SlideShare a Scribd company logo
26 NOVEMBER
2019
Banqiao
Dam
Presented By
(702,709,718,723 & 724)
2
Construction of the Banqiao dam began in April 1951
on the Ru River.
The help of Soviet consultants as part of a project to
control flooding and provide electrical power
generation.
The construction was a response to severe flooding in
the Hua River Basin in 1949 and 1950.
The dam was completed in June 1952.
Because of the absence of hydrology data the design
standard was lower than usual.
After the 1954 Huai River great flood, the upstream
reservoirs including Banqiao were extended,
constructed, and consolidated. Banqiao Dam was
increased in height by three meters.
History of Banqiao Dam
3
The dam crest level was 116.34
meters above sea level and the crest
level of the wave protection wall was
117.64 meters above sea level.
The total capacity of the reservoir
was 492 million m3 (398,000-acre
feet), with 375 million m3 (304,000-
acre feet) reserved for flood storage.
The dam was made of clay and was
24.5 meters high. The maximum
discharge of the reservoir was 1742
m3/s.
Banqiao Dam
4
Cracks in the dam and sluice
gates appeared after completion due to
construction and engineering errors.
They were repaired with the advice
from Soviet engineers and the new design,
dubbed the iron dam, was considered
unbreakable.
Chen Xing one of China's
foremost hydrologists was involved in the
design of the dam but he was also a vocal
critic of the government's dam building
policy which involved many dams in the
basin.
Banqiao Dam
5
He had recommended 12 sluice gates for the Banqiao Dam, but
this was criticized as being excessive and the number was
reduced to five.
Other dams in the project, including the Shimantan Dam, had a
similar reduction of safety features and Chen was removed from
the project.
In 1961, after problems with the water system were revealed, he
was brought back to help.
Chen continued to be an outspoken critic of the system and was
again removed from the project.
Banqiao Dam
Abstract
During 4–8 August 1975, an extreme
storm occurred in Henan Province,
China. The maximum 5-day rainfall
reached a record of 1,631 mm.
Two large dams (Banqiao Dam and
Shimandan Dam) two medium dams
(Tiangang Dam and Zhugou Dam) and
58 small dams failed from overtopping
in the storm event.
6
7
The breach peak flow rate was as high as 78,100 m3/s from the
Banqiao reservoir and 30,000 m3/s from the Shimantan reservoir.
The breaching of these dams caused an inundated area of 12,000
km2, a death toll of over 26,000, and economic loss of more than
RMB10 billion.
This paper introduces 26 dam failures in a smaller region of
Zhumadian, i.e., Banqiao Dam, Zhugou Dam, and 24 small dams.
The catastrophic event is described in detail especially for Banqiao
Dam and Zhugou Dam.
The causes and mechanisms of the principal failures are discussed,
as well as the influence of an upstream dam failure on the
downstream dams.
Lessons from the catastrophe are discussed.
Continue…
8
Reasons of the
Banqiao Dam Failure
Understanding
In August of 1975, typhoon Nina
pelted the region with the heaviest
rains ever recorded in the area.
More than a year’s worth of water
fell in 24 hours. The previous record
was 800 mm (31.5”) of rain, and the
stalled typhoon Nina dropped a new
record of 1060 mm (41.73”).
9
10
The rainfall caused massive downstream
flooding and, because of the flooded
downstream areas, one request to open the
dam was rejected on August 6.
On August 7, the request to open the dam
was accepted but this information did not
reach the dam, as the storm had brought
down the telegraph wires.
The under-designed sluice gates were unable
to handle the water volume and the first dam
failure warning was sent.
The water crested on August 8 at 0.3 meter
(0.0984’) higher than the protection wall on
the dam, which failed. 62 other dams in the
Huai river basin also failed.
Reasons of the Banqiao Dam
Failure
11
The Banqiao Dam failure caused a huge wave, 10 kilometers
(6.2 miles) wide and 3-7 meters (9.8-23ft) high to rush
downstream at 50 kilometers per hour (31 mph), inundating the
lower area with speeding floodwaters.
Approximately 26,000 people died from flooding and another
145,000 died afterward as a result of epidemics and famine.
Some 5,960,000 buildings collapsed, and 11 million residents
were affected.
Unofficial estimates of the number of people killed by the
disaster have run as high as 230,000 people.
Reasons of the Banqiao Dam
Failure
12
Environmental Impacts
Visible:
Floods (river, coastal, mudflow), Large-scale disturbance of hydro and
geological systems, Reduced ecological / hydrological connectivity
Environmental impacts
Dam failure
Health Impacts
Visible:
Accidents, Exposure to unknown or uncertain complex risks (radiation,
etc…), Deaths
Impacts of Banqiao dam failure:
13
Health impacts
The largest dam failure ever, over two hundred thousand deaths.
Socio-economical Impacts
Visible:
Displacement, Loss of livelihood, Specific impacts on women, Violations of
human rights, Land dispossession, Loss of landscape/sense of place.
Impacts of Banqiao dam failure:
14
Within eleven years of the dam failure, the
lower reach of the River Ru Zhumadian City,
experienced several more disastrous floods.
After many feasibility studies, the new
Banqiao Reservoir reconstruction was listed
as a key national project of The Seventh
Five-Year Plan of China.
The project owner was Huai River Water
Resources Commission.
The construction contractor was Changjiang
Gezhouba Engineering Bureau.
Reconstruction
15
By the end of 1986, the rebuilding project
commenced. On June 5, 1993, the project
was certified by the Chinese government.
The reconstructed Banqiao Reservoir
controls a catchment area of 768 km2.
The maximum reserve capacity is
675 million m3 (178 billion gallons), a
capacity increase of 34% above the
capacity of the failed dam.
The effective storage is
256 million m3 (67.6 billion gallons) and the
corresponding normal high-water level is
111.5 m (366 ft) above sea level
Reconstruction
16
The flood control storage is
457 million m3 (121 billion gallons).
The dam is made of clay and is
3,720 m (12,200 ft) long and 50.5 m
(166 ft) high.
The dam crest level is 120 m (390 ft)
above sea level.
The maximum discharge of the
reservoir is 15000 m3/s (about
3.96 million gallons/s).
Reconstruction
THANK YOU!
MUHAMMAD NAWAZ SHREEF UNIVERSITY OF
ENGINEERING AND TECHNOLOGY

More Related Content

What's hot

Run of River and Pumped Storage Plants
Run of River and Pumped Storage PlantsRun of River and Pumped Storage Plants
Run of River and Pumped Storage Plants
Satish Taji
 
6.three gorges
6.three gorges6.three gorges
6.three gorges
SANDEEPpv91
 
Water Woes of Mumbai City by Mr.P.K.Charankar
Water Woes of Mumbai City by Mr.P.K.CharankarWater Woes of Mumbai City by Mr.P.K.Charankar
Water Woes of Mumbai City by Mr.P.K.Charankar
Ekonnect Knowledge Foundation
 
Haiti Earthquake Case Study
Haiti Earthquake Case StudyHaiti Earthquake Case Study
Haiti Earthquake Case Study
The Axe Valley Community College
 
Three georges dam
Three georges damThree georges dam
Three georges dam
Jimmi Anderson
 
Report on Neelum Jhelum Hyrdoelectic project
Report on Neelum Jhelum Hyrdoelectic projectReport on Neelum Jhelum Hyrdoelectic project
Report on Neelum Jhelum Hyrdoelectic project
Rubnawaz Bhatti
 
performance evaluation of desilting devices
performance evaluation of desilting devicesperformance evaluation of desilting devices
performance evaluation of desilting devicesGurdeep singh Johar
 
Field visit report of Moragahakanda reservoir project
Field visit report of Moragahakanda reservoir project Field visit report of Moragahakanda reservoir project
Field visit report of Moragahakanda reservoir project
Deshan Arachchige
 
Mangla Dam
Mangla Dam Mangla Dam
Mangla Dam
EhteshamAkhtar3
 
KOYNA DAM,MAHARASHTRA
KOYNA DAM,MAHARASHTRAKOYNA DAM,MAHARASHTRA
KOYNA DAM,MAHARASHTRA
SameerNaik40
 
Neelum jhelum hydroelectric project ( NJHEP)
Neelum jhelum hydroelectric project ( NJHEP)Neelum jhelum hydroelectric project ( NJHEP)
Neelum jhelum hydroelectric project ( NJHEP)
Rubnawaz Bhatti
 
Intake structures in wwwe
Intake structures in wwweIntake structures in wwwe
Intake structures in wwwe
tirath prajapati
 
Methods Of Flood Control
Methods Of Flood Control Methods Of Flood Control
Methods Of Flood Control
HNurton
 
Jal manthan 16 april 2016
Jal manthan  16 april 2016Jal manthan  16 april 2016
Jal manthan 16 april 2016
Jaspreet Aulakh
 
KOYNA HYDROELECTRIC POWER PLANT
KOYNA HYDROELECTRIC POWER PLANTKOYNA HYDROELECTRIC POWER PLANT
KOYNA HYDROELECTRIC POWER PLANT
uzma shaikh
 
Hydropower
HydropowerHydropower
Hydropower
Yashraj Patil
 

What's hot (20)

Run of River and Pumped Storage Plants
Run of River and Pumped Storage PlantsRun of River and Pumped Storage Plants
Run of River and Pumped Storage Plants
 
6.three gorges
6.three gorges6.three gorges
6.three gorges
 
Water Woes of Mumbai City by Mr.P.K.Charankar
Water Woes of Mumbai City by Mr.P.K.CharankarWater Woes of Mumbai City by Mr.P.K.Charankar
Water Woes of Mumbai City by Mr.P.K.Charankar
 
Haiti Earthquake Case Study
Haiti Earthquake Case StudyHaiti Earthquake Case Study
Haiti Earthquake Case Study
 
Three georges dam
Three georges damThree georges dam
Three georges dam
 
Report on Neelum Jhelum Hyrdoelectic project
Report on Neelum Jhelum Hyrdoelectic projectReport on Neelum Jhelum Hyrdoelectic project
Report on Neelum Jhelum Hyrdoelectic project
 
THE THREE GORGES ppt
THE THREE GORGES pptTHE THREE GORGES ppt
THE THREE GORGES ppt
 
performance evaluation of desilting devices
performance evaluation of desilting devicesperformance evaluation of desilting devices
performance evaluation of desilting devices
 
Field visit report of Moragahakanda reservoir project
Field visit report of Moragahakanda reservoir project Field visit report of Moragahakanda reservoir project
Field visit report of Moragahakanda reservoir project
 
Tarbela dam
Tarbela damTarbela dam
Tarbela dam
 
BHUJ EARTHQUAKE
BHUJ EARTHQUAKEBHUJ EARTHQUAKE
BHUJ EARTHQUAKE
 
Mangla Dam
Mangla Dam Mangla Dam
Mangla Dam
 
KOYNA DAM,MAHARASHTRA
KOYNA DAM,MAHARASHTRAKOYNA DAM,MAHARASHTRA
KOYNA DAM,MAHARASHTRA
 
Neelum jhelum hydroelectric project ( NJHEP)
Neelum jhelum hydroelectric project ( NJHEP)Neelum jhelum hydroelectric project ( NJHEP)
Neelum jhelum hydroelectric project ( NJHEP)
 
Intake structures in wwwe
Intake structures in wwweIntake structures in wwwe
Intake structures in wwwe
 
Nagarjun sagar dam
Nagarjun sagar damNagarjun sagar dam
Nagarjun sagar dam
 
Methods Of Flood Control
Methods Of Flood Control Methods Of Flood Control
Methods Of Flood Control
 
Jal manthan 16 april 2016
Jal manthan  16 april 2016Jal manthan  16 april 2016
Jal manthan 16 april 2016
 
KOYNA HYDROELECTRIC POWER PLANT
KOYNA HYDROELECTRIC POWER PLANTKOYNA HYDROELECTRIC POWER PLANT
KOYNA HYDROELECTRIC POWER PLANT
 
Hydropower
HydropowerHydropower
Hydropower
 

Similar to Banqiao Dam Failure

Macchu dam
Macchu dam Macchu dam
Macchu dam
vishvjeet tholia
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
SiraskarCom
 
The Three Gorges Dam
The Three Gorges DamThe Three Gorges Dam
The Three Gorges Dam
Kella Randolph
 
The Three Gorges Dam
The Three Gorges Dam The Three Gorges Dam
The Three Gorges Dam
Kella Randolph
 
Three gorges dam project
Three gorges dam projectThree gorges dam project
Three gorges dam project
Noor Fatima
 
Three georges dam (china) real##
Three georges dam  (china) real##  Three georges dam  (china) real##
Three georges dam (china) real##
Nomaan . zs
 
water resource management and women (2000년대 중반)
water resource management and women (2000년대 중반)water resource management and women (2000년대 중반)
water resource management and women (2000년대 중반)
여성환경연대
 
Three Gorges Dam
  Three Gorges Dam  Three Gorges Dam
Three Gorges Dam
Ajmal Afzal
 
Dams by Luke Camilleri, 3.01
Dams by Luke Camilleri, 3.01Dams by Luke Camilleri, 3.01
Dams by Luke Camilleri, 3.01
geographystudents
 
TEHRI DAM & ITS IMPLICATIONS
TEHRI DAM & ITS IMPLICATIONSTEHRI DAM & ITS IMPLICATIONS
TEHRI DAM & ITS IMPLICATIONS
A Y V CHENULU
 
Dams
DamsDams
TanYe&Cui(55CWRA)
TanYe&Cui(55CWRA)TanYe&Cui(55CWRA)
TanYe&Cui(55CWRA)shiqiang Ye
 
Three gorges dam,china
Three gorges dam,chinaThree gorges dam,china
Three gorges dam,china
ARJUMAND EJAz
 
Cowlitz falls paper naes power contractors lewis county pud-final
Cowlitz falls paper   naes power contractors lewis county pud-finalCowlitz falls paper   naes power contractors lewis county pud-final
Cowlitz falls paper naes power contractors lewis county pud-final
NAES Corporation
 
MAUI - IAO STREAM (WAILUKU WATER CO) - County of Maui and US Army Corps of En...
MAUI - IAO STREAM (WAILUKU WATER CO) - County of Maui and US Army Corps of En...MAUI - IAO STREAM (WAILUKU WATER CO) - County of Maui and US Army Corps of En...
MAUI - IAO STREAM (WAILUKU WATER CO) - County of Maui and US Army Corps of En...
Clifton M. Hasegawa & Associates, LLC
 
Hydroelectric Group 4
Hydroelectric Group 4Hydroelectric Group 4
Hydroelectric Group 4
Lisa Surihani
 
Mullaperiyar dam voice of 3.5 million
Mullaperiyar dam voice of 3.5 millionMullaperiyar dam voice of 3.5 million
Mullaperiyar dam voice of 3.5 million
Vimal Kumar
 
Displacement case study- three gorges, China
Displacement case study- three gorges, China Displacement case study- three gorges, China
Displacement case study- three gorges, China
Aneisha Samuels-Sanford
 
Neelum jehlum hydropower project
Neelum jehlum hydropower projectNeelum jehlum hydropower project
Neelum jehlum hydropower project
Muhammad Aqeel
 
hydroelectric power plant.pptx
hydroelectric power plant.pptxhydroelectric power plant.pptx
hydroelectric power plant.pptx
CARLOBEJER1
 

Similar to Banqiao Dam Failure (20)

Macchu dam
Macchu dam Macchu dam
Macchu dam
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
 
The Three Gorges Dam
The Three Gorges DamThe Three Gorges Dam
The Three Gorges Dam
 
The Three Gorges Dam
The Three Gorges Dam The Three Gorges Dam
The Three Gorges Dam
 
Three gorges dam project
Three gorges dam projectThree gorges dam project
Three gorges dam project
 
Three georges dam (china) real##
Three georges dam  (china) real##  Three georges dam  (china) real##
Three georges dam (china) real##
 
water resource management and women (2000년대 중반)
water resource management and women (2000년대 중반)water resource management and women (2000년대 중반)
water resource management and women (2000년대 중반)
 
Three Gorges Dam
  Three Gorges Dam  Three Gorges Dam
Three Gorges Dam
 
Dams by Luke Camilleri, 3.01
Dams by Luke Camilleri, 3.01Dams by Luke Camilleri, 3.01
Dams by Luke Camilleri, 3.01
 
TEHRI DAM & ITS IMPLICATIONS
TEHRI DAM & ITS IMPLICATIONSTEHRI DAM & ITS IMPLICATIONS
TEHRI DAM & ITS IMPLICATIONS
 
Dams
DamsDams
Dams
 
TanYe&Cui(55CWRA)
TanYe&Cui(55CWRA)TanYe&Cui(55CWRA)
TanYe&Cui(55CWRA)
 
Three gorges dam,china
Three gorges dam,chinaThree gorges dam,china
Three gorges dam,china
 
Cowlitz falls paper naes power contractors lewis county pud-final
Cowlitz falls paper   naes power contractors lewis county pud-finalCowlitz falls paper   naes power contractors lewis county pud-final
Cowlitz falls paper naes power contractors lewis county pud-final
 
MAUI - IAO STREAM (WAILUKU WATER CO) - County of Maui and US Army Corps of En...
MAUI - IAO STREAM (WAILUKU WATER CO) - County of Maui and US Army Corps of En...MAUI - IAO STREAM (WAILUKU WATER CO) - County of Maui and US Army Corps of En...
MAUI - IAO STREAM (WAILUKU WATER CO) - County of Maui and US Army Corps of En...
 
Hydroelectric Group 4
Hydroelectric Group 4Hydroelectric Group 4
Hydroelectric Group 4
 
Mullaperiyar dam voice of 3.5 million
Mullaperiyar dam voice of 3.5 millionMullaperiyar dam voice of 3.5 million
Mullaperiyar dam voice of 3.5 million
 
Displacement case study- three gorges, China
Displacement case study- three gorges, China Displacement case study- three gorges, China
Displacement case study- three gorges, China
 
Neelum jehlum hydropower project
Neelum jehlum hydropower projectNeelum jehlum hydropower project
Neelum jehlum hydropower project
 
hydroelectric power plant.pptx
hydroelectric power plant.pptxhydroelectric power plant.pptx
hydroelectric power plant.pptx
 

More from Imran Nawaz

Design Considerations for AASHTO Flexible pavement design
Design Considerations for AASHTO Flexible pavement designDesign Considerations for AASHTO Flexible pavement design
Design Considerations for AASHTO Flexible pavement design
Imran Nawaz
 
Determining equivalent single wheel load.(ESWL)
Determining equivalent single wheel load.(ESWL) Determining equivalent single wheel load.(ESWL)
Determining equivalent single wheel load.(ESWL)
Imran Nawaz
 
Pavement & Foundations
Pavement & FoundationsPavement & Foundations
Pavement & Foundations
Imran Nawaz
 
Pavement & Foundations
Pavement & FoundationsPavement & Foundations
Pavement & Foundations
Imran Nawaz
 
Use of computer in project management
Use of computer in project managementUse of computer in project management
Use of computer in project management
Imran Nawaz
 
Inventory Management
Inventory ManagementInventory Management
Inventory Management
Imran Nawaz
 
Introduction of MatLab
Introduction of MatLab Introduction of MatLab
Introduction of MatLab
Imran Nawaz
 
Seismic motions, Measuring earth quake sizes
Seismic motions, Measuring earth quake sizesSeismic motions, Measuring earth quake sizes
Seismic motions, Measuring earth quake sizes
Imran Nawaz
 
Assignment 2
Assignment 2Assignment 2
Assignment 2
Imran Nawaz
 
Concrete ppt
Concrete pptConcrete ppt
Concrete ppt
Imran Nawaz
 
Fundamentals of computer
Fundamentals of computerFundamentals of computer
Fundamentals of computer
Imran Nawaz
 

More from Imran Nawaz (11)

Design Considerations for AASHTO Flexible pavement design
Design Considerations for AASHTO Flexible pavement designDesign Considerations for AASHTO Flexible pavement design
Design Considerations for AASHTO Flexible pavement design
 
Determining equivalent single wheel load.(ESWL)
Determining equivalent single wheel load.(ESWL) Determining equivalent single wheel load.(ESWL)
Determining equivalent single wheel load.(ESWL)
 
Pavement & Foundations
Pavement & FoundationsPavement & Foundations
Pavement & Foundations
 
Pavement & Foundations
Pavement & FoundationsPavement & Foundations
Pavement & Foundations
 
Use of computer in project management
Use of computer in project managementUse of computer in project management
Use of computer in project management
 
Inventory Management
Inventory ManagementInventory Management
Inventory Management
 
Introduction of MatLab
Introduction of MatLab Introduction of MatLab
Introduction of MatLab
 
Seismic motions, Measuring earth quake sizes
Seismic motions, Measuring earth quake sizesSeismic motions, Measuring earth quake sizes
Seismic motions, Measuring earth quake sizes
 
Assignment 2
Assignment 2Assignment 2
Assignment 2
 
Concrete ppt
Concrete pptConcrete ppt
Concrete ppt
 
Fundamentals of computer
Fundamentals of computerFundamentals of computer
Fundamentals of computer
 

Recently uploaded

LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 

Recently uploaded (20)

LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 

Banqiao Dam Failure

  • 2. 2 Construction of the Banqiao dam began in April 1951 on the Ru River. The help of Soviet consultants as part of a project to control flooding and provide electrical power generation. The construction was a response to severe flooding in the Hua River Basin in 1949 and 1950. The dam was completed in June 1952. Because of the absence of hydrology data the design standard was lower than usual. After the 1954 Huai River great flood, the upstream reservoirs including Banqiao were extended, constructed, and consolidated. Banqiao Dam was increased in height by three meters. History of Banqiao Dam
  • 3. 3 The dam crest level was 116.34 meters above sea level and the crest level of the wave protection wall was 117.64 meters above sea level. The total capacity of the reservoir was 492 million m3 (398,000-acre feet), with 375 million m3 (304,000- acre feet) reserved for flood storage. The dam was made of clay and was 24.5 meters high. The maximum discharge of the reservoir was 1742 m3/s. Banqiao Dam
  • 4. 4 Cracks in the dam and sluice gates appeared after completion due to construction and engineering errors. They were repaired with the advice from Soviet engineers and the new design, dubbed the iron dam, was considered unbreakable. Chen Xing one of China's foremost hydrologists was involved in the design of the dam but he was also a vocal critic of the government's dam building policy which involved many dams in the basin. Banqiao Dam
  • 5. 5 He had recommended 12 sluice gates for the Banqiao Dam, but this was criticized as being excessive and the number was reduced to five. Other dams in the project, including the Shimantan Dam, had a similar reduction of safety features and Chen was removed from the project. In 1961, after problems with the water system were revealed, he was brought back to help. Chen continued to be an outspoken critic of the system and was again removed from the project. Banqiao Dam
  • 6. Abstract During 4–8 August 1975, an extreme storm occurred in Henan Province, China. The maximum 5-day rainfall reached a record of 1,631 mm. Two large dams (Banqiao Dam and Shimandan Dam) two medium dams (Tiangang Dam and Zhugou Dam) and 58 small dams failed from overtopping in the storm event. 6
  • 7. 7 The breach peak flow rate was as high as 78,100 m3/s from the Banqiao reservoir and 30,000 m3/s from the Shimantan reservoir. The breaching of these dams caused an inundated area of 12,000 km2, a death toll of over 26,000, and economic loss of more than RMB10 billion. This paper introduces 26 dam failures in a smaller region of Zhumadian, i.e., Banqiao Dam, Zhugou Dam, and 24 small dams. The catastrophic event is described in detail especially for Banqiao Dam and Zhugou Dam. The causes and mechanisms of the principal failures are discussed, as well as the influence of an upstream dam failure on the downstream dams. Lessons from the catastrophe are discussed. Continue…
  • 8. 8
  • 9. Reasons of the Banqiao Dam Failure Understanding In August of 1975, typhoon Nina pelted the region with the heaviest rains ever recorded in the area. More than a year’s worth of water fell in 24 hours. The previous record was 800 mm (31.5”) of rain, and the stalled typhoon Nina dropped a new record of 1060 mm (41.73”). 9
  • 10. 10 The rainfall caused massive downstream flooding and, because of the flooded downstream areas, one request to open the dam was rejected on August 6. On August 7, the request to open the dam was accepted but this information did not reach the dam, as the storm had brought down the telegraph wires. The under-designed sluice gates were unable to handle the water volume and the first dam failure warning was sent. The water crested on August 8 at 0.3 meter (0.0984’) higher than the protection wall on the dam, which failed. 62 other dams in the Huai river basin also failed. Reasons of the Banqiao Dam Failure
  • 11. 11 The Banqiao Dam failure caused a huge wave, 10 kilometers (6.2 miles) wide and 3-7 meters (9.8-23ft) high to rush downstream at 50 kilometers per hour (31 mph), inundating the lower area with speeding floodwaters. Approximately 26,000 people died from flooding and another 145,000 died afterward as a result of epidemics and famine. Some 5,960,000 buildings collapsed, and 11 million residents were affected. Unofficial estimates of the number of people killed by the disaster have run as high as 230,000 people. Reasons of the Banqiao Dam Failure
  • 12. 12 Environmental Impacts Visible: Floods (river, coastal, mudflow), Large-scale disturbance of hydro and geological systems, Reduced ecological / hydrological connectivity Environmental impacts Dam failure Health Impacts Visible: Accidents, Exposure to unknown or uncertain complex risks (radiation, etc…), Deaths Impacts of Banqiao dam failure:
  • 13. 13 Health impacts The largest dam failure ever, over two hundred thousand deaths. Socio-economical Impacts Visible: Displacement, Loss of livelihood, Specific impacts on women, Violations of human rights, Land dispossession, Loss of landscape/sense of place. Impacts of Banqiao dam failure:
  • 14. 14 Within eleven years of the dam failure, the lower reach of the River Ru Zhumadian City, experienced several more disastrous floods. After many feasibility studies, the new Banqiao Reservoir reconstruction was listed as a key national project of The Seventh Five-Year Plan of China. The project owner was Huai River Water Resources Commission. The construction contractor was Changjiang Gezhouba Engineering Bureau. Reconstruction
  • 15. 15 By the end of 1986, the rebuilding project commenced. On June 5, 1993, the project was certified by the Chinese government. The reconstructed Banqiao Reservoir controls a catchment area of 768 km2. The maximum reserve capacity is 675 million m3 (178 billion gallons), a capacity increase of 34% above the capacity of the failed dam. The effective storage is 256 million m3 (67.6 billion gallons) and the corresponding normal high-water level is 111.5 m (366 ft) above sea level Reconstruction
  • 16. 16 The flood control storage is 457 million m3 (121 billion gallons). The dam is made of clay and is 3,720 m (12,200 ft) long and 50.5 m (166 ft) high. The dam crest level is 120 m (390 ft) above sea level. The maximum discharge of the reservoir is 15000 m3/s (about 3.96 million gallons/s). Reconstruction
  • 17. THANK YOU! MUHAMMAD NAWAZ SHREEF UNIVERSITY OF ENGINEERING AND TECHNOLOGY