 = ($3,180)

   – Project A is superior to Project B because PVBa > PVCa and
     PVBb < PVCb
   – Return on Project B is insufficient to justify investment
     given firm’s cost of capital.
Net Present Value
Selection of a Discount Rate
• To find discounted present value of sum of
  money to be received in future, choose rate at
  which money in hand may be invested
  between now and future period in which
  money is to be received.
  – This rate represents individual’s “opportunity
    cost,” or cost of next-best opportunity.
Internal Rate of Return
• Discount rate that exactly equates present value of
  expected benefits to cost (drives NPV to zero)
• Find this discount rate by trial and error
• Ex.:
   – Use discount rate of 20% as first estimate of IRR on Project
     A.
     NPVa = PVBa – PVCa
     NPVa = $40,040
   – Since NPV is too high, use higher estimate of 40%.
     NPVa = $1,240
   – Use estimate of 41% to get closer to zero.
      NPVa = $290
Internal Rate of Return
• Investment of $100,000 at 41% annual compound rate of
  return allows withdrawal of that investment as a cash flow of
  $50,000 at end of 1 year, $50,000 at end of 2nd year, and
  $110,000 at end of 3rd year.

                      Project A Cash Flow Schedule
                                             Year
                                       1          2       3
     Beginning investment         $100,000    $91,000 $78,310
     Annual earnings at 41%          41,000     37,310 _32,107
         Subtotal                  $141,000   $128,310 $110,417
     Annual cash flow               (50,000)   (50,000) (110,417)
         Ending investment          $91,000    $78,310    $-0-
Internal Rate of Return
• In general, any project with IRR greater than
  or equal to cost of capital should be
  accepted. Any project with IRR less than cost
  of capital should be rejected.
• In this case, Project A would be accepted.
Internal Rate of Return
• Ex. (continued):
• IRR for Project B is approximately 8.75%.
  NPVb = $120
• 8.75% per year is less than cost of capital of
  12%. Achieved rate of return on Project B falls
  short of attainable rate of return on other
  opportunities.
Internal Rate of Return
IRR of an Annuity
• Project A and Project B do not provide benefits in form of
  annuity (constant annual cash flow).
• If project costing $100,000 and returning $25,000 per year for
  5 years is available, calculate appropriate annuity factor:
                  $100,000 = $25,000X
                         X = 4.0
• X represents annuity factor that will cause $25,000, 5-year
  annuity to have present value of $100,000.
• Refer to table of annuity factors in Exhibit 11.4 to find
  discount rate that has present value of annuity factor equal to
  4.00 after 5 years.
Internal Rate of Return
Personal Computer Applications
• Most basic business-oriented electronic
  calculators, personal computers, business-
  oriented spreadsheet applications, special-
  purpose capital budgeting software packages
  can do actual calculations or be programmed
  to solve capital budgeting problems.
Profitability Index
• Also benefit/cost ratio
• Calculated as ratio of present value of
  benefits of investment to cost of investment
           PI = NPV(benefits)/NPV(costs)
• General rule: All projects with PI > 1.0 should
  be accepted.
• Between two or more mutually exclusive
  projects having different costs, choose project
  with highest profitability index.
Profitability Index
• Investment decisions based on profitability
  index will be same as decisions made using
  net present value.
• All projects having positive net present value
  have profitability index larger than 1.0 and
  therefore are acceptable.
Selection of Method
• All 3 methods (net present value, internal rate
  of return, profitability index) result in same
  accept-reject decision for given investment
  opportunity.
• There are three important circumstances
  under which methods may yield conflicting
  decisions.
Selection of Method
1. Choosing from among mutually exclusive
    investment projects with similar costs, but
    radically differing time patterns of cash inflows.
   – Ex. One project provides large cash flows in early
       years and small cash flows in later years
       compared with another project providing small
       cash flows in early years but large cash flows in
       later years.
     •   Project having highest net present value and
         profitability may have lowest internal rate of return.
Selection of Method
1. (continued)
  – Choice of method depends on which assumption
    is closest to reality.
  – Choice should be based on which reinvestment
    rate is closest to rate that firm will be able to
    earn on cash flows generated by project.
    •   If cash flows can be reinvested at cost of capital,
        select project with higher net present value.
    •   If cash inflows can be reinvested at IRR of project,
        select project with higher IRR.
Selection of Method
1. (continued)
  – General rule: NPV method should be preferred if
    conflict arises because projects with very high
    IRRs relative to firm’s cost of capital are rare. In
    most cases, reinvestment rate will be closer to
    cost of capital than to IRR and thus, NPV method
    is normally preferred to IRR method.
Selection of Method
2. Choosing from among mutually exclusive
   projects with widely differing costs.
  – If project with highest NPV has lowest PI and IRR,
    in general, give preference to project with
    highest NPV since this will maximize value of
    firm.
  – If project with highest PI and IRR is substantially
    less expensive than competing project, former is
    selected because lower-cost project may be
    perceived as less risky than higher-cost project.
Selection of Method
3. Capital rationing where insufficient capital
   is available to accept all projects having
   positive NPVs.
  – Rank-order projects from highest IRR to lowest
    and select projects that firm has sufficient capital
    to accept.

  •   In general, NPV method preferred over IRR and
      PI methods.
Dealing With Uncertainty
• In practice, uncertainty is often dealt with
  through simple mechanism of assigning
  higher discount rate to riskier projects.
  – How much higher depends on management’s
    perception of degree of risk and additional
    compensation required because of that risk
Case Study
• Droppitt Parcel Company is considering purchasing new
  equipment to replace existing equipment that has book value
  of zero and market value of $15,000.
• New equipment costs $90,000 and is expected to provide
  production savings and increased profits of $20,000 per year
  for the next 10 years.
• New equipment has expected useful life of 10 years, after
  which its estimated salvage value would be $10,000.
• Straight-line depreciation
    Effective tax rate: 34%
    Cost of capital: 12%
• “Machinery Replacement” Problem: Should Droppitt replace
  current equipment?
Case Study
• See Exhibit 12.4
1. Effective cost of new equipment: $80,100
  – Droppits trades its old equipment in for new
    equipment by selling it and applying sale
    proceeds to new equipment.
Case Study
2. Calculate present value of expected benefits
   of new equipment.
  –  All benefits have been converted to after-tax basis before
     present values are calculated.
  – Profit increase is multiplied by 0.66 (1.00 – tax rate) to
     determine increased profit remaining after tax.
  – Calculate tax benefit resulting from effect of depreciation by
     multiplying annual depreciation deduction by effective tax
     rate.
  – Reflects salvage value of new equipment at end of its expected
     useful life.
    • No tax effect here because there is no profit or loss
         involved.
Case Study
3. NPV: $13,068
4. IRR (solved by trial and error using electronic
   calculator): 15.7%
• New machine should be purchased to
   replace old machine since NPV is positive
   and IRR exceeds cost of capital.

More Related Content

What's hot

Functions of financial manager
Functions of financial managerFunctions of financial manager
Functions of financial managerShristi Giri
 
Financial appraisal
Financial appraisalFinancial appraisal
Financial appraisalDhwani Shah
 
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar GSocial Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar GMohan Kumar G
 
Economic Value Added (EVA), Finance, Performance Measurement by Vikash Goel
Economic Value Added (EVA), Finance, Performance Measurement by Vikash GoelEconomic Value Added (EVA), Finance, Performance Measurement by Vikash Goel
Economic Value Added (EVA), Finance, Performance Measurement by Vikash GoelVikash Goel
 
Modigliani and miller approach
Modigliani and miller approachModigliani and miller approach
Modigliani and miller approachMeenuKhurana7
 
Financial statement analysis
Financial statement analysisFinancial statement analysis
Financial statement analysisAnuj Bhatia
 
Cost volume profit analysis.
Cost volume profit analysis.Cost volume profit analysis.
Cost volume profit analysis.Varadraj Bapat
 
Cash flow analysis
Cash flow analysisCash flow analysis
Cash flow analysisAdil Shaikh
 
Capital rationing - Meaning, Types and Problems of Project Selection under ca...
Capital rationing - Meaning, Types and Problems of Project Selection under ca...Capital rationing - Meaning, Types and Problems of Project Selection under ca...
Capital rationing - Meaning, Types and Problems of Project Selection under ca...Sundar B N
 
Operating, financial and combined leverage
Operating, financial and combined leverageOperating, financial and combined leverage
Operating, financial and combined leverageSimran Kaur
 
Working capital management ppt
Working capital management pptWorking capital management ppt
Working capital management pptShanu Aggarwal
 

What's hot (20)

Functions of financial manager
Functions of financial managerFunctions of financial manager
Functions of financial manager
 
Working capital
Working capitalWorking capital
Working capital
 
Capital structure ppt
Capital structure pptCapital structure ppt
Capital structure ppt
 
Financial appraisal
Financial appraisalFinancial appraisal
Financial appraisal
 
Capital structure
Capital structureCapital structure
Capital structure
 
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar GSocial Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
 
Economic Value Added (EVA), Finance, Performance Measurement by Vikash Goel
Economic Value Added (EVA), Finance, Performance Measurement by Vikash GoelEconomic Value Added (EVA), Finance, Performance Measurement by Vikash Goel
Economic Value Added (EVA), Finance, Performance Measurement by Vikash Goel
 
Modigliani and miller approach
Modigliani and miller approachModigliani and miller approach
Modigliani and miller approach
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
Rate of return
Rate of returnRate of return
Rate of return
 
Responsibility Accounting
Responsibility AccountingResponsibility Accounting
Responsibility Accounting
 
Finance Case studies
Finance Case studiesFinance Case studies
Finance Case studies
 
Capital budgeting Techniques
Capital budgeting TechniquesCapital budgeting Techniques
Capital budgeting Techniques
 
Financial statement analysis
Financial statement analysisFinancial statement analysis
Financial statement analysis
 
Cost volume profit analysis.
Cost volume profit analysis.Cost volume profit analysis.
Cost volume profit analysis.
 
Cash flow analysis
Cash flow analysisCash flow analysis
Cash flow analysis
 
Capital rationing - Meaning, Types and Problems of Project Selection under ca...
Capital rationing - Meaning, Types and Problems of Project Selection under ca...Capital rationing - Meaning, Types and Problems of Project Selection under ca...
Capital rationing - Meaning, Types and Problems of Project Selection under ca...
 
Transfer Pricing
Transfer PricingTransfer Pricing
Transfer Pricing
 
Operating, financial and combined leverage
Operating, financial and combined leverageOperating, financial and combined leverage
Operating, financial and combined leverage
 
Working capital management ppt
Working capital management pptWorking capital management ppt
Working capital management ppt
 

Similar to case study-capital budgeting

Bsics of Capital Budgeting.pptx
Bsics of Capital Budgeting.pptxBsics of Capital Budgeting.pptx
Bsics of Capital Budgeting.pptxMohamoud9
 
capital budgeting process investment rules.pptx
capital budgeting process investment rules.pptxcapital budgeting process investment rules.pptx
capital budgeting process investment rules.pptxATEEQURRehman366058
 
Net Present Value Vs Profitability Index
Net Present Value Vs Profitability IndexNet Present Value Vs Profitability Index
Net Present Value Vs Profitability IndexAseem R
 
FM_Unit 4 - Part 1.pptx
FM_Unit 4 - Part 1.pptxFM_Unit 4 - Part 1.pptx
FM_Unit 4 - Part 1.pptxNishaGoyal63
 
Capital expenditure control
Capital expenditure controlCapital expenditure control
Capital expenditure controlSatish Bidgar
 
capital budgeting concept meaning and types
capital budgeting concept meaning and typescapital budgeting concept meaning and types
capital budgeting concept meaning and typesDrSurabhiBharti
 
LECTURE 4 (2).pptx
LECTURE 4 (2).pptxLECTURE 4 (2).pptx
LECTURE 4 (2).pptxhaiqamalik
 
Net Present Value - NPV
Net Present Value - NPVNet Present Value - NPV
Net Present Value - NPVASAD ALI
 
Chapter 4 CBT&D.pptx
Chapter 4 CBT&D.pptxChapter 4 CBT&D.pptx
Chapter 4 CBT&D.pptxSaif Uddin
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgetingnarman1402
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgetingSouman Guha
 
Chapter 9: CAPITAL BUDGETING
Chapter 9: CAPITAL BUDGETINGChapter 9: CAPITAL BUDGETING
Chapter 9: CAPITAL BUDGETINGAJ SEBUC
 
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...Akhil Sabu
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgetingpremarhea
 

Similar to case study-capital budgeting (20)

capital budgeting
capital budgeting capital budgeting
capital budgeting
 
Bsics of Capital Budgeting.pptx
Bsics of Capital Budgeting.pptxBsics of Capital Budgeting.pptx
Bsics of Capital Budgeting.pptx
 
capital budgeting process investment rules.pptx
capital budgeting process investment rules.pptxcapital budgeting process investment rules.pptx
capital budgeting process investment rules.pptx
 
Capital Budgeting.pdf
Capital Budgeting.pdfCapital Budgeting.pdf
Capital Budgeting.pdf
 
Net Present Value Vs Profitability Index
Net Present Value Vs Profitability IndexNet Present Value Vs Profitability Index
Net Present Value Vs Profitability Index
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
FM_Unit 4 - Part 1.pptx
FM_Unit 4 - Part 1.pptxFM_Unit 4 - Part 1.pptx
FM_Unit 4 - Part 1.pptx
 
Capital expenditure control
Capital expenditure controlCapital expenditure control
Capital expenditure control
 
capital budgeting concept meaning and types
capital budgeting concept meaning and typescapital budgeting concept meaning and types
capital budgeting concept meaning and types
 
2. capital budgeting review
2. capital budgeting review2. capital budgeting review
2. capital budgeting review
 
LECTURE 4 (2).pptx
LECTURE 4 (2).pptxLECTURE 4 (2).pptx
LECTURE 4 (2).pptx
 
Net Present Value - NPV
Net Present Value - NPVNet Present Value - NPV
Net Present Value - NPV
 
Chapter 4 CBT&D.pptx
Chapter 4 CBT&D.pptxChapter 4 CBT&D.pptx
Chapter 4 CBT&D.pptx
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgeting
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
ch11.pptx
ch11.pptxch11.pptx
ch11.pptx
 
Lecture 3
Lecture 3Lecture 3
Lecture 3
 
Chapter 9: CAPITAL BUDGETING
Chapter 9: CAPITAL BUDGETINGChapter 9: CAPITAL BUDGETING
Chapter 9: CAPITAL BUDGETING
 
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 

case study-capital budgeting

  • 1. Capital Budgeting Chapter 12
  • 2. • Capital budgeting: process by which organization evaluates and selects long-term investment projects – Ex. Investments in capital equipment, purchase or lease of buildings, purchase or lease of vehicles, etc. • There are various techniques used to make capital budgeting decisions.
  • 3. Payback • Small businesses use this method because it is simple • Requires calculation of number of years required to pay back original investment • Payback-based decisions: – Between two mutually exclusive investment projects, choose project with shortest payback period – Set a predetermined standard • Ex. “Accept all projects with payback of less than 5 years and reject all others”
  • 4. Payback • Poor method on which to rely for allocation of scarce capital resources because: 1. Payback ignores time value of money 2. Payback ignores expected cash flows beyond payback period. • Ex.: PROJECT A PROJECT B Cost = $100,000 Cost = $100,000 Expected Future Cash Flow: Expected Future Cash Flow: Year 1 $50,000 Year 1 $100,000 Year 2 $50,000 Year 2 $5,000 Year 3 $110,000 Year 3 $5,000 Year 4 and thereafter: None Year 4 and thereafter: None Total = $210,000 Total = $110,000 Payback = 2 years Payback = 1 year -Payback period for Project B is shorter, but Project A provides higher return -Project A is superior to Project B.
  • 5. Net Present Value • Difference between present value of expected future benefits of project to present value of expected cost of project • If NPV is positive (if present value of benefits exceeds present value of cost), then project is accepted. • If NPV is negative (if present value of costs exceeds present value of benefits), then project is rejected. • NPV = PVB – PVC – Where NPV = net present value PVB = present value of benefits PVC = present value of costs
  • 6. Net Present Value • Between two mutually exclusive projects, choose project with highest net present value. • Ex.: Consider Project A and Project B and 12% discount rate PVBa = ($50,000)(0.893) + ($50,000)(0.797) + ($110,000)(0.712) PVBa = $162,820 PVBb = ($100,000)(0.893) + ($5,000)(0.792) + ($5,000)(0.712) PVBb = $96,820 PVCa = PVCb = $100,000 NPVa = $162,000 – $100,000 = $62,800 NPVb = $96,820 – $100,000 = ($3,180) – Project A is superior to Project B because PVBa > PVCa and PVBb < PVCb – Return on Project B is insufficient to justify investment given firm’s cost of capital.
  • 7. Net Present Value Selection of a Discount Rate • To find discounted present value of sum of money to be received in future, choose rate at which money in hand may be invested between now and future period in which money is to be received. – This rate represents individual’s “opportunity cost,” or cost of next-best opportunity.
  • 8. Internal Rate of Return • Discount rate that exactly equates present value of expected benefits to cost (drives NPV to zero) • Find this discount rate by trial and error • Ex.: – Use discount rate of 20% as first estimate of IRR on Project A. NPVa = PVBa – PVCa NPVa = $40,040 – Since NPV is too high, use higher estimate of 40%. NPVa = $1,240 – Use estimate of 41% to get closer to zero. NPVa = $290
  • 9. Internal Rate of Return • Investment of $100,000 at 41% annual compound rate of return allows withdrawal of that investment as a cash flow of $50,000 at end of 1 year, $50,000 at end of 2nd year, and $110,000 at end of 3rd year. Project A Cash Flow Schedule Year 1 2 3 Beginning investment $100,000 $91,000 $78,310 Annual earnings at 41% 41,000 37,310 _32,107 Subtotal $141,000 $128,310 $110,417 Annual cash flow (50,000) (50,000) (110,417) Ending investment $91,000 $78,310 $-0-
  • 10. Internal Rate of Return • In general, any project with IRR greater than or equal to cost of capital should be accepted. Any project with IRR less than cost of capital should be rejected. • In this case, Project A would be accepted.
  • 11. Internal Rate of Return • Ex. (continued): • IRR for Project B is approximately 8.75%. NPVb = $120 • 8.75% per year is less than cost of capital of 12%. Achieved rate of return on Project B falls short of attainable rate of return on other opportunities.
  • 12. Internal Rate of Return IRR of an Annuity • Project A and Project B do not provide benefits in form of annuity (constant annual cash flow). • If project costing $100,000 and returning $25,000 per year for 5 years is available, calculate appropriate annuity factor: $100,000 = $25,000X X = 4.0 • X represents annuity factor that will cause $25,000, 5-year annuity to have present value of $100,000. • Refer to table of annuity factors in Exhibit 11.4 to find discount rate that has present value of annuity factor equal to 4.00 after 5 years.
  • 13. Internal Rate of Return Personal Computer Applications • Most basic business-oriented electronic calculators, personal computers, business- oriented spreadsheet applications, special- purpose capital budgeting software packages can do actual calculations or be programmed to solve capital budgeting problems.
  • 14. Profitability Index • Also benefit/cost ratio • Calculated as ratio of present value of benefits of investment to cost of investment PI = NPV(benefits)/NPV(costs) • General rule: All projects with PI > 1.0 should be accepted. • Between two or more mutually exclusive projects having different costs, choose project with highest profitability index.
  • 15. Profitability Index • Investment decisions based on profitability index will be same as decisions made using net present value. • All projects having positive net present value have profitability index larger than 1.0 and therefore are acceptable.
  • 16. Selection of Method • All 3 methods (net present value, internal rate of return, profitability index) result in same accept-reject decision for given investment opportunity. • There are three important circumstances under which methods may yield conflicting decisions.
  • 17. Selection of Method 1. Choosing from among mutually exclusive investment projects with similar costs, but radically differing time patterns of cash inflows. – Ex. One project provides large cash flows in early years and small cash flows in later years compared with another project providing small cash flows in early years but large cash flows in later years. • Project having highest net present value and profitability may have lowest internal rate of return.
  • 18. Selection of Method 1. (continued) – Choice of method depends on which assumption is closest to reality. – Choice should be based on which reinvestment rate is closest to rate that firm will be able to earn on cash flows generated by project. • If cash flows can be reinvested at cost of capital, select project with higher net present value. • If cash inflows can be reinvested at IRR of project, select project with higher IRR.
  • 19. Selection of Method 1. (continued) – General rule: NPV method should be preferred if conflict arises because projects with very high IRRs relative to firm’s cost of capital are rare. In most cases, reinvestment rate will be closer to cost of capital than to IRR and thus, NPV method is normally preferred to IRR method.
  • 20. Selection of Method 2. Choosing from among mutually exclusive projects with widely differing costs. – If project with highest NPV has lowest PI and IRR, in general, give preference to project with highest NPV since this will maximize value of firm. – If project with highest PI and IRR is substantially less expensive than competing project, former is selected because lower-cost project may be perceived as less risky than higher-cost project.
  • 21. Selection of Method 3. Capital rationing where insufficient capital is available to accept all projects having positive NPVs. – Rank-order projects from highest IRR to lowest and select projects that firm has sufficient capital to accept. • In general, NPV method preferred over IRR and PI methods.
  • 22. Dealing With Uncertainty • In practice, uncertainty is often dealt with through simple mechanism of assigning higher discount rate to riskier projects. – How much higher depends on management’s perception of degree of risk and additional compensation required because of that risk
  • 23. Case Study • Droppitt Parcel Company is considering purchasing new equipment to replace existing equipment that has book value of zero and market value of $15,000. • New equipment costs $90,000 and is expected to provide production savings and increased profits of $20,000 per year for the next 10 years. • New equipment has expected useful life of 10 years, after which its estimated salvage value would be $10,000. • Straight-line depreciation  Effective tax rate: 34%  Cost of capital: 12% • “Machinery Replacement” Problem: Should Droppitt replace current equipment?
  • 24. Case Study • See Exhibit 12.4 1. Effective cost of new equipment: $80,100 – Droppits trades its old equipment in for new equipment by selling it and applying sale proceeds to new equipment.
  • 25. Case Study 2. Calculate present value of expected benefits of new equipment. – All benefits have been converted to after-tax basis before present values are calculated. – Profit increase is multiplied by 0.66 (1.00 – tax rate) to determine increased profit remaining after tax. – Calculate tax benefit resulting from effect of depreciation by multiplying annual depreciation deduction by effective tax rate. – Reflects salvage value of new equipment at end of its expected useful life. • No tax effect here because there is no profit or loss involved.
  • 26. Case Study 3. NPV: $13,068 4. IRR (solved by trial and error using electronic calculator): 15.7% • New machine should be purchased to replace old machine since NPV is positive and IRR exceeds cost of capital.