SlideShare a Scribd company logo
Todd Blechinger / Jeff Devers: LMT, Inc.
William A. Jensen: NextEra Energy Point Beach
A Case Study of Phased Array UT Examination
in Lieu of Radiography
• Basic Concept
• Job Scope
• Point Beach Specifics
• Examination Equipment
• Planning Activities
• Implementation
• Lessons Learned/Conclusions
• Current Code & Utility Activities
Overview
Basic Concept
• In the Summer of 2008, while reviewing work scope for the
Unit 1 Extended Power Uprate (EPU) Project – Feedwater
Heater Replacement, the Point Beach Nuclear Plant (PBNP)
NDE Level III recognized that the Code used for the
installation of new Feedwater Piping would allow for the use
of Radiography or Ultrasonic examination (ASME B31.1,
2004 Edition)
• This appeared to present an opportunity to apply a high-
quality examination technology and save the site a sizable
amount of time/cost by reducing the impact of NDE on
other work groups.
ASME/ANSI B31.1 2004 Requirements
136.4.6 Ultrasonic Examination. When required by this Chapter (see Table
136.4), ultrasonic examination (UT) shall be performed in accordance with
Article 5 of
Section V of the ASME Boiler and Pressure Vessel Code and the following
additional requirements.
(A) The following criteria shall also be met when performing ultrasonic
examinations.
(A.l) The nominal thickness of the material being examined shall be greater
than ½ in. (13 mm).
(A.2) The equipment used to perform the examination shall be capable of
recording the UT data including the scanning positions. Where physical
obstructions prevent the use of systems capable of recording the UT data
including the scanning positions, manual UT may be used with the approval
of the Owner.
(A.3) NDE personnel collecting and analyzing UT data shall have
demonstrated their ability to perform an acceptable examination using
written procedures. The procedures shall have been demonstrated to yield
acceptable results when applied to a calibration block fabricated in
accordance with ASME Section V, Article 5, T-542.2.
Point Beach Specifics
• Located on Lake Michigan approximately 30 miles
southeast of Green Bay, Wisconsin.
• Two, two-loop Westinghouse pressurized water reactors
newly up-rated to approximately 624 MWe.
• Both units were scheduled for multiple outage EPU
activities, starting with Unit 1 in the Fall of 2008, then Unit
2 in the Fall of 2009 and the Spring of 2011, completing
with Unit 1 in the Fall of 2011.
• The EPU scope included replacing all 5 sets of Feedwater
Heaters, Main Feed Pumps and associated piping up to the
ASME Section XI boundary valve just outside containment.
The concept was originally brought forward due to the location of
the Unit 1 #4 and #5 Feedwater Heaters, radiography would
be extremely intrusive on the already tight outage schedule:
1. Heaters are within 40 feet of the entrance to the RCA.
2. Major foot-traffic routes traverse within 20-40 feet of the
area.
3. Similar issues existed on the Unit 2 side with the exception of
the RCA entrance.
Unit 1 - Location, Location, Location
Location of
Feedwater
Heaters
Entrance to RCA
General Layout of Unit 1 Turbine Building (26 ft)
Major Foot-
Traffic Routes
Open Above &
Below
Movement of a FW Heater To 26 ft. Elevation
Open space above (Turbine Deck)
Open space below
Impact of RT on the Outage
• Due to the thickness [>1.0 inch(2.54 cm)] and diameter
[16 and 18 inch (40.6 and 45.7 cm) NPS], there would be
at between 6 and 8 exposures per weld, at approximately
2-3 hours per weld. Co-60 would likely be used, thus
creating an exclusion zone which would cover portions of
all three elevations of the Unit 1 Turbine Building and a
portion of the Primary Auxiliary Building (PAB).
• The best estimated time for radiography (assuming no RP
holds, re-shots, etc.) was 5, 12-hour shifts.
Impact of RT on the Outage
• This would have likely stopped all work on the Low
Pressure Turbine overhaul (1 elevation above),
condenser work (adjacent and below), and all welding
associated with the FW Heater replacement.
• The Unit 1 & Unit 2 # 4 & 5 FW Heater Replacement
Projects were at or near Critical Path for much of the
outage without factoring in RT.
• RT would have caused a minute-for-minute delay in
essentially all FW Heater work as well as a number of
other projects in the vicinity.
Planning for UT
• Due to the way the first FW Heater Replacement was
planned, a construction vendor was responsible for the
turn-key installation.
• PBNP NDE personnel presented the idea of UT in lieu of
RT to NextEra / FPL EPU personnel and received initial
push-back due to issues with UT in lieu of RT at Seabrook
Station.
• After discussions with the Seabrook Level III, it was
obvious that UT was not the problem.
• In early August 2008, the PBNP Level III discussed the idea
with several vendors, including PBNP’s ISI vendor (LMT),
who agreed it was a great opportunity to use Phased
Array (PA-UT).
Planning for UT
• The PBNP Level III presented the information regarding
PA-UT and the advantages over RT to the construction
vendor site manager, and provided contact information
to LMT.
• EPU personnel received the recommendation and
recommended that the construction vendor contract
for UT in lieu of RT
• LMT received a contract from the installation vendor in
late August, which gave them only about five weeks to
prepare a technique, procure probes, develop a
procedure, etc.
Equipment Used
• LMT used the Zetec Omniscan® 32P-32 R PA system with
a custom-built hand scanner for data acquisition on the
complex geometries encountered during the
replacement. This would be upgraded to an automated
scanner in later outages.
• GE IT 2-D Matrix-Array probes with a nominal frequency
of 3.5 MHz.
• UltraVision® Software was used for analysis.
Equipment Used
UltraVision Ultrasonic Data Analysis Software
Features:
 Allows Analyst to Manipulate UT Data in multiple scenarios
to assist with flaw detection and characterization
 Data Analysis in multiple planes (3-D)
 Analysis of Merged Ultrasonic Data along with Raw
Ultrasonic Data
 Portability of Analysis workstation (Laptop PC) allows for in
field analysis
 Permanent digital record of examination results
Encoded PAUT Analysis Advantages
UltraVision Ultrasonic Data Analysis Software
3- Plane Data Analysis
 Flaw location can be visualized in Top, Side, and End views
 Hard copy of examination results available in all three planes
 Permits easy and precise mapping for detected defect removal
Top View (C-scan) very similar to RT results- flaw is
only recognized in one plane
UltraVision Ultrasonic Data Analysis Software
Side View (B-scan) not available with RT. Flaw
depth within
volume is an added dimension
UltraVision Ultrasonic Data Analysis Software
End View (D-scan) not available with RT.
Flaw location within volume is another added
dimension
UltraVision Ultrasonic Data Analysis Software
Demonstration Mockup
The following slides illustrate the results obtained on a Mock-up
with “manufactured” embedded fabrication flaws.
Mock-up specifics:
 16 in. (40.64 cm) SCH 100 (1.031 in. / 2.62 cm) A106 GrB Carbon Steel-
Narrow groove configuration
Mock-up Specifics
 13 Typical welding flaws
 Flaw placement spread throughout weld volume
 Flaw height for planar flaws typical for weld process
employed (SMAW)
 Several of the flaw lengths at ASME B31.1 threshold for
Accept/Reject
Mockup Flaws #1-7
Mockup Flaws #8-13
Mockup Flaw #1- Sidewall Lack of Fusion
Mockup Flaw #2- Slag Inclusion
Mockup Flaw #3- Sidewall Lack of Fusion
Mockup Flaw #4- Slag Inclusion
Mockup Flaw #5- Sidewall Lack of Fusion
Mockup Flaw #6- Slag Inclusion
Mockup Flaw #7- Cluster Porosity
Mockup Flaw #8- ID Root Crack
Mockup Flaw #9- OD Centerline Crack
Mockup Flaw #10- Lack of Penetration
Mockup Flaw #11- OD Connected Lack of
Fusion
Mockup Flaw #12- Internal Crack
Mockup Flaw #13- Start/Stop Lack of Fusion
(Axial)
First Implementation – U1R31 (Fall 2008)
• LMT and PBNP worked together to put a procedure
into the PBNP NDE format to ease approval and
any future changes.
• Rev. 0 of NDE-142, “Fully Encoded Phased Array
Ultrasonic Examination of Ferritic Piping Welds”
was issued on October 10, 2008.
• PA-UT of pre-fabrication welds commenced the
same day.
• After finding minor glitches in the procedure, Rev. 1
was issued on Oct. 24, with no delays in on-going
pre-fabrication work.
First Implementation – U1R31 (Fall 2008)
• Approximately forty (40) welds were examined
using a combination of semi-automated UT and
manual “pick-ups”.
• Zero welds were rejected by PA-UT
• An estimated $2.5 million in “lost” outage time was
saved from the use of PA-UT in lieu of RT.
First Implementation – U1R31 (Fall 2008)
Typical Completed Weld
First Implementation – U1R31 (Fall 2008)
Typical Completed Weld
Typical Work Environment
Typical Work Environment
Second Implementation – U2R30 (Fall 2009)
• Due to the change in installation vendors, a similar
series of discussions between PBNP and the
vendor ensued regarding the use of PA-UT in lieu
of RT.
• The installation vendor’s NDE staff liked the idea of
PA-UT but were hesitant about the use of PBNP’s
vendor of choice (LMT).
• This concern was worked through & the work went
very smoothly.
• One weld out of approximately 35 required repairs
due to an lack of fusion and multiple inclusions.
Second Implementation – U2R30 (Fall 2009)
Sidewall Lack of Fusion detected in a 16 in. (40.6 cm) Schd.
100 Carbon Steel field weld
• It should be noted that this particular weld was in a
very unfavorable location for the welder.
Second Implementation – U2R30 (Fall 2009)
Dye Penetrant examination results after weld removal
Third Implementation – U2R31 (Spring 2011)
• PBNP management had been convinced of the use
of PA-UT in lieu of RT was worth what appeared on
paper initially to be additional expense.
• This outage had approximately 35 welds & included
several welds in the façade area (unheated building
around the containment) due to temperatures
dipping to 10°F -15°F (-9° to -12°C) at night.
• The automated scanner with a water delivery
system was fully implemented during this outage
will great success.
• Although the overall outage was delayed due to
piping installation issues, there were zero rejects.
Final Implementation – U1R33 (Fall 2011)
• The work scope was essentially identical to the Unit
2 work in the Spring.
• This outage again included several welds in the
façade area, however the temperatures were much
warmer than in the Spring.
• The final weld exam was completed on November
25th, 2011 (the day after Thanksgiving)
• PA-UT again had zero rejects.
The Automated Scanner With H2O Delivery
System
The Welds
• ASME Task Group – Alternative NDE for Repair,
Replacement and Modification Activities (TG – Alt
NDE) met in Nashville on May 15, 2012.
• NRC report “UT in Lieu of RT Program Status for TG
Alt NDE” is out to committee members for comment
• Report provides information on a project currently
in progress to compare the effectiveness of UT
techniques and RT techniques in the detection of
fabrication flaws in ferritic piping samples;
• The NRC acknowledges that UT has great
potential to be used in lieu of RT for RRA and,
eventually, for new construction examinations.
Current Code Activities
• EPRI presented a draft of a proposed new Code
Case (not a revision to N-713).
• Code Case will provide rules substituting UT for
RT when repairs or replacements involve welds in
ferritic piping;
• Code Case will provide rules substituting UT for
RT when repairs or replacements involve welds
in ferritic piping;
• Proposed Code Case limits alternative to ferritic
piping welds only;
• Not enough data on austenitic piping welds to
support technical basis at this time.
Current Code Activities
• Key open topics remaining in the effort to complete
this Code Case include:
• Acceptance criteria:
• ASME Section III
• ASME Section XI
• RMS tolerance values during performance
demonstration
• Length sizing [0.75 in (19 mm)]
• Through-wall sizing [0.125 in. (3 mm)]
Current Code Activities
Areas that worked:
• The use of the ISI vendor for this work meant that the
vast majority of personnel had previously worked at
PBNP and were familiar with site processes.
• Use of a site-specific procedure allowed for relatively
quick processing of changes.
• Up-front involvement of the Authorized Inspector kept
questions during examinations to a minimum.
Conclusions
Areas that worked:
• Site NDE personnel were involved throughout the
process, which allowed a level of trust to be built with
the EPU organization during non-outage times. This
helped immensely when questions arose during
actual implementation.
• LMT provided basic training and a computer to the
site NDE Level III for data review which kept the AI
from bothering LMT data analysts as much.
Conclusions
Areas for improvement:
• Originally, LMT worked under contract to the
installation vendors, this was found to be very
cumbersome.
• At times, the installation vendor would report welds
as “waiting on NDE” to the EPU Team Room prior to
telling NDE they were ready.
Conclusions (Cont.)
Areas for improvement:
• EPU personnel determined mid-way through an
outage that they wanted 24/7 coverage based on the
installation vendor’s complaints. This caused LMT to
jump through hoops to get qualified personnel on site
quickly. This could have been averted by the
installation vendor providing feedback to PBNP NDE
/ LMT early in the outage.
Conclusions (Cont.)
Thank You for Your Attention

More Related Content

What's hot

Phased Array Ultrasonic Testing Presentation
Phased Array Ultrasonic Testing PresentationPhased Array Ultrasonic Testing Presentation
Phased Array Ultrasonic Testing Presentation
Connor Marshman
 
Phased array & tofd
Phased array & tofdPhased array & tofd
Phased array & tofd
Jagan Durga
 
Phased Array Scan Planning and Modeling for Weld inspection
Phased Array Scan Planning and Modeling for Weld inspectionPhased Array Scan Planning and Modeling for Weld inspection
Phased Array Scan Planning and Modeling for Weld inspection
Olympus IMS
 
Diverse Uses of Advanced Ultrasonic Inspection Technologies for Pipeline
Diverse Uses of Advanced Ultrasonic Inspection Technologies for Pipeline Diverse Uses of Advanced Ultrasonic Inspection Technologies for Pipeline
Diverse Uses of Advanced Ultrasonic Inspection Technologies for Pipeline
Olympus IMS
 
Paut full notes
Paut  full notesPaut  full notes
Paut full notes
indukuri sraju
 
TOFD PRO System
TOFD PRO SystemTOFD PRO System
TOFD PRO System
Svitlana Priannikova
 
Introduction to Phased Array Using the OmniScan MX2 - Part Two
Introduction to Phased Array Using the OmniScan MX2 - Part TwoIntroduction to Phased Array Using the OmniScan MX2 - Part Two
Introduction to Phased Array Using the OmniScan MX2 - Part Two
Olympus IMS
 
ULTRASONIC TESTING (UT) & ACOUSTIC EMISSION (AE)
ULTRASONIC TESTING (UT)  &  ACOUSTIC EMISSION (AE)ULTRASONIC TESTING (UT)  &  ACOUSTIC EMISSION (AE)
ULTRASONIC TESTING (UT) & ACOUSTIC EMISSION (AE)
laxtwinsme
 
Pipe wizard olympus
Pipe wizard olympusPipe wizard olympus
Pipe wizard olympus
Sungsoo Han
 
Advanced Probes for Austenitic and CRA Weld Inspection Webinar
Advanced Probes for Austenitic and CRA Weld Inspection WebinarAdvanced Probes for Austenitic and CRA Weld Inspection Webinar
Advanced Probes for Austenitic and CRA Weld Inspection Webinar
Olympus IMS
 
criteria of weld defects
criteria of weld defects criteria of weld defects
criteria of weld defects
Saqib Rasool
 
Muravin - Understanding ASNT snt-tc-1a - acoustic emission traning series
Muravin - Understanding ASNT snt-tc-1a - acoustic emission traning seriesMuravin - Understanding ASNT snt-tc-1a - acoustic emission traning series
Muravin - Understanding ASNT snt-tc-1a - acoustic emission traning series
mboria
 
NDT presentation
NDT presentationNDT presentation
NDT presentation
Manish Meena
 
ASTM Standard Practice for Ultrasonic Testing of Wrought Products.pdf
ASTM Standard Practice for Ultrasonic Testing of Wrought Products.pdfASTM Standard Practice for Ultrasonic Testing of Wrought Products.pdf
ASTM Standard Practice for Ultrasonic Testing of Wrought Products.pdf
mahmoodkhan77
 
Improved Inspection of Composite Wind Turbine Blades with Accessible, Advanc...
Improved Inspection of Composite Wind Turbine Blades with Accessible, Advanc...Improved Inspection of Composite Wind Turbine Blades with Accessible, Advanc...
Improved Inspection of Composite Wind Turbine Blades with Accessible, Advanc...
Olympus IMS
 
Long range ultrasonic testing by kevin ukueku
Long range ultrasonic testing by kevin ukuekuLong range ultrasonic testing by kevin ukueku
Long range ultrasonic testing by kevin ukuekuKevnuk
 
Overview: Principles of Full Matrix Capture (FMC) and Total Focusing Method (...
Overview: Principles of Full Matrix Capture (FMC) and Total Focusing Method (...Overview: Principles of Full Matrix Capture (FMC) and Total Focusing Method (...
Overview: Principles of Full Matrix Capture (FMC) and Total Focusing Method (...
Zetec Inc.
 
Ultrasonic Testing (UT)- NDT
Ultrasonic Testing (UT)- NDTUltrasonic Testing (UT)- NDT
Ultrasonic Testing (UT)- NDT
Sukesh O P
 

What's hot (20)

Phased Array Ultrasonic Testing Presentation
Phased Array Ultrasonic Testing PresentationPhased Array Ultrasonic Testing Presentation
Phased Array Ultrasonic Testing Presentation
 
Phased array & tofd
Phased array & tofdPhased array & tofd
Phased array & tofd
 
Phased Array Scan Planning and Modeling for Weld inspection
Phased Array Scan Planning and Modeling for Weld inspectionPhased Array Scan Planning and Modeling for Weld inspection
Phased Array Scan Planning and Modeling for Weld inspection
 
Diverse Uses of Advanced Ultrasonic Inspection Technologies for Pipeline
Diverse Uses of Advanced Ultrasonic Inspection Technologies for Pipeline Diverse Uses of Advanced Ultrasonic Inspection Technologies for Pipeline
Diverse Uses of Advanced Ultrasonic Inspection Technologies for Pipeline
 
Paut full notes
Paut  full notesPaut  full notes
Paut full notes
 
TOFD PRO System
TOFD PRO SystemTOFD PRO System
TOFD PRO System
 
Introduction to Phased Array Using the OmniScan MX2 - Part Two
Introduction to Phased Array Using the OmniScan MX2 - Part TwoIntroduction to Phased Array Using the OmniScan MX2 - Part Two
Introduction to Phased Array Using the OmniScan MX2 - Part Two
 
ULTRASONIC TESTING (UT) & ACOUSTIC EMISSION (AE)
ULTRASONIC TESTING (UT)  &  ACOUSTIC EMISSION (AE)ULTRASONIC TESTING (UT)  &  ACOUSTIC EMISSION (AE)
ULTRASONIC TESTING (UT) & ACOUSTIC EMISSION (AE)
 
Pipe wizard olympus
Pipe wizard olympusPipe wizard olympus
Pipe wizard olympus
 
Advanced Probes for Austenitic and CRA Weld Inspection Webinar
Advanced Probes for Austenitic and CRA Weld Inspection WebinarAdvanced Probes for Austenitic and CRA Weld Inspection Webinar
Advanced Probes for Austenitic and CRA Weld Inspection Webinar
 
criteria of weld defects
criteria of weld defects criteria of weld defects
criteria of weld defects
 
Muravin - Understanding ASNT snt-tc-1a - acoustic emission traning series
Muravin - Understanding ASNT snt-tc-1a - acoustic emission traning seriesMuravin - Understanding ASNT snt-tc-1a - acoustic emission traning series
Muravin - Understanding ASNT snt-tc-1a - acoustic emission traning series
 
Ultrasonics aws
Ultrasonics awsUltrasonics aws
Ultrasonics aws
 
NDT presentation
NDT presentationNDT presentation
NDT presentation
 
ASTM Standard Practice for Ultrasonic Testing of Wrought Products.pdf
ASTM Standard Practice for Ultrasonic Testing of Wrought Products.pdfASTM Standard Practice for Ultrasonic Testing of Wrought Products.pdf
ASTM Standard Practice for Ultrasonic Testing of Wrought Products.pdf
 
236135365 heat-treatment-manual
236135365 heat-treatment-manual236135365 heat-treatment-manual
236135365 heat-treatment-manual
 
Improved Inspection of Composite Wind Turbine Blades with Accessible, Advanc...
Improved Inspection of Composite Wind Turbine Blades with Accessible, Advanc...Improved Inspection of Composite Wind Turbine Blades with Accessible, Advanc...
Improved Inspection of Composite Wind Turbine Blades with Accessible, Advanc...
 
Long range ultrasonic testing by kevin ukueku
Long range ultrasonic testing by kevin ukuekuLong range ultrasonic testing by kevin ukueku
Long range ultrasonic testing by kevin ukueku
 
Overview: Principles of Full Matrix Capture (FMC) and Total Focusing Method (...
Overview: Principles of Full Matrix Capture (FMC) and Total Focusing Method (...Overview: Principles of Full Matrix Capture (FMC) and Total Focusing Method (...
Overview: Principles of Full Matrix Capture (FMC) and Total Focusing Method (...
 
Ultrasonic Testing (UT)- NDT
Ultrasonic Testing (UT)- NDTUltrasonic Testing (UT)- NDT
Ultrasonic Testing (UT)- NDT
 

Similar to Case Study of Phased Array UT for B31.1 Piping

An Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara SeaAn Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara SeaAli Osman Öncel
 
Ml101610106
Ml101610106Ml101610106
Seimic Qualification of Transformers - Pradeep ProSIM
Seimic Qualification of Transformers - Pradeep ProSIMSeimic Qualification of Transformers - Pradeep ProSIM
Seimic Qualification of Transformers - Pradeep ProSIM
ProSIM R & D Pvt. Ltd.
 
Presentation 1
Presentation 1Presentation 1
Introduction to NDE automation1.pdf
Introduction to NDE automation1.pdfIntroduction to NDE automation1.pdf
Introduction to NDE automation1.pdf
Yung how Wu
 
Lessons Learned from the Licensing of Fermi 3 Nuclear Power Plant
Lessons Learned from the Licensing of Fermi 3 Nuclear Power PlantLessons Learned from the Licensing of Fermi 3 Nuclear Power Plant
Lessons Learned from the Licensing of Fermi 3 Nuclear Power Plant
Brock Palen
 
Roxtec BG Applications
Roxtec BG ApplicationsRoxtec BG Applications
Roxtec BG Applications
Roxtec Brasil
 
Asce 7 10 presentation on seismic bracing for mep systems
Asce 7 10 presentation on seismic bracing for mep systemsAsce 7 10 presentation on seismic bracing for mep systems
Asce 7 10 presentation on seismic bracing for mep systems
michaeljmack
 
Oil pipiline stress monitoring
Oil pipiline  stress monitoringOil pipiline  stress monitoring
Oil pipiline stress monitoring
Juan David Betancur
 
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs) Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Audubon Engineering Company
 
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser Projects
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser ProjectsISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser Projects
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser ProjectsJean-Francois Saint-Marcoux
 
EMCLO PROJECT: EMC DESIGN METHODOLOGY FOR LAYOUT OPTIMIZATION
EMCLO PROJECT: EMC DESIGN METHODOLOGY FOR LAYOUT OPTIMIZATIONEMCLO PROJECT: EMC DESIGN METHODOLOGY FOR LAYOUT OPTIMIZATION
EMCLO PROJECT: EMC DESIGN METHODOLOGY FOR LAYOUT OPTIMIZATION
Piero Belforte
 
AFS Pipeline Compliance, Integrity & Corrosion
AFS Pipeline Compliance, Integrity & Corrosion  AFS Pipeline Compliance, Integrity & Corrosion
AFS Pipeline Compliance, Integrity & Corrosion
Audubon Engineering Company
 
Advances in EM Simulations
Advances in EM SimulationsAdvances in EM Simulations
Advances in EM SimulationsAltair
 
ASME Section VIII Div 1. design training
ASME Section VIII Div 1.  design trainingASME Section VIII Div 1.  design training
ASME Section VIII Div 1. design training
Sam Jose
 
Asme sec viii div 1 icb
Asme sec viii div 1 icbAsme sec viii div 1 icb
Asme sec viii div 1 icb
Praj Industries Ltd.
 
MIL-STD-461G - Filosofia
MIL-STD-461G - FilosofiaMIL-STD-461G - Filosofia
MIL-STD-461G - Filosofia
Alessandro Corniani
 
Lessons Learned of AC Arc Flash Studies for Station Auxiliary Service Systems
Lessons Learned of AC Arc Flash Studies for Station Auxiliary Service SystemsLessons Learned of AC Arc Flash Studies for Station Auxiliary Service Systems
Lessons Learned of AC Arc Flash Studies for Station Auxiliary Service Systems
Power System Operation
 

Similar to Case Study of Phased Array UT for B31.1 Piping (20)

An Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara SeaAn Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara Sea
 
Ml101610106
Ml101610106Ml101610106
Ml101610106
 
Seimic Qualification of Transformers - Pradeep ProSIM
Seimic Qualification of Transformers - Pradeep ProSIMSeimic Qualification of Transformers - Pradeep ProSIM
Seimic Qualification of Transformers - Pradeep ProSIM
 
Keepintouch2008_v3
Keepintouch2008_v3Keepintouch2008_v3
Keepintouch2008_v3
 
Presentation 1
Presentation 1Presentation 1
Presentation 1
 
Introduction to NDE automation1.pdf
Introduction to NDE automation1.pdfIntroduction to NDE automation1.pdf
Introduction to NDE automation1.pdf
 
Lessons Learned from the Licensing of Fermi 3 Nuclear Power Plant
Lessons Learned from the Licensing of Fermi 3 Nuclear Power PlantLessons Learned from the Licensing of Fermi 3 Nuclear Power Plant
Lessons Learned from the Licensing of Fermi 3 Nuclear Power Plant
 
Roxtec BG Applications
Roxtec BG ApplicationsRoxtec BG Applications
Roxtec BG Applications
 
Asce 7 10 presentation on seismic bracing for mep systems
Asce 7 10 presentation on seismic bracing for mep systemsAsce 7 10 presentation on seismic bracing for mep systems
Asce 7 10 presentation on seismic bracing for mep systems
 
Pipininspect
PipininspectPipininspect
Pipininspect
 
Oil pipiline stress monitoring
Oil pipiline  stress monitoringOil pipiline  stress monitoring
Oil pipiline stress monitoring
 
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs) Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
 
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser Projects
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser ProjectsISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser Projects
ISOPE-2010-TCP-0462 Lessons Learnt from deepwater Riser Projects
 
EMCLO PROJECT: EMC DESIGN METHODOLOGY FOR LAYOUT OPTIMIZATION
EMCLO PROJECT: EMC DESIGN METHODOLOGY FOR LAYOUT OPTIMIZATIONEMCLO PROJECT: EMC DESIGN METHODOLOGY FOR LAYOUT OPTIMIZATION
EMCLO PROJECT: EMC DESIGN METHODOLOGY FOR LAYOUT OPTIMIZATION
 
AFS Pipeline Compliance, Integrity & Corrosion
AFS Pipeline Compliance, Integrity & Corrosion  AFS Pipeline Compliance, Integrity & Corrosion
AFS Pipeline Compliance, Integrity & Corrosion
 
Advances in EM Simulations
Advances in EM SimulationsAdvances in EM Simulations
Advances in EM Simulations
 
ASME Section VIII Div 1. design training
ASME Section VIII Div 1.  design trainingASME Section VIII Div 1.  design training
ASME Section VIII Div 1. design training
 
Asme sec viii div 1 icb
Asme sec viii div 1 icbAsme sec viii div 1 icb
Asme sec viii div 1 icb
 
MIL-STD-461G - Filosofia
MIL-STD-461G - FilosofiaMIL-STD-461G - Filosofia
MIL-STD-461G - Filosofia
 
Lessons Learned of AC Arc Flash Studies for Station Auxiliary Service Systems
Lessons Learned of AC Arc Flash Studies for Station Auxiliary Service SystemsLessons Learned of AC Arc Flash Studies for Station Auxiliary Service Systems
Lessons Learned of AC Arc Flash Studies for Station Auxiliary Service Systems
 

Recently uploaded

Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
BookNet Canada
 
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
James Anderson
 
Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........
Alison B. Lowndes
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
RTTS
 
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
Sri Ambati
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
Jemma Hussein Allen
 
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Tobias Schneck
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Jeffrey Haguewood
 
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdfFIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
Product School
 
Essentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with ParametersEssentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with Parameters
Safe Software
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Product School
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
DianaGray10
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance
 
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdfFIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
OnBoard
 
Key Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfKey Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdf
Cheryl Hung
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
DianaGray10
 
How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...
Product School
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
Product School
 

Recently uploaded (20)

Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
 
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
 
Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
 
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
 
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
 
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdfFIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
 
Essentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with ParametersEssentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with Parameters
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
 
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdfFIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
 
Key Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfKey Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdf
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
 
How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
 

Case Study of Phased Array UT for B31.1 Piping

  • 1. Todd Blechinger / Jeff Devers: LMT, Inc. William A. Jensen: NextEra Energy Point Beach A Case Study of Phased Array UT Examination in Lieu of Radiography
  • 2. • Basic Concept • Job Scope • Point Beach Specifics • Examination Equipment • Planning Activities • Implementation • Lessons Learned/Conclusions • Current Code & Utility Activities Overview
  • 3. Basic Concept • In the Summer of 2008, while reviewing work scope for the Unit 1 Extended Power Uprate (EPU) Project – Feedwater Heater Replacement, the Point Beach Nuclear Plant (PBNP) NDE Level III recognized that the Code used for the installation of new Feedwater Piping would allow for the use of Radiography or Ultrasonic examination (ASME B31.1, 2004 Edition) • This appeared to present an opportunity to apply a high- quality examination technology and save the site a sizable amount of time/cost by reducing the impact of NDE on other work groups.
  • 4. ASME/ANSI B31.1 2004 Requirements 136.4.6 Ultrasonic Examination. When required by this Chapter (see Table 136.4), ultrasonic examination (UT) shall be performed in accordance with Article 5 of Section V of the ASME Boiler and Pressure Vessel Code and the following additional requirements. (A) The following criteria shall also be met when performing ultrasonic examinations. (A.l) The nominal thickness of the material being examined shall be greater than ½ in. (13 mm). (A.2) The equipment used to perform the examination shall be capable of recording the UT data including the scanning positions. Where physical obstructions prevent the use of systems capable of recording the UT data including the scanning positions, manual UT may be used with the approval of the Owner. (A.3) NDE personnel collecting and analyzing UT data shall have demonstrated their ability to perform an acceptable examination using written procedures. The procedures shall have been demonstrated to yield acceptable results when applied to a calibration block fabricated in accordance with ASME Section V, Article 5, T-542.2.
  • 5. Point Beach Specifics • Located on Lake Michigan approximately 30 miles southeast of Green Bay, Wisconsin. • Two, two-loop Westinghouse pressurized water reactors newly up-rated to approximately 624 MWe. • Both units were scheduled for multiple outage EPU activities, starting with Unit 1 in the Fall of 2008, then Unit 2 in the Fall of 2009 and the Spring of 2011, completing with Unit 1 in the Fall of 2011. • The EPU scope included replacing all 5 sets of Feedwater Heaters, Main Feed Pumps and associated piping up to the ASME Section XI boundary valve just outside containment.
  • 6. The concept was originally brought forward due to the location of the Unit 1 #4 and #5 Feedwater Heaters, radiography would be extremely intrusive on the already tight outage schedule: 1. Heaters are within 40 feet of the entrance to the RCA. 2. Major foot-traffic routes traverse within 20-40 feet of the area. 3. Similar issues existed on the Unit 2 side with the exception of the RCA entrance. Unit 1 - Location, Location, Location
  • 7. Location of Feedwater Heaters Entrance to RCA General Layout of Unit 1 Turbine Building (26 ft) Major Foot- Traffic Routes Open Above & Below
  • 8. Movement of a FW Heater To 26 ft. Elevation Open space above (Turbine Deck) Open space below
  • 9. Impact of RT on the Outage • Due to the thickness [>1.0 inch(2.54 cm)] and diameter [16 and 18 inch (40.6 and 45.7 cm) NPS], there would be at between 6 and 8 exposures per weld, at approximately 2-3 hours per weld. Co-60 would likely be used, thus creating an exclusion zone which would cover portions of all three elevations of the Unit 1 Turbine Building and a portion of the Primary Auxiliary Building (PAB). • The best estimated time for radiography (assuming no RP holds, re-shots, etc.) was 5, 12-hour shifts.
  • 10. Impact of RT on the Outage • This would have likely stopped all work on the Low Pressure Turbine overhaul (1 elevation above), condenser work (adjacent and below), and all welding associated with the FW Heater replacement. • The Unit 1 & Unit 2 # 4 & 5 FW Heater Replacement Projects were at or near Critical Path for much of the outage without factoring in RT. • RT would have caused a minute-for-minute delay in essentially all FW Heater work as well as a number of other projects in the vicinity.
  • 11. Planning for UT • Due to the way the first FW Heater Replacement was planned, a construction vendor was responsible for the turn-key installation. • PBNP NDE personnel presented the idea of UT in lieu of RT to NextEra / FPL EPU personnel and received initial push-back due to issues with UT in lieu of RT at Seabrook Station. • After discussions with the Seabrook Level III, it was obvious that UT was not the problem. • In early August 2008, the PBNP Level III discussed the idea with several vendors, including PBNP’s ISI vendor (LMT), who agreed it was a great opportunity to use Phased Array (PA-UT).
  • 12. Planning for UT • The PBNP Level III presented the information regarding PA-UT and the advantages over RT to the construction vendor site manager, and provided contact information to LMT. • EPU personnel received the recommendation and recommended that the construction vendor contract for UT in lieu of RT • LMT received a contract from the installation vendor in late August, which gave them only about five weeks to prepare a technique, procure probes, develop a procedure, etc.
  • 13. Equipment Used • LMT used the Zetec Omniscan® 32P-32 R PA system with a custom-built hand scanner for data acquisition on the complex geometries encountered during the replacement. This would be upgraded to an automated scanner in later outages. • GE IT 2-D Matrix-Array probes with a nominal frequency of 3.5 MHz. • UltraVision® Software was used for analysis.
  • 14. Equipment Used UltraVision Ultrasonic Data Analysis Software Features:  Allows Analyst to Manipulate UT Data in multiple scenarios to assist with flaw detection and characterization  Data Analysis in multiple planes (3-D)  Analysis of Merged Ultrasonic Data along with Raw Ultrasonic Data  Portability of Analysis workstation (Laptop PC) allows for in field analysis  Permanent digital record of examination results
  • 15. Encoded PAUT Analysis Advantages UltraVision Ultrasonic Data Analysis Software 3- Plane Data Analysis  Flaw location can be visualized in Top, Side, and End views  Hard copy of examination results available in all three planes  Permits easy and precise mapping for detected defect removal
  • 16. Top View (C-scan) very similar to RT results- flaw is only recognized in one plane UltraVision Ultrasonic Data Analysis Software
  • 17. Side View (B-scan) not available with RT. Flaw depth within volume is an added dimension UltraVision Ultrasonic Data Analysis Software
  • 18. End View (D-scan) not available with RT. Flaw location within volume is another added dimension UltraVision Ultrasonic Data Analysis Software
  • 19. Demonstration Mockup The following slides illustrate the results obtained on a Mock-up with “manufactured” embedded fabrication flaws. Mock-up specifics:  16 in. (40.64 cm) SCH 100 (1.031 in. / 2.62 cm) A106 GrB Carbon Steel- Narrow groove configuration
  • 20. Mock-up Specifics  13 Typical welding flaws  Flaw placement spread throughout weld volume  Flaw height for planar flaws typical for weld process employed (SMAW)  Several of the flaw lengths at ASME B31.1 threshold for Accept/Reject
  • 23. Mockup Flaw #1- Sidewall Lack of Fusion
  • 24. Mockup Flaw #2- Slag Inclusion
  • 25. Mockup Flaw #3- Sidewall Lack of Fusion
  • 26. Mockup Flaw #4- Slag Inclusion
  • 27. Mockup Flaw #5- Sidewall Lack of Fusion
  • 28. Mockup Flaw #6- Slag Inclusion
  • 29. Mockup Flaw #7- Cluster Porosity
  • 30. Mockup Flaw #8- ID Root Crack
  • 31. Mockup Flaw #9- OD Centerline Crack
  • 32. Mockup Flaw #10- Lack of Penetration
  • 33. Mockup Flaw #11- OD Connected Lack of Fusion
  • 34. Mockup Flaw #12- Internal Crack
  • 35. Mockup Flaw #13- Start/Stop Lack of Fusion (Axial)
  • 36. First Implementation – U1R31 (Fall 2008) • LMT and PBNP worked together to put a procedure into the PBNP NDE format to ease approval and any future changes. • Rev. 0 of NDE-142, “Fully Encoded Phased Array Ultrasonic Examination of Ferritic Piping Welds” was issued on October 10, 2008. • PA-UT of pre-fabrication welds commenced the same day. • After finding minor glitches in the procedure, Rev. 1 was issued on Oct. 24, with no delays in on-going pre-fabrication work.
  • 37. First Implementation – U1R31 (Fall 2008) • Approximately forty (40) welds were examined using a combination of semi-automated UT and manual “pick-ups”. • Zero welds were rejected by PA-UT • An estimated $2.5 million in “lost” outage time was saved from the use of PA-UT in lieu of RT.
  • 38. First Implementation – U1R31 (Fall 2008) Typical Completed Weld
  • 39. First Implementation – U1R31 (Fall 2008) Typical Completed Weld
  • 42. Second Implementation – U2R30 (Fall 2009) • Due to the change in installation vendors, a similar series of discussions between PBNP and the vendor ensued regarding the use of PA-UT in lieu of RT. • The installation vendor’s NDE staff liked the idea of PA-UT but were hesitant about the use of PBNP’s vendor of choice (LMT). • This concern was worked through & the work went very smoothly. • One weld out of approximately 35 required repairs due to an lack of fusion and multiple inclusions.
  • 43. Second Implementation – U2R30 (Fall 2009) Sidewall Lack of Fusion detected in a 16 in. (40.6 cm) Schd. 100 Carbon Steel field weld • It should be noted that this particular weld was in a very unfavorable location for the welder.
  • 44. Second Implementation – U2R30 (Fall 2009) Dye Penetrant examination results after weld removal
  • 45. Third Implementation – U2R31 (Spring 2011) • PBNP management had been convinced of the use of PA-UT in lieu of RT was worth what appeared on paper initially to be additional expense. • This outage had approximately 35 welds & included several welds in the façade area (unheated building around the containment) due to temperatures dipping to 10°F -15°F (-9° to -12°C) at night. • The automated scanner with a water delivery system was fully implemented during this outage will great success. • Although the overall outage was delayed due to piping installation issues, there were zero rejects.
  • 46. Final Implementation – U1R33 (Fall 2011) • The work scope was essentially identical to the Unit 2 work in the Spring. • This outage again included several welds in the façade area, however the temperatures were much warmer than in the Spring. • The final weld exam was completed on November 25th, 2011 (the day after Thanksgiving) • PA-UT again had zero rejects.
  • 47. The Automated Scanner With H2O Delivery System
  • 49. • ASME Task Group – Alternative NDE for Repair, Replacement and Modification Activities (TG – Alt NDE) met in Nashville on May 15, 2012. • NRC report “UT in Lieu of RT Program Status for TG Alt NDE” is out to committee members for comment • Report provides information on a project currently in progress to compare the effectiveness of UT techniques and RT techniques in the detection of fabrication flaws in ferritic piping samples; • The NRC acknowledges that UT has great potential to be used in lieu of RT for RRA and, eventually, for new construction examinations. Current Code Activities
  • 50. • EPRI presented a draft of a proposed new Code Case (not a revision to N-713). • Code Case will provide rules substituting UT for RT when repairs or replacements involve welds in ferritic piping; • Code Case will provide rules substituting UT for RT when repairs or replacements involve welds in ferritic piping; • Proposed Code Case limits alternative to ferritic piping welds only; • Not enough data on austenitic piping welds to support technical basis at this time. Current Code Activities
  • 51. • Key open topics remaining in the effort to complete this Code Case include: • Acceptance criteria: • ASME Section III • ASME Section XI • RMS tolerance values during performance demonstration • Length sizing [0.75 in (19 mm)] • Through-wall sizing [0.125 in. (3 mm)] Current Code Activities
  • 52. Areas that worked: • The use of the ISI vendor for this work meant that the vast majority of personnel had previously worked at PBNP and were familiar with site processes. • Use of a site-specific procedure allowed for relatively quick processing of changes. • Up-front involvement of the Authorized Inspector kept questions during examinations to a minimum. Conclusions
  • 53. Areas that worked: • Site NDE personnel were involved throughout the process, which allowed a level of trust to be built with the EPU organization during non-outage times. This helped immensely when questions arose during actual implementation. • LMT provided basic training and a computer to the site NDE Level III for data review which kept the AI from bothering LMT data analysts as much. Conclusions
  • 54. Areas for improvement: • Originally, LMT worked under contract to the installation vendors, this was found to be very cumbersome. • At times, the installation vendor would report welds as “waiting on NDE” to the EPU Team Room prior to telling NDE they were ready. Conclusions (Cont.)
  • 55. Areas for improvement: • EPU personnel determined mid-way through an outage that they wanted 24/7 coverage based on the installation vendor’s complaints. This caused LMT to jump through hoops to get qualified personnel on site quickly. This could have been averted by the installation vendor providing feedback to PBNP NDE / LMT early in the outage. Conclusions (Cont.)
  • 56. Thank You for Your Attention