BIM Show Live 2015. Man City Stadium Construction – from Design to mass Fabrication– Using custom BIM tools to maximise the efficiency of the production of a Stadium Seating Bowl by Populous
Class Project for PM class, Scenario Based Presentation. This presentation has some details based on a question. Overall it gives an idea about critical path of a project . I will soon post the question for more clarity . Many thanks for your time.
presentation gives data on "how Modeling procedure and Case study of ‘Gocheok Sky Dome’ was done" and how mathematics and finite elemental analysis are useful for as a part of analysis of stresses strain,wind loading..ect.
Stadium Design and Reference Guide with Meru Networks WLANKevin Coppins
Balancing the fan experience with the business of stadium management. Properly designing for device density & diversity, application complexity & criticality as well RF.
Class Project for PM class, Scenario Based Presentation. This presentation has some details based on a question. Overall it gives an idea about critical path of a project . I will soon post the question for more clarity . Many thanks for your time.
presentation gives data on "how Modeling procedure and Case study of ‘Gocheok Sky Dome’ was done" and how mathematics and finite elemental analysis are useful for as a part of analysis of stresses strain,wind loading..ect.
Stadium Design and Reference Guide with Meru Networks WLANKevin Coppins
Balancing the fan experience with the business of stadium management. Properly designing for device density & diversity, application complexity & criticality as well RF.
BIM Show Live 2015: The challenges and the wins of Information Management on...BuiltEnvironmentUBM
BIM Show Live 2015 presentation by Antonio Torres, Robin Gomez, James Martin, Andrew Bell
Register for the next BIM Show Live http://www.bimshowlive.co.uk/
BIM Show Live 2015 presentation from Andrew Turner, Jonathan Munkley, Marina Machado, David Miller, Duncan Reed.
Register for the next BIM Show Live http://www.bimshowlive.co.uk/
65. C90
C75
C90, 800mm Rows 4/5 Row cantilever
Upper Tier
C75, 800mm Rows 8 Row cantilever
Mid Tier
C90, 780mm Rows
Lower Tier
C90
C90 Diagram showing C value
90 mm = C90
B
66. ADDITIONAL FEATURES
• 2 /3 NEW ROWS
• 1,355 ADDITIONAL SEATS
• NEW WHEELCHAIR SUPERRISER
• NEW AWAY FAN SEGREGATION
• AISLE WIDENING TO ACCOMODATE LARGER CONCERT CAPACITY
67. ADDITIONAL FEATURES
• NEW LEGENDS LOUNGE CORPORATE OFFER
• 661 ADDITIONAL SEATS
• NEW WHEELCHAIR & COMPANION LOCATIONS
• NEW AWAY FAN SEGREGATION
68. NEW FEATURES
• NEW SOUTH UPPER STAND
• NEW EXTENSION TO THE EAST AND WEST STANDS
• ADDITIONAL 6,805 SEATS
• NEW AWAY FAN SEGREGATION
69.
70. PROPOSED NEW STADIUM FOOTPRINT:
L01 LOWER CONCOURSE 2,171m2
L02 CLUB EVEL 3,271m2
L03 BOX LEVEL 2,017m2
L04 UPPER CONCOURSE 2,904m2
L05 PLANT LEVEL 1,338m2